(W. B. S):
Project A
Mobilization Works
Soil Works
Concrete Works
Concrete Works
Finishing Works
Concrete Works
Finishing Works
Project A
Mobilization Works
1 Soil Works:-
1- Excavation
2 Back filling
Site offices
3 Bitumen &insulation
ACTIVITY ID
WBS ID
A.01
A.01
A.01
A.02.10
A.02.10
A.02.10
A.02.20
A.02.20
A.02.20
A.02.20
A.02.20
A.02.20
A.03.10.01
A.03.10.01
A.03.10.01
A.03.10.01
A.03.10.01
A.03.10.01
A.03.10.01
A.03.10.01
A.03.10.02
A.03.10.02
A.03.10.02
A.03.10.02
A.03.10.02
A.03.10.02
A.03.10.02
A.03.10.02
A.03.10.02
A.03.10.02
ACTIVITY ID
ACTIVITY NAME
Mobilization Works
A1000
Cleaning & Leveling
A1010
Fixing the fence
A1020
Supply & Erection of Site offices
Sub_ Structure Works
A1030
Excavation
A1040
Back filling
A1050
Bitumen &insulation
A1060
Shuttering P.C Footing
A1070
Placing P.C Footing
A1080
De shuttering P.C Footing
A1090
Shuttering R.C Footing
A1100
Steel Fixing R.C Footing
A1110
Placing R.C Footing
A1120
De shuttering R.C Footing
Super _ Structure Works
A1130
A1140
A1150
A1160
A1170
A1180
A1190
A1200
A1210
A1220
A1230
A1240
A1250
A1260
A1270
A1280
A1290
A1300
WBS ID
A.03.20.01
A.03.20.01
A.03.20.01
A.03.20.01
A.03.20.01
A.03.20.01
A.03.20.01
A.03.20.02
A.03.20.02
A.03.20.02
A.03.20.02
A.03.20.02
A.03.20.02
A.03.20.02
A.03.20.02
A.03.20.02
A.03.20.02
ACTIVITY ID
A1310
A1320
A1330
A1340
A1350
A1360
A1370
A1380
A1390
A1400
A1410
A1420
A1430
A1440
A1450
A1460
A1470
ACTIVITY NAME
Steel Fixing 1st _ Floor R.C Columns
Placing 1st _ Floor R.C Columns
De shuttering 1st _ Floor R.C Columns
Shuttering 1st _ Floor R.C Slab
Steel Fixing 1st _ Floor R.C Slab
Placing 1st _ Floor R.C Slab
De shuttering 1st _ Floor R.C Slab
Brick Works
Preliminary Carpentry Works
Preliminary Electrical Works
Preliminary Sanitary Works
Plastering
Painting
Flooring
Finishing of Carpentry Works
Finishing of Electrical Works
Final Finishing
Creating Codes
Schedule of rates
Package deal
Unit price
Cost + % fee
Target cost
B Categories:Categories
Infrastructure Projects
Residential Projects
Nonresidential Projects
Industrial Projects
Small Projects
Less than 30 M
M
Middle Projects
Big Projects
B Area Department :-
Resource Management
-:
1 Labors.
2 Equipment.
3 Materials.
-:
1 m
2 . m2
3 . m3
4 . ton
5 . each
4 S/C (Subcontractor).
. Lump SUM
.
-:
1
.
2 .
- 3 .
4 .
5 .
-:
- :
Site preparation
-:
. 2
. - 1
4 labors
30 LE/day
Equipment cost:No.
Equipment
Loader 3.5m3
600 LE/day
Scraper
400 LE/day
Total cost:-
Excavation Activity
From Cost Estimate:A - Excavation works
- Surface drilling cube dimensions and drawings of specific data for operational level
and even the Earth's natural level of incorporation
In sand soil
Q = 2500 m3
o
Truck capacity=10 m3
Eff. = 0.8
Total cycle time of truck =( loading time +going time +dumping time
+return time + maneuver time)
Equipment
Excavator
800 LE / day
Loader
600 LE / day
Truck
300 LE / day
NO.
2
Labors
Cost /day
Unskilled
35 LE /day
item
quantity
unit
Unit D.C
LE / m3
TOTAL D.C
EXCAVATION
in sand soil
2500
m3
8.28
20700
Back filling
- :
. 3
. 2
. - 1
equipment
Roller 10t
550 LE /day
loader
600 LE /day
truck
300 LE /day
170 LE /day
NO.
labors
Cost / day
Un skilled
35 LE /day
ITEM
FILLING WITH
SAND
QUANTITY
2100
UNIT
m3
UNIT D. C
TOTAL D. C
LE/m3
LE
22.94
48165
Primary cost
Discounts 10 % from market
15
1.5
Handling 5 %
0.75
Waste 5 %
0.75
2.25
Total
1.5
3.75
2.25
Total cost
17.25
Primary cost
Discounts 10 % from market
60
6.0
Handling 5 %
3.00
Waste 5 %
3.00
9.00
Total
6.00
15.0
9.0
Total cost
69.0
Primary cost
Discounts 10 % from market
550
55
Handling 5 %
27.50
Waste 5 %
27.50
82.50
Total
55
82.50
27.50
Total cost
577.50
Primary cost
Discounts 10 % from market
3500
350
Handling 5 %
175
Waste 5 %
175
525
Total
350
875
525
Total cost
4025
Primary cost
Total
320
32
Handling 5 %
16
Waste 5 %
16
48
32
80
48
Total cost
368
Material type
Unit
Cement
1 ton
577.50 LE
Sand
1 m3
17.25 LE
Gravel
1 m3
69 LE
Water
Steel
Bricks
1 m3
1ton
1000 Bricks
4.5 LE
4025 LE
368 LE
- Isolation
LABOR
COST/DAY
P.R
Skilled
50/labor
75 m2/ labor
Duration = Q / PR
Duration = 830 / 3 * 225 = 3.69 days 4 days
LABOR COST = 4 * 50 * 3 * 3 = 1800 LE
Material cost
1 Barrel PAINT 20 m2
42 Barrel PAINT 830 m2
ALL IN RATE (BITUMINE)
Factor
Deduct
/BARRLE
Add /BARRLE
330
33
16.50
16.50
49.50
Total deductions/additions
Total
/BARRLE
33
82.50
Total additions
49.5
379.5
ITEM
QUANTITY
UNIT
Isolate with
bitumen
830
M2
UNIT D. C
TOTAL D. C
LE/m2
LE
21.37
17739
(
3 / 252
Plain concrete for foundation:
-
I. Form works:
a) Material.
b) Labor.
a) Material cost analysis:
* Cost of Form works.
Cost of 1 m3 wood
= 2500 LE
Labors
Cost/ day
Carpenter
110LE /day
assistant
60 LE /day
unskilled
35 LE /day
Placing works
a) Material.
b) Labor.
c) Equipment.
Labors
Cost/ day
60 LE/ day
Forman
60 LE/ day
carpenter
assistant
60 E/ day
c) Equipment analysis:-
NO.
Equipment
Vibrator
150 LE /day
UNIT D. C TOTAL D. C
QUANTITY UNIT
90
M3
LE/m3
LE
628.63
56576.7
A) Material.
b) Labor.
c) Equipment.
Unit
1 ton
1 m3
1 m3
1 m3
Unit
Cement
1 ton
577.50 LE
Sand
1 m3
17.25 LE
Gravel
1 m3
69 LE
Water
1 m3
4.5 LE
Material Cost =
69 + 0.50 x 17.25 + (5 / 20) x 577.50 + 0.175*4.5
= 222.79 LE/m3
b) Labor:
No
Labor
Cost/day
30 LE/day
30 LE/day
30 LE/day
30 LE/day
60 LE/day
110 LE/day
60 LE/day
c) Equipment:-
No
Equipment
Mixer
400 LE/day
Vibrator
150 LE/day
UNIT D. C
TOTAL D. C
LE/m3
LE
410.6
36954
QUANTITY UNIT
90
M3
- :
P.R = 12 M3/day
NO.
Labors
Cost/ day
Unskilled
35 LE /day
P.R = 12 m3/day
No. of crew = 3
Duration = 90 / 12 * 3 = 2.5 = 3 days
Cost of labor = 3 * 3 * 3 * (35) = 945 LE
Cost of labor/m3 = 945 / 90 = 10.5 LE/m3
= 2500 LE
P.R = 5 M3/day
NO.
Labors
Cost/ day
Carpenter
110LE /day
assistant
60 LE /day
unskilled
35 LE /day
days
2) Reinforcement
A) Material analysis
1) Reinforcement
80kg reinforcement in 1m3 concrete
price of 1 ton of reinforcement include transportation All in rate
= 4025 LE
Total quantity of steel = 110 x 80 /1000 = 8.80 ton
Direct cost of reinforcement / m3 = 80 * 4025/1000
= 322 LE/ m3
2) Anchorage wire
Vendor price of anchorage wire = 7 LE /kg
1 ton reinforcement needs 7 kg anchorage wire
= 7 * 80 / 1000 = 0.56 kg / m3 concrete
Direct cost of Anchorage wire/ m3 =0.56 *7=3.92 LE /m3
Total direct cost of material / m3 = 322 + 3.92 = 325.92 LE /m 3
Labors
Cost / day
commando
110 LE/day
Fixer
60 LE/day
assistant
45 LE/day
unskilled
35 LE/day
3) Placing
**in case of use ready mix concrete
I. Placing works:
a) Material.
b) Labor.
c) Equipment.
a) Material cost analysis:
use a ready mix concrete )Cost of 1 m3 concrete = 600 LE/m3
** test concrete cubic take 6 cubic every 50 m3
Cost of 1 cubic = 30 LE
Cost of 6 cubic = 6*30 = 180 LE
Cost of 1 m3 concrete = 180 / 50 = 3.60 LE
Material Direct cost /m3 = 3.60 + 600 = 603.60 LE/m3
Labors
Cost/ day
60 LE/ day
Forman
60 LE/ day
carpenter
assistant
60 E/ day
c) Equipment analysis:-
NO.
Equipment
Vibrator
150 LE /day
- :
P.R = 12 M3/day
NO.
Labors
Cost/ day
Unskilled
35 LE /day
P.R = 12 m3/day
No. of crew = 3
Duration = 110 / 12 * 3 = 3 days
Cost of labor = 3 * 3 * 3 * (35) = 945 LE
Cost of labor/m3 = 945 / 110 = 8.60 LE/m3
2 Columns (25*40)
(1)Sheathing
First Side = 2.5*40*100*2 = 20000 cm3
Second side = 2.5*25*100*2 = 12500 cm3
Total = 32500 cm3
10 Columns (40*30)
(1)Sheathing
First side = 2.5*40*100*2 = 20000 cm3
Second side = 2.5*30*100*2 = 15000 cm3
Total = 35000 cm3
5 Columns (30*50)
(1)Sheathing
First side = 2.5*50*100*2 = 25000 cm3
Second side = 2.5*30*100*2 = 15000 cm3
Total = 40000 cm3
2 Columns (30*60)
(1)Sheathing
First side = 2.5*60*100*2 = 30000 cm3
Second side = 2.5*30*100*2 = 15000 cm3
Total = 45000 cm3
3Columns (30*70)
(1) Sheathing
First side = 2.5*70*100*2 = 35000 cm3
Second side = 2.5*30*100*2 = 15000 cm3
Total = 50000 cm3
6 Columns (25*80)
(1) Sheathing
First side = 2.5*80*100*2 = 40000 cm3
Second side = 2.5*25*100*2 = 12500 cm3
Total = 52500 cm3
1 Column (80*30)
(1) Sheathing
First side = 2.5*80*100*2 = 40000 cm3
Second side = 2.5*30*100*2 = 15000 cm3
Total = 55000 cm3
2Column (40*65)
(1)Sheathing
First side = 2.5*65*100*2 = 32500 cm3
Second side = 2.5*40*100*2 = 20000 cm3
Total = 52500 cm3
= 2500 LE
Labors
Cost/ day
Carpenter
110LE /day
assistant
60 LE /day
unskilled
35 LE /day
days
(A) Materials:-
1) Reinforcement
2) Anchorage wire
Vendor price of anchorage wire = 7 LE /kg
1 ton reinforcement needs 7 kg anchorage wire
= 7 * 3.586 / 16.7 = 1.5 kg / m3 concrete
Direct cost of Anchorage wire/ m3 = 1.5 *7= 10.5 LE /m3
3
Labors
Cost / day
commando
110 LE/day
Fixer
60 LE/day
assistant
45 LE/day
unskilled
35 LE/day
(3) Placing
Labors
Cost/ day
60 LE/ day
Forman
60 LE/ day
carpenter
assistant
60 E/ day
c) Equipment analysis:-
NO.
Equipment
Vibrator
150 LE /day
Labors
Cost/ day
Carpenter
110LE /day
assistant
60 LE /day
unskilled
35 LE /day
2) Reinforcement
a) Material cost analysis :
- Wastage = 2 %
- Handling = 2 %
- Cost of 1 ton Steel = 4025 LE
- Amount of steel = 9.5 ton
- Total cost of steel = 4025 * 9.5 = 38237.5 LE
- Cost of steel for 1m3 concrete = 38237.5 / 78 = 490.22 LE / m3
- 1 ton reinforcement needs 7 kg anchorage wire = 7 * 9.5 / 78 = 0.85 kg /m3
- Direct cost of anchorage wire / m3 = 0.85 x 7 = 5.95 LE / m3
- Total direct cost of material / m3 = 490.22 + 5.95 = 496.1 LE / m3
Labors
Cost / day
commando
110 LE/day
Fixer
60 LE/day
assistant
45 LE/day
unskilled
35 LE/day
3) Placing
In case of use ready mix concrete
a) Material cost analysis :
- Cost of ready mix concrete of 1 M3 concrete (Delivery & Pumping) =
600 LE
- test concrete cubic take 6 cubic every 50 M3
- Cost of 1 cubic = 30 LE
- Cost of 6 cubic = 6*30 = 180 LE
- Total cost of 1 M3 concrete = 180 / 50 = 3.6 LE
- Total cost of 1m3 concrete = 3.6 + 600 = 603.6 LE /m3
- Total cost of concrete = 603.6 x 78 = 47080.8 LE
b) Labor cost analysis
P.R = 320 m3/day
NO.
Labors
Cost/ day
60 LE/ day
Forman
60 LE/ day
carpenter
assistant
60 E/ day
c) Equipment analysis:-
NO.
Equipment
Vibrator
150 LE /day
-:
- :
2 .
1 .
- :
1 .
2 .
3 .
-:
= 434
% 5
% 22
-:
= 55
% 5
= 54 = 1025 x 55
= 202213
% 22
- :
Production Rate = 6 m3 / day or 40 m2 / day
Cost per day
Labor Type
Number
Brick Worker
110 LE / Day/Each
Assistant
60 LE / Day/Each
Unskilled
40 LE / Day/Each
Labor
35 LE / Day/Each
1
.
- :
= 1112
= 213
- :
= 6342 = 54 * 112
= 20,5 = 20225 * 112 3
= 96205 = 352 * 20,5 .
- :
= 9242= 462 * 22
= 5022 = 2.25 * 22 3
= 1522 = 322 * 5022 .
-:
= 15621 = 0241 + 6331
= ,,,5 = 5,11 + 2,,5 3
= 2462,5 = 1511 + 062,5 = 2,51
-:
= 2,,5 = 41 \ 111
= 3,33 = 6 \ 21
= , = 3,33 + 2,,5
-:
= ( 3055 = , * 565 = , * ) 35 + 41 * 2 + 61 * 2 + 111 * 3
= ,333,5 = 5,,,5 * 2,5 + 1,,25 * ,,,5 + 363,5 * 15,621
= 11233,5 = ,333,5 + 3055
Activity Steps
Steps WBS
.
Steps
( ) G.F. SLAB
-:
Steps
Steps
Steps Add
- :
Wood form
Materials
Shuttering Crew
Labors
Original Duration = 6
Original Lag = 0
Steel Fixing 2 6 13
7 6 13 - :
Steel Reinforcement
Anchorage Wires
Steel Crew
Step -:
Original Duration = 7
Original Lag = 6
Materials
Labors
Placing Concrete 3 13 14
1 13 14
- :
Budget Unit = 78 m3
Budget unit / time = 1 d / d
Budget unit / time = 1 d / d
Materials
Equipment's
Labors
Step -:
Original Duration = 1
Original Lag = 13
De shuttering 3 21 24
3 21 24 - :
DE shuttering Crew
Labors
Step -:
Original Duration = 3
Original Lag = 21
- :
7 lag .
Resources Codes
Labors Crews Needed
Res ID
Resource Name
Default Units
/ time
Max Units /
time
Price / unit
L.S.L
1d / d
1d / d
120 LE
Ex.L
Excavation Crew
1d / d
4d / d
70 LE
B.F.L
1d / d
3d / d
70 LE
SH.L
Shuttering Crew
3d / d
6d / d
520 LE
DSH.L
DE shuttering Crew
3d / d
6d / d
105 LE
ISO.L
Isolation Crew
1d / d
4d / d
150 LE
ST.L
3d / d
6d / d
390 LE
CON.L
1d / d
3d / d
470 LE
BR.L
Bricks Crew
2d / d
4d / d
565 LE
SA.L
Sanitary Crew
1 LS / d
1LS / d
25000 LE
ELE.L
Electrical Crew
1 LS / d
1LS / d
15000 LE
CAR.L
Carpenter's Crew
1 LS / d
1LS / d
12000 LE
PLS.L
Plastering Crew
1 LS / d
1LS / d
8000 LE
PIN.L
Painting Crew
1 LS / d
1LS / d
10000 LE
FIN.L
Finishing Crew
1 LS / d
1LS / d
2000 LE
CNR.L
1d / d
3d / d
290 LE
Res ID
Resource Name
Default Units
/ time
Max Units /
time
Price / unit
LO.E
Loader
1d / d
3d / d
600 LE
SC.E
Scraper
1d / d
4d / d
400 LE
EX.E
Excavator
1d / d
3d / d
800 LE
TRK.E
Truck
3d / d
6d / d
300 LE
RO.E
Roller
3d / d
6d / d
550 LE
WTK.E
1d / d
4d / d
170 LE
VB.E
Vibrator
3d / d
6d / d
150 LE
MIX.E
Concrete Mixer
1d / d
3d / d
470 LE
Material Needed
Res ID
Resource Name
Default Units
/ time
Max Units /
time
Price / unit
SAN.M
Fine Sand
8m3 / d
50m3 / d
17.25 LE
GAR.M
Gravel
8m3 / d
50m3 / d
69 LE
CEM.M
Bortland Cement
8ton / d
20ton / d
577.5 LE
BAR.M
Bitumen
1ea / d
10ea / d
379.5 LE
BR.M
Bricks ( 6 x 12 x 25 )
1000ea / d
5000ea / d
0.368 LE
CON.M
100m3 / d
150m3 / d
458.60 LE
ST.M
Reinforcement Steel
10ton / d
20ton / d
4025 LE
WO.M
Wood Forms
5m3 / d
10m3 / d
2500 LE
ANC.M
Anchorage Wire
100kg / d
400kg / d
7 LE
WAT.M
Water
5m3 / d
10m3 / d
4.5 LE
CONRC.M
100m3 / d
150m3 / d
603.60 LE
Time Control
Cost Control
1 - Time Control
*
.
.2- Despite the good planning, many activities consume more time than Planned.
- :
-1 Variability's are very high
& material delay
&Equipment break down Labor accident
-2
. Reliability is low
3- Frequent changes are introduced to the scope of work.
.
4- Some trades proceed slower then required, thus produce delays.
.5- Dealing with suppliers and subcontractors is not easy.
.6- Change in actual activity duration or network logic.
.7- Sudden changes of labor availability.
.
8 - Strikes.
.9 - Change in design.
- .
Schedule updating: -
Project Maintain Baseline - :
Add - :
ok
.
- :
B1 B1
.
- :
Project Baseline .
User Baselines .
Ok .
Tools
Update Progress
.
-:
-:
1 Physical Percent Complete: .
2 Duration Percent Complete:
)Duration Percent Complete = (Original Duration Remaining Duration
Original Duration x 100
3 Unit Percent Complete:
Unit Percent Complete = (Actual Units / At Completion) x 100
- :
- :
- :
1 Original: .
2 Actual:
For Completed Activities
Actual = Zero
3 Remaining:
For Completed Activities
Remaining = Zero
Remaining = Original
4 At Complete: - :
For Completed Activities
At Complete = Actual
At Complete = Original
5 Started:
A
. Actual Start
5 Finished:
Duration % In progress
Actual
Finished At Complete .
6 Duration % : .
7 Suspended:
.
8 Resume:
. Suspended
2 Cost Control
cost control -:
1- monitor: -
- ( ) Actual
2- compare: -
3- Analysis: -
4- Action: - .
Actual cost
A
)Actual cost (AC
.) Work performed ( WP
- .
ACWP
Budget Cost Work Schedule
3- Analysis: -:
Cost Analysis
Time Analysis
1 Cost Analysis:
Under Budget
Cost Variance:-
As Budget
0.0
Over Budget
-ve
Under Budget
As Budget
Over Budget
At Completion
Estimated Cost
BAC
BAC .
Budget Cost At Completion
. BAC
1 Time Analysis:
.
Ahead
As Planned
Behind & Delay
Schedule Variance:-
Ahead
As Planned
Behind & Delay
TAC
TAC
.
Time At Completion
.TAC