Sei sulla pagina 1di 30

Prepared by ESA MetOp-SG Team

Reference MOS-LI-ESA-INS-0436
Issue 1
Revision 0
Date of Issue 17/07/2012
Status Approved/Applicable
Document Type List
Distribution

ESA UNCLASSIFIED For Official Use
estec
European Space Research
and Technology Centre
Keplerlaan 1
2201 AZ Noordwijk
The Netherlands
T +31 (0)71 565 6565
F +31 (0)71 565 6040
www.esa.int






MetOp-SG Instruments
Document Requirements List [DRL]


MOS-LI-ESA-INS-0436


Page : 2/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use


Title MetOp-SG Instruments Document Requirements List [DRL]
Issue 1 Revision 0
Author
MetOp-SG Team
Date 17/07/2012
Reviewed by Date

Signed on original


Approved by Date

Signed on original








Reason for change Issue Revision Date
First Issue 1 0 16/07/2012






Issue Revision
Reason for change Date Pages Paragraph(s)



Page : 3/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
Table Of Contents
1 INTRODUCTION ................................................................................................... 4
1.1 Scope ................................................................................................................ 4
1.2 Applicability ..................................................................................................... 5
2 DOCUMENTS ........................................................................................................ 6
2.1 Applicable Documents ...................................................................................... 6
3 DOCUMENTATION REQUIREMENTS ................................................................... 7
3.1 Milestones ........................................................................................................ 7
3.2 Document Category And Structure ................................................................... 7
3.3 Document Format And Contents ...................................................................... 8
3.4 Document Delivery Format .............................................................................. 8
3.5 Documentation Completeness .......................................................................... 9
4 INSTRUMENT PROJECT MANAGEMENT ............................................................ 11
5 INSTRUMENT LEVEL DOCUMENTS ................................................................... 14
6 INSTRUMENT SYSTEM ENGINEERING ............................................................. 20
7 INSTRUMENT SUPPORT SPECIFICATIONS ....................................................... 22
8 INSTRUMENT INTERNAL AND EXTERNAL INTERFACES ................................. 24
9 INSTRUMENT DRAWINGS ................................................................................. 25
10 INSTRUMENT ASSEMBLY, INTEGRATION AND VERIFICATION ..................... 26
11 INSTRUMENT PRODUCT ASSURANCE ............................................................. 27



Page : 4/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012

ESA UNCLASSIFIED For Official Use
1 INTRODUCTION
1.1 Scope
The MetOp-SG instruments Documentation Requirement List [DRL] specifies the minimum list of
documents to be delivered in the course of the MetOp-SG instruments projects, with a particular
focus on deliveries required for the formal Customer reviews. This list should not be considered, by
the MetOp-SG instrument contractor, as being exhaustive, particularly with respect to the
deliveries required from lower tier contractors and suppliers.

The Customer reserves the right to request additional documents and/or interim deliveries of
specified documents, as deemed necessary to ensure full and timely understanding and/or visibility
of the instrument design evolution or verification status.

Further interim deliveries should be foreseen
- to support the timely definition and implementation of the operational documentation for
the MetOp-SG instruments;
- to support the timely definition and implementation of the MetOp-SG Ground Segment
with respect to satellite monitoring and control and data processing facilities;
- to support the relevant MetOp-SG satellite prime contractor with respect to the process of
timely and consistent analytical and physical integration of the instruments with the
relevant satellite.

This document is supported by the MetOp-SG Instruments Document Requirements Description
(DRD), [AD18], providing a preliminary definition of the expected content of each document
specified. All DRL and DRD references are identified by {}, e.g. {ins-PM-01}.

For the recurrent instruments, deliverable documentation shall focus mainly on the management
and implementation of the recurrent AIT activities, the associated demonstration of the instrument
verification and model specific performances, characteristics, parameters, etc.

Update and revision of design documentation will only be required in case of enforced design
changes or where specific data is required to complete the preparation for and implementation of
the recurrent MetOp-SG satellite LEOP, commissioning and routine operations and associated
system performances.

Throughout this document, the following terms are used:
- ESA to refer to ESA as the top level customer for MetOp-SG;
- the Customer to refer to the relevant MetOp-SG satellite Prime Contractor, who
represents the immediate customer with respect to the MetOp-SG
instrument Prime Contractor;
- the Supplier to refer to the MetOp-SG instrument Prime Contractor;
- the Project to refer to the specific MetOp-SG instrument project.




Page : 5/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
1.2 Applicability
Unless otherwise stated, the document requirements are applicable to all instruments developed
under the ESA MetOp-SG Programme, i.e.:
- MicroWave Sounder (MWS);
- SCAtterometer (SCA);
- Radio Occultation sounder (RO);
- MicroWave Imager (MWI);
- Ice Cloud Imager (ICI);
- Multi-viewing, Multi-channel, Multi-polarisation Imager (3MI).





Page : 6/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
2 DOCUMENTS
2.1 Applicable Documents
The following documents are applicable to this DRL.

AD Title Reference
AD14
MetOp-SG Instruments Product Assurance And Safety
Requirements [PARD]
MOS-RS-ESA-INS-0434
AD15
MetOp-SG Instruments Management Requirements
[MARD]
MOS-RS-ESA-INS-0435
AD16 MetOp-SG Deliverable Items And Services List [DISL] MOS-LI-ESA-SYS-0067
AD18
MetOp-SG Instruments Document Requirements
Definition [DRD]
MOS-LI-ESA-INS-0437



Page : 7/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
3 DOCUMENTATION REQUIREMENTS
3.1 Milestones
The milestones used in this MetOp-SG Instruments DRL are as follows.

Milestone Notes
Phase B2
SRR MetOp-SG System Requirements Review
PDR Instrument Preliminary Design Review

Phase C/D
Phase C/D Kick-
Off
Instrument Phase C/D Kick-Off Note 1
CDR Instrument Critical Design Review
QR Instrument Qualification Review
AR Instrument Acceptance Review (per instrument)

Phase E1
SIOVR Satellite In-Orbit Verification Review (per satellite)

Notes:
(1) This column contains the documents required at the end of the Phase B2, not being updated
in the frame of the PDR, to support the validation of the Phase C/D contractual offer.

3.2 Document Category And Structure
The document categories are as defined in the MetOp-SG Instrument Management Requirements
[MARD].

Doc Category Note
A
To be formally approved by the Customer (and possibly ESA) as a strict
condition to authorise the instrument contractor work associated to this
document.
R
To be reviewed by the Customer (and possibly ESA). Review of these
documents is required such that feedback can be provided to the Contractor
prior to execution of the tasks driven by this document.
I
For Information Only. These documents are supporting documents providing
visibility to the Customer but not requiring formal review and/or approval.



Page : 8/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
The DRL is structured according to families, with the following identification code:

ins-typ-nn

where ins represents the Instrument Code as defined below;
typ represents the Family Type as defined below;
nn represents a number.

Instrument Code Description
ICI Ice Cloud Imager
MWS MicroWave Sounder
MWI MicroWave Imager
RO Radio Occultation sounder
SCA SCAtterometer
3MI Multi-viewing, Multi-channel, Multi-polarisation Imager

Family Type Description
PM Instrument Project Management
IN Instrument Level Documents
SY Instrument System Engineering
SS Instrument Supporting Specifications
IF Instrument Internal and External Interfaces
DR Instrument Drawings
AV Instrument AIV (including GSE aspects)
PA Instrument Product Assurance and Safety

For consistency across the MetOp-SG programme, the defined DRL references are the same for all
MetOp-SG instruments, with the exception a unique prefix code as defined above. In the
subsequent tables the Instrument Code is identified as ins, which shall be replaced by the specific
Instrument Code for a given instrument, e.g. instead of ins-PM-01, MWI-PM-01 shall be used
for the MWI instrument, 3MI-PM-01 for the 3MI instrument, etc.

The Supplier shall respond to the DRL ensuring completeness and consistency of his
documentation with the families of documents defined above.

3.3 Document Format And Contents
In the subsequent tables, the last column remarks makes reference to a document requirement
description defined either in a general standard (ECSS) or in the specific MetOp-SG instruments
DRD.

3.4 Document Delivery Format
All DRL documents shall be delivered to both the Customer and ESA in electronically generated
and native searchable PDF format (scanned pages only accepted for hand written documents, e.g.
minutes of meetings, and in specific cases where no original electronic version of the document is
available, such as the case of very old documentation). Furthermore, PDF documents shall have
their Table of Contents, where present, available as PDF bookmarks.


Page : 9/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use

Upon the Customers or ESAs request (e.g. when a portion of documentation needs to be imported
in Customer's documentation), the Supplier shall also deliver the native word/excel version of the
documents, even though it is understood that the only contractually binding document will remain
the PDF version.

All drawings shall be generally provided in A3 PDF format, with additional A0 format for very large
drawings (e.g. grounding diagrams, overall schematics, etc.). In addition, one paper copy shall also
be delivered for all drawings.

Where mentioned in the DRL, on-line access to real time up-to-date electronic database or
spreadsheet is additionally assumed (e.g. for NCRs database).

In case of reviews, the Supplier shall deliver:
- for satellite level reviews (instrument inputs), 6 paper copies and 12 sets of
CD/DVD/memory stick;
- for instrument level reviews, 6 paper copies and 12 sets of CD/DVD/memory stick;
- for lower level (subsystem, equipment) reviews, 3 paper copies and 6 sets of
CD/DVD/memory stick.

Deliveries of Review Data Packages shall be to two locations:
- the Customer;
- ESA/ESTEC, Noordwijk, the Netherlands;
- EUMETSAT, Darmstadt, Germany.

The Review Data Packages shall be distributed at least three weeks prior to the review presentation
by the Supplier.

3.5 Documentation Completeness
The current list of documents identified and called upon within the instrument SOW shall be
reviewed and completed as necessary by the Supplier before the instrument PDR, to ensure that:
- all instrument development activities that pertain to the fulfilment of the baseline
requirements are properly documented;
- the final list of documents to be agreed at the instrument PDR is consistent with the
instrument Specification and Plan Tree (a formal update of this DRL will be defined and
agreed prior to Phase C/D Kick-Off).




Page : 10/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use



















This page intentionally left blank.




Page : 11/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012

ESA UNCLASSIFIED For Official Use
4 INSTRUMENT PROJECT MANAGEMENT
DRL
Reference
CAT Instrument Project
Management
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-PM-01 A
Project Management
Plan
X X X
Requires ESA approval;
As per Annex A of ECSS-M-ST-10C, Rev 1.
ins-PM-02 R Progress Report X
Every 8 weeks, from B2 K.O. until PDR, every 10
weeks afterwards;
As per DRD {ins-PM-02}.
ins-PM-03 I Project Meetings Plan X
Monthly, from KO plus weekly update for short term
(4 week) time window;
As per DRD {ins-PM-03}.
ins-PM-04 A/I Minutes of Meetings X
"A" applies to meetings with Customer; I applies to
meetings with lower tier / sub-contractors, others;
MoM with Customer issued not later than 1 week
following the meeting, signed by all attending parties;
No DRD.
ins-PM-04A I
Meeting and Reviews
Presentations
X No DRD.
ins-PM-05 I Project Directory X X
Further updates as required;
As per DRD {ins-PM-05}.
ins-PM-06 R
Contractors ITT to Sub-
contractors
X 3 weeks prior to issuing ITT; No DRD.
ins-PM-07 I Inventory Record X X X As per Annex I of ECSS-M-ST-60C.
ins-PM-8 R
Schedule Reporting
(including Master
Schedule)
X
Every 8 weeks after B2 Kick-Off until PDR, every 10
weeks thereafter, together with Progress Report, with
lower level inputs;
As per Annex C of ECSS-M-ST-60C and Annex B of
ECSS-M-ST-60C.


Page : 12/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Project
Management
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-PM-08A R
Instrument Software
DD&V Progress
Reporting
X
With {ins-PM-08};
No specific DRD.
ins-PM-09 A Contract Change Notice X
As required;
As per Annex O of ECSS-M-ST-60C.
ins-PM-10 R Change Status List X
Every 8 weeks, from B2 K.O. until PDR, every 10
weeks thereafter, together with Progress Report.
ins-PM-11 R Action Item Status List X
Common database to be maintained by the Supplier
but readable (and commendable) by the Customer;
Extract to be provided for each Progress Meeting, as
per DRD {ins-PM-11}.
ins-PM-12 R Instrument Product Tree X X X X
As per Annex B of ECSS-M-ST-10C, Rev 1; updates for
Phase C/D KO, as required.
ins-PM-13 R
Work Breakdown
Structure
X
Additional updates as required;
As per Annex C of ECSS-M-ST-10C, Rev 1.
ins-PM-14 R
Work Package
Description
X
Additional updates as required;
As per Annex D of ECSS-M-ST-10C, Rev 1.
ins-PM-15 I
Invoicing and Payments
Status Report
X
Every 8 weeks, from B2 K.O. until PDR, every 10
weeks thereafter, together with Progress Report {ins-
PM-02}.
ins-PM-16 A Milestone Payment Plan X
Updates as required;
As per Annex H of ECSS-M-ST-60C.
ins-PM-18 A Contract Structure X X X
Initial version to be provided by the Supplier for the
Phase B2/C/D/E offer;
Thereafter, to be provided and maintained by the
Customer based on Supplier inputs as required;
As per DRD {ins-PM-18}.
ins-PM-19 A
Geographical
Distribution of the Work
X
Regular Reporting during Phase B2 and early Phase C;
As per Annex E of ECSS-M-ST-60C.


Page : 13/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Project
Management
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-PM-20 A
Configuration Control
and Documentation
Management Plan
X X X
Updates as required;
As per Annex A of ECSS-M-ST-40C, Rev 1 (including
Document Management Procedure).
ins-PM-21 A/R
Document Change
Notice
X
As required; Approval required for CAT A documents
as per DRD {ins-PM-21}.
ins-PM-22 A
Contract Close-Out Data
Package
X
Timing at instrument, subsystem and equipment
levels to be consistent with the Contract;
As per DRD {ins-PM-22}.
ins-PM-23A A Request for Deviation X X X X
As applicable; Approval required for all those items
which will result in a degradation with respect to the
customer specified requirements;
As per Annex I of ECSS-M-ST-40C, Rev 1.
ins-PM-23B A Request for Waiver X X X X
As applicable;
Approval required for all those items which will result
in a degradation with respect to the customer
specified requirements;
As per Annex J of ECSS-M-ST-40C, Rev 1.
ins-PM-24 A
Project Organisation
Breakdown Structure
X X As per DRD {ins-PM-24}.
ins-PM-25 A
Industrial Procurement
Plan
X X X
Updates in Phase B2 & Phase C, as required;
as per DRD {ins-PM-25}.
ins-PM-26 R
Configuration Item Data
List (CIDL)
X X X X
As per Annexes B and C of ECSS-M-ST-40C, Rev 1;
(Including RFD/RFW Status List).
ins-PM-27 R Document Status List X X X X X As per DRD {ins-PM-27}.
ins-PM-28 A
Risks Assessment and
Management Plan
X X X X As per Annex B of ECSS-M-ST-80C.
ins-PM-29 R
Risks Register and Risk
Report
X
Status of Major Risks; presented at all Progress
Meetings; based on Annexes C, D of ECSS-M-ST-80C.
ins-PM-30 I
List of Acronyms and
Abbreviations
X X X X X Updates as required; No DRD.


Page : 14/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
5 INSTRUMENT LEVEL DOCUMENTS
DRL
Reference
CAT Instrument Level
Documents
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-IN-01 R
Instrument Design and
Technical Description
X X X X X
From proposal level and includes design and
performance descriptions, in response to {ins-IN-02};
As per DRD {ins-IN-01}.
ins-IN-01A R
Subsystem and
Equipment Design
Definition Documents
X X X
To be delivered consistent with lower tier reviews;
As per Annex G of ECSS-E-ST-10C.
ins-IN-02 A
Instrument
Requirements
Specification

Draft version from the Supplier for the Phase
B2/C/D/E offer;
Thereafter, to be provided and maintained by the
Customer;
Based on Annex A of ECSS-E-ST-10-06C;
As per DRD {ins-IN-02}.
ins-IN-03 I
Requirements
Traceability Database
X X X
Formal extracts of the populated DOORS Database to
be provided at major reviews and in any case at least
on 4-months interval (TBC), based on Annex A of
ECSS-E-ST-10-06C;
As per DRD {ins-IN-03}.
ins-IN-04 R
Instrument Subsystem /
Equipments
Requirements
Specifications
X X X
As available at SRR in view of Best Practice;
Based on Annex A of ECSS-E-ST-10-06C.
ins-IN-05 R
Instrument Technical
Budgets Report
X X X X X
As per DRD {ins-IN-5}; Includes engineering,
performance and on-ground characterisation as input
to satellite level budget documentation;
As per Annex I of ECSS-E-ST-10C;


Page : 15/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Level
Documents
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-IN-06 A
Instrument Budgets and
Margins Definition
Document
X X X
Engineering and Performance Budgets compiled
within {ins-IN-09};
As per DRD {ins-IN-06}.
ins-IN-07 R
Instrument Design
Justification File
X X X
As per Annex K of ECSS-E-ST-10C;
As per DRD {ins-IN-07}.
ins-IN-07A R
Subsystem and
Equipment Design
Justification Documents
X X
To be delivered consistent with lower tier reviews;
Shall include all specific analyses required, as defined
in the instrument SOW and applicable ECSS;
As per Annexes K and L of ECSS-E-ST-10C;
As per DRD {ins-IN-07}.
ins-IN-08 I
Instrument Performance
Model Description
X X X X X As per DRD {ins-IN-08}.
ins-IN-09 R
Instrument Analysis
Reports
X X X X X X
As required in support of Design Justification
Document;
As per Annex Q of ECSS-E-ST-10C.
ins-IN-10A R
Instrument Straylight
Analyses
X X X X
Applicable only for 3MI;
As per DRD {ins-IN-10A}.
ins-IN-10B R
Instrument Tolerance
Analyses
X X X X
Applicable only for ICI, MWI, MWS, and 3MI;
As per DRD {ins-IN-10B}.
ins-IN-10C R
Impact Analysis of In-
Orbit Radiation
Environment on
Detector
X X
Applicable only for 3MI;
As per DRD {ins-IN-10C}.
ins-IN-10D R
Instrument Sun
Intrusion Analysis
X X X X
Applicable only for ICI, MWI and MWS;
As per DRD {ins-IN-10D}.
ins-IN-10E R
Instrument Multi-Path
Analysis
X X X X
Applicable only for RO and SCA;
As per DRD {ins-IN-10E}.
ins-IN-10F R
Instrument RF
Interference Analysis
X X X X
Applicable only for ICI, MWI, MWS, RO and SCA;
As per DRD {ins-IN-10F}.


Page : 16/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Level
Documents
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-IN-10G R
GNSS Acquisition,
Tracking and Processing
Algorithms Analysis
X X X X
Applicable only for RO;
As per DRD {ins-IN-10G}.
ins-IN-11 A
Instrument
Design, Development
and Verification Plan
X X X X
Covered the pre-launch activities; As per DRD {ins-
IN-11};
Also covers pre-development and technology matrix
and associated plan as per ECSS-E-ST-10C annexes E
and F;
Also covers Verification Plan as per ECSS-E-ST-10-
02C Annex A.
ins-IN-11A R
Subsystem and
Equipment Design,
Development and
Verification Plan
X X X
To be delivered consistent with lower tier reviews;
As per DRD {ins-IN-11}.
ins-IN-12 A Instrument AIT Plan X X X X
Includes AIT and on-ground characterisation;
As per DRD {ins-IN-12}.
ins-IN-13 A
Instrument Verification
Control Document
(VCD)
X X X X X X
Applicable to the full instrument technical baseline
requirements. Evolving from Verification Matrix
(includes verification method/stage/level) with open
traces (to verification close-out doccs etc.) at SRR, to
include full Verification Reports at FAR.
VCD can also be used for statements of compliance.
As per Annexes B and F of ECSS-E-ST-10-02C.
Note: At SRR the definition of verification methods /
levels / stages will be limited to subset of whole
documentation (to be agreed at Phase B2 KO).
ins-IN-13A R
Subsystem and
Equipment Verification
Control Document
(VCD)
X X X X
To be delivered consistent with lower tier reviews;
As per Annexes B and F of ECSS-E-ST-10-02C.


Page : 17/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Level
Documents
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-IN-14 R
Instrument Verification
Matrix
X X X X X
As per DRD {ins-IN-14};
Can be contained in {ins-IN-13}.
ins-IN-14A R
Subsystem and
Equipment Verification
Matrix
X X X X
To be delivered consistent with lower tier reviews;
As per DRD {ins-IN-14A}.
ins-IN-15 A Instrument Test Plans X X X
As per DRD {ins-IN-15};
Also includes inputs to satellite level testing.
ins-IN-15A R
Subsystem and
Equipment Test Plans
X
To be delivered consistent with lower tier reviews;
As per DRD {ins-IN-15A}.
ins-IN-15B A
Instrument Test
Specifications
X X X
As per Annex C of ECSS-E-10-03A;
Also includes inputs to satellite level testing.
ins-IN-15C R
Subsystem and
Equipment Test
Specifications
X
To be delivered consistent with lower tier reviews;
As per Annex C of ECSS-E-10-03A.
ins-IN-16 R
Instrument Test
Procedures
X X X As per DRD {ins-IN-16}.
ins-IN-16A R
Subsystem and
Equipment Test
Procedures
X
To be delivered prior to lower tier Test Readiness
Reviews (TRR);
As per DRD {ins-IN-16A}.
ins-IN-16B R
Instrument to Satellite
Integration Procedures
X X X Inputs, as required.
ins-IN-17 R Instrument Test Reports X X X As per Annex C of ECSS-E-ST-10-02C.
ins-IN-17A R
Subsystem and
Equipment Test Reports
X
To be delivered consistent with lower tier reviews, e.g.
TRB;
As per Annex C of ECSS-E-ST-10-02C.
ins-IN-18 R
Instrument Test
Correlation Reports
X X X
Electrical, Mechanical, Thermal, Performance, Stray-
light, Contamination, etc.;
As per DRD {ins-IN-18}.


Page : 18/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Level
Documents
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-IN-19 A
Instrument
Characterisation and
Performance Verification
Plan
X X X X As per DRD {ins-IN-19}.
ins-IN-20 A
Instrument Calibration
Plan
X X X X X As per DRD {ins-IN-20}.
ins-IN-21 R
Instrument Data
Simulator Requirements
Specification
X X X X As per DRD {ins-IN-21}.
ins-IN-22 R
Instrument Data
Evaluation Algorithms
Detailed Design
Description
X X X As per DRD {ins-IN-22}.
ins-IN-24 R
Instrument
Characterisation and
Calibration Data Base
Specification
X X X As per DRD {ins-IN-24}.
ins-IN-25 A
Instrument Flight
Operations Manual
X X X X X
Outline to be delivered at PDR;
DRD as per DRD {ins-IN-25};
Deliveries and versioning per MetOp-SG DISL [AD16].
ins-IN-25A R
Instrument Flight
Operations Procedures
X
Covers nominal control, contingency/recovery and on-
board control procedures;
No DRD;
Deliveries and versioning per MetOp-SG DISL [AD16].
ins-IN-26 R
Instrument GSE
Requirement
Specifications
X X
Several distinct specifications to procure e.g. EGSE,
MGSE, OGSE;
As per Annex A of ECSS-E-ST-10-06C.
ins-IN-27 R
Instrument GSE Design
Justification / Definition
File
X X Based on Annexes G and K of ECSS-E-ST-10C.


Page : 19/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Level
Documents
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-IN-28 R
Instrument GSE
Verification Reports
X X As per Annex F of ECSS-E-ST-10-02C.
ins-IN-29 R
Instrument Performance
and Calibration Analysis
X X X X X As per DRD {ins-IN-29}.
ins-IN-30 R
Instrument
Contamination Analyses
X X X X
Theoretical Analyses at PDR and CDR, analyses
supported by tests at AR in line with instrument SOW;
As per DRD {ins-IN-30}.
ins-IN-31 A
Instrument Review Data
Package
X X X X X
Data package consistent with ECSS-M-30A;
Further details as per review procedure.
ins-IN-35 R
GPP Algorithm
Theoretical Baseline
Document (ATBD)
X X X X As per DRD {ins-IN-35}.
ins-IN-36 R
GPP Detailed Processing
Model
X X X As per DRD {ins-IN-36}.
ins-IN-37 R
GPP Input / Output Data
Specification (IODS)
Document
X X X X As per DRD {ins-IN-37}.
ins-IN-38 R
Instrument Forward
Model / Instrument Data
Simulator
X X X X To be integrated as a section of {ins-IN-35}.
ins-IN-39 A/R
GPP Software
Documentation
X X X X
GPP software documentation as specified in
instrument SOW;
DRD according to ECSS-E-ST-40C, Category D.



Page : 20/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
6 INSTRUMENT SYSTEM ENGINEERING
DRL
Reference
CAT Instrument System
Engineering
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-SY-01 A
Specifications, ICD and
Plan Tree
X X X As per DRD {ins-SY-01}.
ins-SY-02 R Mission Analysis Report X X X X
Updated as required;
As per Annex B of ECSS-E-ST-70C.
ins-SY-03 R
Instrument Autonomy
and Failure Detection,
Isolation and Recovery
Concept Document
X X X X
Following approval of concept, the FDIR approach will
be supported by dedicated specifications, overall
MetOp-SG satellite design documentation issued by
the Customer and {ins-PA-18};
As per DRD {ins-SY-03}.
ins-SY-05 A
Instrument Calibration
and Level 1b Products
Validation Plan
X X X X
Covering radiometric and spectral/frequency aspects;
As per DRD {ins-SY-05}.
ins-SY-06 A
Instrument Pointing
Apportionment
Document
X X X X X
Updates, as required in Phase B2;
As per Instrument SOW.
ins-SY-09 R
Instrument Reference
Data Base
X X X X
Instrument input to the MetOp-SG SRDB;
Deliveries and versioning per MetOp-SG DISL [AD16].
ins-SY-10 R
Instrument On-Ground
Characterisation and
Calibration Data Base
X X X X
Input to Customer Characterisation and Calibration
Data Base;
Deliveries and versioning per MetOp-SG DISL [AD16].
ins-SY-11 R
LEOP Operations
Timeline
X X X Part of instrument FOM {ins-IN-25}, if relevant.
ins-SY-12 R
Reference Routine
Mission Timeline
X X X X Part of instrument FOM {ins-IN-25}.
ins-SY-13 A
Instrument In-Orbit
Verification Plan
X X X X
Covers the Instrument In-Orbit Characterisation,
Calibration and Performance Assessment;
As per DRD {ins-SY-13}.


Page : 21/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument System
Engineering
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-SY-14 R
Instrument In-Orbit
Verification Report
X
In-Orbit Verification Report covers in-orbit
characterisation and calibration;
As per DRD {ins-SY-14} and Annex F of ECSS-E-ST-
10-02C.
ins-SY-25 A
GPP Requirements
Specification
X X X
As per DRD {ins-SY-25};
Ref. Annex A of ECSS-E-ST-10-06C.
ins-SY-26 R
GPP Technical
Description
X X
As per DRD {ins-SY-26};
Ref. Annex A of ECSS-E-ST-10-06C and Annex M of
ECSS-E-ST-10C.
ins-SY-27 A
GPP Design,
Development and
Verification Plan
X X X
As per DRD {ins-SY-27};
Ref. Annex A of ECSS-E-ST-10-02C.
ins-SY-28 R GPP Verification Report X X X As per Annex F of ECSS-E-ST-10-02C.
ins-SY-29 R
GPP Installation and
Users Manual
X X X
As per DRD {ins-SY-29};
Ref. Annex P of ECSS-E-ST-10C.
ins-SY-30 R
Instrument Specification
for SATSIM

Consistent with the MetOp-SG programme, it is
expected that an incremental delivery of these items
will be required from the Supplier for provision to the
Customer. The format, timing and content is TBD;
As per DRD {ins-SY-30}.



Page : 22/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
7 INSTRUMENT SUPPORT SPECIFICATIONS
DRL
Reference
CAT Instrument Support
Specifications
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-SS-06 A
Instrument Reference
Coordinate System
X X As per Annex A of ECSS-E-ST-10-09C.
ins-SS-09 R
Instrument EMC Control
Plan
X X As per Annex A of ECSS-E-ST-20C.
ins-SS-11 R
Instrument Alignment
Requirements and
Control Plan
X X X X As per DRD {ins-IN-32}.
ins-SS-15 R
Microvibration Analysis
and Mitigation Plan
X X As per DRD {ins-SS-15}.
ins-SS-21 R
On-Board Software
Design Document
X X X X
Including definition of Cat B software;
As per Annex F of ECSS-E-ST-40C.
ins-SS-22 R
Software Requirements
Specifications
X X As per Annex D of ECSS-E-ST-40C.
ins-SS-23 A
Software Design,
Development and
Verification Plan
(X) X X
Dedicated chapter will be provided in {ins-IN-11} at
SRR;
Not part of instrument PDR, however to be delivered
at lower level PDR to the Customer;
As per Annexes O, I and J of ECSS-E-ST-40C.
ins-SS-24 I
Software Design
Justification File
X X X
As per Annex K of ECSS-E-ST-10C and based on
Annex F of ECSS-E-ST-40C.
ins-SS-25 R
Software Verification
Report
X X As per Annex M of ECSS-E-ST-40C.
ins-SS-26 R
Independent Software
Verification and
Validation Report
X X X
For Cat B Software, if required;
Based on Annex M of ECSS-E-ST-40C.


Page : 23/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Support
Specifications
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-SS-27 R
Software Development
and Validation
Environment
Specification
X X As per DRD {ins-SS-27}.
ins-SS-29 I Manufacturing File X X X As per DRD {ins-SS-29}.
ins-SS-30 I
Mechanical, Thermal
and Geometrical
Mathematical Models
and Description
X X X X
See DISL [AD16] for deliverables;
Based on Customer requirements & specification;
See Annex B of ECSS-E-ST-31C, ECSS-E-ST-32C.
ins-SS-31 R
Instrument
Housekeeping Telemetry
Data Definition
Document
X X X X As per DRD {ins-SS-31}.
ins-SS-32 A Long Term Storage Plan X X X X
As per DRD {ins-SS-32};
Includes also spares philosophy.
ins-SS-33 A
Instrument Design
Considerations and
Requirements for Long
Term Storage
X X X
Special provisions;
As per DRD {ins-SS-33}.
ins-SS-35 R
Instrument, Subsystem
and Equipments Review
Synthesis Report
X X X
For all instrument and satellite level reviews;
As per DRD {ins-SS-35}.
ins-SS-36 R
Subsystem and
Equipments
Review Data Packages
X X X X
3 weeks in advance of the related lower tier review;
As per review procedure by the Supplier.



Page : 24/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
8 INSTRUMENT INTERNAL AND EXTERNAL INTERFACES
DRL
Reference
CAT Instrument Internal and
External Interfaces
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-IF-03 R
Instrument to Test
Facilities Interface Control
Document
X X X
First version for selection of test facility;
As per DRD {ins-IF-03}.
ins-IF-06 R
Instrument Subsystem
Interface Control
Document
X X X X As per DRD {ins-IF-06}.
ins-IF-07 A
Instrument Interface
Control Document

Draft version from the Supplier for the Phase
B2/C/D/E offer;
Thereafter, to be provided and maintained by the
Customer;
As per DRD {ins-IF-07}.
ins-IF-08 R
Instrument to GSE
Interface Control
Document
X X X As per DRD {ins-IF-08}.
ins-IF-11 R Instrument Software ICD X X X X As per Annex E of ECSS-E-ST-40C.



Page : 25/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
9 INSTRUMENT DRAWINGS
DRL
Reference
CAT Instrument Drawings SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-DR-04 R
Instrument Operations
Modes and Mode
Switching Diagrams
X X X X X
In addition appended to the Instrument FOM;
As per DRD {ins-DR-04}.
ins-DR-05 I
Switching Diagrams and
Command/Control
Synoptic
X X X X
In addition appended to the Instrument FOM;
Down to equipment level;
As per DRD {ins-DR-05}.
ins-DR-06 I
Electrical Grounding
Diagrams
X X X X
In addition appended to the Instrument FOM;
As per DRD {ins-DR-06}.
ins-DR-07 I
Instruments Assembly and
Accommodation Drawings
X X X X X
Per instrument unit (e.g. instrument main unit,
electronic unit, etc.) mounted separately on the
MetOp-SG satellite;
As per DRD {ins-DR-07}.
ins-DR-09 I
Instruments Mechanical
and Thermal Interface
Drawings
X X X X As per DRD {ins-DR-09}.
ins-DR-10 I
Instruments Electrical
Block Diagrams
X X X X As per DRD {ins-DR-10}.
ins-DR-11 I
Instruments Equipment
Circuit Diagrams
X X As per DRD {ins-DR-11}.



Page : 26/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
10 INSTRUMENT ASSEMBLY, INTEGRATION AND VERIFICATION
DRL
Reference
CAT Instrument Assembly,
Integration &
Verification
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-AV-03 R
GSE Design and
Development Plan
X X X
Based on {ins-UV-11};
Document covers GSE and all non flight deliverables.
ins-AV-04 A
Hardware/Software
Matrix
X X X
Covers instrument and GSE;
As per DRD {ins-AV-04}.
ins-AV-06 R GSE Design Description X X Based on Annex G and Annex K of ECSS-E-ST-10C.
ins-AV-07 I
GSE Verification and
Calibration Reports
X
As needed;
Based on Annex F and Annex K of ECSS-E-ST-10-02C.
ins-AV-08 R
Test Facilities Utilisation
and Instrument
Transportation Plan
X X X X
Proposal version for kick-off;
As per DRD {ins-AV-08}.
ins-AV-16 A
Inputs to Launch Site
Operations Plan
X X X
To be finalised at satellite FAR (for PFM) or PSR (for
recurrent satellites).
ins-AV-17 R
Inputs to Launch Site
Operations Procedures
X X
To be finalised at satellite FAR (for PFM) or PSR (for
recurrent satellites).
ins-AV-19 A
Inputs to Ground
Operations Handling
Constraints
X X X
ins-AV-21 R
Long Term Storage
Procedures
X PSR
Refer to {ins-SS-32}; To be fully reviewed at PSR of
each satellite prior to entering long-term storage;
As per DRD {ins-AV-21}.
ins-AV-22 A
Inputs to Long Term
Storage Facilities
Requirements Document
X X As per Annex A of ECSS-E-ST-10-06C.
ins-AV-23 A
Instrument De-storage
Verification and Test Plan
X X PSR
To be fully reviewed at PSR of each satellite prior to
entering long-term storage;
As per DRD {ins-AV-23}.


Page : 27/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
11 INSTRUMENT PRODUCT ASSURANCE
DRL
Reference
CAT Instrument Product
Assurance
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-PA-01 A
Product Assurance &
Safety Plan
X X X As per DRD {ins-PA-01}.
ins-PA-02 A
Subcontractors PA
Requirements
X X X As per DRD {ins-PA-02}.
ins-PA-03 R Audit Plan X X X As per DRD {ins-PA-03}.
ins-PA-04 R
Audit Checklists and
Reports
X
As per DRD {ins-PA-04};
As available.
ins-PA-05 R Critical Items List X X X X X As per ECSS-Q-ST-10-04C, Annex A.
ins-PA-06 A/R
Non Conformance
Reports
X X X To be available on-line on the NCTS database.
ins-PA-07 R NCR Status List X X X As per ECSS-Q-ST-10-09C, Annex B.
ins-PA-08 R Qualification Status List X X X X As per ECSS-Q-ST-10C, Annex B.
ins-PA-09 R MIP/KIP List X X As per DRD {ins-PA-09}.
ins-PA-10 R Alert Status List X X X X As per DRD {ins-PA-10}.
ins-PA-11 R
End Item Data Packages
(EIDP)
X
To be provided together with each physical item
delivered (i.e. STM, EM, PFM, FMs, GSE, etc.);
As per ECSS-Q-ST-20C, Annex B.
ins-PA-12 R Long Lead Items List X X X As per DRD {ins-PA-12}.
ins-PA-13 A
Cleanliness and
Contamination Control
Plan (C&CCP)
X X X As per ECSS-Q-ST-70-01C, Annex B.
ins-PA-14 A
Cleanliness
Requirements
Specification (CRS)
X X X As per ECSS-Q-ST-70-01C, Annex A.
ins-PA-15 R
Reliability and
Availability Prediction
Report
X X X X X As per ECSS-Q-ST-30C, Annex E.


Page : 28/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Product
Assurance
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-PA-16 R FMEA Report X X X X X
As per ECSS-Q-ST-30-02C, Annex A (including
Annexes B, C and D).
ins-PA-17 R Safety Data Package X X X X
As per launch authority requirements;
Including ECSS-Q-ST-40C Annex C+D.
ins-PA-18 R
FDIR Implementation
Report
X X X X As per ECSS-Q-ST-30C, Annex F.
ins-PA-19 R
Worst Case Analysis
Report
X X X As per ECSS-Q-ST-30C, Annex J.
ins-PA-20 A
Parts Approval
Document (PAD)
X
As per ECSS-Q-ST-60C, Rev.1, Annex D;
As required.
ins-PA-21 R
Declared Components
List (DCL)
X X X X As per ECSS-Q-ST-60C, Rev.1, Annex B.
ins-PA-22 R
Radiation Analysis and
test Report
X X X As per ECSS-Q-ST-70-06C, Rev.1, Annex C.
ins-PA-23 R
Parts Derating Analysis
Reports
X X X As per DRD {ins-PA-23}.
ins-PA-24 A Request For Approval X
As per ECSS-Q-ST-70C, Annex D;
As required.
ins-PA-25 R
Declared Mechanical
Parts List (DMPL)
X X X X As per ECSS-Q-ST-70C, Annex B.
ins-PA-26 R
Declared Material List
(DML)
X X X X As per ECSS-Q-ST-70C, Annex A.
ins-PA-27 R
Declared Process List
(DPL)
X X X X As per ECSS-Q-ST-70C, Annex C.
ins-PA-28 R
Software Maintenance
File
X X X X As per DRD {ins-PA-28}.
ins-PA-29 R
Software Criticality
Analysis Report
X X X As per DRD {ins-PA-29}.


Page : 29/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Product
Assurance
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-PA-30 R
Software Product
Assurance Milestone
Report (SPAMR)
X X X X X As per ECSS-Q-ST-80C, Annex C.
ins-PA-31 A
Software Product
Assurance Plan
X X X As per ECSS-Q-ST-80C, Annex B.
ins-PA-32 A/R MIP/KIP Report X
As per DRD {ins-PA-32};
As available.
ins-PA-33 A
Certificate of
Conformity
X X As per ECSS-Q-ST-20C, Annex D.
ins-PA-34 A
Component Control
Plan
X X X As per ECSS-Q-ST-60C, Rev1, Annex A.
ins-PA-35 R Logbook X X As per ECSS-Q-ST-20C, Annex C.
ins-PA-36 A OTS Item List X X As per DRD {ins-PA-36}.
ins-PA-37 R OTS Suitability File X X X As per DRD {ins-PA-37}.
ins-PA-38 R
Declared Software Tool
List
X X X X As per DRD {ins-PA-38}.
ins-PA-40 R
ASIC and FPGA Control
Plan

X
++
## According to ECSS-Q-ST-60-02C Annex A.
ins-PA-41 I
ASIC and FPGA
Development Plan

X
++
## According to ECSS-Q-ST-60-02C Annex B.
ins-PA-42 R
ASIC and FPGA
Requirements
Specification

X
++
## According to ECSS-Q-ST-60-02C Annex C.
ins-PA-43 I
ASIC and FPGA
Verification Plan

++
(RTL
level)

##

(Gate
level)
According to ECSS-Q-ST-60-02C Annex E.
ins-PA-44 R
ASIC and FPGA
Verification Report

++
(RTL
level)

##

(Gate
level)
According to ECSS-Q-ST-60-02C.


Page : 30/30
Document: MOS-LI-ESA-INS-0436
Issue : 1.0
Date : 17/07/2012
ESA UNCLASSIFIED For Official Use
DRL
Reference
CAT Instrument Product
Assurance
SRR PDR C/D
K.O.
CDR QR AR SIOVR Remarks
ins-PA-45 I
ASIC and FPGA
Validation Plan
## According to ECSS-Q-ST-60-02C Annex F.
ins-PA-46 R
ASIC and FPGA
Validation Report

X

According to ECSS-Q-ST-60-02C.
ins-PA-47 R
ASIC and FPGA Risk
Assessment and
Feasibility Plan

X
++
According to ECSS-Q-ST-60-02C Annex D.
ins-PA-48 R
Traceability Matrix of
ASIC and FPGA
Requirements
++ ##
ins-PA-49 R
ASIC and FPGA Burn-in
Procedure
X Also to be delivered with PAD sheet release.
ins-PA-50 R
ASIC and FPGA Post
Burn-in Report
X
ins-PA-51 I
Experience Summary
Report
X
X

X As per ECSS-Q-ST-60-02C, Annex I.

Notes: Where ++, ##, marks are used with respect to ASIC/FPGA documents, it means that documents shall be delivered during the
ASIC/FPGA development reviews; in some cases, these documents shall be delivered in addition to the delivery required for the
instrument level review (X mark ):
++ documents shall be supplied as part of data package for ASIC/FPGA SRR/PDR (these reviews could be combined if agreed by the
Customer);
## documents shall be supplied as part of data package for ASIC/FPGA DDR/CDR;
documents shall be supplied as part of data package for ASIC/FPGA QR (review could be combined with instrument level QR if
agreed by the Customer).




End of Document

Potrebbero piacerti anche