1 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
OPIM 5894 MANAGING ID PROJECTS
FINAL EXAM (April 2014) Instructor: Dr. M. Diaby
YOUR NAME: Venkata Vijayanarayana Varanasi
YOUR STUDENT NUMBER: 2094711
The take-home examination question paper has 10 pages (including the appendices) and contains 6 problems. The exam will count 20% towards the course average. One point out of this will be deducted for each hour the exam is late.
I certify that the work I have submitted is my own work and that I have not collaborated and discussed with any other students on this examination
Signed: _________V. V. Varanasi_____________________ Date: __04.07.2014____
2 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
Question 1: Project implementation life cycle (10 points)
You are an international consultant specializing in the management of development projects. The government of a developing country has commissioned your firm to assist in the development of a standard project implementation life cycle. The government has developed a draft of a project implementation life cycle that has 26 steps. You are to meet with several of your colleagues to review the governments latest draft and to suggest revisions in the sequence of the suggested steps. This draft just arrived by FAX, and you need to review the draft before you meet with the group.Provide the sequence of the 26 steps, starting with 1 for the first step and ending with 26 for the last step. Write your ranking in the third column on the worksheet.
Step Step description Ranking
ID
A. Develop work breakdown structure (WBS) 11
B. Generate a list of activities and assign responsibility 7
C. Replan and reschedule as required 17
D. Establish functional personnel qualifications 4
E. Organize procurement for services, equipment, and works 19
F. Review WBS costs with each functional manager 13
G. Measure progress 24
H. Develop a plan to cope with potential problems caused by actors
And 14
I. Develop detailed schedules 15
J. Determine resource requirements 3
K. Clarify and refine the project's key parameters, objectives, 1
and scope
L. Coordinate ongoing activities 22
M. Close out functional work orders 21
N. Conduct endofproject audit 26
O. Negotiate for qualified functional personnel 5
P. Prepare final report 25
Q. Modify the schedule accordingly to meet time and resource
Constraints 16
R. Clarify organizational relationships, roles, and responsibilities 6
S. Authorize departments to begin work 20
T. Develop linear responsibility chart 10
U. Estimate the duration of each activity and establish the 8
sequence of activities
V. Obtain management final approval of project schedule, budget and
resource plans 18
W. Develop gross schedule 9
X. Price out WBS 12
Y. Identify relevant actors and factors 2
Z. Determine means for measuring progress 23
3 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
3 | P a g e
Question 2: Project initiation and setting up (25 points)
Read the minicase titled Good Health Hospital Elective Admissions Project provided in Appendix A of this document and provide answers to the following questions:
(a) What is the problem or opportunity motivating this project? (2 point)
Answer: The main problem / objective for this project is to improve the patient admission process and make it smoother and on par with other similar sized hospitals.
(b) Develop the goals and objectives for the project. (3 point)
Answer: The following goals / objectives can be put for the project: Improvement in the elective patient admission process Reduce the admission wait times to as less as 20mins on par with the best similar- sized hospitals Address concerns of the nursing, admittance and the environment(services) departments regarding the admissions process Improve the hospital operational performance especially in admissions so that the Joint Commission on Accreditation of Healthcare Organizations certification can be obtained easily To finish this project in 6 month time period
(c) Identify the project boundaries (i.e., where does the project start and end)? (3 points)
Answer: The project has to be finished in 6 month time period well before the inspection of the Joint Commission on Accreditation of Healthcare Organizations for accreditation. The inspection is going to happen in the next calendar year. (d) Who are the stakeholders for this project? (3 points)
Answer: The following are the stakeholders for this project: THE CEO of the Hospital The individual department managers( nursing, admittance and environment) The elective patients who chose this hospital for getting health services The families of the patients who have to attend to the patients The nurses, physicians, etc who attend the patient
(e) Create a maximum of 10 project metrics for this project (3 points).
Answer: The following are the project metrics for this project as given below: 1) The project duration should not extend 6 months 2) The admissions time should not be more than 20 mins for each elective patient 3) A small budget of $2000 has been allocated which should not be exceeded. 4) Each project team member will allocate 2 hrs per day to the project over their regular job duties 5) Patient Intake should be streamlined by no data missing on their forms
(f) Identify a preliminary set of project deliverables. For each deliverable you identify, determine what additional information the team may need to precisely
4 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
specify the deliverable (in other words, what questions does your team need to have answered to clearly describe each deliverable? (5 points).
Answer: The following are the preliminary set of project deliverables: (a) Elective patient forms should be fully filled by the time they reach nurses table. So a check to perform this should be in place. The question for the team would be that who performs this check before the nurses division receive the patient and who will be receiving the patient first? (b) The schedule of elective patients arrival should be controlled by allocating a certain time period when they can arrive and get admitted. This has to be done at the appointment booking time itself. The question for this deliverable is that who shall be doing it during the appointment booking and who is in charge of the schedule maintenance? (c) To showcase operations improvement by improving the patient admission time in the hospital to the Joint Commission on Accreditation of Healthcare Organizations committee. The question for this deliverable is that who shall be made in charge of this process and who will guide the whole project for the same? (d) Streamlining and reduction in the patient admission time to 20 mins. The question will be who is going to decide on this project metric and who will be the process owner for this. Who will be in charge of this after the project is handed over and regularized into daily operations?
(g) Develop a plan for communicating with Dave Wait, the CEO (use the model shown on slides #6061 of the project initiation lecture notes). (3 points)
Responsible for creating this communication: Project lead of the Elective Admissions Project with input from team Person Responsible for sending this communication: Team Leader / Project Lead of the Elective Admissions Project Dave Wait, CEO of the Good Health Hospital High-level information about the project progress, the budget utilized and the schedule. Knowledge of any issues problems and their proposed solutions that may require his authorization or intervention to resolve Every week and monthly Email for weekly updates and monthly face to face meeting with elective admissions project steering team. Provide minutes of the meeting and agenda. Stake Holder What does this Person or Group Frequency of Medium Elective Admissions Project Project Management Office Project at Good Health Hospital
5 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
(h) Critique the composition of the team as described in the project background information in terms of area representation, size, and time available. Why did the Hospital Process Improvement Steering Committee add a physician to the team? Do you agree with this decision? Should a patient be added to the team? Why or why not? What else might you want to know about each of these team members? (3 points)
Answer: The team consists of the admitting manager, two admission clerks, a physician, two nurses, and an environmental services (i.e., housekeeping) supervisor. As individuals who work in or directly with admitting, you know the critical role the admitting process plays in smooth hospital operations. The admitting function, in fact, is a hub of activity that affects almost all other hospital activities and departments. The composition of the team is well represented by the concerned departments however, there are no members of the other important departments in this project team like from finance who shall discuss the costs involved in the whole project and the subsequent changes to be made. It doesnt involve the IT department personnel who shall be responsible for making the necessary software changes to streamline the appointment and the admissions process and also make certain elements of the admission like the form filling less tedious and automated so that no errors and unfilled information is left. Also there are no representation from the senior management side which will show that the management is quite strongly backing this project initiative and also there is no representation from the patients side.
Adding a physician is quite valuable to this team as he shall be able to guide on the technical aspects of the various diseases for which each patient gets admitted like the duration of treatment, what information needs to be gathered, what can be the expected cost etc. We would also like to add a patients representative to highlight the real difficulties they face during the admissions process and how it can be eliminated and it will give a firsthand information on customer satisfaction to the team.
6 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
Question 3: Project charter (15 points)
Review the sample project charter shown in Appendix B o f t h i s d o c u m e n t for a development project. Discuss any weaknesses or omissions you see in the charter and recommend changes you would propose.
Answer: The sample project charter should be given as below as taught from the class notes: I have recreated the whole project charter again including points that have been left behind. As such the given charter is very strong very few omissions and weaknesses. It is given very clear and concise manner and gives the roles and responsibilities very effectively. Also the various functions and duties have been well defined. However, there is no indication of the project timeline and when the project is expected. This would be greatly helpful in creating a proper schedule and tracking and monitoring the progress of the project. The Project deadline can be defined with the help of this and can be useful in having a proper project closure. Also there should be a mention of the project steering board which helps in ensuring all the stakeholders who go through the project charter that the project is well represented and well backed up by the senior management team. A brief project objective / goal statement and also the indications of possible risk are included in the project charter to give a high level understanding of the whole project. Many a companies also include the project scope or the project priority matrix along with the project benefits for the understanding of the project sponsor and the project team members in addition to the senior and top management team. Overall responsibility of the Project Manager The project manager (PM) is responsible for the overall completion of the different components of the development project, in a coordinated manner, within the cost, time, and quality parameters defined for the project from time to time. The PM ensures that the overall project and component plans, schedules, and budgets fit together and will accomplish the project's objectives. The PM also ensures coordinated action on all components (including follow-up on decisions of relevant studies) for the effective utilization of the programs supported by the development project.
Relationships The PM reports directly to the minister and interacts directly with other government and nongovernmental
7 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
agencies as needed to follow-up and resolve problems affecting the project. The PM is supported by the project management unit (PMU) staff, which assists in the coordination and monitoring as well as the procurement and accounting activities associated with project management. The PM and all the component managers constitute the project team (PT), which will coordinate the work programs and will monitor overall project progress. Main Functions a. Project Implementation Coordination Role Regarding objectives and plans Clarify objectives. Prepare plans, schedules, and budgets. Arrange commitment of resources. Approve all changes in plans and scope. Chair periodic PT meetings (preferably monthly), organized by the PM, for implementation coordination, including taking operational decisions that flow from review and monitoring meetings on subjects, such as delays and plans to make up lost time, cost overruns, progress according to linkages defined between components, and so forth. Follow-up on previous decisions in review and monitoring meetings of PT. Direct coordination with individual component managers (CMs).
b. Management of PMU
Recruit and hire staff.
Supervise the management of the computerized database for the project monitoring system
Supervise monitoring and evaluation (PMS).
Set up control system to measure progress versus plan for schedule and budget. Prepare budget and financial and schedule reports. Submit regular reports to ILA and the government.
Develop and maintain project files.
Manage the procurement function through the procurement officer.
Manage the project accounts, audits, and so forth.
Arrange training.
8 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
c. The Role of the PMU
The PMU will provide the PM and CMs with the following services:
Coordination and monitoring Project and procurement accounting Procurement for the identified components of the overall project Maintenance of the computerized PMS, measuring progress versus plan for schedule, cost, and performance and issuing reports and revised plans as necessary and when directed by the PM.
Delegation of Authority The day to day management of the affairs of the project are directly dealt with by the project manager in coordination with the CMs as needed. Similarly, the PM seeks approval and guidance from the minister from time and time as necessary.
The CMs have full authority to take all operational decision for their components within the bounds of the controls of their own ministries/agencies.
9 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
Question 4 Risk process management (15 points)
A project team at Scanda Pharmaceutical is using FMEA to assess risks for a celebration to be held when a major project milestone, completion of clinical trials for a promising new drug in a country where the disease prevalent, is completed. The celebration will be held on the gardens of Scandas headquarters in Bergen, Norway. Project team members, top company officials, and representatives from major customer groups will attend the event, which will include a gourmet meal, elaborate decorations, speeches, and live entertainment. The team responsible for planning the event decided to use FMEA, and members generated a long list of risks, five of which are shown in the matrix below. Each team member had the opportunity to give his or her ratings for these risks, which are shown in the matrix following the risk list. 4 | P a g e
Top Five Ri.sks
Effect on the Project as It Is
Risk Currently Planned Possible Causes
1. Invited VIP guests Major embarrassment to Invitations sent to incorrect
don't attend the company. Loss of marketing addresses. Invitations don't
event. opportunity. convey a sense of the impor-
tance of the event.
2. Guests get food Bad image for the company. Food spoils in hot weather.
poisoning. Could hurt sales. Careless caterer.
3. Clinical trials prove to Bad publicity in the market. Researchers giving falsely
be unsuccessful but it Delay in getting to market. optimistic reports during
is too late to cancel Stock analysts produce nega- the trials. Error in data
the event. tive reports. analysis not caught soon
enough. Event scheduled
prematurely.
4. Another major event hosted by a competi- tor is scheduled for the same day. 5. Major rainstorm.
Dilution of publicity: Some VIPs attend competitor's event.
Not possible to hold the event outdoors wit hout everyone getting wet.
Insufficient investigation of potential conflicts. Intentional move on part of competitor. Atmospheric conditions outside the control of the team. Weathe r patterns characteristic of the time of year
10 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
FMEA Ratings for
Detection Individual
Milestone Celebration
Risk# Rater# Severity Likelihood Difficulty RPN
1 Evelyn 9 3 4 108
Arve 8 5 6 240
Kyrre 6 6 2 72
Sindre 3 6 3 54
2 Evelyn 10 2 7 140
Arve 9 4 5 180
Kyrre 6 4 3 72
Sindre 8 5 2 80
3 Evelyn 10 4 6 240
Arve 9 4 9 324
Kyrre 7 2 4 56
Sindre 8 5 3 120
4 Evelyn 8 5 1 40
Arve 7 6 1 42
Kyrre 9 3 4 81
Sindre 5 8 1 40
5 Evelyn 10 5 2 100
Arve 9 6 1 54
Kyrre 5 3 3 45
Sindre 8 8 2 128
11 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
a. Calculate individual and aggregated mean RPN scores for each of the five risks. (3 points) Ans: The individual RPN, Aggregate RPN and the mean RPN have been calculated in the table below: Risk# Rater# Severity Likelihood Difficulty Individual RPN Aggregate RPN Mean RPN 1 Evelyn 9 3 4 108 474 118.5 Arve 8 5 6 240 Kyrre 6 6 2 72 Sindre 3 6 3 54 2 Evelyn 10 2 7 140 472 118 Arve 9 4 5 180 Kyrre 6 4 3 72 Sindre 8 5 2 80 3 Evelyn 10 4 6 240 740 185 Arve 9 4 9 324 Kyrre 7 2 4 56 Sindre 8 5 3 120 4 Evelyn 8 5 1 40 230 57.5 Arve 7 6 1 42 Kyrre 9 3 4 108 Sindre 5 8 1 40 5 Evelyn 10 5 2 100 327 81.75 Arve 9 6 1 54 Kyrre 5 3 3 45 Sindre 8 8 2 128
b. Based on RPN scores, identify the risks most relevant for further consideration. Would you completely trust the numbers, or would you seek further discussion or investigation? Why? (4 points)
Answer: Based on the above scores, we can identify that risk number 3 is the highest priority and most relevant for further consideration as it has the highest aggregate RPN and the Mean RPN amongst all the risk raters.
However, I would definitely like to have a further discussion or investigation as many of the risk raters have shown a lot of variability in the their ratings for the same rating. For eg. In risk 3, the range of RPN is from 56 to 324 which is a huge variation. Other risks also have similar variations. Hence a further discussion will narrow down the variations and let us focus on the most relevant risks better.
12 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
c. For the three most relevant risks, describe the actions you would take. For each action you recommend, identify which of the four unfavorable uncertainty action categories best describes what you are recommending. (4 points)
Answer: From the above table, we can clearly see that risk Number 3, risk number 1 and risk number 2 have the highest relevancy in that order respectively based on their aggregate RPN. For risk 3: Risk Uncertainty and Response( Mitigate) 3. Clinical trials prove to be unsuccessful but it is too late to cancel The event. Bad publicity in the market. Delay in getting to market. Stock analysts produce negative reports. Researchers giving falsely optimistic reports during the trials. Error in data analysis not caught soon enough. Event scheduled This is a technical uncertainty action category and hence the action taken here can be either to re-launch the studies or training of the researchers against to avoid future such occurrences. prematurely.
For Risk 1: Risk Uncertainty and Response ( Mitigate) 1. Invited VIP guests don't attend the event. Major embarrassment to company. Loss of marketing Opportunity. Invitations sent to incorrect addresses. Invitations don't convey a sense of the importance of the event. This is a Customer oriented uncertainty and in this case the action taken can be to get marketing people to get commitments about the VIPs and make them endorse the product to associate the product and VIP hence making them participate.
For Risk 2: Risk Uncertainty and Response (Avoid) 2. Guests get food Bad image for the company. Food spoils in hot weather. This is a contract uncertainty on part of caterer. Hence food inspection needs to be done and damages claimed.
Poisoning. Could hurt sales. Careless caterer.
d. Prepare a risk-response matrix. (4 points)
Answer: From the given details we have to create a risk response matrix and allocate responsibility for each action.
For risk number three which is the highest risk we can use the response of mitigating the risk and the action needs to undertake by the Clinical trial Manager who is responsible for the overall authenticity and results of the clinical trial
13 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
For risk number 1 where important guests are not arriving we can use the response of mitigating the risk by keeping a backup list of celebrities and VIPs who shall be invited incase the primary guests dont turn up and also there needs to be response risk avoidance by asking the VIPs to endorse the project and their endorsements be prominently displayed during the launch which will ensure the other guests about their association with the product to be launched.
For the risk number 2 where the food can be spoiled due to carelessness can be avoided by taking insurance policy of the event success and also keeping a medical personnel as backup for any eventuality. Also the food needs to be thoroughly inspected before the event begins.
From the above diagram of a risk response matrix we can see that Risk number 3 has the highest risk impact and hence it would be in the red zone. Similarly Risk number 1 and 2 will have medium impacts and hence they will be in the yellow boxes and the risk number 4 and 5 with low risk consequences will be in the moderate 2 improbable C green zones. The risk response matrix is a very easy pictorial manner of depicting risk and gives a visual analysis of the risks and their likelihood along with consequences. The risk response matrix and the risk responses have been answered in the previous section of the answer where the contingency answers have been elucidated.
14 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
Question 5: Procurement of works (15 points)
What are the appropriate type of sourcing and contracting for each of the following situations?
a. Provision of 20 timber roof girders for a new school assembly hall. Assume that the design of the girders is complete. (3 points)
Answer: This has to be a Cost reimbursement contract as it is the most common form of contract where the usual project costs are usually fixed and in this case the girders are like a raw material for the eventual construction.
b. Construction of a simple, single-lane earth road from a main highway to serve a rural community. The alignment has been laid out on the site, and it follows a watershed. Thus, there is no need for bridges or culverts. (3 points)
This has to be a local communitys contract as the following are the benefits: Enhances the sense of ownership and commitment to maintenance Increases speed and economy Increases the skills and capacity of the community Generates local employment
c. Removal of material from a landslide. A road has been blocked, and essential traffic and emergency vehicles cannot pass. Alternative routing does not exist. (3 points)
Answer: This has to be undertaken by way of a Department Works Contract with a cost reimbursement like a Target contract. Usually by the Ministry of Roads of the government as it is a social emergency and has to be done on a priority basis and no bidding etc. can be done to avoid delay in implementation. Also cost is not a factor and it will be supervised. Local communities contract can be subcontracted for faster speed and economy.
d. Leveling of a tract of land to be used in a new agricultural scheme. The existing land levels and the proposed levels have been accurately determined. (3 points)
Answer: This has to be procurement of works through a measured Output contract
e. Design and construction of a manufacturing plant to produce specified grades and quantities of fertilizer. (3 points)
This has to be a turnkey project contract because of the following: Single-point responsibility Savings in cost Savings in time Lump-sum contract Design by contractor Lump-sum contract Contractor obligation
15 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
Question 6: Procurement of services (20 points)
According to the latest census, the city, Metropolis, has a rapidly growing population, currently estimated at 5 million. Only one-third of the population has access to piped water provided by the Municipal Water Authority; the remainder draws water from shallow, protected wells or simply from polluted surface streams. The population is routinely advised to boil all water used for drinking and cooking. The city is built on flat terrain close to the sea. A system of canals from up-country could possibly bring in more water for the city. The distribution system has not been thoroughly studied. The authority distributes piped water in rotation for a few hours each day to the districts of the city. Water is also bought from vendors, but the cost of so doing amounts to about 20 percent of the earnings of the low-income families who make up the greater part of the population. In spite of universal metering, the water authority believes that unaccounted-for water may be as high as 60 percent of the total, but it does not have the resources to investigate the causes. Tariff collections, which are beginning rapidly to fall into arrears, cover only a small proportion of the cost of production. The city has a core sewer system that serves only about 20 percent of the population; the rest of the city relies mostly on unsanitary methods of excreta disposal. Sewage is currently evacuated from the city in open canals. The city intends to provide a potable water supply and adequate sanitation for the entire city and is about to seek consultant expertise to carry out a feasibility study that would examine the options (technical, environmental, economic, financial, social, and institutional) open to it for providing these services. 6 | P a g e
Your assignment:
1. Consider all possible sources of consulting expertise and determine which would be the most appropriate for executing the feasibility study. (5 points) Answer: There are various sources of Consultants that are available for any procurement of services. Generally, the most appropriate source selection depends upon a variety of factors like expertise, cost, availability, local knowledge, past experience of similar projects, ability to handle such projects, knowledge of the field in which the study has to be conducted etc. Some of the most common sources of consulting expertise are as below: Private partnerships Public companies Government-owned firms Public sector and nonprofit organizations Universities and institutes Law, accounting, and engineering firms Individuals Out of these sources, the most appropriate one for our case above would be private partnerships which have a good background in conducting eco-engineering projects and also they can hire some local geologists for this project for the local knowledge. There work will be very professional and thorough.
2. Write an outline of the TOR for the study. In the TOR, the consultants should be required to provide specific information on both the present condition of, and future needs for,
16 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
potable water and sanitation. The consultants should be instructed, among other matters, that their report would serve as a basis for
(a) Selecting appropriate levels of service, or a mix of service levels (b) Evaluating future water needs and possible additional sources of supply
(c) Reviewing options for financing water supply and sanitation services and for taking measures to improve the operating efficiency of the water authority.
(15 points) Answer: The TOR (terms of reference) is usually used to describe the purpose roles and structures of projects, consultants hired to conduct studies, the working groups, any reference groups and committees. They are guidelines for the way the individuals or a group members will work with each other and are usually the first task undertaken by the client as it gives the consultant with a clear definition of the scope of work and the expected reports. They make a written basis for making decisions, confirming a common understanding between the parties involved and how they shall work together. A well prepared TOR is very comprehensive, detailed and unambiguous with clearly stated objectives and determination of the scope. For the above case, a sample TOR can be provided as given below: Background (Introduction or Preamble): The city of Metropolis has a rapidly growing population with the current population being about 5 million. Most of the citizens currently face an acute shortage of water supply and whatever supply is available is much polluted. The distribution system has never been studied properly and there is a lack of accountability of the water supplied. The tariff collections are rapidly dipping and are not covering the cost of production. The citys sewer system only serves 20% of the population and that too through open canals. The city intends to provide a potable water supply and adequate sanitation for the entire city and hence wants to conduct a feasibility study for the same. Objectives (What: Specific Outputs) : The city wants to seek consultant expertise to carry out a feasibility study that would examine the options (technical, environmental, economic, financial, social, and institutional) and have the following major objectives fulfilled in the study: 1. Selecting appropriate levels of service, or a mix of service levels 2. Evaluating future water needs and possible additional sources of supply 3. Reviewing options for financing water supply and sanitation services and for taking measures to improve the operating efficiency of the water authority. 4. The water distribution system should be accounted for and the ways to improve tariff collection 5. The sewer system should be modernized and elimination of the open canal system. 6. Water supply and sewer system amenities should be available for the whole population
17 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
7. These amenities should be planned in such a way that they should account for the rapidly growing population and be adequate in the future as well. Scope (How): The hired consultant enterprise should do a ground study involving the technical, environmental, economic, financial, social and institutional aspects and give a feasibility report. The team doing the study will have to spend their time on the site at least 5 days a week and will have to provide their report within 3 months. All necessary equipment and personnel will have to be sourced by the team themselves. Facilities and access to all the required information including the transportation will be provided by the city government. Requirements for training and skill transfer: Since majority of the team will be involving foreign nationals for their expertise, it would be advisable for the team to hire local personnel for ease of communication, knowledge of geology and geography, and dealing with the local officials. Such people will have to be trained through the study such that further such studies can be undertaken indigenously. All the requirements for training and skills and the important intelligence data will have to be deposited with the city at the end of the study. Reporting and approval procedures: A thorough final report fulfilling all the above objectives will have to be presented at the end of the study. All necessary access to information and locations will be provided. Necessary approvals will be provided on a need basis as required and will have to be obtained prior to commissioning of the feasibility study. Clients contribution: The client, in this case the city government, shall provide a lump sum remuneration at the end of the feasibility study upon being presented the final report. Also it will provided all the necessary transportation to the various locations and access. Local talent can be provided if requested by the team where necessary.
18 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
7 | P a g e
APPENDIX A
Good Health Hospital Elective Admissions Project
Project Background
Congratulations! The Good Health Hospital Process Improvement Steering Committee has approved your request to study and improve the admitting process for elective hospital patients. (Elective patients are non-urgent, non-emergency patients for whom hospital admission reservations are made in advance.) Your study has attracted the attention of Dave Wait, chief executive officer of the hospital. Recent customer survey data reveal that "long waits in elective admissions" are a major source of customer dissatisfaction. Dave regularly reviews the minutes of the steering committee and has long felt the elective admissions process was a key candidate for improvement. Apparently, Dave has been the recipient of numerous complaints from physicians and their elective patients about the long waits in admissions. He has sent your team a brief note of encouragement (see below). Good Health Hospital, located in a rapidly growing semi-metropolitan area of northern California, is a 250-bed general hospital helping serve the medical needs of a district with an approximate population of 100,000 people. Opened in 1972, Good Health has as its mission to provide quality health care serving the inpatient disease and injury needs of the Santa Rosa community. Your team consists of the admitting manager, two admission clerks, a physician, two nurses, and an environmental services (i.e., housekeeping) supervisor. As individuals who work in or directly with admitting, you know the critical role the admitting process plays in smooth hospital operations. The admitting function, in fact, is a hub of activity that affects almost all other hospital activities and departments. Your project began as the result of casual lunchtime conversation among the managers of nursing, environmental services, and admitting. In recent brainstorming meetings with their individual staffs, these three had discovered that problems in processing elective patients into the hospital were particularly frustrating to each area, although for different reasons. Nursing complained that patient records that accompanied the patients from admitting were incomplete. Patients also arrived at nurse stations unexpectedly. In addition, according to nurses, elective patients seemed to arrive at the most inconvenient times. Environmental services complained that everything is always in a rush. Admitting department personnel are frustrated because rooms seem never to be available. Patients and their loved ones get anxious and upset when they have to wait and, as the first point of contact in the hospital, admitting personnel must interface directly with dissatisfied customers. The admitting department, in fact, had recently gathered data on average elective patient wait time and had found it to be over an hour. They defined patient wait time as the elapsed time between a patients arrival at the hospital reception desk and his or her arrival at either a room or one of the hospital departments for tests or procedures. Admitting personnel also experienced frustration because parts of their jobs (for example, verifying insurance and tracking down missing test results) took lots of time. And, in some instances, these tasks had to be completed the day the patient arrived for a hospital stay. Occasionally, admitting personnel had to gather additional information from the physicians offices and sometimes patients had to wait in admitting because no escorts were available to transport them to a room or test- procedure location. In follow-up conversations, the admitting, nursing, and environmental services
19 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
staffs agreed to collaborate on a joint improvement project; they were all involved in the process in one way or another, so a cross-departmental effort seemed to make sense. The three managers submitted a request, with a list of proposed team members, to the hospital Process Improvement Steering Committee. The committee approved the project, adding a physician to the proposed team. Everyone agreed the problem was an important one. Improving this process should increase external customer satisfaction and have a positive impact on internal hospital operations as well.
20 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
8 | P a g e
Letter from the CEO - MEMORANDUM
TO: Elective admissions process improvement team FROM: Dave Wait, CEO
I am pleased to learn your group will be tackling the important process of elective admissions. As you may know, Good Health's increasing occupancy rate (over 85%) coupled with our successful efforts to reduce average lengths of stay, has resulted in an increasing number of admissions. I am concerned by physician, patient, and nurse complaints about the excessive time required to admit an elective patient. I understand it has taken some patients as long as two hours to be admitted. I am especially disturbed that, in a recent customer satisfaction survey, the number one most frequent source of dissatisfaction among elective patients was "long wait time in admissions." Increasing patient satisfaction is one of several key initiatives at Good Health, and improving the elective admissions process will certainly contribute to achieving this important strategic objective. Because we have some control over the schedule of elective admissions, I am confident your team will be able to significantly reduce wait times. At recent Directions in Health Care CEO Symposium, I learned that the best hospitals in our size and occupancy category are able to process incoming elective admissions in about 20 minutes. I am disturbed that we are nowhere near that figure. However, it is critical that, in reducing elective admission times, we do not compromise the quality of admission service. The information admitting provides to the rest of the hospital must remain timely, accurate, and complete. Finally, you may be aware that we expect a visit from the Joint Commission on Accreditation of Healthcare Organizations sometime next calendar year. Because of their interest in efforts to improve operational performance, it would be ideal if you could complete your work and be able to demonstrate some real improvement in this area within six months. Doing so would provide us an opportunity to showcase a successful improvement effort.
I have encouraged your managers to provide you with the time you need estimated at an average of two hours a week for the duration of the project to address this important problem. In addition, a small budget of $2,000 is available to the team to cover expenses associated with meetings, data gathering, benchmarking, and the like. I wish you the best of luck in your efforts. I hope you will keep me informed as the project unfolds, and I look forward to reading your final report and recommendations, and to hearing your team's final presentation.
21 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
9 | P a g e
APPENDIX B
Development Project: Roles and Responsibility of the Project Manager and the Project Management Unit
Overall responsibility of the Project Manager
The project manager (PM) is responsible for the overall completion of the different components of the development project, in a coordinated manner, within the cost, time, and quality parameters defined for the project from time to time. The PM ensures that the overall project and component plans, schedules, and budgets fit together and will accomplish the project's objectives. The PM also ensures coordinated action on all components (including follow-up on decisions of relevant studies) for the effective utilization of the programs supported by the development project.
Relationships
The PM reports directly to the minister and interacts directly with other government and nongovernmental agencies as needed to follow-up and resolve problems affecting the project. The PM is supported by the project management unit (PMU) staff, which assists in the coordination and monitoring as well as the procurement and accounting activities associated with project management.
The PM and all the component managers constitute the project team (PT), which will coordinate the work programs and will monitor overall project progress.
Main Functions
a. Project Implementation Coordination Role (i) Regarding objectives and plans Clarify objectives. Prepare plans, schedules, and budgets. Arrange commitment of resources. Approve all changes in plans and scope. (ii) Chair periodic PT meetings (preferably monthly), organized by the PM, for implementation coordination, including taking operational decisions that flow from review and monitoring meetings on subjects, such as delays and plans to make up lost time, cost overruns, progress according to linkages defined between components, and so forth.
(iii) Follow-up on previous decisions in review and monitoring meetings of PT. Direct coordination with individual component managers (CMs).
b. Management of PMU Recruit and hire staff. (i) Supervise the management of the computerized database for the project monitoring system.
(ii) Supervise monitoring and evaluation (PMS).
22 | F i n a l E x a m : V e n k a t a V i j a y a n a r a y a n a V a r a n a s i O P I M 5 8 9 4
Set up control system to measure progress versus plan for schedule and budget. Prepare budget and financial and schedule reports. Submit regular reports to ILA and the government. Develop and maintain project files. 10 |
(iii) Manage the procurement function through the procurement officer. Manage the project accounts, audits, and so forth.
(iv) Arrange training. c. The Role of the PMU
The PMU will provide the PM and CMs with the following services: Coordination and monitoring Project and procurement accounting Procurement for the identified components of the overall project Maintenance of the computerized PMS, measuring progress versus plan for schedule, cost, and performance and issuing reports and revised plans as necessary and when directed by the PM.
Delegation of Authority
The day to day management of the affairs of the project are directly dealt with by the project manager in coordination with the CMs as needed. Similarly, the PM seeks approval and guidance from the minister from time and time as necessary.
The CMs have full authority to take all operational decision for their components within the bounds of the controls of their own ministries/agencies.