Iway Dev Consolidated Report From 1st Nov To 30 Nov 2012
Sl# Category Effort(Hrs) Effort(Days) Jira #
1 New product/feature development 0 0 0 2 Bug fix/Patches/cumulative fixes 436 54.5 16 3 Customer issues/hot track cases 8 1 1 4 Documentation 77 9.625 1 5 Maintenance 127 15.875 6 6 Meeting 34 4.25 7 Research And Analysis 65 8.125 4 8 Testing & Release 0 0 Iway Dev Consolidated Report From 1st Nov To 30 Nov 2012 Remarks Iway Dev Consolidated Report From 1st Nov To 30 Nov 2012 Sl# Resource Effort Hrs Man Days Leave Days Holidays 1 Jeyakumar 183 22.875 3 1 2 Pravin 181 22.625 #VALUE! 3 Veera 194 24.25 7 4 Susanta 189 23.625 4 Avg Effort Hrs= 186.75 Avg Man Days= 23.34375 Resource New Product Bug Fixes Document Maintenance Research ORA-678 SPO-2482 ORA-682 Pravin ORA-683 Jeyakumar SPO-696 CTN-409 ORA-680 CTN-430 ORA-681 CTN-409 CTN-424 SOC-2606 CTN-414 CTN-428 CTN-427 CTN-423 CTN-426 Veeramani SOC-6270 SOC-6249 SOC-6268 SOC-6253 SOC-6266 SOC-6269 Susanta CTN-437 CTN-420 ORA-679 SPO-2245 Jira 0 16 1 6 4 Customer Issue Jira 4 13 6 IRN- 83252553 5 28 DATE Metrics TOPIC/ISSUE STATUS 11/1/2012 Documentation CTN-420 completed 11/2/2012 Documentation CTN-420 completed 11/5/2012 Documentation CTN-420 In Progress 11/6/2012 Documentation CTN-420 In Progress 11/7/2012 Documentation CTN-420 In Progress 11/8/2012 Documentation CTN-420 In Progress 11/9/2012 Documentation CTN-420 In Progress 11/12/2012 On Leave On Leave 11/13/2012 11/14/2012 Documentation CTN-420 In Progress 11/15/2012 Documentation CTN-420 In Progress 11/16/2012 Documentation CTN-420 In Progress 11/19/2012 Documentation CTN-420 In Progress 11/20/2012 Bug fix/Patches/cumulative fixes ORA-679 In Progress 11/21/2012 Bug fix/Patches/cumulative fixes ORA-679 In Progress 11/22/2012 Bug fix/Patches/cumulative fixes ORA-679 In Progress 11/23/2012 Bug fix/Patches/cumulative fixes ORA-679 In Progress 11/26/2012 On Leave On Leave 11/27/2012 Bug fix/Patches/cumulative fixes ORA-679 In Progress 11/28/2012 Bug fix/Patches/cumulative fixes ORA-679 In Progress 11/29/2012 Bug fix/Patches/cumulative fixes ORA-679 In Progress 11/30/2012 Bug fix/Patches/cumulative fixes ORA-679 In Progress 5th Week (26th Nov - 30th Nov '12) Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) STEPS TAKEN FOR SOLUTION FILES MODIFIED (IF ANY) Summary of screen shots on Testing the Insert, Update, Query, Delete Nodes Summary of screen shots on Issues gathered (20 Issues) from Siebel- MVG Adapter Testing for Error Interaction screens for multiple insert Testing for Error Interaction screens for Update, wrong location in payload Testing for Error Interaction screens for Query, wrong location in payload Testing for Error Interaction screens for Query expression Testing for search expressions in Query node AMTEX HOLIDAY Editing QueryProcessor.java for like operator, """ Working on new build + Meeting with client 2 hrs Working on new build + Meeting with Sai Collecting additional issues on Siebel-MVG adapter Going through documents on Peoplesoft Exploring the ORA-652, history of issues, sub-tasks Connecting Target Populatinng nodes on people soft using App. Explorer Code Analysis on People soft, Source code generation from psjoa.jar Listing the Objects names using PSoftModel.java, Identified scroll levels to be commons for tables, views and triggers Read Document for peoplesoft from Oracle website, scroll level discussion with QA Team Listing the Messages and field names using PSoftModel.java Listing the Messages and field names using PSoftModel.java 5th Week (26th Nov - 30th Nov '12) Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) Project Hours spent Break time Siebel MVG 8 Siebel MVG 8 Siebel MVG 8 Siebel MVG 8 Siebel MVG 8 Siebel MVG 9 Siebel MVG 8 Siebel MVG 8 Siebel MVG 10 Siebel MVG 7 CTN-420 8 Peoplesoft 8 Peoplesoft 9 Peoplesoft 8 Peoplesoft 8 ORA-679 8 ORA-679 9 ORA-679 9 ORA-679 10 5th Week (26th Nov - 30th Nov '12) 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) DATE Metrics TOPIC/ISSUE STATUS 11/1/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/2/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/5/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/6/2012 Bug fix/Patches/cumulative fixes ORA-652 In Progress 11/7/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/8/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/9/2012 Bug fix/Patches/cumulative fixes ORA-652 In Progress 11/12/2012 Bug fix/Patches/cumulative fixes ORA-652 In Progress 11/13/2012 11/14/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/15/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/16/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/2/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/2/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/2/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/2/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/2/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) Fix has been implemented for SPO-2245 and testing in different environment is in progress. 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) 11/26/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/26/2012 Meeting Client Call Completed 11/27/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/27/2012 Meeting Client Call Completed 11/28/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/28/2012 Meeting Client Call Completed 11/29/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/29/2012 Meeting Client Call Completed 11/30/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/30/2012 Bug fix/Patches/cumulative fixes ORA-678 In Progress 11/30/2012 Meeting Client Call Completed 5th Week (26th Nov - 30th Nov '12) STEPS TAKEN FOR SOLUTION FILES MODIFIED (IF ANY) Fix implement by changing the root node from "Siebel Response" to "Response". Root Node is set from Adapter. New JIRA SPO-2482 has been created for Ora10g IBSE SOAP UI issue and the same has been assigned to you. Testing carried out in different environment and also tested the fix with BO objects and ensured fix is provided only for RPC nodes. Updated the code and the same has been checked in athttp://iwsource2/odin/projects/OEMs/projects/Chennai/Jira/SPO- 2245/iwsiebel-unified/src/com/ibi/adapter/siebelaf/XDSiebelAdapter.java Updated the JIRA with comments and assigned it back to Elvira. XDSiebelAdapter.java Analyzed the issue and discussed the same with Elvira. Understanding more about Application Designer is in progress. Requested QA to provide KT on Application Designer. Studying the Jira is in progress Analyzed the issue and discussed the same with Elvira. Understanding more about Application Designer is in progress. KT received from Ramesh team on the KT received from Ditty on installation and configuration of Application Designer. AMTEX HOLIDAY Issue reopened. decompiled the jar and noticed that provided fix was not available. Tested the latest build, ISM 6.1.000_xfoc.37233, 11/12/2012. -Test failed. Decompiled the code and found that our fix is not available. Following information was found in the MANIFEST file. Name: af Specification-Title: iWay Adapter Framework Specification-Vendor: iWay Software Specification-Version: 1.0 Build-Track: OEMs/xfoc/ADAPTERS/application/iwsiebel-mvg Build-Revision: 99089 Build-Version: xfoc Found that the Build-Track is OEMs/xfoc/ADAPTERS/application/iwsiebel- mvg. Fix need to be merged in iwsiebel-mvg for testing. Siebel Schema Analysis is in progress. Configuring the Application Designer for ISDSRV11 is in progress. Able to repro the issue with ISM as the backend. Used IIT as the application explorer. Configured the Application designer for ISDSRV11. Downloaded the documents related to peoplesoft and understanding the APIs is in progress. Downloaded the iwpeoplesoft code and went through the code and discussed the same with the team Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) Fix has been implemented for SPO-2245 and testing in different environment is in progress. 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) Understanding peoplesoft Application Designer and attributes of CI is in progress Had client call with Elvira. Understanding peoplesoft Application Designer and attributes of CI is in progress Had client call with Elvira. Understanding peoplesoft Application Designer and attributes of CI is in progress Had client call with Elvira. Understanding peoplesoft Application Designer and attributes of CI is in progress Had client call with Elvira. Understanding peoplesoft Application Designer, adpater code and attributes of CI is in progress Presentation on people soft is in progress Had client call with Elvira. 5th Week (26th Nov - 30th Nov '12) Project Hours spent Break time 9 8 9 10 8 8 9 9 10 10 8 9 10 8 8 1st Week ( 1st Nov - 2nd Nov '12) Fix has been implemented for SPO-2245 and testing in different environment is in progress. 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) 8 1 9 1 9 1 8 1 6 3 1 5th Week (26th Nov - 30th Nov '12) DATE Metrics TOPIC/ISSUE STATUS 11/1/2012 Research And Analysis CTN-409 IN PROGRESS 11/2/2012 Bug fix/Patches/cumulative fixes CTN-423 IN PROGRESS 11/3/2012 Bug fix/Patches/cumulative fixes CTN-424 IN PROGRESS 11/2/2012 Research And Analysis CTN-409 IN PROGRESS 11/3/2012 Bug fix/Patches/cumulative fixes CTN-423 COMPLETED 11/4/2012 Bug fix/Patches/cumulative fixes CTN-426 COMPLETED 11/5/2012 Bug fix/Patches/cumulative fixes CTN-424 IN PROGRESS 11/6/2012 Bug fix/Patches/cumulative fixes CTN-427 IN PROGRESS 11/6/2012 Bug fix/Patches/cumulative fixes CTN-424 IN PROGRESS 11/7/2012 Bug fix/Patches/cumulative fixes CTN-424 IN PROGRESS 11/8/2012 Bug fix/Patches/cumulative fixes CTN-427 IN PROGRESS 11/8/2012 Bug fix/Patches/cumulative fixes CTN-424 IN PROGRESS 11/9/2012 Bug fix/Patches/cumulative fixes CTN-424 IN PROGRESS 11/12/2012 Bug fix/Patches/cumulative fixes CTN-428 IN PROGRESS 11/13/2012 11/14/2012 Bug fix/Patches/cumulative fixes CTN-428 IN PROGRESS 11/15/2012 Bug fix/Patches/cumulative fixes CTN-428 IN PROGRESS 11/16/2012 Meeting Meeting COMPLETED 11/16/2012 Bug fix/Patches/cumulative fixes CTN-428 COMPLETED 11/17/2012 Bug fix/Patches/cumulative fixes CTN-430 IN PROGRESS 11/19/2012 Bug fix/Patches/cumulative fixes CTN-430 IN PROGRESS 11/20/2012 Meeting Meeting COMPLETED 11/20/2012 Bug fix/Patches/cumulative fixes CTN-430 IN PROGRESS 11/21/2012 Meeting Meeting COMPLETED Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) 11/21/2012 Bug fix/Patches/cumulative fixes CTN-430 IN PROGRESS 11/22/2012 Meeting Meeting COMPLETED 11/22/2012 Bug fix/Patches/cumulative fixes CTN-409 IN PROGRESS 11/23/2012 Meeting Meeting COMPLETED 11/23/2012 Bug fix/Patches/cumulative fixes CTN-409 IN PROGRESS 11/24/2012 Meeting Meeting COMPLETED 11/26/2012 Bug fix/Patches/cumulative fixes CTN-430 COMPLETED 11/26/2012 Meeting Meeting COMPLETED 11/27/2012 Bug fix/Patches/cumulative fixes ORA-652 IN PROGRESS 11/27/2012 Bug fix/Patches/cumulative fixes ORA-680 IN PROGRESS 11/28/2012 Meeting Meeting COMPLETED 11/28/2012 Bug fix/Patches/cumulative fixes ORA-680 IN PROGRESS 11/29/2012 Meeting Meeting COMPLETED 11/29/2012 Bug fix/Patches/cumulative fixes ORA-680 IN PROGRESS 11/30/2012 Bug fix/Patches/cumulative fixes ORA-680 IN PROGRESS 5th Week (26th Nov - 30th Nov '12) STEPS TAKEN FOR SOLUTION FILES MODIFIED (IF ANY) Debugging the compilation failed adapters and testing is in progress. Created new JIRA for iwgeolad adapter compilation failed for JUnit test cases and debugging is in progress. Created new JIRA for iwpeoplesoft adapter compilation failed for JUnit test cases and debugging is in progress. Debugging the compilation failed adapters and testing is in progress. Modified the code for compiling the Junit test cases for iwgeoload adapters. Total test cases was 19 out of which 4 throws an error and 2 of them get failure. Modified the syntax for Juni test cases. Compilation of the Junit test cases was successful. Total test cases was 49 out of which 25 throw an error and 4 of them get failure. Debugging the iwpeoplesoft adapter compilation failed for JUnit test cases and it is in progress. Debugging the error for iwora adapter compilation failed. Debugging the iwpeoplesoft adapter compilation failed for JUnit test cases and it is in progress. Modified the syntax and code has been merged to Chennai Jira. Debugged the syntax and the code has been merged to Chennai Jira Executing the Junit test cases cause memory error and server unavailable. Debugging the error in progress. Executing the Junit test cases cause memory error and server unavailable. Debugging the error in progress. Debugging the telnet adapter compilation failed for Junit test cases. AMTEX HOLIDAY Debugging the telnet adapter compilation failed for Junit test cases. Debugging the telnet adapter compilation failed for Junit test cases. Meeting with Elvira and discussed about Jiras. Commented the unwanted s.o.p line which call the unavailable method from the Test1.java. iwtelnet adapter is compiled. Debugging the file protocol adapter compilation failed for Junit test cases. Debugging the file protocol adapter compilation failed for Junit test cases. Meeting with Elvira and discussed about Jiras. The issue is in IWAFAdapterTest.java file in iwaftest. The logic used to get the path of jar file causing the issue. We found a fix, but we have to make a generic solution where all adapters uses Junit test cases.Further analysis is in progress. Meeting with Elvira and discussed about Jiras. Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) The issue is in IWAFAdapterTest.java file in iwaftest. The logic used to get the path of jar file causing the issue. We found a fix, but we have to make a generic solution where all adapters uses Junit test cases.Further analysis is in progress. Meeting with Elvira and discussed about Jiras. Testing the adapters with updated code and further analysis in progress. Meeting with Elvira and discussed about Jiras. Testing the adapters with updated code and further analysis in progress. Meeting with Elvira and discussed about Jiras. Updated track.xml merged to svn and the issue was not repro. Iwfile adapter compiled successfully and test cases are executed. Meeting with Elvira and discussed about Jiras. Analysing the people soft adapter. Analysing the people soft adapter. Walk through the code and debugging the issue. Meeting with Elvira and discussed about Jiras. Issue was not repro with new iwpeoplesoft.jar file. Further analysis is in progress. Meeting with Elvira and discussed about Jiras. Issue was not repro with new iwpeoplesoft.jar file. Further analysis is in progress. Issue was not repro with new iwpeoplesoft.jar file. Further analysis is in progress. 5th Week (26th Nov - 30th Nov '12) Project Hours spent Break time 4 4 2 2 4 4 5 5 8 4 4 5 4 8 8 9 1 5 5 9 1 8 1 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) 7 1 7 1 8 1 9 1 6 5 1 9 1 8 8 5th Week (26th Nov - 30th Nov '12) DATE Metrics TOPIC/ISSUE STATUS 11/1/2012 Bug fix/Patches/cumulative fixes CTN-402 IN PROGRESS 11/2/2012 Bug fix/Patches/cumulative fixes CTN-402 COMPLETED 11/2/2012 Maintenance SOC-6253 COMPLETED 11/5/2012 Maintenance SOC-6266 In Progress 11/6/2012 Maintenance SOC-6266 Completed 11/7/2012 Maintenance SOC-6249 In Progress 11/8/2012 Maintenance SOC-6249 In Progress 11/9/2012 Maintenance SOC-6249 In Progress 11/12/2012 Maintenance SOC-6268 In Progress 11/13/2012 11/14/2012 Maintenance SOC-6268 In Progress 11/15/2012 Maintenance SOC-6269 Completed 11/16/2012 Maintenance SOC-6249 In Progress 11/19/2012 Maintenance SOC-6249 Completed 11/19/2012 Maintenance SOC-6268 Completed Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) 11/20/2012 Maintenance SOC-6270 In Progress 11/21/2012 Maintenance SOC-6271 Completed 11/22/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/23/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/26/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress 11/27/2012 Bug fix/Patches/cumulative fixes SPO-2246 In Progress 11/28/2012 Bug fix/Patches/cumulative fixes SPO-2247 In Progress 11/29/2012 Bug fix/Patches/cumulative fixes SPO-2248 In Progress 11/30/2012 Bug fix/Patches/cumulative fixes SPO-2249 In Progress 5th Week (26th Nov - 30th Nov '12) STEPS TAKEN FOR SOLUTION FILES MODIFIED (IF ANY) Found the issue and analyzing the ibse code to fix this issue, startchannel and suspended channel is working fine with out any date modifying. Deep observation is found exact place to fix this issue. same is tested with different scenario with multiple times using xml spy. code changes checked in to the chennai jira. ChannelManager.java Updated where XMLDocument, XMLNode and XMLParser objects are instantiated. Same is Tested and code changes checked in to the chennai jira. InboundTest.java, PsoftTest.java, test_ORA261.java, test_ORA285.java, testISM_1804.java, testISM_1806.java,testISM_2116. java, testPsoftAdp.java Updating DQC Adapter sources are in progress DQC Adapter sources are updated where XMLDocument, XMLNode and XMLParser objects are instantiated Updating Exchange Adapter sources are in progress Updating Exchange Adapter sources are in progress Updating Exchange Adapter sources are in progress Updating sources are in progress AMTEX HOLIDAY Updating sources are in progress Updated where XMLDocument, XMLNode and XMLParser objects are instantiated. Code changes checked in to the Chennai Jira. JDEWorldTest.java Exchange adapter source is updated where XMLDocument, XMLNode and XMLParser objects are instantiated Testing updated changes with ant build are successfull. 1.TestInbound.java 2.TestEWS.java Adapter source is updated where XMLDocument, XMLNode and XMLParser objects are instantiated. Updated changes are tested successfully. 1.testISM_2043.java 2. testISM_2002.java 3.testISM_2001.java 4. testISM_2059.java 5.testISM_2042.java 6. TestCases.java Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) Lawson adapter source is updated where XMLDocument, XMLNode and XMLParser objects are instantiated. Updated chnages are in progress 1. IBILawson.java Analysis is in progress Analysis is in progress Analysis is in progress New Target Created, Schemas are generated. Payload executed. Response Document is generated from the schema. Schema is analysed to tightly coupled with the namespace prefix. W3g Documents are analysed to find details about the namespace prefix. Found the element form default attribute value is incorrect. Updating the value to "qualified" resolves the issue As suggested IBSEGEN, and Oracle Xfoc and Ora11G branches are tested and found the this attribute value is correct in XDSOAPAdapterfactory, Only ISM xfoc branch contains the incorrect value and required to be updated. 5th Week (26th Nov - 30th Nov '12) Project Hours spent Break time IBSE 8 IBSE 4 PeopleSoft 5 DQC 9 DQC 8 Exchange 10 Exchange 8 Exchange 9 Geo load 8 Geo load 9 JDE World 9 Exchange 9 Exchange 10 10 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) Lawson 8 Lawson 9 Siebel Unified 8 Siebel Unified 8 Siebel Unified 8 Siebel Unified 8 Siebel Unified 10 Siebel Unified 9 Siebel Unified 10 5th Week (26th Nov - 30th Nov '12) DATE Metrics TOPIC/ISSUE STATUS 11/1/2012 Documentation CTN-420 In Progress Meeting Client Meeting Completed Bug fix/Patches/cumulative fixes SPO-2245 Completed 11/2/2012 Documentation CTN-420 In Progress Bug fix/Patches/cumulative fixes CTN-423 Completed Meeting Client Meeting Completed Documentation WSR Completed 11/5/2012 Documentation Offsohore Metrics Completed Meeting Client Meeting Completed Documentation CTN-420 In Progress 11/6/2012 Documentation CTN-420 In Progress Research And Analysis ORA-678 In Progress Meeting Client Meeting Completed 11/7/2012 Research And Analysis ORA-652 In Progress Documentation CTN-420 In Progress Meeting Client Meeting Completed 11/8/2012 Documentation CTN-420 In Progress Maintenance SOC-6249 In Progress 11/9/2012 Research And Analysis ORA-652 In Progress Maintenance SOC-6249 In Progress Documentation IwayDev WSR Completed 11/12/2012 Research And Analysis SPO-2245 Completed Documentation CTN-420 In Progress Meeting Client Meeting In Progress Research And Analysis ORA-652 In Progress 11/13/2012 11/14/2012 Bug fix/Patches/cumulative fixes SPO-2245 Completed Meeting Client Meeting Completed Documentation CTN-420 In Progress 11/15/2012 Bug fix/Patches/cumulative fixes CTN-428 Completed Meeting Client Meeting Completed Documentation CTN-420 In Progress 11/16/2012 Research And Analysis CTN-428 Completed Meeting Client Meeting Completed Documentation CTN-420 In Progress 11/19/2012 Research And Analysis CTN-409 In Progress Research And Analysis CTN-420 Completed Documentation WSR Completed Meeting Client Meeting Completed 11/20/2012 Research And Analysis ORA-679 Completed Research And Analysis CTN-430 Completed Meeting Client Meeting Completed Documentation CTN-420 Completed 11/21/2012 Research And Analysis CTN-409 Completed Maintenance SOC-3141 Completed Research And Analysis SPO-696 In Progress Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) Meeting Client Meeting Completed Research And Analysis ORA-679 Completed 11/22/2012 Research And Analysis ORA-679 In Progress Research And Analysis SPO-696 In Progress Research And Analysis CTN-409 Completed Meeting Client Meeting Completed 11/23/2012 Research And Analysis ORA-679 In Progress Meeting Client Meeting Completed Documentation IwayDev WSR Completed 11/26/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress Research And Analysis ORA-679 In Progress Documentation CTN-420 Completed Documentation WSR Completed Meeting Client Meeting Completed 11/27/2012 Research And Analysis ORA-679 In Progress Documentation CTN-420 Completed Meeting Client Meeting Completed 11/28/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress Research And Analysis ORA-679 In Progress Customer issues/hot track cases IRN Issue PS In Progress Meeting Client Meeting Completed 11/29/2012 Bug fix/Patches/cumulative fixes SPO-2245 In Progress Customer issues/hot track cases IRN- 83252553 In Progress Research And Analysis ORA-679 In Progress Documentation Weekly Minutes In Progress 11/30/2012 Bug fix/Patches/cumulative fixes CTN-437 In Progress Meeting Client Meeting Completed Customer issues/hot track cases IRN- 83252553 In Progress Research And Analysis ORA-679 In Progress 5th Week (26th Nov - 30th Nov '12) STEPS TAKEN FOR SOLUTION FILES MODIFIED (IF ANY) Updating Siebel MVG Test Plan is in progress. Daily Client Conference Call Worked with response schema updation for Siebel Siebel MVG Test Plan Specification Draft design sent for review. Worked with Geo load unit test cases. Weekly Client Conference Call Weekly Status Report for the current week is completed Offshore Metrics are prepared for Adapter Team for the month of October Weekly Client Conference Call Siebel MVG Test Plan Specification Draft in progress. Siebel MVG Test Plan Specification Draft in progress. Analysis started for Peoplesoft issues Weekly Client Conference Call Analysis is in Progress for Peoplesoft Siebel MVG Test Plan Specification Draft Delivered. Daily Client Conference Call Siebel MVG Test Plan Specification Final Version is in progress. Worked with Exchange adapter Peoplesoft Analysis and object exploration with PT are in progress Worked with Exchange adapter Weekly Status Report for the current week is completed Worked with Siebel Siebel MVG Test Plan Specification document updation in progress Daily Client Conference Call Peoplesoft Issues Analysis AMTEX HOLIDAY Worked with Siebel Schemas Daily Client Conference Call Siebel MVG Test Plan Specification Worked with Telnet Adapter Daily Client Conference Call Siebel MVG Test Plan Specification Final Draft is in progress Worked with unit test cases for File Adapter. Daily Client Conference Call Siebel MVG Test Plan Specification Build properties are updated, Junit classpath are updated Siebel MVG Health Check Weekly Status Report for the last week is delivered. Daily Client Conference Call Jira management is done. Basic Planning is done for fixing Peoplesoft Issues. Worked with File adapter Junit test cases Daily Client Conference Call Updating Siebel MVG Test Plan Specification Final version is in progress track.xml changes are analyzed and details are sent to client Total Adapter list marked for update with XMLNodes instatiation etc. is sent to client. Update and Delete operations are analysed in Peoplesoft Adapter Work done for the month of November 2012 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) Daily Client Conference Call Analysis started for Peoplesoft custom CI. Peoplesoft objects, behavior and properties are analyzed. Related documents are collected. Update and Delete operations are analysed in Peoplesoft Adapter track.xml changes are analyzed and details are sent to client Daily Client Conference Call Analysis of Peoplesoft Object and API uses done. Daily Client Conference Call Weekly Status Report for the current week is completed Response Schema and doc are analysed. h852.jar Peoplsoft java doc generated. Updating Siebel MVG Test Plan Specification Final version is in progress Weekly Status Report for the last week is delivered. Daily Client Conference Call Model designed to access Peoplsoft and populate CI objects Siebel MVG Test Plan Specification Final version delivered Daily Client Conference Call Worked with Siebel Model is tested connecting Peoplesoft and populating CI objects Analysis started for Peoplesoft custom CI. Daily Client Conference Call Siebel Code Analysis is done for Response Schema root node difference Analysis done on the client traces for Peoplesoft custom CI. Peoplesoft documents are collected and adapter command flow is studied. Minutes are prepared and sent to client JCA environment is configured with Jboss and latest iway jca packages. Issue could not be simmulated. Further analysis is in progress. Daily Client Conference Call Analysis done on the client traces for Peoplesoft custom CI. Peoplsoft API analysis and uses in adapter are in progress. 5th Week (26th Nov - 30th Nov '12) Project Hours spent Siebel MVG 6 1 Siebel 1 Siebel 3 Junit/ Build 1 1 3 3 1 Siebel MVG 5 Siebel MVG 4 Peoplesoft 2 1 Peoplesoft 4 Siebel MVG 5 1 Siebel MVG 6 Exchange 3 Junit/ Build 3 Exchange 1 4 Siebel 4 Siebel MVG 2 2 Peoplesoft 4 Siebel 4 1 Siebel MVG 4 Junit/ Build 2 1 Siebel MVG 5 Junit/ Build 1 1 Siebel MVG 6 Junit/ Build 1 Siebel-MVG 1 4 1 Peoplesoft 4 Junit/ Build 2 1 Siebel MVG 3 Junit/ Build 2 2 Peoplsoft 1 1st Week ( 1st Nov - 2nd Nov '12) 2nd Week (5th Nov - 9th Nov '12) 3rd Week (12th Nov - 16th Nov '12) 4th Week (19th Nov - 23rd Nov '12) 1 4 Peoplesoft 3 Peoplesoft 2 Junit/ Build 4 1 Siebel 4 1 4 Siebel 4 Junit/ Build 1 Siebel-MVG 1 4 1 Peoplesoft 4 Siebel MVG 3 1 2 2 4 2 Siebel 1 Peoplsoft 2 Peoplsoft 4 2 RDBMS 4 1 Peoplsoft 2 Peoplsoft 2 5th Week (26th Nov - 30th Nov '12) Sl# Jira Asignee Type 1 CTN-437 Susanta Bug 2 SPO-696 Jeyakumar Bug 3 ORA-678 Pravin Bug 4 ORA-679 Susanta Bug 5 ORA-680 Jeyakumar Bug 6 ORA-681 Jeyakumar Bug 7 ORA-682 Pravin Bug 8 ORA-683 Pravin Bug 9 CTN-409 Jeyakumar Research 10 CTN-424 Jeyakumar Bug 11 CTN-414 Jeyakumar Bug 12 SPO-2245 Susanta Bug 13 IRN Issue Susanta Customer Issue 14 CTN-430 Jeyakumar Research 15 CTN-420 Susanta Document 16 CTN-409 Jeyakumar Research 17 SOC-6270 Veera Maintenance 18 SOC-6249 Veera Maintenance 19 SOC-6268 Veera Maintenance 20 CTN-428 Jeyakumar Bug 21 SOC-6269 Veera Maintenance 22 SPO-2482 Pravin Bug 23 CTN-427 Jeyakumar Bug 24 CTN-423 Jeyakumar Bug 25 CTN-426 Jeyakumar Bug 26 SOC-6253 Veera Maintenance 27 SOC-6266 Veera Maintenance 28 SOC-2606 Jeyakumar Research SPO-696 CTN-437 ORA-680 ORA-679 ORA-681 SPO-2245 IRN- 83252553 CTN-420 CTN-424 CTN-414 CTN-428 CTN-427 CTN-423 CTN-426 CTN-409 CTN-430 CTN-409 SOC-2606