PROJECT BRIEF/ DESCRIPTION

(CENTRAL MRCF)
I. NAME OF PROJECT : Iligan City Solid Waste Management System

: The Central Material Recovery and Composting Facility


II. PROJECT SITE / LOCATION (or CMRCF) which shall be operated by the City
Government shall be located at Sitio Bangko, Barangay
Bonbonon Iligan City; while the Barangay MRF (for 28
coastal barangays – see Annex A for the Population
Projection of the said Coastal Barangays) shall be
located in each Barangay, or cluster of Barangays at
their option:

 Distance of Central MRCF - 7.5 km


from City Proper
 Available Area - Approximately 5
hac (out of 12 hac
total area)

: Scheduled to be completed on or before December 2008


III. TIMEFRAME
: The proposed Iligan City Solid Waste management System
IV. SOLID WASTE MANAGEMENT is shown in Annex B-Schematic Diagram of the Iligan City
Solid Waste Management System.
SYSTEM FRAMEWORK
Below is the brief description of this system:

1. A Central MRCF shall be constructed to handle the


solid waste fro the following sources: a) Barangay
MRF residuals, b) the mixed/special solid waste from
the city markets /institutional sources; and c) the
mixed solid waste from households which are beyond
the capacity of the individual Barangay MRF’s to
process.

2. The 28 coastal barangays shall each put up their own


barangay MRF, or in clusters - to handle
segregation, recycling, composting, and others.
Residuals shall be handled by the Central MRCF.

3. All commercial (markets) and institutional sources


(hospitals, schools, etc.) mixed solid/special waste
shall be handled by the Central MRCF. /hazardous
waste shall have a designated disposal area to be built
and operated by each hospital, with the City to put up a
Special and Hazardous Waste Facility with central
autoclaving system (for small hospitals). Hospitals may
also opt to put up their privately-operated MRF’s in
their property for medical wastes -subject to the EIS
requirements.
4. Excess solid waste generated from households (that
can’t be absorbed by Barangay MRF), and for those
Barangay still without MRF’s shall be processed at
the CMRCF.

5. The collection/hauling of solid waste shall be done by


both the Barangay MRF within their area of
responsibility, and/or by the City Government through
the Public Services Division in the case of the Central
MRCF.
: The solid waste management system with its various
V. PROJECT COMPONENTS project component is briefly described below:

PHASE DESCRIPTION

A. Basic Engineering Activities : 1. Feasibility study including site selection

2. Financial sourcing (in-house for the


equities/collaterals, and out-sourced funds mostly
from the banks)

3. The Initial Environmental Examination Checklist


(IEE) and other permitting requirements such as
Environmental Compliance Certificate (ECC),
Authority to Construct, Notice to Proceed, and others

4. Preparation of the Santiago Open Dumpsite Closure


Plan

5. Upgrading of the Iligan City Solid Waste


Management Plan, and its approval by the National
Solid Waste Management Commission

B. Detailed Engineering : 1. Detailed plans, estimates, tender documents,


specifications, and program of works for all the
project packages/modules (civil works and others)

2. Legal requirements including appropriation


ordinances and others

3. Market development plan for the recycled waste


products, compost and others

4. Information and education campaign (IEC) plan


including for the pilot material recovery facility
proposed to be located at Barangay Del Carmen.

5. Solid waste management plan for the hinterland


barangays (separate plan from that of the coastal
barangays)

C. Construction : 1. Bidding activities ( for civil work, equipment, and


others)

2. Civil works implementation of all project


packages/modules

3. Public Services Division (PSD) equipment upgrading


and procurement (for CMRCF operation and solid
waste hauling/collection operation)

4. Closure of the Barangay Santiago Controlled


Dumpsite Facility (CDF)
D. Operation and Maintenance 1. Institutionalization of the solid waste management
system (creation of the Central MRCF management
team, tipping fees, etc)

2. Marketing development implementation

3. Training of operations/maintenance/marketing
personnel

4. Transitory provisions (maintenance and operating


supplies, budget, security, safety, etc)

5. Operation and maintenance manuals including


operation systems and procedures, closure plans,
mitigation measures, abandonment plans and others)

6. Long term maintenance of the Barangay Santiago


closed dumpsite

VI. PROJECT PROPONENT : City Government of Iligan

Contact Person:

Hon. Lawrence Ll. Cruz


City Mayor
Buhanginan Hills, Iligan City

VII. PURPOSE / OBJECTIVE : The purpose of the project is to establish a financially


viable and environmentally sustainable solid waste
management system to benefit the people of Iligan
City, to be operated within the carrying
capacity of the supporting ecosystem, and at the same
time satisfy the requirements of intergenerational
equity and social justice.
VIII. TARGET BENEFICIARIES : Present and future residents of Iligan City and
neighboring areas.