Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
.." C1
Ztl. I
rt. ,/
r- Ni
I
li RV I
In ' :.-1 VI.
Ng .
It -.
bt et: P.I
.1003. IN
CIP
tri.
V.1
INT
44
CR
an
CR
at --
2 It.'..
2
2
Swl
Wei
Coll
tet
ter .
:J
CR
CR
V. DM CR
M P.9 . IV) V! . All :rat Ca. ox 7.P. CR : CR C 7
In : Oa trc : IN .74 an. an N. CR ' CR .C.
C
I44 en ow eri. V. en. . to aCI o o CA
PIP Pr [
. 1
1. II. :. .7. ,
_
;A .
..-
,:,
.
:R
.
b. Improved Procurement and Inventory Management
A host of improvements were made to the procurement and inventory management
processes. The first was to simply organize all inventories into racks and bins:
After this, important steps included setting up Vendor Managed Inventory (VMI) cages
which removed the burden of procuring repeated tooling from the inventory group and moved it
to the supplier. An added benefit is the organization and accountability that comes with this
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 80
cage-style approach (trade associates now need to sign for all tooling, which leads to less waste
and less likelihood of theft or other abuses):
The team then expanded its use of the in-house ERP system JD Edwards to better
manage inventory receiving and ordering.
Similarly, standard approaches for inventory management and receiving such as three-
way matching were implemented with much success.
Improvements in management continue, as Fastenal vending machines were installed on
May 27th, 2014. The machines further facilitate the material distribution of high volume/high
cost items.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 81
C Incremental Improvements
A common characteristic seen in organizations that effectively move down the learning
curve is a culture of continuous incremental improvement. These small solutions make
incremental improvements in the effort required for a given task, reduce waste, and reduce the
variability in the processes.
Numerous examples of these types of improvements exist. An example of this can be
seen in the pictures below showing the processes required for moving a bathroom pod into final
position. A before picture shows that the process required a large team of trade associates
dragging the pod using a combination of straps and manual force. Aside from being an
ergonomic risk, this was a time, and manpower consuming task. In the after picture, heavy duty
casters have been temporarily attached to the pod chassis. Installing the pods to the mods is now
a simple matter of a small number of trade associates pushing the pod into place, then removing
the casters. Less trade associates labor is needed, less time is required, and the risk for injury
drastically reduced.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 82
A second example is the organization and installation of tile into the kitchen and
bathrooms. In order to save time and cost, the tile used in each area are large sheets- some of
which are almost 7 feet long and weighing 300 pounds each. Complicating matters is the fact
that slight variations in the manufacturing processes of these tiles result in different batches
having slight color differences. Therefore, it is critical that each bathroom use sheets from the
same batch throughout. With the various sheet sizes being so heavy, yet fragile, finding the
correct sheets to use proved very time consuming, with significant ergonomic challenges, and a
high rate of breakage.
Improvements in the process include the creation of multiple staging racks that allow the
sheets to be sorted in sequence of batch numbers. In other words, each rack has batch A sheets
on the top, then batch B, etc. So, trade associates no longer need to sort for matching sheets.
This requires pre-sorting the sheets upon receipt, but the ultimate time savings have proved well
worth it. In addition, a specialized tool was found that allows the trade associates to lift the
sheets much more ergonomically (also reducing the risk of breakage).
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 83
d.
Skills assessment
Improvements were instrumental in bringing productivity down the learning curve.
Placing better skilled trade associates into the appropriate roles impacts the overall performance
and improvement rate of the team.
I. Actual Results vs. Predicted Results
As the graph below shows, the net result of all of the improvements and learning from the
team is a learning curve that is strikingly similar to what was mathematically predicted.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 84
Actual Results vs Predicted Learning Curve
2000
1800
1600
1400
1200
1000
800
600
400
200
0
Floor 2 Floor 3 Floor 4 Floor 5 Floor 6
o Man Hours/Mod - Shipbuitcling Leaning Curve
It is conclusive that the team's performance has met expected benchmarks for a high-
performing group. This learning curve trend will continue through the life of the B2 Project and
would continue to B3 absent the improper repudiation of the LLC Agreement by FC.
As a result, Skanska is entitled to an extension of time and additional compensation.
FC HAS MATERIALLY BREACHED THE CM AGREEMENT AND
CAUSED DELAY TO THE PROJECT BECAUSE THE DESIGN FOR THE
B2 PROJECT, INCLUDING THE MODULES TO BE FABRICATED AND
INSTALLED, WERE NOT COMPLETE, DETAILED AND SUFFICIENT
FOR THE COMPLETION OF WORK AS OF THE EFFECTIVE
DATE OF THE CM AGREEMENT
EXECUTIVE SUMMARY
FC represented in the CM Agreement that it "engaged professional engineer/design firms
to develop a complete and detailed design for the B2 Project, including but not limited to, the
modules to be fabricated and installed by Contractor at the Site and the balance of the Work,
which Owner represents is sufficient for the completion of the Work as of the Effective Date."
M
a
n
h
o
u
r
s
p
e
r
m
o
d
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 85
This is a representation that the design has considered the IP and incorporated the IP into it.
Stated otherwise, this is a modular project and a complete, detailed and buildable modular design
was to be provided. This representation was inaccurate and constitutes a material breach of the
CM Agreement.
As confirmed by the numerous publications and public comments made by any SHoP
Architects, Arup and FC, the design of modular building is a "Swiss watch" which must be fully
frozen before building commences if the work is to be productively performed in the factory. A
complete design is needed for production drawings and changing the design impacts
procurement and production. Simply put, you cannot manufacture without approved production
drawings. It is an undisputed fact that the design was not complete as of the CM Agreement's
effective date.
Over 600 RFIs were generated in the factory and field. Unless the RFI was answered by
a reference to an existing drawing, the design is not complete. Assertions of means and methods
cannot and do not constitute excuses for a failure to design.
Additionally, numerous changes were made in the factory and field which were not
discretionary, but rather the result of incomplete and incorrect design.
All of this impacted performance. It is an Owner Caused Event for which Skanska is
entitled to a Change Order providing compensation and time extension relief.
DETAILED DISCUSSION
The IP for the production of modules for each floor was required in five (5) phases. Each
phase had multiple activities, with each activity having multiple tasks. A summary of the
activities, listed by phase, is.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 86
Phase I Activities:
Layout Modules
Install Fire-Rated Ceilings
Install Column Wraps
Install Exterior End-Purlin Wraps
Install Fire-Rated Partitions
Core MEP Penetrations
Phase II Activities:
Set PODs44
Install Corridor MEP Hangers & Cartridges
Install Interior Partitions
Install Soffit MEP Hangers & Cartridges
Rough-in HVAC Duct
Rough-in Sprinkler Piping
Rough-in Plumbing Piping
Rough-in Electrical
Complete all MEP Mini-Matelines
Install Architectural Soffits
Phase III Activities:
Drywall Finish & Paint
Load and Stage Finish/Trim Materials
Install Exterior Wall Panels
Phase IV Activities:
44
For the initial floor in production (2nd Floor), the plan was to install the PODs on the first day of production, as
part of Phase I. It was later changed to Phase II by FC+S.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 87
Construct Kitchens
Finish Closets
Install MEP Trim
Install Door Frames
Install Flooring
Phase V Activities:
Install PTACs
Install Wood trim
Install Doors
Install Appliances
Final QA/QC Walk-Thru
The successful production of modules starts with the 100% complete design of the
Project, prepared by SHoP Architects, FC's project architect, and the acquisition and delivery of
materials to the factory. To implement an efficient procurement process, FC+S hired Fulcro to
perform 3D Modeling of the SHoP design. The 3D modeling, among other things,45 generated
Bills of Materials (BOM), allowing FC+S to solicit quotes from vendors, resulting in making
proper material submittals to SHoP for approval, which culminated in the fabrication and/or
delivery of materials to the factory to be used in the production of the modules. The efficient
implementation of this "procurement process" is dependent on a complete and accurate design.
On this Project, the design was contractually required to be 100% complete as of Notice
to Proceed. It was not. After the effective Notice to Proceed date of December 21, 2012, nine
(9) bulletins were issued by FC's project architect which added, deleted and revised various
45 3D Modeling also results in identifying some, not all, conflicts in the design.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 88
components of the Project. These changes impacted the timely execution of the procurement
process.
Bulletin
No. Issued
1 01/24/13
1(IFC)46 03/20/13
2 04/11/13
3 06/10/13
4 06/29/13
5 07/01/13
6 08/05/13
7 09/03/13
8 10/21/13
9 02/14/14
In addition to being incomplete, the design contained numerous errors and omissions.
Some of the design defects were uncovered while the modules were actually in production on the
factory floor, causing immediate and time consuming delays. While some of the design defects
were discovered in advance of actually assembling the modules in the factory, a significant
portion of them still resulted in impacts to the procurement process, which in turn impacted the
timely completion of module production.
Due to the nature of essentially working on one floor's worth of modules before being
able to work on the next floor's set of modules, the delays experienced due to design conflicts,
errors and omissions were cumulative e.g. Impacts to Floor 2 necessarily impacted Floor 3.
I. Specific Impacts
The Delay Analysis prepared by Skanska covers the time period from the December 21,
2012 effective Notice to Proceed through July 28, 2014. The first portion of the Delay Analysis
46
IFC is an acronym for Issued For Construction
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 89
covers critical path delays to the establishment of a functional factory for producing modules
(Factory Fit-out). The second portion of the Delay Analysis covered the identification and
quantification of critical path delays experienced during the actual production of modules.
Through July 28, 2014, delays to module production of Floors 2 through 10 were as follows.
Floor
No.
Actual
Start
Actual
Finish
Delay
Days
Delay
No.
2 09/3/13 11/06/1347
39
WDs 4
3 11/7/13 01/22/14
43
WDs 5
4 01/23/14 02/27/14
18
WDs 6
5 02/28/14 04/01/14
16
WDs 7
6 04/2/14 04/28/14
12
WDs 8
7 04/29/14 05/21/14
10
WDs 9
8 05/22/14 06/11/14 7 WDs 10
9 06/12/14 07/03/14 9 WDs 11
10 07/7/14 07/28/14 9 WDs 12
Totals
163
WDs
CD Conversion
227
CDs
There were generally two origins of design impacts to the production of modules;1) there
were design changes implemented by FC/SHoP48 via Bulletins, and 2) there were changes that
47
The 2nd Floor Modules were pulled off the production line on November 6, 2013 to allow the 3rd Floor Module
production to commence. The Defective Intellectual Property portion of this letter addresses impacts to the rate of
module production due to the fundamentally erroneous nature of the GTW concept, conceptualized and
implemented by FC. It also discusses delay impacts due to the lack of acceptable labor productivity which resulted
from FC's establishment of the Modular Trade Associates Union, and the low wage rates provided in its negotiated
Collective Bargaining Agreement. Both of these issues severely impacted the timely completion of module
production. In addition, there were specific delays caused by design impacts.
48 References to SHoP are inclusive of its engineering subconsultant, Amp. Arup was also hired directly by FCRC.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 90
resulted from answers to RFIs. The RFIs generated by FC+S resulted from two conditions: (i)
when, during 3D modeling, design errors were discovered and brought to the attention of SHoP
for resolution; and (ii) when during the course of module production, design errors and conflicts
were encountered by factory workers and supervisory staff. Both of these conditions had the
potential to impact the procurement process and/or the actual module assembly process.
2nd Floor Design Impacts
The 2nd Floor module production essentially started on September 3, 2013. During
production numerous design impacts were encountered which caused extensive delays. On or
about November 6, 2013, due in part to the fact that many design related impacts were
preventing the completion of the 2nd Floor modules; FC+S moved the 2nd Floor modules out of
the factory and started on the production of the 3rd Floor modules.49 Therefore, the critical
delays to the completion of 2nd Floor modules were encountered between September 3rd and
November 6th, 2013. Below is a compilation of documented design related impacts.
1. Sanitary Waste and Vent Re-Design
The design of the sanitary and waste vent did not meet code and needed to be re-
designed. This was initially discovered to be applicable to Floors 4 and 5. Upon receiving the
particulars of the design change, on September 23, 2013 FC+S issued RFI #302 notifying Arup
that the same conditions for Floors 4 and 5, existed for Floor 2 and wanted confirmation that the
revised design for Floors 4 and 5 was applicable to Floor 2. On September 26, 2013 Arup
confirmed direction to revise the 2nd Floor accordingly.
49
It was the intent of FC+S to complete the 2nd Floor Modules at night and on weekends, as the resolution of design
impacts was achieved. Ultimately, production of the 2nd Floor Modules was completed on or about January 3, 2014.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 91
The re-design of the 2nd Floor was finalized and submittals were made to Arup, which
were approved on or about October 4, 2013. This required FC+S to re-procure materials to
implement the changes required.
This change delayed the completion of the bathroom PODs, which were originally
scheduled to be installed into the Modules on the first day of production. Instead, the bathroom
PODs were not set until October 8, 2013. This delay encompassed at least sixteen (16) calendar
days (9/23/13 to 10/8/13).
2. DT-09 Column Wrap
On August 23, 2013 FC+S submitted RFI #258 and re-submitted as RFI #269 on
September 4, 2013. The Vendor submittal reflecting the new material (Deep F-Channel with
Intumescent) was received on September 16, 2013 and approved by SHoP on September 19,
2013. After receipt of the approval FC+S then proceeded with the procurement process of
performing a quantity take-off (QTO), preparing a Bill of Material (BOM), placing an order for
the material, and receiving the materials in order to continue with the work. On or about
September 24, 2013 FC+S was forced to suspend working on the column wraps on eight
columns of 2nd Floor Modules, waiting for materials. The materials were received on October
18, 2013. This delay encompassed at least twenty-five (25) calendar days (9/24/13 to 10/18/13).
3. Added Cantilevered Wing Walls to both Sides of Mateline Braceframe to
Extend Fire Protection
Per detail 05 on drawing A002 there was no subfloor where the fire rated exterior wall
assembly was supposed to be installed. In the answer to RFI-269, the designer provided FC+S
with sketch SKC-26 and a prototypical detail to add intumescent tape and cantilevered wing
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 92
walls in order to achieve the necessary fire rating. FC+S estimated there was 5,120 linear feet of
assembly required to be installed and would take 512 TA hours to implement the added work.
RFI 269 was written on August 29, 2013, prior to the effective start of Floor 2 module
production and was answered on September 4, 2013, the same day Floor 2 effectively started.
Subsequent to the receipt of the answer, the vendor's submittals were received by FC+S and
submitted to SHoP on September 16, 2013 and approved by SHoP on September 19, 2013. The
materials, which included studs, channel, angle and intumescent tape, were a six-week lead time.
Materials were received on or about October 31, 2013. Therefore, the critical path delay for
floor 2 due to the timing of the resolution of the design error was 57 days (September 4 to
October 31, 2013)
4. HVAC Ductwork
The Arup ductwork design per the contract documents was not developed to a level that
allowed a shop drawing to be generated. The design lacked critical items including location of
faade connections, microwave connections, and other necessary penetrations. United Air
Conditioning (the ductwork vendor from inception) used the inadequate contract documents as
the basis for the shop drawings submitted to Arup on July 31, 2013. There was no formal written
response from Arup to these shop drawings. To mitigate critical path delays to Floor 2 due to
Arup's failure to address the submittal, FC+S was forced to order materials shortly after this
submission was made, prior to a formal approval of shop drawings.
Those original pieces of duct work were delivered on or about August 5, 2013. Then,
FC+S encountered ductwork that would not connect to the facades and was not coordinated with
other MEP that was being installed.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 93
To date, Arup has never provided a detail of what the faade connection should look like,
but has, instead, stated that FC+S was responsible for submitting that detail on its shop drawings.
In other words, FC+S was directed to complete Arup's incomplete design.
In light of the problems encountered and Arup's stated position, FC+S asked United in
early October 2013 to fabricate the needed pieces to conform to the conditions seen on the
factory floor and to provide updated shop drawings to reflect all the modifications needed to be
done including the faade connection. The updated shop drawings were submitted on October
23, 2013 and Amp approved them on October 24, 2013.
Some of the new ductwork pieces arrived on or about October 28, 2013. Additional
pieces arrived after November 4th. The impact in procuring proper ductwork affected every
GTW for the 2nd Floor, delaying their completion on a day-for-day basis from at least October 1,
2013 to the receipt of ductwork on October 28, 2013, or 28 calendar days.
5. 12" Storm Drain Riser Support
Due to a design omission (there was no detail provided in the contract documents for any
support to the 12" storm drain), a support for the 12" storm drain had to be added. From October
1, 2013 when FC+S discovered the omission, through October 10, 2013, when Amp approved
the proposed remedy, ten (10) calendar days of delay to Phase II of the 2nd Floor Modules was
incurred.
6. Gas Pipe/Riser
As early as October 1, 2013, FC+S identified that the design did not specify the proper
hangers/supports for the gas pipe/riser. On or about October 9, 2013 FC+S submitted JPR
(vendor) submittal to Arup for approval. Although this work was necessary to complete Phase 5
of the 2nd Floor modules, as of November 14, 2013 Amp had not yet approved the submittal for
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 94
this work. The delay in rectifying this design omission extended beyond the November 6, 2013
date when FC+S transferred the 2nd Floor modules out of the factory. This work was performed
during the time when the 2nd Floor modules were not in the factory, so the delay to the critical
path ended on November 6, 2013, even though the overall delay to the 2nd Floor continued. The
total critical path delay for this issue was therefore limited to only thirty-seven (37) calendar
days (10/1/13 to 11/6/13).
7. Added Intumescent Tape between Floor and Ceiling Decks
The fire rated assembly as specified in the original design documents did not meet fire
rating code as described on Drawing G-004, Code Summary 0 Column Protection. In
answering RFI-360, the designer provided FC+S with direction to proceed to add intumescent
tape to achieve the necessary fire rating.
FC+S estimated there was 14,880 linear feet of intumescent tape required to be installed
and would take 880 TA hours to implement the added work. This affected 3,520 columns,
requiring .25 hours of TA labor per column.
RFI 360 was written on October 21, 2013 while Floor 2 module production was in
progress, and answered on December 10, 2013, long after Floor 2 modules were set aside in
order to start Floor 3 module production.
Floor 2 impact was 50 calendar days (October 21 to December 10, 2013), of which 16
days were critical (October 21, 2013 through November 6, 2013) when Floor 2 was moved aside
in favor of starting Floor 3.
This also impacted Floor 3. The delay to Floor 3 is captured in the section below under
Floor 3 Delays.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 95
2nd Floor Summary
In summary, aside from the labor productivity issues discussed in the IP section causing
the work to take longer even when otherwise not delayed by design problems, there were
numerous design deficiencies which caused delays to the POD fabrication process, as well as
module production. The cut-off for the impact to Project completion was November 6, 2013
because FC+S made a strategic, and correct, decision to move the 2nd Floor modules off the
production line on that date in order to start the 3rd Floor production. While there are numerous
other instances of design deficiencies causing stoppages of work during the module production
process, below is a summary of the significant impacts discussed above. The number of delay
days noted are not cumulative, as many of the delays overlapped.
2nd Floor Impact Summary
Impact
No.
Impact Description Start Finish CDs
1 Sanitary and Waste Vent Re-
Design
09/23/13 10/08/13 16
2 DT-09 Column Wrap 09/24/13 10/18/13 25
3 Added Cantilevered Wing Walls 09/04/13 10/31/13 57
4 HVAC Ductwork 10/01/13 10/28/13 28
5 12" Storm Drain Riser Support 10/01/13 10/10/13 10
6 Gas Pipe/Riser 10/01/13 11/06/13 37
7 Added Intumescent Tape 10/21/13 11/06/13 16
3rd Floor Design Impacts
The 3rd Floor module production started on November 7, 2013, the day after FC+S re-
staged the 2nd Floor modules outside of the assembly area. The 3rd Floor modules were
completed on or about January 22, 2014. During this 2 1/2 month period, design deficiencies
continued to impact module production.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 96
1. Core Design Issues
Multiple design issues surrounding the support of walls, continuity of fire ratings from
floor to floor, and a lack of details to complete the design of the walls inside the core resulted in
RFIs and field walk-throughs to resolve. The material could not be ordered until the design
questions were answered. This resulted in multiple causes of delay affecting the core work. To
segregate the delays is problematic as they are intertwined and continuing along with other
delays caused by the issues previously mentioned. The core design issues were primarily related
to framing conditions that were not picked up on the contract drawings. Below is a compilation
of the relevant RFIs affecting the Core Design, grouped by affected work.
(a) Shaft ways and the trash chute contained a number of issues with respect to
framing and support (RFIs 357, 365, 457)
(b) Issues with framing of shaft walls throughout the core where continuity of
sheetrock could not be maintained (RFIs 352, 352a, 366, 373)\
(c) Ceilings inside the stairs were also a design element not included with the
contract drawings (RFI 352 and 352a)
(d) Impact resistant sheetrock needed clarifications as the plans did not explain to
what extent they needed to be installed (RFI 379)
The referenced RFIs impacted production of the core modules by date answered:
RFI 352 (10/18/13) Ceiling for Emergency Stair - Answered 10/25/13
RFI 357 (10/21/13) Trash Chute Clearances - Answered 10/27/13
RFI 366 (10/28/13) Issues with Shaft Wall - Answered 11/1/13
RFI 365 (10/28/13) Stair Pressurization Shaft Detail - Answered on 11/4/13
RFI 379 (11/1/13) Impact resistant Gypsum - Answered on 11/4/13
RFI 373 (10/29/13) Shaft Wall Detail - Answered on 12/19/13
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 97
RFI 457 (12/19/13) Stair Pressurization Shaft - Answered on 12/20/13
These design issues were resolved by SHoP by December 20, 2013. This represents 63
days of delay in the core module production (10/18/13 to 12/20/13) simply to get the design
issues resolved. Critical path delay to Floor 3 was therefore 43 days (November 7, 2013 when
Floor 3 was moved into place through December 20, 2013 when the design issues were finally
resolved). Additional delays were incurred in procuring materials, plus the additional labor it
took to implement the design changes.
2. Added Intumescent Tape between Floor and Ceiling Decks
The fire rated assembly as specified in the original design documents did not meet fire
rating code as described on Drawing G-004, Code Summary 0 Column Protection. In the
answer to RFI-360, the designer provided FC+S with direction to proceed to add intumescent
tape to achieve the necessary fire rating.
FC+S estimated there was 14,880 linear feet of intumescent tape required to be installed
and would take 880 TA hours to implement the added work. This affected 3,520 columns,
requiring .25 hours of trade associates labor per column.
RFI 360 was written on October 21, 2013 while Floor 2 module production was in
progress, and answered on December 10, 2013, long after Floor 2 modules were set aside in
order to start Floor 3 module production.
FC+S received approval to proceed and immediately ordered material for the short term,
so it could perform the remedial work on modules already in production, while it prepared a
quantity take off for the long-term purchase of the materials necessary for future module
production. The materials for the 2nd and 3rd Floor modules arrived on or about January 10,
2013.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 98
Floor 3 experienced a critical path delay of 64 calendar days (November 7, 2013 when
Floor 3 was moved into place through January 10, 2014 when material arrived to implement the
change).
3. Temporary Roofing Protection EPDM
The contract documents did not contain any design details for terminating the temporary
EPDM roofing at the exterior wall system.
In answering RFI-206, SHoP required FC+S to provide a fully adhered roofing system,
not previously provided in the contract documents. This required FC+S to implement the
installation of the EPDM cover board immediately after the module frames were placed onto the
production line so the fasteners (screws) were not installed after the above-ceiling electrical
rough-in which would risk damaging the electrical installation. The remaining work was
installed after the modules were fabricated and removed from the production.
FC+S estimated would take 4.878 trade associate hours to implement the added work
while the modules were on the production line, and 9,756 trade associate hours while the
modules were in the weatherproofing area of the factory.
RFI 206 was written on July 23, 2013 and answered on August 12, 2013, before Floor 2
module production was in production.
The submittal (308-075323-0) for the EPDM roofing installation was submitted on
October 9, 2013 and was reviewed and approved by SHoP on October 16, 2013 (marked
"Provide as Corrected").
FC+S estimated it would take 4,878 trade associate hours to complete the extra work
when the modules were put onto the production line. This equates to one full day of work per
floor to accomplish the work, in advance of performing the rest of the critical work in the
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 99
modules. This delay would apply to floors 3 through 33/34, and would be linear; meaning none
of the extra work was concurrent with other delays. This equals 31 workdays of critical path
delay.
For the current request for an extension of time (data date 07/28/14), 8 workdays of total
delay on Floors 3 through 10 are accounted for in the delay analysis (one workday per floor).
The projected delay to the project going forward is 23 work days (approximately one month).
Solely for Floor 3, one day of critical path delay was experienced.
3rd Floor Summary
In summary, the labor productivity issues discussed in the IP section continued during the
production of 3rd floor modules. However, since numerous design deficiencies were resolved
during the 2nd floor module production, there were less design impacts experienced during the
3rd floor module production. Nonetheless, there still were design deficiencies encountered
which caused delays to the 3rd floor modules. While there are other instances of design
deficiencies causing stoppages of work during the module production process, below is a
summary of the significant impacts discussed above. The number of delay days noted are not
cumulative, as many of the delays overlapped.
3rd Floor Impact Summary
Impact
No.
Impact Description Start Finish CDs
1 CORE Design Issues 11/07/13 12/20/13 43
2 Intumescent Tape 11/07/13 01/10/14 64
3 Temp. Roof Protection
EPDM
11/07/13 11/07/13 1
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 100
4th Floor Design Impacts
The 4th floor module production started on January 23, 2014 and was completed on or
about February 27, 2014, a significantly shorter period of time than that taken to produce the 2nd
and 3rd floor modules. The 4th floor module production was the first floor performed after
eliminating the GTW labor concept discussed in the IP section, and instead assigning trade
associates to perform narrower sets of tasks based on their skill level. This resulted in increased
productivity, but labor productivity still remained at unacceptable levels due to the other factors
noted in the IP section.
The 4th floor experienced significantly less impacts due to design deficiencies due to the
fact that the solutions to design errors encountered on the 2nd and 3rd floors often times applied
to the 4th floor. Nonetheless, some design deficiencies did indeed cause delays.
Floors 5-10
Given the continuing changes, the issues arising from floors 5 and above are not
independently quantified. They are part of the cumulative impact on the Project. A sampling of
these issues are:
Above the floor rough for shower pans at floor 5: (Delays, new added work, poor design
coordination):
(a) Approved shower pan would not allow for code required plumbing system as
designed by engineer to fit above the floor and below the pan. Arup had no details
to show how to complete this work. SHoP picked a shower pan product that did
not interface with the rest of the designed plumbing (wouldn't fit with pipes)
(b) 1/21/14 the approved Shower pans were at factory
(c) Between the date above and below the factory was reviewing the pan and
attempting to find a solution using the shower pan in place and working on how to
install it without having to send the entire pod to the field for construction
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 101
(d) 3/10/14 - After multiple reviews, it was settled that the solution was to use a p-
trap and cut into the fire rated floor
(e) 3/17/14 sequencing of work was required to install p-trap and go under module
to apply required fire rated caulkirg at hole due to cutting into the floor
Faade Connections Not Detailed at Cantilevered 6th Floor
The 6th Floor presents a unique and atypical construction element in building in that the
floor is to cantilever out by 5 or 6 feet on the north and south sides. The design issue which
arose centered around the details provided by SHoP Architects as to how the faade panels were
to be connected to the underside of the cantilever. The failure of SHoP to provide clear and
workable details in the first instance (or after multiple later failed attempts), delayed production
and caused re-work to occur to these modules after they were off the pedestals.
The history is as follows:
3/6/14: RFI #539 was written to question some of the details on the contract drawings as to the
faade connections;
3/10/14: RFI was answered by SHoP but the confirmed details did not actually work/were not
buildable;
4/8/14: This and other related issues were noted by Kristopher St Claire (of FCS) during
construction while trying to utilize SHoP's RFI response;
4/25/14: New details were produced by SHoP to depict the new approach to connecting the
facade panels;
5/19/14: A new problem arose and RFI #636 was issued asking how to sequence the work and
still be able to move the modules;
5/19/14: SHoP answered this RFI the same day;
5/20/14: An email was issued directing the installation to be completed per the latest SHoP
issued design/RFI answers.
It is obvious that SHoP did not fully consider or design the faade connections for the
unique cantilevered portions of Floor 6 as it should have. This issue was discovered by FCS
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 102
while the modules were on the pedestals and the original designed approach proved unworkable.
This caused delay. SHoP then failed in its many attempts to provide a better design and
workable solution. This caused further delay. Once the final design was provided by SHoP, this
work had to be performed by trade associates while the modules were off pedestal. The majority
of this work was actually performed in the parking lot. Re-work was also involved in order to
accommodate the final design solution. This error and omission affected the 6th Floor.
G.6 Unit Coordination and delays for enlarged steel and fire rating continuity at door (4 guys
needed for 1 day to complete all newly-noted work) 6th Floor:
(a) Architectural drawings did not contain details to account for modified steel
columns inside unit G.6, resulting in redesigning the closet and adjacent door for
this unit and additional labor on the factory floor (designer beefed up columns and
this conflicted with door)
(b)
4/4/14 Architect sent a sketch addressing the issue the new detail required a
field walk with the Architect as it did not address all door and closet issues.
Enlarged Steel at Facades and 2 hour wrapping (6th Floor)
(a) Architectural design documents did not account for the enlarged steel at the
faade and thus a new detail was required that modified the ceiling inside
modules 0617 and 0621
(b) 10/2/13 RFI #319 Section Through Faade at 17/21 Answered on 10/7/13 At
(2) coordination meetings prior to 10/2/13. The detail was to wrap the enlarged
steel at the noted condition was discussed and the RFI and detail were generated.
Until this RFI was approved the work was not able to be completed.
EMR Room (Service Elevator Mechanical Room) on 7th Floor (coordination of trades and
delays):
(a) This room had to be re-laid out multiple times on account of poorly located
electric panels, ductwork and sprinkler heads by designers [poor design
coordination].
(b) Contract ductwork was not coordinated with equipment inside room and
additional FSDs were added, requiring multiple coordination attempts with
sprinkler and adjacent trades.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 103
(c) Ductwork was completed by subcontractors on 4/4/14, requiring re-work of
production drawings for factory construction and delaying the release of the
ductwork to the factory due to the errors and omissions that were discovered
(d) Duct delivery actually occurred on 4/18/14; installation began 4/22/14;
(e) Normally, the wall frames are prepared 1 week prior to construction, start. Here,
there was insufficient time to have all of the wall frames prefabricated for this
module since there was only 2 days from when coordination was done and the
duct had to be installed.;
(f)
Another issue arose on 5/12/14 RFI #634 Sprinkler Head in Doorway
Answered 5/14/14 - Sprinkler head inside space was installed per approved shop
drawings. However, the location put it under a large duct at an elevation that was
not accepted by the engineer on a walk-through of the space. The moving of the
sprinkler resulted in re-work inside the module after completion;
(g)
There was additional movement of the electric panel for the elevator multiple
times which impacted FCS' work. The fact that design coordination for the layout
ofthe electrical panel in the EMR continued well into the trade coordination of
the mechanicals for the same space (chiefly mechanical ducting and fire
suppression piping) resulted in a schedule delay and additional direct costs (extra
sprinkler piping / sprinkler heads along with additional labor to effect changes).
LT-07D EM Fixture that required re-design (affects floors 8, 9 and 1 1):
(a) Original Submission 8/2/13
(b) Final Approval 5/2/14
(c) Numerous emails between Rachel Janzen (FCS) and architect / lighting consultant
(d) Approximately 2 lost days of Rachel's time
(e)
Designer changed this fixture multiple times and took well beyond the contractual
timeframe to respond to submittals
10th Floor Mechanical Space (at least 9 days of delay to complete)
(a) Height Clearance
i. Coordination for the 10th Floor Mechanical Space was delayed due to a
late-issued requirement by the Architect calling for a height clearance
throughout the space of 3' x 6'-6". This meant that ductwork, mechanical
piping and electric lines previously coordinated on drawings had to be re-
drawn and moved so as to meet the clearance requirement.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 104
ii. This requirement was not called out in a design detail or drawing note, as
required by a complete and detailed design. Instead, SHoP noted this as a
code requirement during a coordination meeting on 5/29/14.
iii. At that time, all the subcontractors and vendors had completed their
respective work [models were done by the 5/29/14 meeting]. The result
was that FCS had to direct vendors to adjust their scope to accommodate
this new requirement, when the requirement should have been noted
clearly in the original design. This issue affected floor 10 only.
The history is as follows:
iv. 5/29/14 all models complete by subcontractors / vendors
v. 5/29/14 - issue mentioned by Architect in coordination meeting
vi. 6/11/14 - Updated models reflecting the change were completed so work
could be released
(b) Fan Coil Unit Relocation (Floor 10)
i. When attempting to coordinate FCUs per contract documents, numerous
conflicts with ductwork, equipment, equipment clear space, head
clearance and other trades were encountered.
ii. The MEP trades had already laid out their work per the design when it
became apparent that the MEP runs would have to be re-routed in order to
maintain the required clearances around the FCUs. Following a
discussion of this design error at a coordination meeting on 5/29/14, Amp
provided a revised layout of equipment so as to afford the needed
clearance that FCS and subcontractors were previously prevented from
developing by following to the original design.
iii. FCS lost time, at a minimum, between 5/29 and 6/12/14 due to this design
error and omission. This issue affected the 10th Floor.
The history is as follows:
iv. 5/29/14 all models complete by subcontractors / vendors
v. 5/29/14 - issue mentioned at coordination meeting
vi. 6/11/14 - Updated models reflecting the change were completed so work
could be released
vii. 6/12/14 coordination of the 10th Floor MEP space completed
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 105
Changes required for Amenity Bathroom Pod 9 (multiple floors affected)
(a) Multiple changes to BR POD 9 were required which either delayed development
of Surround Stone Panels or forced modification to them or required additional
coordination and construction delays which would not have occurred had the
design been locked in at an earlier date, as it should have been.
(b) 1/27/14 RFI #495 Pod 0927 and 1127 Fixture Swap Answered 2/11/14
Resulted in Delay of production drawings and stone shop drawings since the toilet
and sink needed to be swapped as a result of the unachievable MEP design
originally specified by Designers;
(c) 3/21/14 RFI #571 Level 07 BR Pod 9 Fixture Clash Answered 3/27/14
Resulted in changing what should have been a typical plumbing system inside the
wall of the pod to a modified system requiring additional coordination and
delayed production drawings
3/24/14 RFI #572 Unspecified Door types for POD 0927 and 1127 Answered
3/28/14 Failure to specify the proper door type for module resulted in delays to
order proper door and coordinate same on production drawings
4/17/14 RFI #593 All BR Pod Type 9 Answered 4/23/14 Missing electrical
outlets from architectural plans resulted in requiring additional coordination and
modifying production drawings
4/22/14 RFI 598 (3) Pod Type 9 Answered 4/22/14 Box out added to BR
pod as a result of incomplete plumbing design. This resulted in modifying
surround stone that was to come from China as well as delaying production
drawings
(g)
4/29/14 RFI 611 Pod Type 9BS Answered 5/2/14 Shower Assembly never
specified Not having the assembly of the shower specified resulted in
production drawing delays due to re-work when the proper items were specified
by SHoP
(h) 5/21/14 RFI 643 Not enough space for control valve at POD 9BS Answered
5/24/14 Pod construction was underway when it was noticed the approved
control valve was too large for the wall that was to contain it This resulted in
additional work on the factory floor, approximately 1 day
11th Floor Amenity Area Lounge Millwork and piping modifications
(a) Missing Architectural Design for Level 11 Lounge to conceal bathroom drainage
piping in a finished area. The architectural finishes for these areas was provided
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 106
by SHoP without recognition that this pipes would be present. Consequently,
SHoP had to redesign the finishes and account for how to conceal the pipes.
(b) 2/6/14 - RFI #506 Answered 3/13/14 Back and forth at coordination meetings
for over a month with the designers to provide details and drawings for the
required architectural finish work for the amenity space. This resulted in delaying
the completion of the Fulcro production drawings (since the architectural design
of the space was incomplete) and SHoP asked FCS to change the contract piping
layout and provide a drawing showing the limits of the space the piping would
occupy. This impacted the completion of coordination for the area as well as the
sprinkler vendor since no ceiling in this area could be finalized.
THE FAILURE OF B2'S DESIGN PROFESSIONALS
CONSTITUTES A MATERIAL BREACH OF THE CM AGREEMENT
AND CONSTITUTES A CAUSE OF CONTINUING DAMAGE
EXECUTIVE SUMMARY
Implicit both in the presence of a unique design and in the contractual structures forming
the B2 Project are concepts of partnership and cooperation among the parties, principles that are
inherent to the special circumstances of this Project and necessary to its success. As work began
and problems were being encountered in the factory and on site, Skanska sought out the
assistance of FC and its design team, with the expectation they would recognize that success in
this Project depended upon joint efforts at every step. Consistently, however, Skanska's
overtures were rebuffed, frequently with extreme antagonism and an outright refusal to engage in
a mutual effort to solve problems. One consequence of the total absence of cooperation by FC
and of its adversary stance on all matters has been the necessity for Skanska to obtain assistance
in its effort to resolve the many fabrication, assembly and financial issues now outstanding on
the Project. Any such resolution must take into account the contractual and claim information
set forth in this letter, and it must take into account also the serious design failures, errors and
omissions identified as a result of the independent design review as set forth below.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 107
The design brought to this Project by FC and its design team contains substantial errors
and omissions directly causing the cost and schedule overruns experienced to date and projected
to be experienced through Project completion. The most fundamental error of the FC design
team was its failure to recognize the B2 modular building as essentially different from a
conventional high-rise steel structure and its consequent failure to address the entire process
from an integrated design perspective in which the designer examined not only the
characteristics of the completed building but also the process and actions that would make it
possible to achieve the completed structure envisioned by the design. In particular, although not
to the exclusion of other omissions, the FC design wholly ignores the consequences of changes
in the characteristics of the modules as they progressed from bare frames at the Banker Steel
Company ("Banker") plant in Virginia to fully fitted out modules assembled at the Project site in
Atlantic Yards, Brooklyn, changes and consequences of which the design team and its modular-
experienced advisors could and should have been aware but which were plainly beyond the
knowledge of any construction manager or contractor. This defective design was produced by
FC and its consultants long before any Skanska entity had any contact with this Project, and
apart from already severe financial results, it is producing a building for which there can be no
certainty as to whether it will experience leaking at the thousands of joints between module
faade elements, both now and for the foreseeable future. Further, the FC design team also
provided a prototyping process apparently intended to demonstrate whether the modules as
designed in fact could be fabricated in the factory and assembled at the site on the planned
schedules and at the anticipated costs. Because the prototyping process itself was radically
deficient, it is not surprising to discover, after the fact, that it failed to reveal the design
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 108
deficiencies that underlie much of the fabrication, assembly, structural, schedule and cost issues
that together constitute the catastrophic state of the Project today.
The principal specific design failures identified to date include:
(a) Failure to recognize essential differences between conventional bare steel
("stick") construction and assembly of prefabricated modules.
(b) Failure to recognize that inevitably some number of modules will arrive on site
out of alignment.
(c) Absence of any design solution for the need to adjust modules in elevation to
achieve required vertical alignment of module columns
(d) Having designed the curtain wall to be assembled in the factory as part of each
individual module, the absence of any design to permit adjustment of the facade
panels in the field.
(e) Failing to resolve issues raised in the Thornton Tomasetti peer review report,
particularly as to adjustability of raked modules.
(f)
Providing a prototyping process that was insufficient to identify structural issues
that could arise during actual field erection of the building.
(g)
The absence of a designer's response to the prototyping report's finding that joints
between modules were more than 100% out of tolerance
(h) Providing a prototyping process incapable of testing the reality of proposed
scheduling or of cost estimates for factory work.
(i)
The absence of design criteria for achieving and maintaining alignment tolerances
in the factory, including for the use of match plates.
DETAILED DISCUSSION
1. Failure of Design Team to Provide Means of Adjusting Modules for Proper Assembly on Site
Because it was experiencing difficulty in setting and aligning the modules from the
beginning of assembly on site, the first structural issue Skanska had examined was whether the
distortions to the frames occurring during assembly could lead to structural distress. A
deformation analysis was performed on several representative frames, and it demonstrated that
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 109
distortions to the frames experienced in the assembly process are not a concern structurally. This
conclusion is consistent with a fundamental assumption on which the AISC Code of Standard
Practice is based: small residual stresses are expected and tolerated during steel fabrication and
erection, provided the work is completed according to Standard Practice. Structural integrity
notwithstanding, however, it was apparent from this study that the bare steel frames are relatively
flexible prior to fit-out in the factory, especially in their tendency to warp and rack in out of
vertical alignment. Thus, when a support is slightly off dead level, the frame will also rack
horizontally. This is especially true in the transverse direction which relies on rigidity through
frame action. As bare steel, the longitudinal direction is somewhat stiffer because of the
diagonal strap bracing, a characteristic that should have been clear to the design team from the
outset and should have alerted them of the necessity of dealing with such flexibility in the
factory.
(a) Original Design Did Not Allow for Stiffness of Modules
As erection progressed on the Project, it became apparent that although many of the steel
frames forming the modules have been assembled within tolerance, not all of the modules have
stacked with the level of precision required to maintain system tolerances as specified by the
design team. The most critical details with respect to system tolerance are the seals between each
module's individual factory installed faade panels. If these joints do not properly seal, the
building envelope will be compromised.
If the modules were erected as bare steel frames without prior fit-out, some warping of
the module's steel skeleton after release from the fabrication jig would not adversely affect their
erection on site, because the flexible modules could be warped back into place during erection
without compromising their structural integrity. Within the limits of the AISC Code of Standard
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 110
Practice, which is the reference standard in the Project specifications and New York City
Building Code, maneuvers such as this constitute a fundamental principle of steel design and
construction. In the case of this modular Project, however, the ability to warp/rack modules back
into place for final assembly is compromised by the stiffening of the finished modules when they
are fit out at the factory. The recognition that the modules would become stiffer during the
factory fit-out process, the consequences of that circumstance for the assembly of modules in the
field, and the need to deal with those consequences are a prime example both of design issues
peculiarly within the competence of the FC design team and of the failure of the design team to
treat this Project holistically and design an entire modular process. The absence of any means to
maneuver in the finished condition shows that no attention was paid to the fact that the modules
would be made rigid in the factory. For instance, exposed hard points could have been provided
in the design for attaching temporary bracing, jacks, come-alongs or other devices typically used
during steel erection to true members and systems into their final vertical alignment on site.
The modular system employed was represented as a ready-to-build, efficient system.
While the design provided some adjustability during final erection on site with respect to the
horizontal location of units in plan, it failed to include any adjustability in elevation (i.e.
plumbness of the columns). This is a clear design error, for without the ability to warp/rack the
units into place and plumb the columns, the only corrective measure available to the erector is to
slide the units horizontally. Such adjustments may move the module's column top closer to its
theoretical location but does not correct an out of plumb condition and on a cumulative basis,
depending on the tolerances in the modules immediately above, could result in an overall out of
tolerance condition. Because the design team mandated the Project to conform to tolerances in
three dimensions, but provided adjustment measures for only two dimensions at each floor level,
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 111
the erection team has been confronted repeatedly with situations in which the ability to adjust for
required tolerances is excessively constrained in comparison to the industry standards of steel
construction. While these design tolerances should be achievable in a conventional high-risc
design, the documents specifying the unique design for this building did not disclose to the
contractor that the tools normally used to align elements in the field would not be available, since
the module, "stiffened" by all the finishes applied in the factory, was not able to be adjusted in
the field. From the point of view of constructability, this is a critical failure in the B2 design.
(b) Thornton Tomasetti Peer Review
As early as May 7, 2012 an agenda prepared for a Thornton Tomasetti peer review
meeting asked, "What are adjustability measures if module is fabricated wide or racked?" In the
TT Structural System Review Report dated June 18, 2012, this issue is discussed at some length.
The agenda question is repeated in the Report's summary matrix at item G2 (page 9), and there is
a discussion on pages 25 through 27. The Report states, "In our experience, items can be out of
tolerance in the field even though the alignments were strictly monitored in the shop due to
shake-out and posting (sic.) welding effects." This supports Skanska's conclusion, reached when
forced by FC's conduct to make its own structural design review, that configuration changes in
the modules arriving on site were inevitable and accordingly a means of adjustment should have
been provided for; it also was advance warning to the FC design team that was not acted upon.
Further, on page 27 of the same TT peer review report, attention is drawn expressly to the
unique character of modular construction and to the fact that access to structural elements is lost
early in the process, and the recommendation is made that "that repair procedures for out-of-
tolerances or out-of-alignment elements or connections are evaluated in advance to avoid any
slowdown in the erection process." This again directly parallels a principal finding of Skanska's
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 112
subsequent structural review, that there needed to be provision for adjustment of modules that
arrived on site out of alignment; and again, compounding error upon error, the peer review
advice was not acted upon.
Both the peer review agenda document and the Report discussed above call out the
question of how the curtain wall would be attached to the modules, and the Report requests
"architectural drawings for further review." While the final resolution of this issue in the peer
review (if indeed there was one) is not yet known, the attention to faade issues and the request
for drawings demonstrate that the curtain wall design was certainly considered within the
responsibility of the design team. What we know today is that the fixed faade approach
selected by FC's design team taken together with the other elements of their modular design
have resulted in a situation where the integrity of the curtain wall will remain highly uncertain
until the FC design team acknowledges responsibility for the whole modular design and provides
some system for adjusting either the modules on which faade panels are placed or adjusting the
panels themselves after assembly of the modules.
(c) Enlargement of Match Plate Holes
It was clear from the beginning of module erection that match plates designed by Amp
were flawed. The match plates are the 3/8" thick plates which tie the modules together and are
detailed completely, including bolt holes and size, on Project Drawings S-750 through S-807.
Although the Amp drawings and specifications call for a 1/4" tolerance between columns in the
modules, the bolt holes in the originally designed match plates allowed for only 1/16" of
horizontal sliding of the units during on-site erection. Soon after commencement of erection,
Arup realized the building could not be assembled unless it enlarged the match plate hole
diameter through issuance of SSK265. This standing alone should have set off serious alarms in
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 113
the design team and resulted in a review of how tolerances in the module columns were going to
be handled. Moreover, although SSK265 references allowable reams that extend original holes
by 1/4" in a single direction, Banker's May 6, 2014 test report indicates that the holes were
reamed to 1 3/4" diameter. This allowed more room for an individual unit to be set in place;
however, it also created the potential for larger deviations from total system tolerance.
Enlargement of the tie plate holes to allow misaligned module columns to be connected thus had
the net effect of increasing the opportunity for a condition where the corner post above does not
align with the corner post below. Until the building is completed, no one can know how often
that opportunity becomes fact, but every time it does, it brings the likelihood of a leaking curtain
wall.
An alternative to enlarging the match plate holes to the extent approved by Arup would
have been to alter the module design in such a way as to allow adjustment in elevation via
warping/racking. As noted above, this could have been accomplished with hard points to which
temporary bracing or guy wires could be attached for the purpose of truing the modules in
elevation. The fact that Arup addressed the issue of module adjustability during erection only in
terms of plan position demonstrates that FC's design team continued to ignore the three
dimensional aspects of module alignment even as the module assembly process itself was
revealing the consequences of the underlying design error.
(d) Requirements of the AISC Code of Standard Practice
The American Institute of Steel Construction (AISC) Code of Standard Practice
specifically recommends how designers should handle special erection conditions in Section
7.10. Section 7.10.1(b) states:
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 114
The Owner's Designated Representative for Design shall identify
the following in the Contract Documents:
(b) Any special erection conditions or other considerations that are
required by the design concept, such as the use of shores, jacks or
loads that must be adjusted as erection progresses to set or
maintain camber [or] position within specified tolerances or
prestress.
Section 7.10.3 states:
Based on upon the information provided in accordance with
Sections 7.10.1 and 7.10.2, the Erector shall determine, furnish and
install all temporary supports, such as temporary guys, beams,
falsework, cribbing or other elements required for the erection
operation. These temporary supports shall be sufficient to secure
the bare Structural Steel framing or any portion thereof against
loads that are likely to be encountered during erection, including
those due to wind and those that result from erection operations.
Thus, the erector need not consider loads during erection that result from the performance
of work by, or the acts of, others, except as specifically identified by the Owner's Designated
Representatives for Design (FC's design team), nor those that are unpredictable such as loads
due to hurricane, tornado, earthquake, explosion or collision. Temporary supports that are
required during or after the erection of the structural steel frame for the support of loads caused
by non-structural steel elements, including cladding, interior partitions and other such elements
that will induce or transmit loads to the structural steel frame during or after erection, shall be the
responsibility of others.
According to this section of the AISC Code of Standard Practice, it was the responsibility
of the Owner's design team to identify the special erection condition of fully finished modules
and the attendant difficulties of locating these modules in plan and truing them in elevation
(Section 7.10.1(b)). Furthermore, while it was the erector's responsibility to determine the
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 115
temporary supports, guys, etc. required for erecting the "bare steel," it was not the erector's
responsibility to determine similar supports for loads caused by "non-Structural Steel elements,
including cladding, interior partitions and other such elements" (Section 7.10.3). Thus, the
erector was not responsible for the effects of finishes on the adjustability required for the steel
module frames during erection; this section of the Code can be further explained by the simple
truth that an erector is not in a position to have any knowledge of the effects of finishes on the
structural characteristics of a modular unit, not to mention the assembly consequences of such
effects.
(e) Conclusion
While the design did attempt to account for adjustability in the plane of each floor level,
it failed altogether to provide an opportunity to plumb the columns in the finished modules and
achieve correct vertical alignment of the modules during erection on site. In their unfinished
form as steel frames, the modules are flexible. Once finishes are installed, the modules become
much heavier and stiffer. In their finished state, higher forces are necessary to true them for final
assembly; and because no provision has been made to develop these forces, final assembly
cannot proceed according to the established norms of steel construction. The design of the
modules removed opportunities for the erector to use means and methods that are standard
practice, and did not replace these opportunities with sufficient alternative means and methods to
ensure proper adjustability on site. This violates the AISC Code of Standard Practice. The
design did not adequately address the fundamental steel construction principle that some
warping/racking of the units after their removal from the jigs and during and after installation of
finishes was to be expected, and it therefore would be necessary to correct the warping during
erection on site through the use of appropriate force.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 116
The structural drawings and specifications call for tighter-than-industry-standard
tolerances in the fabrication shop and in the field erection, primarily so as to assure fit-up of the
curtain wall panels which are installed in the factory and cannot be adjusted in the field.
Achieving tolerance is critical for achieving an effective weather seal with the curtain wall, but
adjustability to ensure that the building envelope is weather tight is lacking in the design. In a
typical steel frame building, this adjustability would come from four sources:
1. Plan position of the steel framing;
2. Elevation warping/racking of the steel framing;
3. Plan position of the slab edge and other structural faade supports;
4. Adjustment of the faade itself with respect to the building structure.
For the B2 Project as designed, however, the plan position of the modules (item 1)
constitutes the only source of adjustability. Other sources of adjustability are available in the
factory, but are no longer available on site in a manner consistent with the norms of steel frame
building construction. As the Project moves forward, FC's design team should develop
additional sources of adjustability for the faade panels on site. Depending on the precise needs
for adjustability and the most economical and effective means for providing such adjustability,
this new adjustability might be developed to come from sources 2 and 4 above in addition to
source 1. In the absence of such additional adjustability, the building is expected to continue
experiencing problems that will make it difficult or impossible to maintain the tolerance between
faade panel gaskets that is required to support the warranty of these panels and their
performance as a building envelope. This issue is particularly troubling when one considers that
the out of plumbness of assembled module columns can, depending upon the extent and direction
of variance of each module, be cumulative.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 117
While the full extent to which these problems will persist is difficult, if not impossible, to
predict, the necessity for additional adjustability to address these same problems is very clear.
Erection crews have had to struggle with bringing the module columns as close to specified
alignments as possible, using the limited resources made available by the incomplete design, and
large parts of the heavy cost overruns incurred in the field are traceable to this issue. Moreover,
in addition to the increased costs of assembly, a major and important consequence of the
problems discussed above is that it is impossible to predict that the building when completed will
perform as designed; and in particular, it is impossible to predict that the curtain wall joints will
be and, over time, will remain effective barriers to the passage of air and water in simple terms,
no one knows if the building is going to leak. There is risk in this Project substantially in excess
of a conventional high-rise commercial building, and that risk arises directly from a defective
design that ignores in important places the unique circumstance of a modular as opposed to
conventional high-rise structure.
2. Failure of Design Team to Provide Direction for Structural Aspects of Factory Fabrication
The failure of the FC design team to exercise design responsibility for the entire modular
building process, and not just for the completed structure, is further evidenced by FC's attitude
toward the factory work. At every juncture, FC and its design team have taken the position that
every aspect of factory operations was solely a matter of "methods and means", as if the factory
were a construction site and not a place where modules were being manufactured under
conditions that have little to do with ordinary construction. The failure of the design with respect
to the build out of the modules was highlighted by Arup's response to RFI 568, dated March 14,
2014, which had asked:
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 118
Please review and confirm the below items that need to be
performed in the FCS factory to mitigate matchplate, column and
curtain wall misalignment due to frame racking (this was sent in an
email on 3/4/2014).
2. Use connection plates at the top of all columns in the
factory to true up module frames prior to installation of the
primary walls and facades.
Arup encouraged the implementation of Provision 2 of RFI 568; however, it also claimed
that such a decision was within the contractor's means and methods, and therefore resided
outside of the design team's ultimate responsibility. Arup's position contradicts its position in
Drawings S-750 through S-807 with regard to detailed instructions for positioning the modules
in plan. Furthermore, Arup's position in this instance also contradicts the basis for Section 7.10
of the Code of Standard Practice, which distinguishes the erector's responsibility for means and
methods related to the erection of bare steel (the steel frame prior to the addition of finishes)
from the design team's responsibility for special erection methods and consideration of loads
imposed by non-structural steel elements, such as partition walls, facade panels and other
finishes. The Code of Standard Practice states explicitly that the erector is to account for such
loads "as specifically identified by the Owner's Designated Representatives," however no such
direction for vertical alignment was provided by FC's design team.
In this Project, by requiring that the units be finished at the factory prior to erection of the
steel, the FC's design team removed opportunities for field adjustment that the erector could rely
upon in a typical steel frame building and thereby made the fabrication in the factory all the more
critical. What the designers should have known and what the fabricator needed to know was that
the frames would arrive at the factory as relatively flexible structures almost certain to have
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 119
experienced some warping/racking out of vertical alignment and almost certainly out of
tolerance, and that they would leave the factory with little flexibility. To deal with this
circumstance, the designer should have provided a specific program to insure the completed
modules would be in proper shape for assembly on site, including tolerances applicable to the
modules while in the factory, instructions for surveying the frames once in place on the
pedestals, methodologies for bringing the frames into tolerance, and clearly stated methods for
keeping them in tolerance and as true as possible during the factory work. This is a design
responsibility because it is based on knowledge peculiarly in the realm of the designer and
because it relates directly to the ability of the overall modular design of the building to perform
as intended. Moreover, it could not have been imagined that there would be anything in the
experience of any fabricator operating the factory that could have formed the basis for "means
and methods" regarding those issues since they relate to the effects of non-structural steel
elements on the erection of the steel modules . Indeed, the concept of "means and methods" is
foreign to and not applicable to factory work.
Over time, the factory and Banker, working together on the basis of experience as
numerous problems were encountered, developed a series of approaches to the problems caused
by or not addressed in the Owner's original design. In addition to the installation of match plates
at the column tops per RFI 568, survey practices and programs were developed at various stages
of the factory process. This created the effective fabrication process absent from FC's design
and improved the assembly process in the field. This need to provide by trial and error what
should have been part of the design stretched out the factory's learning curve, increased costs
and extended the productions schedule.
3. The Prototype Project Was Not Properly Designed to Prove
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 120
Fabrication, Erection, Cost and Schedule Elements of the Project
Consistent with the idea that this modular building system is new, the design team
specified and oversaw the construction of a prototype structure in the fall of 2012. This was
preceded by extensive planning and design work, resulting in a set of prototype construction
documents used to build the prototype modules. Early on there were at least six matrices, headed
"Design/Engineering Testing & Prototyping", describing the activities and goals of the process,
together with two scope documents, all of which set forth in detail a substantial effort. These
documents also indicate that the proposed scope of the prototyping plan was reduced over time
from as many as 16 modules to the six in the final plan; and at one point it was proposed to stack
the test modules three high instead of only two, as in the final plan.
Arup provided Prototype Testing Status reports on October 29, 2012 and November 21,
2012. The November 21 report indicates that the prototype consisted of 6 modules, all of which
had been delivered by the report date. The four modules representing the 12th floor had been
75% fit out (with finishes) and two modules representing the 13th floor were just bare steel
frames and thus did not in any respect replicate conditions that would exist during actual
assembly of the modules. Amp's observed that in module 1218 "the end purlin was not lined up
with the outside of the column." In this area, the match plate bolt holes had been reamed to a
larger diameter in order to provide adjustability, foreshadowing the eventual decision behind
SSK 265 (discussed in the previous section) which was a response to a similar need to enhance
adjustability in the actual building. In addition to the Amp report, a SHoP Architects PC
("SHoP") report from December 8, 2012, including site observations from November 13, 2012
noted, "Joints between the modules did not hold the 1" tolerance between the two modules, and
in some cases this approached nearly 2-1/4".
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 121
Commenting on the erection of the two bare steel modules representing the 13th floor,
Arup noted: "The tolerances for the setting of the 13th floor modules proved to be within setting
limits and the speed of erection was truly impressive. On all accounts, the setting of the modules
was a complete success." Arup commented further, "the 13th floor modules did not have the
faade on during the set sequence the fit-up of the facades and the sealing of the mateline gap
has not yet been proven through testing."
Similarly the SHoP report concluded:
The work of the prototype has confirmed the feasibility of the
project design approach... In no case has the work on the
prototype suggested any flaws in the design approach that would
prove fatal to the scheme and we are not aware of any issues
stemming from the modular prototypes and/or the B2 Design that
would prevent or affect the construction of the B2 Property in
accordance with the B2 Design documents.
Although Amp and SHoP somehow declared the prototype and its erection sequence to
be successful, the prototype erection sequence failed to simulate the actual erection sequence in
several critical ways:
(a) the four 12th Floor units were not 100% finished;
(b) the two 13th Floor units contained no finishes (bare steel) and so could be aligned
according to the Code of Standard Practice;
(c) the four 12th Floor units were set under ideal shop conditions, which were likely
to be more level than the top of the 11th Floor in the field;
(d) the two 13th Floor units were insufficient in number to produce an over-
constrained field condition, such as where four units come together their corners,
or three units come together at a reentrant corner while they are constrained on
their other sides by other units; and
(e) two stories were insufficient to produce a situation where units within tolerance
could produce compounding errors that resulted in the system being out of
tolerance at a higher story.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 122
Considering these discrepancies between the prototype structure and the actual building,
the prototype plainly was not designed and constructed to represent critical erection conditions
and in fact it failed to reveal the serious problems that would be encountered in attempting to
assemble the modules to the required tolerances.
Apart from providing a prototype procedure that was wholly inadequate, FC's design
team ignored an important piece of information that the procedure actually did produce. The
very first Observation in SHoP's the December 8, 2012 prototype assessment reports that "Joints
between the modules did not hold the 1" tolerance between the two modules, and in some cases
this approached nearly 2-1/4." Nothing further is stated about this finding, but it is completely
inconsistent with the conclusion that "the setting of the modules was a complete success." At this
time it is not known whether FC's design team felt the prototype process was not meaningful or
somehow did not consider the 2'/2 gap between modules to be important. In any event, this is a
further indication that the prototype process was not serving an intended purpose. More than
that, this event should have raised a large red flag concerning the need for design attention to the
critical issues surrounding assembly of modules (as opposed to conventional steel members) on
site within the very close tolerances that FC's modular design of the building demanded. If FC
had not been so profit and schedule driven at this stage of the Project, if it had been willing to
step back and consider seriously the implications of its own prototyping information, the
possibility existed for catching at the outset an important problem in its design the inherent
tension between very tight assembly tolerances and the inevitability of some deformity in the
stiffened modules being delivered to the site. The enormous increase in site work resulting from
this lost opportunity has become, and unless corrected will continue to be, a very expensive
consequence of FC's haste.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 123
B2 HAS MATERIALLY BREACHED THE CM AGREEMENT
BY FAILING TO ISSUE CHANGE ORDERS AND DIRECTED CHANGES
EXECUTIVE SUMMARY
The Owner must issue a change order when there is a scope change requested or, among
other things, as a result of the fault or negligence of its design professional. (CM Agreement,
5.4 and 15). Section 15.3 addresses the instance in which the Owner and Skanska do not
agree to the terms of a particular change order. In that event, the Owner is to issue a Directed
Change providing for the undisputed adjustment in price and time. Upon receipt of the Directed
Change, Skanska reserves its claim for the disputed amount of cost and schedule relief.
Skanska is also entitled to full compensation for Force Majeure Events lasting more than
five (5) days and Owner Caused Events in all circumstances ( 5.4). Generally stated, a Force
Majeure Event is one beyond the reasonable control of Skanska. An Owner Caused Event,
generally stated, is a change in the Work requested by FC or resulting from the fault, neglect or
other negligent or wrongful act or failure to act by Owner, Owner's Representative, its Design
Professionals, and others for whom the Owner is responsible.
Outstanding requests for additional cost and/or time include:5
Bulletins
Field Cost Events
FC+S Cost Events
Anticipated Subcontractor Claims
The Owner has failed to issue change orders for most all of these items. They have
rejected change requests improperly and have disingenuously asserted lack of notice, when
5 Given the challenging nature of this Project and the failure in design and IP, issues are constantly arising.
Consequently some CEs may not be fully developed, whether it is racking module steel and/or faade costs, costs
resulting from transfer of work from factory to field and subcontractor claims. Additional CEs arose as a result of
ongoing or other issues. Consequently, the information set forth in this portion of the Notice of Termination is that
which existed as of July 1, 2014.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 124
indeed it is the rarest of occasions if in fact any occasion exists where notice is truly an issue.
Moreover, FC has repudiated its contractual obligation by refusing to issue Directed Changes.
These actions are a material breach of the CM Agreement entitling Skanska the right to provide
notice of termination and absent a cure, terminate the CM Agreement. On an individual basis,
these change requests entitle Skanska to additional compensation and a time extension.
DETAILED DISCUSSION
Bulletins
There are nine bulletins totaling $4,223,011 and the status is as follows:
BULLETIN STATUS
BULLETIN DATE PRICE
SUBMITTED
PRICE
SUBMITTED
CURRENT
STATUS
1 10/1/13, $1,291,000 OPEN
CE #3
2 10/1/13, $488,578 OPEN
CE #4
3 10/1/13, $657,040 OPEN
CE # 35
4 10/14/13, $47,372 OPEN
CE # 42
5B 4/29/14, $1,455 OPEN
CE # 62
Disputed CO 5
language.
Directed change
not issued
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 125
6 4/29/14,
CE # 63
$394,853 OPEN
7 4/29/14, $61,522 OPEN
CE # 64
8 4/29/14, $403,521 OPEN
CE # 93
9 6/20/14, $877,670 OPEN
CE 160
There is no indication that FC has any intention of acting in good faith to resolve any of
these Change Orders, Bulletins and issues. They are simply acting in furtherance of the FC
business ethic of denial, regardless of its contractual obligations and the legitimacy of the other
party's rights.
Some representative examples of this are offered.
First, a hardwood flooring CE was submitted to FC. It has not yet been priced, but it is
expected to exceed $1.5 million.
Hardwood flooring was specified for the Project. As everyone knows that this is a
modular project, the work is to be performed in the factory. Conditioning sufficient for the
installation of wood flooring was not included in the fit-out budget provided by FC under the
LLC Agreement.
Prior to February 20, 2014, Roger Krulak and others met with Armstrong Flooring at
which time the supplier advised that the installation of the wood flooring in the factory would
void the warranty. This was then stated in a letter addressed to Jonathan Clouser dated February
20, 2013 with a copy to Roger Krulak.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 126
Although the subject of past discussions, in May of 2014, Skanska "formally" requested
direction from FC as to whether to install the wood flooring in the factory and lose the warranty
or to install it in the field at an increase in price.
Scott Stutman responded on June 6, 2014 disingenuously claiming late notice and
asserting that it was Skanska and FC+S' responsibility because this is a "means and methods
item." In fact, FC and Scott Stutman had actual notice of the existence of the issue, that it was a
design error and that a cost and time impact would exist. This is proven without contradiction
by:
Roger Krulak's February 18, 2014 email advising of his meeting with Armstrong
flooring and the existence of "a specification problem."
Roger Krulak's February 19, 2014 emails advising that the issue "negates
modular installation," acknowledging the existence of a cost impact for field
installation and representing that "Scott" was advised of the issues.
In response Mr. Stutman actually alleged that the emails were taken out of context and
that a "design error must be proven" before Skanska can rely on 2.4 which requires Skanska to
"await further instructions from Owner" once it discovers and then reports the existence of
errors, omissions or inconsistencies in the B2 Design.
These actions repudiating responsibility for the effects of the design error constitute a
material breach of the CM Agreement.
FC also refused to pay for extended liability insurance. In part, FC objected to the
change, alleging a "Contractor Caused Delay". As to that, FC is wrong. As set forth herein, the
delay on this Project is based on Owner Caused Events and Force Majeure Events. FC also
refused to pay for insurance which falls within the original schedule. As to that, it makes
reference to an unwritten agreement that the insurance was to be shared by FC and Skanska as a
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 127
cost of the FC+S business, in contradiction to the fact that it is a required payment as an amount
in excess of an allowance in the CM Agreement. No such agreement exists and this failure to
issue a Change Order is a material breach of the CM Agreement.
Finally, FC has refused to follow the Directed Change provision in 15.3 of the CM
Agreement.
First, as to the quantum of the change order, if there are disagreements between the
parties, FC is required to issue a Directed Change and pay the undisputed amount, with the rights
of the parties reserved as to the balance in dispute. FC refuses to do so, evidencing that it is
either their amount or no change order will be issued.
Second, as to form, on change orders 1-3, FC improperly and intentionally included
language that payment of the change order constituted "full payment of the additional work
covered thereby and for any delay, disruption, cost or expense occasioned by reason of such
change and shall release Owner from any further liability. All other terms and conditions of the
contract are unchanged". (Emphasis added). The terms of the CM Agreement do not require a
waiver. In fact the CM Agreement is clear. Change Orders include only the "Costs of
Additional Work". These are the direct "sticks and bricks" of the change ( 15.2). Accordingly,
by issuing the change order in the improper form, FC intentionally sought to prejudice Skanska.
FC tried to further their misconduct in the May 2014 Change Order No. 4. Skanska objected and
returned the change order with language preserving for itself the right to claim impact. FC then
revised that change order going through a number of machinations as to language including
reserving to itself the right to challenge the change order at a later date both as to quantum and
entitlement while never addressing Skanska's concern; that being its right to assert the existence
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 128
of schedule impacts. While ongoing, FC refuses to issue a Directed Change for the agreed
amount of the change or pay for the agreed amount.
The amounts of change orders 4 and 5 are not in dispute. Skanska is entitled to payment.
Skanska has billed these amounts and FC has not paid the amount because Skanska will not
execute FC's form of change order.
Under these facts, the sums due and owing under the CM Agreement have not been paid
for a period of thirty days. Under the CM Agreement, Skanska may terminate the CM
Agreement under 14.7(b) as an amount properly due which has not been paid within 30 days
after it became payable.
FIELD COST EVENTS
After Cost Events are submitted to the Owner, an Authorization Request follows with the
final price for the change. The items identified below are only those Cost Events for which final
pricing has been provided. There are other CEs which have been submitted but for which
pricing has not been finalized.
SITE AUTHORIZATION REQUEST STATUS CHART
(Exclusive of Bulletin Pricing)
COR (AR)
NUMBER
DATE
SUBMITTED
DESCRIPTION DOLLARS
SOUGHT
STATUS
2 3/25/2013 Road / Curb
Modifications at
Intersection of
Navy & Tillary
Streets
$75,623 OPEN
9 11/26/2013 Furnish and
Install Glass
Protection on
$44,177 OPEN
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 129
South Facade of
Barclays Center
10 11/27/2013 MEP Tunnel
Additional Scope
$125,793 PRICE
APPROVED,
disputed Change
Order 04
14 12/16/2013 Stop Work Order
from MTA
$12,707 OPEN
15 12/16/2013 Civetta Work for
Roux (hazardous
fill)
$9,466 OPEN
16 12/18/2013 Existing SOE for
sewer line and
underpinning of
sewer line
$49,387 OPEN
17 5/5/2014 Trash Chute
Framing per RFI
118 & 205
$30,748 Rejected
19 2/10/2014 CE#0156 -
Civetta - Bollard
Modification
$14,256 OPEN
20 3/31/2014 FCS Schedule
Delay Impacts &
Associated
SUSA Extended
GC's
$28,427,465 Rejected
25 6/25/2014 Fulcro
Reconciliation
$1,113,534 Rejected in part,
7/23/2014
26 5/5/2014 Field Weld
Plinth Plates in
Lieu of Shop
Weld due to
Erection
$68,277 Rejected
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 130
Tolerances
27 5/5/2014 Furnish and
Install Additional
Flue Riser
Supports
$6,118 OPEN as to price
29 6/16/2014 Remove Decking
and Versaroc on
Mod 13-01 floors
2-7
$5,012 OPEN
31 6/25/2014 FCS Extended
General Liability
Insurance
$1,157,796 Rejected,
7/23/2014 (as
Contractor
caused delay)
32 6/25/2014
7/15/14 (rev 1)
FCS Insurance
Adjustment
(Deductible and
Stop Loss Cap)
$255,099 Rejected,
7/23/2014 (as
budgeted factory
cost and for
disputed mark-
ups)
TOTAL
TOTAL
excluding AR 20
$31,395,458
$2,967,993
The information above demonstrates that FC has persistently failed to timely and fairly
address Change Order Requests (COR's). There is approximately $2.9 Million dollars pending
in submitted CORs, exclusive of the amounts submitted as Bulletin pricing (which is another
$4.2 Million for Bulletins 1 through 9) and the rejected COR 20. Some CORs have been
pending with FC since 2013, while others which should be routinely acknowledged and
processed as valid extra work claims are subject to multiple rounds of negotiation and emails by
FC. The end result is that Skanska is unjustly deprived of payment for clear items of extra work.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 131
As seen in COR 10 for the MEP Tunnel Additional Scope, while both parties have
acknowledged this as additional work and FC has agreed to the price, FC has frustrated the
payment process by insisting, first, that waiver language be included in the change order to be
signed by the parties, despite the fact that there is no contractual basis for it to insist that such
language be included. While Skanska has demanded the issuance of a Directed Change, FC
continues to refuse to issue a Directed Change for items of acknowledged extra work, where any
issues remain in dispute. If FC complied with the CM Agreement, it would issue the Directed
Change and pay the undisputed portions of the COR. The disputed portions of the COR would
be preserved for later claim resolution. FC's unwillingness to issue Directed Changes or pay
undisputed portions of CORs is again manifest in its recent response to COR 25 "Fulcro
Reconciliation," for amounts FC knows to be owed for sums in excess of the allowance provided
for this work item in the agreements. As opposed to following the CM Agreement's Directed
Change procedure, FC has been content to act in a commercially unreasonable manner to deprive
Skanska of payment. Stated otherwise, the Directed Change provision is a contract term. It was
specifically negotiated to protect Skanska and because it removes leverage from FC, they have
steadfastly refused to honor it.
FC's dismal record in timely processing CORs becomes all the more shocking when
viewed in light of the fact that, to date, only three CORs have been approved by Owner. Those
three CORs date back to May, November and December 2013 and amount to a total value of
$79,860 all for extra work to date. On a Project of this magnitude and one with extra work
claims approximating $10 Million, FC's total payment of approximately $80,000 is a stark
indictment of how FC abusively handles the change and payment process.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 132
FC+S COST EVENTS
There are 65 Cost Events which have been submitted by FC+S to Skanska.
FC+S CE STATUS REPORT
Factory
CE No
Description RFI
Created
RFI
Answered
Amount
Sought
TT001 Temporary Roofing
Protection EPDM (RFI 206)
7/23/13 5/20/14 $1,519,840
MC046 Bus Duct Switch AIC
Changed (RFI 597)
4/22/14 4/29/14 $32,827
TT003 Under Cabinet Gap Closure
(RFI 570
3/21/14 3/28/14 $36,021
TT004 LT-04 Diffuser (RFI 430) 11/21/13 11/21/13 $16,076
TT005 LT-21 Additional Fixture
Heads (RFI 609)
4/28/14 5/5/14 $2,997
TT006 Additional LT-04 Lighting
in Amenity (RFI 627)
5/8/14 5/15/14 $907
TT007 SVT Flooring (RFI 450) 12/18/13 12/20/13 $30,661
TT008 Pocket Door Wall Interior
Finish (RFI 583)
4/9/14 4/16/14 $20,743
TT009 POD 9A Door Added (RFI
572)
3/24/14 3/31/14 $3,170
TT011 Sprinkler Piping-Soffit
Coordination Amenity
Levels 07, 08, 09 (RFI 573)
4/1/14 4/8/14 $7,292
TT012 Closet PTAC Location P.6
P.7 (RFI 578)
4/2/14 4/9/14 $2,948
TT013 Panel Relocation E.2A (RFI
579)
4/3/14 4/10/14 $9,855
TT014 Bathroom POD 1B at Level 4/7/14 4/14/14 $6,427
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 133
07 Mateline Connections
(RFI 582)
TT015 PTAC Sleeve Extension
(RFI 633)
5/12/14 5/19/14 $1,624
MC069 McGrath Backcharge for
0836 Faade
6/4/14 6/4/14 $1,012
TT017 Relocate Vent at Riser 14
(RFI 595)
4/21/14 4/28/14 $329
TT018 LT-22 Finish Specification
Required (RFI 626)
5/8/14 5/15/14 $996
TT020 NCR Gap Between
Electric Range (ER-30) and
Backsplash (RFI 651)
6/4/14 6/11/14 $18,642
TT021 Module Strap Securing
HardiBoard (SSK-242 SSK-
243
3/20/13 3/20/13 $38,998
TT022 Exit Sign Upgrade
(Submittal 286)
10/15/13 10/15/13 $13,939
MC066 Bullet 3 + 6 Door Change
Order
8/9/13 8/9/13 $925
TT027 BR Pods 9A Services
Altered (RFI 598)
4/22/14 4/29/14 $3,512
TT030 Soffit for Electrical VML
Connection Mods 0717 &
0721 (RFI 612)
4/29/14 5/6/14 $201
TT031 Shallow Sump Floor Drains
(RFI 620)
5/1/14 5/8/14 $771
TT032 Coordinated Lighting in
Mechanical Space Level 05
(RFI 515)
2/14/14 2/21/14 $1,708
TT033 Column Wrap Detail GL- 2/18/14 2/21/14 $1,327
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 134
7/GL-4 Intersection
(RFI518)
TT024 Fire Rated Access Doors
(RFI 499)
3/11/14 3/18/14 $8,443
TT026 Shower Fixture BR POD
9BS (RFI 611)
4/29/14 5/6/14 $908
TT034 Additional Junction Box
Needed (RFI 548)
3/7/14 3/14/14 $374
TT035 Exposed Ductwork in
Weight Room Level 08
(RFI 552)
3/7/14 3/14/14 $228
TT036 Added Soffits in Conflict
with LT-07 Level 09 (RFI
589)
4/11/14 4/18/14 $590
TT037 Closets in Units A.2 & A.5
(RFI 412 & 489)
1/22/14 1/25/14 $9,267
TT039 Elevator Overrun Ceiling
(RFI 601)
4/24/14 5/1/14 $663
TT038 Missing Arch and Elect
Design for PTAC MOD
0725 (RFI 635)
5/12/14 5/19/14 $597
TT041 Architectural Finish
Discrepancies Level 08
(RFI 553)
3/7/14 3/14/14 $1,848
TT045 Finish Schedule Floors 33-
34 (RFI 500)
1/31/14 2/3/14 $21,868
TT043 5th Floor Mystery Space
(RFI 501)
1/31/14 2/3/14 $8,258
TT040 Decora Light Switch
Change (RFI 423)
11/15/13 11/21/13 $21,511
TT044 4th Floor West Wing 2/3/14 2/6/14 $218
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 135
__.
Column Welds That Are
NCM (RFI 502)
TT046 Level 11 Piping Clash with
Amenity Lounge Millwork
(RFI 506)
2/6/14 2/9/14 $1,480
TT047 Kitchens and Furring Walls
for Piping (RFI 223)
8/1/13 8/8/13 $3,431
TT050 Column Wrap Detail
Horizontal Section Through
Acute Corner (RFI 239)
8/13/13 8/20/13 $3,802
TT051 Column Wrap Detail
Horizontal Section Through
Obtuse Corner (RFI 238)
8/13/13 8/20/13 $5,493
TT052 Column Wrap Detail Plan
Detail at C.L 7, 5, H (RFI
240)
8/13/13 8/20/13 $8,209
TT053 Column Wrap at Brace
Frame Perimeter Condition
(RFI 269)
8/29/13 9/5/13 $62,670
TT054 Fire Rated at Floor and
Ceiling Decks (RFI 360)
10/21/13 10/25/13 $144,284
TT055 Missing Hard 1A01 and
1B01 (RFI 233)
8/12/13 8/19/13 $675
TT056 Fire Rated Assembly at
Exterior Walls (RFI 268)
8/29/13 9/5/13 $266,229
TT057 PTAC Installation Issues
(RFI 363)
10/25/13 11/6/13 $79,756
TT058 Issues with Shaft Wall (RFI
366)
10/28/13 11/4/13 $6,340
TT060 Shaft Wall Detail (RFI 373) 10/29/13 11/5/13 $25,179
TT062 Missing Mateline Detail in 6/10/13 6/17/13 $2,147
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 136
Unit A.2 (RFI 140)
TT064 Trash Chute Support (RFI
118)
5/24/13 5/31/13 $1,652
TT063 Frame Screen Horizontal
Section Through Rotated
Columns (RFI 190)
7/11/13 7/18/13 $12,808
TT065 Floor Finish, POD 1 at WD
Closet (RFI 101)
5/15/13 5/21/13 $6,245
TT066 Reflective Ceiling Plan
Floors 2 & 3 Need for
Soffit Locations (RFI 103)
5/15/13 5/21/13 $2,012
TT067 ER-30 Range Electrical
Design Conflict (RFI 497)
1/30/14 2/2/14 $3,630
TT068 Fire Extinguisher and
Cabinet Models (RFI 226)
8/5/13 8/12/13 $8,115
TT069 Countertop Overhang (RFI
511)
2/12/14 2/15/14 $90,141
TT070 Missing Closet Ceilings
(RFI 147)
6/11/13 6/18/13 $83,793
TT073 Bulletin 6 8/2/13 $106,582
TT076 Bulletin 7 9/3/13 $50,000
TT077 Bulletin 8 10/17/13 $66,650
TT078 Bulletin 9 2/14/14 $313,189
MC068 Replacing Gray Electrical
Panel Covers (RFI 662)
6/13/14 6/20/14 $621
TT075 PTAC Sleeve and Furring
Wall Depth Discrepancy
(RFI 661)
6/13/14 6/20/14 $43,552
TT078 Putty Pad for Fire Rating at 2/28/14 3/5/14 $22,326
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 137
Abutting Outlets (Submittal
438-260533)
TT080 Ceiling Type for Emergency
Stair (RFI 352A)
7/2/14 $30,038
TT083 Bulletin 1 3/20/13 $317,158
TT084 Bulletin 2 4/11/13 $94,349
TT085 Bulletin 3 6/10/13 $417,275
TT081 Bulletin 4 6/14/13 $7,324
TT082 Bulletin 5 6/28/13 $0
TOTAL
TOTAL EXCLUSIVE
OF BULLETINS
$4,135,676
$2,763,149
Skanska submitted notice of the CEs upon its receipt of same from FC+S. Skanska's
field costs are being computed to complete the submission and it is expected that they will be
submitted shortly.
Moreover, 54 of the 64 Cost Events51 arose during the timeframe when Roger Krulak was
running the factory and/or Scott Stutman was the Design and Technical Service Director. Of the
64 Factory Cost Events, 25 fell within Mr. Krulak's tenure and 29 others, exclusively during Mr.
Stutman's tenure. Stated otherwise, 54 out of the 64 Cost Events arose when FC employees were
in the positions of leadership.
It was Messrs. Krulak and Stutman who had first knowledge of changes related to these
issues, and it was Messrs. Krulak and Stutman who owed the duty of fidelity and loyalty to
FC+S, to furnish notice to Skanska, so that Skanska could then furnish notice to B2. They did
51
This excludes CEs included in Bulletins.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 138
not do so. In so doing, they sought to guard the financial interests of FC to the damages of
FC+S.52
SUBCONTRACTOR CLAIMS
Subcontractors, particularly Banker and M.G. McGrath, Inc. ("McGrath"), have advised
that a claim for additional compensation will be forthcoming, with McGrath asserting an amount
without backup of $2.5 million and Banker explicitly advising that its claim will be based on the
inadequate design and IP, as well as representations made to it by FC prior to Banker ever
submitting a proposal to Skanska. Banker advises that it will also rely on its involvement with
FC "early on" as a basis for its claim. Skanska has advised FC of its intent to properly process
and submit subcontractor claims to the Owner for appropriate action and payment as warranted.
However, since no actual claim has been received, nothing can be vetted or processed.
FC HAS MATERIALLY BREACHED THE CM AGREEMENT
DUE TO ITS REPEATED AND INTENTIONAL FAILURE TO MAKE
PAYMENT TIMELY AND ITS REPUDIATION OF ITS OBLIGATIONS
TO MAKE TIMELY PAYMENTS
Mid-month and final month payments are due under the CM Agreement timed from the
submission of a "clean invoice" ( 6.2). A clean invoice is achieved after a meeting in which the
pencil copy is reviewed. The clean copy is then uploaded to "Live Link."
If documents or further information is required of Skanska, which is not uploaded with
the clean invoice, that information is due by the time of payment.
There have been disputes between the parties over the nature and quality of the
supporting information required with Skanska always providing what has been requested.
52 In fact, it is known that while "working for FC+S", Mr. Krulak was creating documents regarding production for
FC's use and which FC through Robert Sanna has refused to disclose. It is a fair characterization that Mr. Krulak
was a "spy" for FC while pretending to work for FC+S. On the LLC level, this conduct would clearly constitute a
breach of the covenant of good faith and fair dealing subjecting FC to liability.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 139
Notwithstanding the fact that the due date for payment is timed from the submission of the clean
invoice ( 6.2(a) and (b)(ii) and (iii)), without any justifiable reason and solely to delay payment,
FC has continually ignored the terms of the CM Agreement and timed payment from the date
Skanska uploaded the last document. Skanska continues to protest FC's actions. Regardless of
FC's continual and systematic letter writing campaign of denial, FC has materially breached the
CM Agreement.
FC FAILED TO PROPERLY AND TIMELY FUND OR
ADMINISTER THE IMPREST ACCOUNT REQUIRED BY
THE CM AGREEMENT, WHICH IS A CONTINUING BREACH
OF THE CM AGREEMENT
An Imprest Account was required to be established by FC upon the signing of the CM
Agreement. It was to be established to ensure that security existed for payment on account of
future work as the "next" payment to become due was to be deposited with the current payment
already existing in the account. It was also to expedite payment by authorizing Skanska to
withdraw payment on the due date. The account was not opened as required. Demands were
made by Skanska, and while FC made promises, it did not establish the Imprest Account until
July 2014. Since then, FC has continually failed to properly fund and administer the Imprest
Account. It has also frustrated Skanska's ability to monitor the Imprest Account.
The Owner is not funding the account as required by the Agreement so as to maintain the
balance in accordance with the Payment Schedule. Under Article 6.2 (f) of the Agreement,
Owner is to continually fund the account "so that the balance of the Imprest Account is no less
than the amount shown in the Payment Schedule as the next sum payable from the Imprest
Account." (Emphasis added). Recent correspondence in connection with the short payment of
Payment Application # 34 reveals that the Owner is only funding the account up to the amount it
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 140
believes is currently due and not to the amount of the sum next due for payment under the
Payment Schedule. The Owner is failing to provide the required security bargained for under the
CM Agreement and is using the Imprest Account as a means of delaying payment, instead of as a
tool for expediting payment as contemplated by the CM Agreement.
Further, as currently administered, FC is impeding Skanska's contractual right to monitor
the Imprest Account balance. Pursuant to Article 6.2 (f), " [t]he parties agree that Contractor
shall monitor the Imprest Account balance to assure that it contains adequate funds. If additional
funds are required to cover such amounts, such additional funds shall be deposited into the
Imprest Account as mutually agreed between Owner and Contractor." To date, despite request,
FC has not permitted Skanska to have online access to the account to effectively monitor it,
citing instead FC's "company policy" of not allowing such access. These acts and omissions
constitute a material breach of the CM Agreement.
FC HAS MATERIALLY BREACHED THE CM AGREEMENT
AS IT HAS FAILED TO PROVIDE SECURITY FOR PAYMENT
TO SKANSKA AS REQUIRED BY LAW
The property upon which the Project is being constructed is owned by a public entity.
The Project is being constructed by a private party, FC. Section 5 of the Lien Law of the State of
New York is applicable to this matter. It requires that the private entity (FC) "post, or cause to
be posted, a bond or other form of undertaking guaranteeing prompt payment of monies due to
the contractor, his or her subcontractors and to all persons furnishing labor or materials to the
contractor . . .".
On two occasions, Skanska made demand upon FC for a copy of the bond or undertaking.
On each occasion, FC ignored Skanska's demand.
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 141
Finally, on or about July 24, 2014, General Counsel for Skanska demanded a straight
answer to the question as to whether or not a bond existed. In-house counsel for FC, John Hunt,
admitted that a bond was not posted or issued.
FC's failure to comply with the law is a material breach of the CM Agreement.
FC HAS MATERIALLY BREACHED THE CM AGREEMENT BY FAILING
TO PROVIDE REASONABLE EVIDENCE THAT THE OWNER HAS
MADE FINANCIAL ARRANGEMENTS TO FULFILL ITS OBLIGATIONS
UNDER THE CM AGREEMENT
Section 4.3 of the CM Agreement requires FC to furnish evidence that FC has made
financial arrangements to fulfill its obligations under the CM Agreement. The furnishing of this
information is a condition precedent to Skanska's obligations to continue the work.
Changes in the work exist. In addition to the sums due on account of Force Majeure
Delay Events and Owner Caused Delay Events, there is approximately $10 million outstanding
in change order issues.
As of April 28, 2014, David Berliner advised Richard Kennedy that FC's lending
institution has stopped funding. This fact was confirmed by Robert Sanna on July 7, 2014. As
noted previously, FC has not furnished a bond or undertaking guaranteeing payment to Skanska,
as required by 5 of the Lien Law of the State of New York.
Skanska made written requests on two occasions that FC provide financial assurances as
required by 4.3 of the CM Agreement.
After refusing to do so, in a letter dated August 1, 2014, Robert Sanna materially
breached the CM Agreement on behalf of FC as he, again, refused to provide reasonable
evidence that the Owner had made financial arrangements to fulfill its obligations under the CM
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 142
Agreement and further stated that FC would not respond to any further communications
requesting financial assurances.
The information provided by Robert Sanna on August 1 demonstrates only two things.
First, there is substantial debt encumbering the property and no evidence of loan
agreements was provided or the availability to draw on proceeds from loan agreements.
Second, he made reference to Forest City Enterprises, Inc. as B2's parent and its SEC
filings for proof of sufficient equity/liquidity necessary to complete the construction of B2. This
reference falls short of identifying that financial arrangements exist.
Based upon FC's failure to provide information as required by 4.3 of the CM
Agreement and its repudiation of any intention of providing reasonable financial assurances in
the future, it has materially breached the CM Agreement.
DAMAGES
Individual changes to a contract are priced by the direct cost of the additional work,
together with the appropriate mark-up. Additional time is sought if it can be demonstrated that
the individual change would result in a delay to the completion of the Project. However, when
the number of changes becomes excessive, and/or intertwined with other causes of delay, the
labor productivity on base contract work, and previously negotiated change order work, is
impacted which creates "cumulative impact". Cumulative impact is the effect of a series of
changes, design clarifications, late responses to requests for information (RFIs) and other work
on labor productivity and project cost.
Contemporaneously measuring the impact of a single change on the Project is not
possible because the effects of cumulative impacts are comingled along with other causes of
labor overruns. Accordingly, it is sufficient to demonstrate that an excessive number of changes
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 143
occurred and caused a ripple impact on productivity because there is no way to specifically
identify the effect of each change when they are constant and continuing.
The cumulative impact of changes on this Project start with the incorrect IP and continue
through the discretionary design changes and the changes caused by the incomplete and non-
detailed design. Collectively, there exists a sustained negative effect on the ability to efficiently
produce modular units. These impacts have increased the amount of labor hours required to
perform base contract and change order work. The amount of increased labor hours alone due to
the changes and other impacts experienced in the production of modules through Level 10
amounts to approximately 180,500 hours (roughly 245,100 actual v 64,600 planned).
This increase in the amount of manhours required to produce modules could never have
been anticipated given the information available and assurance of excellence and reliability of
the IP provided in the Opportunity Brief and continuing to the execution of the CM Agreement.
The actual rate of production of modular units has been and continues to be significantly
less than that professed by FC, and relied upon in pricing and planning the work. The causes of
this loss of productivity are numerous and pervasive, so much so that the ability to segregate
with precision that portion driven by the cumulative impact of the changes versus the myriad
other impacts53 is impossible.
Based on the cumulative impact caused by FC to the Project as described in this letter,
Skanska's damages address the anticipated costs to be incurred based on the promises of FC
which resulted in the Contract Price and comparing it to the amount actually incurred based on
53
Other impacts include, but are not limited to: FC's Estimate (ongoing), Lack of Learning Curve (through roughly
May 20 14, GTW manufacturing process (ended after Level 3), Failed IP (ongoing) and Poor Labor (ongoing).
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 144
the failures of FC, as discussed above. As forecasted on July 1, 2014 the anticipated amounts
due Skanska through Project completion are:
Atlantic Yards B2 Project
Anticipated Amounts due as of
July 1, 2014
Field
Field Overrun 4,149,176 A
Skanska Field changes submitted to 2,967,993 Excludes out of scope FC+S CEs
Owner
Design Bulletins 4,223,011
Skanska GC Cost in Field Changes
Lost Fee/Savings 4,646,363 B/C
Total Field 15,986,543
FC+S
Trade Laborers
22,715,108
General Conditions
13,997,072
36,712,180
Materials including sales tax 19,289,186 Excludes out of scope FC+S CEs
reflected below
Insurance 2,551,077
Drawings 1,787,234
Total FC+S Cost Events 2,763,149 Excludes FC+S Bulletin costs
Less Labor in Cost Events (1,008,103)
Less General Conditions in Cost
Events (330,653)
Less Drawings in Cost Events (14,861)
Total
61,749,209
Less Current Budget
(32,550,087)
Total FC+S
29,199,122
Subguard/General Liability 2.25% 854,880 F=(A+B+C+E)*2.25%
Total Before Fee
46,040,545 G=D+E+F
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 145
Fee 9% 3,717,201 Applied on G less $2mn Fee
Holiday, additional insurance cost
and additional drawings cost
Total 49,757,746
Items not included in the above computation are:
2" Floor FCRC Builders Risk Claim 845,000.00 2
nd
Floor and subsequent
damage
3rd Floor FC+S Business GLI for Damage
TBD
re: Water Infiltration During Winter
Transfer of Work from Factory to Field TBD
Subcontractor Delay Claims TBD
Racking Module Steel Added Cost for TBD
Adjusting in Field
Racking Module Faade Added Cost for TBD
Adjusting in Field
Skanska Seconded Overhead Support Costs TBD
Unpriced Field Cost Events
TBD
Unpriced FC+S Cost Events
TBD
Atlantic Yards B2 Owner, LLC
August 8, 2014
Page 146
CONCLUSION
The matters set forth above are not all of the breaches committed by FC, or all amounts
due to Skanska arising out of or related to the CM Agreement, or the agreements between related
parties and affiliates. Rights to recover these sums from FC and its affiliates and third parties are
explicitly reserved and maintained. The matters above are, however, the specified breaches upon
which Skanska has delivered its Notice of Intention to Terminate.
Very truly yours,
Richard Kennedy
Co-Chief Operating Officer
Copy: Atlantic Yards B2 Owner, LLC (Via Hand Delivery)
1 MetroTech Center
Brooklyn, New York 11201
Attention: David L. Berliner, Esq, S.V.P & Secretary
Morrison & Foerster, LLP (Via Hand Delivery)
1290 Avenue of the Americas
New York, New York 10104
Attention: John J. McCarthy, Esq.
Fax No. 212-468-7900