Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
INTERNSHIP REPORT
MUHAMMUD SALMAN ALI SIDDIQUI
Aug 1st to 31st october 2013
Bayer crop science, korangi, karachi site
Submitted to
honorable sir khalid latif
plant/site manager (bcs korangi site)
1
Internship Report- Salman Ali Internee At bayer crop science, korangi site aug 1st 2013
to oct 30th 2013
Table of Contents
Introduction of Electrical Network:.............................................................................. 5
INPUT ELECTRIC SOURCES TO CAA GRID STATION.................................................. 5
DETAIL OF FEEDERS.................................................................................................... 5
Breakup and Assignment of Substations:................................................................ 6
LETTER OF TRANSMITTAL
Dear Sir:
M.SALMAN ALI
Internee
ACKNOWLEDGEMENT:
safety clamps :
A total of 30 earthing clamps were ordered , 20 have to been installed at the
site , among 20 , 19 has been installed , 10 safety clamps are extra for future
needs ad purposes.. it will be indicate whether our system is safely earthed
or not, if its green light starts blinking ,it will indicate that our vessel or
structure is properly other wise not.. all of the safety clamps used at our bcs ,
korangi site is made by NEWSON GAYLE, an american leading manufacturer
and all of them are battery operated
DETAIL OF FEEDERS
JTC FEEDER
SR.
NO
.
1.
2.
3.
4.
5.
FEEDER #
CONNECTED
LOAD (KW)
LOCATION
BH-620
BH-621
BH-622
BH-623
BH-625
3200
3885
3771
3085
400
Sub-Station West
Utility Building-II
Utility Building-I
Sub-Station East
Vault Room I
6.
BH-627
TOTAL
400
14741 KW
15 MW Approx
Vault Room II
There are total of 6 Substations. Of which 5 are proper substations and one is
a KIOSK.
TH PANEL ROOM:
We worked in the TH panel room to make it less messier and installed and shifted
the workshop panel in the workshop from the T.H panel room so that all the
Jinnah Terminal is divided into the East and West Wing. Where east is the
International side and West is the Domestic transit side.
Substations are as follows
1
2
3
4
5
6
TASK ASSIGNED:
Worked on the single line diagrams (sld's) of the whole plant , corrected , rectified and modificated it
where it was necessary and revisited the whole single line diagrams
Iop/production bilding
head offce
th building
stores
b&s panel
One of our major electrical safety audit point was to show the stabiliser in sld showing our chiller plant
and I successfully managed that
I prepared the safety interlock list of the whole plant along with its operating point mentioned on it as
the task was assigned to me on auguust 21 st meeting
Store activity
Worked in the engineering store and preapred the list of inventory palced there , took the remainaing
list of goods present at khalid khan's store and prepared a list of that
Made a quantity sheet for the store telling the qantity of each inventory present at the store
RECOMMENDATIONS FOR THE STORE
A proper audit of our engineering store must be conducted
in order to make sure thhe ultimate transparency, I will recoomend a store keeper there responsible ogf all the
afairs there...
cable schedule
searched, downloaded and made the format of the cable schedule which is one of our safety audit points and got an
approval from mr.sufyan
the work for cable schedule is currently under way , the cable schedule for filling is completed and the cable
schedule for formulation is currently in progress.. this work was assigned to me on 13 th october as I was constantly
enGaged in store before that
cable tagging and amrking will be done once its gets completed
EARTHING PITS
supervised the work on earthing pits in order to ensure proper grounding of our equipments
a total of 3 pits were digged and commissioned
a wire of 70 feet long was placed in each pit ensuring maximium condctivity of current
discharging stations
supervised and worked on the project of the 6 discharging stations which will help s in discharging the static charge
on our bodies,
one at filling area
one at herbicide
one each at w/p area 1&2
one atpacking hall
one at formulation
there are total 6 discharging stations at our site, out of 6 ,5 as been made alive , one ot the formulation is yet to
palced becase of the satinless steel floor work is going on there
surge arrestors:
in the case of lighting strikes at or site,in order to ground the charge, we worked on the completion on 10 surge
arrestors at our roof top
all of them are succesfully installed and working
earthing strips work
along wid or electricians worked in the installation of earthing strips at filling area, packing area, w/p are,
compressor area, in order to ensre the proper conductivity of the ground currents
recommendations
melting the solid for batch production at our site is a very cumbersome and time consuming phenomenoun , and it
always requires haevy maintaianance, in order to avoid this, I will sugest a inducrive drum heaters of thermo safe..
they are ex rated, maintaninance free and lesser time consumming
the drum cutting area at or site is very dangerous and any time can cause an injury , we need to rectify it
in order to all kind of electrical sparking in our ex rated zone in filling area , we can use festo pneumatic motors and
conveyors , instead of the conventional electric motors installed there.. the use of pneumatic equipment will totally
sideline the issue of ex areaq
for the powder filling area , one will recoommend dedicated poch saeling machines of better quality rather the one
currently in use as there rulers and gears get jammed due to the fact that powder usualyy get stick in between
gears and rulers cauusing a lat in machine operational
Chitted and named the each and every box that which inventory or equipment is present in ehich box
V each (BH-620, BH-623) are fed into the JTC Building. One feeder is used for the East side (BH-623)
and one is used for the west side (BH-620). Although there is availability of a bus coupler in case the
east and west sections need to be coupled in case of a power failure on one of the feeders.
Capacity: 350MVA
Panel Quantity: 12 panels
The panels are manufactured by AEG (now known as Areva). And the
Transformers are manufactured by Siemens (capacity is 800KVA each). There
is also one additional panel on the HT side for Power Factor correction. Its
capacitor bank is also installed on HT side
The 11KV incoming is then stepped down to 440V, using 6 transformers each
on the east and west wing of the Jinnah Terminal Building. The transformers,
manufactured by SIEMENS, having a power rating of 800KVA each, are
All the switching in the panels and the switchgear is motorized, and is
done on a 60V DC voltage produced by a Nickel-Cadmium battery bank
installed in the facility. The batteries are manufactured by Alcade. With a
rating of 1.4V per cell, there are total 44 cells running at one time,
whereas 6 cells are spare/backup. The batteries are charged using an AC>DC rectifier circuit, installed with the battery bank.
All panel operations are motorized by 60V DC motors, but there is the
ability of manual override in case of an emergency.
The 60V for this operation is produced by a battery bank. Where there are 50
cells, each capable of producing 1.4Volts. 44 of these cells are online at a
time, whereas the remaining 6 are for backup. Rectifier systems are used for
charging of these batteries.
The building also houses a standby Security lighting system. In case the
KESC Mains and Generator both are not present due to some reason, the
security lighting, placed at diferent places in the JTC Building, provide a
sufficient lighting so that the building is not engulfed in darkness. The
batteries used are Exide lead acid batteries, operating at 2Volts per cell,
giving a total of 220Volts from 110Cells.
Battery Bank for Security Lights (Emergency):
LT Panels:
There are LT Distribution panels placed on the East and West side at every
floor, from where electricity is distributed to that level (floor) only.
There are a total of 180 main and sub-distributors at JTC. Majority of the
Emergency and outdoor type equipment is manufactured by Zelin. And the
Explosion proof equipment is concealed in a Legrand Housing.
The fixed distributors are fed by LV switchgear which is located in
Substations East, West and Satellites East and West.
Utility Building:
The Utility Building for the JTC Complex houses the Air Conditioning system,
as well switchgear for operating the air conditioning system and for the
outgoing lines to the waterworks and street lighting substations.
The building takes input from two feeders (BH-621, BH-622) from the KESC
Grid station. Which are fed into the respective sides of the switchgear. Half
the switchgear is on one feeder and the other half on the other.. This
switchgear is having a facility of a bus coupler, in case of a power failure in
one of the feeders, the bus can be coupled and one feeder may bear the
whole load.
MV Switchgear breakup:
Total Panels: 16
(15 Panels originally installed and one panel installed in 2010 for Power
Factor correction)
The panel for power factor correction on HT side is manufactured by
Siemens. The power factor correction apparatus is mostly used on the LT
side, but here in this setup its used on the HT side. With its capacitor bank
installed alongside it.
The Input is taken from both the input panels from the feeders.
There is a bus sectionalizer panel which connects both the feeder buses in
case of need. It is mostly kept open (both the buses are kept separate as
both are energized by two diferent feeders in normal conditions).
Equipment
Chiller Plants
Incoming from feeders (grid station)
Bus sectionalizer
Transformer Panel (800KVA)
Outgoing for Waterworks Substation
Outgoing for Streetlights KIOSK
Power Factor Correction Equipment
No. Of Panels
4 (one for each chiller)
2 (one for each feeder)
1
3 (one for each T/F)
1
1
1
Spare Panels
Utility Building:
Utility Building Panel Distribution:
Panel No.
P1
P2
P3
P4
P5
P6
P7
P8
P9
P10
P11
Usage
Street lighting KIOSK Substation
Waterworks substation
Spare for motor
Incoming from grid station feeder no. 3
To motor CH2
To motor CH4
To UB1 TRO1
Bus Sectionalizer
To UB1 TRO2
To UB1 TRO3
Incoming from grid station feeder no. 4
P12
P13
P14
P15
P16
To motor CH1
To motor CH3
Spare for motor
Spare for T/F
Power Factor Correction
Vault Station:
There are two runways at Jinnah International Airport. One of them is
powered by the Vault Station. The vault station is located near the runway
and taxiway G. It houses a Transformer Room, an HT room, an LT room, a
CCR room, generator room and a battery room.
a. HT Room: The Vault station has incoming from two feeders from the
KESC Grid, namely the BH-625 and BH-627. Only one feeder is used at
one time, and the other is kept as a standby, due to the high sensitivity
of the location. If one feeder is not operational, then the other can
be used since the runway lights need to be functional at all times
e. Generator Room: The vault station has two generators, of which one is
Waterworks Substation:
Components of Substation:
East and West wing has 6 T/F each of 800KVA
Utility Building has 3 T/Fs of 800KVA each
Waterworks has 1 T/F of 500KVA
Kiosk has 1 T/F of 250KVA
Volts
*C
Watts
Watts
250KVA
1
11000/415
50
760W
441W
-
HT
LT
Secon
ds
HT
98.12%
13.12
347.8
3
Liquid
Disc
500KVA
1
800KVA
15
50
1100W
7800W
5.79
1.56
1.727
40
1450W
11000W
5.89
1.37
1.545
4.792
98.25%
26.24
695.62
4.678
98.46%
41.99
1112.9
LT
Insulation
Impulse Voltage
No. Of Bushings
Neutral Brought Out
HT
LT
Clyd
Class A
75KVA
3
4
Yes
Control System:
a)
Buccholz Relay:
a Buchholz relay, also called a gas relay or a sudden pressure relay, is a safety device mounted on some oil-filled
power transformers and reactors, equipped with an external overhead oil reservoir called a conservator. The Buchholz Relay is
used as a protective device sensitive to the effects of dielectric failure inside the equipment.
The relay has two different detection modes.
b)
c)
Oil Conservator:
There is also an oil conservator which has an Oil level glass sight
indicator.
d)
VCBs are Vacuum Circuit Breakers, they are more efficient than oil
circuit breakers as they are maintenance free and have a long lasting
life. They are used on the Incoming feeder panel and the Coupling
Panel
Load Break Switch:
Transformer Oil:
Dow Corning 561 Silicone
It provides a unique combination of dependable safety features. Heat
stable dielectric coolant does not have any environmental hazards as well.
Specifications:
Appearance: Crystal Clear Liquid
Specific Gravity: 0.960
Di-Electric Strength: 350Volts/mil
Flash Point: 545 degrees Fahrenheit.
Check/Maintenance Procedure
Checking of temperature rise for oil and windings
a) Check oil levels and if the oil level has dropped, then
investigate the reason for abnormality in oil level
b) Check the Silicagel breather
c) Buccholz Relay: Oil Level should be checked and topped
6
Monthly
Annually
5-Yearly
7-Yearly
up
Operate the of-circuit tap changer several times
a) Check the monitoring and protective devices
b) Clean T/F bushings and insulations from dust etc
c) Check for tightness of equipment
Extract oil sample for testing. Replace oil if needed
a) Radiators: Check and clean and repair.
b) Overall check:
i)
Sediments formation in oil or moisture deposit
ii)
iii)
iv)
Transformer Components:
1) Tank
2) Trolley
3) Tank cover
4) Oil conservator
5) Oil level indicator
6) Breather
7) Low tension bushing
8) High tension bushing
9) Name plate
10)
Lifting lug
11)
Explosion vent
12)
Radiator
13)
14)
15)
16)
Earthing screw
17)
18)
The material used in the making of the transformer is checked for all
possible kinds of reactions with the oil used.
The transformer tank cover is made from electrically welded mild steel
sheets
The drying crystals used in the SilicaGel breather are made by KaliChemie AG (Hanover). The crystals are of 3mm to 5mm in size.
There is a system called the AFCoM system. Which deals with all the automation of
all the systems in the JIAP building including switching of electrical equipment,
smoke alarms, emergency equipment etc.
All complains from the JTC are forwarded to AFCoM which then forwards it to the
related department. In some cases the complaint is directly forwarded to the
concerned department. For example, the Electrical Enquiry is responsible for
handling all kinds of electrical queries, including lighting, cables, and all other
related things.
Cabling:
The cables used in JTC are manufactured by AGE, Pakistan Cables and Pioneer
Cables. And are laid either in cable trays or underground or in concealed layout
inside the building. All kinds of precautions are taken to avoid any kind of mishap or
accident.
Flood Lights:
The Flood lights are installed on the apron
to eliminate darkness at night. It
illuminates the whole apron including
parking and gates and other facilities.
The Lamps used in these lights are Son-T
lamps. Manufactured previously by Thorn
with a rating of 400Watts. But the new
installations are manufactured by Phillips
and Osram and have a rating of 1000Watts.
PAPI lights:
PAPI stands for Precision Approach Path Indicator.
The Precision Approach Path Indicator (PAPI) is a light array
positioned beside the runway. It normally consists of four
equi-spaced light units color coded to provide a visual
indication of an aircraft's position relative to the
designated slope for the runway. They are usually placed on
the left side of the runway but can be placed on the right side of the
runway if needed.
of
at
operated from the ATC Tower and the G.O.C (Ground Operations) but they can also
be manually turned on and of if required.
These lights are installed in series arrangement and each and every light has a
transformer of its own. The transformer provides the necessary potential to the
light.
AGNIS is shown on the left, in this example the aircraft is right of the centreline.
On the right is a prototypical PAPA, which features no moving parts or electronics.
The two systems are not shown to scale, an AGNIS lightbox is many times smaller than a PAPA box
If the pilot is on the stand centreline they will see two green lights. If they are of
centreline, one of the lights will appear red and the pilot then steers towards the
green one. AGNIS alone provides only azimuth guidance, it does not inform pilots
when they should stop. It is relatively imprecise but cheap to implement and
reliable.
The Parallax Aircraft Parking Aid is frequently combined with an AGNIS system,
informing flight crews when to stop. The device features no electronics or moving
parts; it consists simply of a large grey box (usually with one or more sides missing)
with a large rectangular slot cut in to the front.
Inside the box, towards the rear, is a white stick or fluorescent tube, which appears
to move from one side of the slot to the other as the viewer moves closer, although
it is in fact fixed and the efect is merely due to perspective. Above and/or below
this slot will be markings in white or yellow, indicating where diferent types of
plane should stop.
Simon Boxer:
The Simon boxer is a Hydraulic lifter that is used at the Jinnah International
Airport. These machines are battery operated which are charged by AC
Current. The lifter has a 3 stage lift that is able to reach heights of more than
75 feet above the ground.
The device is used on the Jinnah International airport mainly in the Domestic
and International lounges, due to the high height of the roof. Service crew
uses the machine to reach up to heights for repair of lighting and other
systems. The lift platform of the hydraulic lifter can be tilted at various
angles according to need.
The power to the lift platform is delivered by the help of flexible cable trays
that run the length of the arm of the lifter.
thrust and fuel burn (and thus the aircraft range and engine horsepower per
pound), 115 volts at 400 Hz ofers a distinct advantage and is much better
than the usual 60 Hz used in utility power generation.
Generation/Conversion:
The 400Hz conversion takes place at the APSS room in the JIAP Building. It gets its
power from the main building but the incoming power is 50Hz AC at 400Volts.
Therefore, by the help of frequency conversion equipment, the frequency is
increased to 400Hz and the voltage is decreased to 26-28Volts.
The generated potential is sent to the corresponding gates/stations from the APSS
control room. There are switches/circuit breakers to control this process.
At each of the gates there is an APSC Unit which further controls the power flow, to
turn it of or on etc. The cable that connects the aircraft to the 400Hz system is
hung from the gate. And there is a mechanism for lowering and raising the cable.
The cable is stashed away in a box and a motor is used to extend or withdraw it.
Due to safety risks, the power is not immediately started only with the press of the
on switch. The aircraft itself provides a small amount of potential to the 400Hz
system which acts as a trigger and thus the 400Hz supply is provided to the aircraft.
In most aircraft the 400Hz cable is attached near the front wheel of the aircraft.
In case of absence of the 400Hz supply on the gates, there is availability of ground
power units. Those provide the power to the aircraft. They need to be connected to
AC mains which are conveniently located at each of the gates and at other needed
places.
The units used at JIAP are
and PowerMaster (new).