0 valutazioniIl 0% ha trovato utile questo documento (0 voti)
47 visualizzazioni7 pagine
This document provides specifications for protecting materials and equipment during construction projects. It outlines requirements for proper handling, storage, identification and protection of pipes, valves, instruments and other items. Temporary preservation methods like greasing and sealing openings are to be used to prevent corrosion and contamination. Strict limits are set for stacking pipes and installation of pipe racks to avoid damage prior to commissioning. Protective measures aim to maintain integrity until equipment is ready for final use.
This document provides specifications for protecting materials and equipment during construction projects. It outlines requirements for proper handling, storage, identification and protection of pipes, valves, instruments and other items. Temporary preservation methods like greasing and sealing openings are to be used to prevent corrosion and contamination. Strict limits are set for stacking pipes and installation of pipe racks to avoid damage prior to commissioning. Protective measures aim to maintain integrity until equipment is ready for final use.
This document provides specifications for protecting materials and equipment during construction projects. It outlines requirements for proper handling, storage, identification and protection of pipes, valves, instruments and other items. Temporary preservation methods like greasing and sealing openings are to be used to prevent corrosion and contamination. Strict limits are set for stacking pipes and installation of pipe racks to avoid damage prior to commissioning. Protective measures aim to maintain integrity until equipment is ready for final use.
PROTECTION OF MATERIALS AND EQUIPMENT DURING CONSTRUCTION
Rev Date Description Checked Approved 0 1999 Issued for Implementation DL
Compiled by Teknica (UK) Ltd GENERAL ENGINEERING SPECIFICATION PROTECTION OF MATERIALS AND EQUIPMENT GES C.02 Page 2 of 7 DURING CONSTRUCTION Rev 0 1999
INDEX
SEC TITLE PAGE
1.0 SCOPE OF SPECIFICATION 3
1.1 Introduction 3 1.2 Other NOC Specifications 3 1.3 Codes and Standards 3
2.0 DEFINITIONS 3
2.1 Technical 3 2.2 Contractual 4
3.0 ESSENTIALS 5
4.0 PIPELINES AND PRE-FABRICATED PIPEWORK 5
5.0 PRESSURE TESTING 6
6.0 EQUIPMENT 7
7.0 PROTECTIVE COATINGS 7 GENERAL ENGINEERING SPECIFICATION PROTECTION OF MATERIALS AND EQUIPMENT GES C.02 Page 3 of 7 DURING CONSTRUCTION Rev 0 1999 1.0 SCOPE OF SPECIFICATION
1.1 Introduction
1.1.1 This specification defines the general requirements for the protection of all equipment and materials used during the construction phase of a project for refineries, on-shore oil and gas installations, and processing facilities.
1.1.2 Such equipment and materials shall be handled and stored specifically to maintain the mechanical integrity and functionality in respect to their end use.
1.1.3 The various procedures included in this specification are meant to protect the items against damage and degradation due to various adversaries such as the weather, lack of care, mishandling, etc.
1.1.4 This specification is not meant to replace or modify the erection and installation procedures, but to supplement them with details of how to ensure overall integrity of equipment and materials during the construction phase.
1.2 Other NOC Specifications
1.2.1 Where indicated in this specification, the following additional NOC Specifications shall apply:
GES C.01 Protection of Materials and Equipment during Storage
1.3.1 There are no specific codes and standards identified which are unique to the scope of this specification, however individual supporting installation and commissioning specifications will identify the appropriate equipment or material codes which may, or may not, provide details on special protection requirements.
2.0 DEFINITIONS
2.1 Technical
2.1.1 The technical terms referred to within this specification are defined as follows:
Deterioration
Deterioration is a condition that adversely affects the properties (physical or chemical) or performance of the item under consideration.
Corrosion
Corrosion is the deterioration through the gradual eating away of a material by the attack of liquids and gases to which it is exposed. The rate of corrosion is affected to a considerable extent by the conditions of exposure, the type of corrosive medium, the nature of the products of corrosion and by the presence of certain bacteria or marine growths. This is a very basic interpretation as many other influencing factors determine the rate or ability of one substance to corrode another. The most common is the corrosion attack on bare steel by moisture which may be accelerated by the presence of other organic and inorganic compounds. GENERAL ENGINEERING SPECIFICATION PROTECTION OF MATERIALS AND EQUIPMENT GES C.02 Page 4 of 7 DURING CONSTRUCTION Rev 0 1999
Contamination
This is any extraneous materials that will give rise to damage, deterioration, or corrosion. This may be products originated within the plant itself, e.g. acidic vapours, or natural elements such as sand and humidity.
Vapour Phase Inhibitors (VPIs) and Preservatives
These are materials that serve as a barrier between the material and the attacking agent either as a mist or vapour that settles out onto the surfaces to be protected or as a positive barrier applied thick enough to prevent the penetration of the attacking agent over a period of time. These materials can provide protection up to a maximum specified time period, after which time they must be replaced. Caution must be exercised in the selection of these materials as they themselves may, in certain circumstances and on certain materials, act as the corroding agent.
2.2 Contractual
The commercial terms used in this specification are defined as follows:
Owner
The oil and gas company, an associate or subsidiary, who is the end user of the equipment and facilities.
Vendor
The company supplying the equipment and material.
Contractor
The main contractor for a defined piece of work
Sub-Contractor
A company awarded a contract by a Contractor to do part of the work awarded to the Contractor.
Inspection Authority
The organisation representing the Owner or Vendor/Contractor that verifies that the equipment and facilities have been designed, constructed, inspected and tested in accordance with the requirements of this specification and the Purchase Order/Contract.
Inspector
A qualified individual representing the Owner, Vendor/Contractor or the assigned Inspection Authority, who verifies that the equipment and facilities have been designed, constructed, inspected and tested in accordance with the requirements of this specification and the Purchase Order/Contract.
3.0 ESSENTIALS
3.1 No material or equipment shall be issued to the field unless it is due for installation, and arrangements are complete for the lifting . This reduces the time the materials and equipment are exposed to the possibility of contamination, and damage. GENERAL ENGINEERING SPECIFICATION PROTECTION OF MATERIALS AND EQUIPMENT GES C.02 Page 5 of 7 DURING CONSTRUCTION Rev 0 1999
3.2 All equipment shall be clearly identified in order to ensure it is not accidentally installed in the wrong location, where it might be subjected to damage or be a safety hazard due to incorrect use. Any item, or material found without correct identification, shall be classed as non-conforming until its identity can be re- established. Identification of all items shall be re-affirmed after installation, during pre-commissioning.
3.3 All materials used in construction that can deteriorate, such as cement, shall be issued from its storage area in only sufficient quantities to complete the task at hand. If large quantities are issued then the surplus from an operation must be returned to the storage area where it can undergo any necessary preservation to prevent its further degradation.
3.4 All equipment items shall remain in their storage packaging until they are ready for use. All openings shall remain sealed and any openings that are made for inspection purposes shall be resealed until the equipment is ready for installation to prevent ingress of foreign materials, e.g. water, refuse, sand, etc.
3.5 Any item removed for testing purposes, e.g. instruments, valves, gauges, etc. shall be positively identified to the unit they were removed from. All resulting openings shall be sealed to prevent ingress of foreign materials and the removed item shall be subjected to preservation, i.e. temporary packaging, greasing, covering, etc.
3.6 All bracing, temporary supports, rotor locking devices, etc., shall remain in place until the equipment is ready to be commissioned. In all cases equipment must be retained in a protected condition until the last moment to avoid unnecessary damage.
3.7 Consideration shall be given to the application of temporary preservatives during the construction on items where there will be some time lag between installation and commissioning. As an example, all anchor bolts must be protected by grease, or proprietary preservatives, from the time of installation until they are used to bolt down the actual installed equipment.
4.0 PIPELINES AND PRE-FABRICATED PIPEWORK
4.1 All pipe flanges shall be kept free from damage and temporary preservative or flange covers applied when the pipeline fabrication was undertaken. They shall not be removed except for inspection, cleaning, testing and installation to minimize the damage and deterioration that can occur.
4.2 Straight lengths of pipe must be correctly stacked. If there are no formally designed pipe racks then the pipework may be laid on timber and stacked in a pyramid style with no stack exceeding 6.5 ft (2 m) for pipe up to 12in (300 mm) diameter and no more than 9.75 ft (3 m) high for larger pipes. There shall be retaining wedges at the outside of the stack firmly secured to the supporting timbers on which the pipe rests. Loose wedges shall not be used.
4.3 Formal pipe racks shall be designed and constructed to accept a range of pipe sizes. The maximum distance between upright supports shall not exceed 6.5 ft (2 m). Pipes shall not be stacked higher than the supports at any time.
4.4 Fabricated pipework shall be offloaded onto timber. Due to the complex shapes of prefabricated pipe spools they are normally not stacked. All flanges shall be protected with wooden or plastic end covers. All butt weld preparations shall be sealed by plastic caps or wooden covers taped into place. Pipe spools shall be laid down in defined areas and, where practical, all of the spools for an isometric drawing shall be stored together.
4.5 When pipework or pipes are required for site installation and fabrication, the construction Contractor shall confirm the identity of each spool, each size, grade and class of each straight length of pipe and any fittings required for fabrication against the appropriate isometric diagram. Materials shall be delivered to the construction area in isometric construction sequence to avoid mix up between similar items on different drawings. GENERAL ENGINEERING SPECIFICATION PROTECTION OF MATERIALS AND EQUIPMENT GES C.02 Page 6 of 7 DURING CONSTRUCTION Rev 0 1999
4.6 Any pipe spool, fitting or straight length of pipe that cannot be positively identified against the isometric drawing due to inadequate identification, shall be quarantined until the identification can be re-established.
4.7 During installation care shall be taken to avoid arc strikes on the material surface. On low alloy materials arc strikes outside of the weld zone will lead to high stress raisers and therefore the welder shall carry a strike plate to strike his arc. Tape shall be applied either side of the weld zone to prevent the occurrence of accidental arc strikes. This is a typical problem in the field fabrication of manifolds, where the access for welding is restricted. Arc strikes on pipelines, or equipment, especially in sour service, shall be avoided as it may result in early failure.
4.8 All electrical connections to pipeline instrumentation are to be isolated during construction. Where practical no instrumentation is to be connected to the pipeline during the fabrication stage, in order to avoid accidental exposure to welding currents.
4.9 All valves, instruments and mechanical equipment items associated with a particular line shall either be left out with distance pieces used for construction purposes, or temporary blanks fitted between these items and the pipeline to prevent any debris from fabrication entering the equipment itself.
4.10 All temporary strainers are to be installed where specified in the installation procedures. Where practical, these are to be fitted with a finer mesh than that to be used in service.
4.11 On certain types of valves, particularly those with weld ends and subject to stress relieving, the internals may be removed during fabrication and testing. When this is permitted by the line specifications, then the removed internals shall be formally packed, preserved as necessary, and identified with the valve serial number as well as any other required identifiers.
4.12 Primed pipe spools shall be handled using flat non-metallic web slings to avoid damage.
5.0 PRESSURE TESTING
5.1 The following general guidelines shall be followed to protect equipment while performing in-situ pressure testing of plant/production facility systems. Detailed test procedures shall be developed for each case, in strict compliance with the methods and procedures provided in the established codes of practice such as ANSI B 31.3, 31.4, 31.8, ASME applicable sections, with needed modifications as required, and approval obtained from the authenticated bodies.
5.2 Any hydraulic testing that takes place must be with potable water, or specially treated low chlorine content water, with a corrosion inhibitor included to prevent rusting from residues.
5.3 Relief valves on process lines will not be fitted during the full hydrostatic test, however there must be precautions in place to prevent over pressurisation. As a minimum two (2) calibrated pressure test gauges must be used during testing to ensure there can be no accidental over pressurisation if one should fail to read correctly. Pressure relief valves are to be calibrated before installation.
5.4 All necessary safety precautions must be followed when testing. In addition special attention must be taken to protect equipment that is in the immediate vicinity of points of discharge from pipework, especially where purging and flushing operations take place.
5.5 Relief/Safety valves on hydraulic packages/systems will not be removed for testing except under the direct instruction of the Inspector or Inspection Authority to avoid contamination of the hydraulic circuits.
5.6 After testing all lines shall be drained and internals dried by blowing dry air. The dryness can be confirmed by a hygroscopic test on the outlet air. Rust inhibitors shall to be applied and surfaces preserved if the lines/vessels are to remain out of service for extended periods. Alternatively, rust prevention can be achieved by the application of other proprietary type mist inhibitors or vapour barriers. GENERAL ENGINEERING SPECIFICATION PROTECTION OF MATERIALS AND EQUIPMENT GES C.02 Page 7 of 7 DURING CONSTRUCTION Rev 0 1999
6.0 EQUIPMENT
6.1 All items of mechanical equipment shall be sited without removing any protective coverings unless it is unavoidable. Any covers removed shall be replaced after equipment has been installed and this must be done at the earliest possible opportunity.
6.2 All small diameter pipes, tubes and other delicate pieces of equipment shall be protected against mechanical damage during handling and installation.
6.3 When the equipment, associated pipework, cabling and instrumentation has been installed, then it can be made ready for commissioning. As part of the preparation any preservatives and temporary attachments, locking devices, etc. shall be removed. Connecting pipework shall only be attached when there is positive evidence that cleaning of the equipment and flange faces has been completed.
6.4 No equipment shall be started up until it is positively confirmed that all lubricants, and other operational fluids, have been applied and all lines are clear. All temporary bracing shall be removed.
6.5 Rotating equipment may have become off balanced during transit and/or installation, therefore all precautions shall be taken to ensure no further damage occurs by starting up equipment that has been installed incorrectly. All start ups are to be made in incremental stages, so that equipment can be quickly shut down in the event of a problem without creating additional problems or damage.
6.6 All installed equipment shall have all unpainted threads, and bare shafts such as those used for operation and adjustment, protected by grease or preservatives so it is in a satisfactory status at the time of start up.
7.0 PROTECTIVE COATINGS
7.1 All protective coatings shall be protected by taking care during handling. All equipment shall be lifted by its lifting lugs, where fitted, using any specified lifting device or spreader bars to avoid damage and to ensure a safe lift. Webbing slings are preferred where they can be used within their safe working load. An alternative is to use protective mats between the item being lifted and any slings.
7.2 Where the protective coating becomes damaged it must be assessed quickly to ensure that there is no danger of corrosion taking place. If the coating is only damaged superficially, then it can be repaired as part of final touch up work. Where the coating is damaged to a point that the metal surface is exposed, then a full or temporary repair must be carried out as quickly as possible.
7.3 Damaged coatings shall be restored in accordance with the project specifications.
D6950D6950M-04 (2012) E1 Standard Practice For Application of Heat Weldable Atactic Polypropylene (APP) Modified Bituminous Waterproofing Membranes Systems For New Building Decks