Sei sulla pagina 1di 121

Missing Link Programme

PARIEJ REGIONAL WATER SUPPLY SCHEME


TA. MATAR, TARAPUR, SOJITRA DIST. KHEDA
Lowering, Laying & Jointing different dia HDPE / PVC Pipeline.
Sub-Estimate No.1

Item No.1 Excavation for pipe line tranches including all safety provisions using
site rails and stacking excavated stuff up to a lead of 90 m clearing
the site etc. comp. for lift and strata as specified in all sorts of
soil and soft murrum upto 1.50 m. depth.

General

Clearing Of Site :

The site of work is to be cleared of all obstructions loose stone and materials,
rubbish of all kinds as well as all trees and brush wood , the roots being entirely grubbed
up.

All holes or hollows , whether originally existing or produced by digging up roots


shall be carefully cleared up with earth well rammed and leveled of as may be directed.

Works For Pipe Trenches Civil Work :

The excavation for the pipe trenches shall be done as per the grade given by the
department by using suitable means the width of the trenches shall be 0.50 mt. wider
than dia. of pipes for A.C. and C.I. pipes, for R.C.C. pipes it shall be 0.60 m. wider than
pipes the measurements for the depth shall be paid up to bottom or pipes. Extra
payment at joint for R.C.C. for extra excavation shall be 0.60 x 0.10 width of trench at
each joint for facilitating jointing work.

Protection :

Necessary protection works like guide ropes crossing planks shall be provided by
the contractor at his own cost. Further suitable visual indicator shall be provide during
day time to indicate works in progress.

Necessary scaffolding as per design to retain and support unstable strata that
shall be met with during excavation for the trenches shall be met with during excavation
for the trenches shall be provided by the contractor and no extra claim shall be
entertained. The excavation shall be done as designed section as directed by the
Engineer in charge. If section and depth is changed without prior written approval of
the engineer in charge, no claim for such extra excavation either due to increase in
width or depth shall be entertained.

The excavated stuff from the trenches shall be dumped at least minimum twice
the design depth below bed level or as directed from the extreme edge the excavation.

After completion of works surplus excavated stuff shall be removed and leveled
of at places directed by the department at the cost of the contractor.

1|Page
Hard Rock ( Blasted )

This shall include all rocks, curing in masses which could best be removed by
blasting and where in the opinion of the Engineer, blasting is necessary and is
permissible.

Hard Rock ( Chiseled, Wedged or Line Drilled )

This shall include all rock, occurring in masses or boulders bigger than half cubic
meter size each, which can best be removed by blasting but which owing to the
proximity of structures, possibility of shattering the rock below or for any other reason
should be cut by means of cold chisels or wedges or line drilling.

Literate

This shall include literate rock soft and hard which can be removed with
hammer, chisels, crow, bars or by blasting lateritic Murom which has not hardened into
stone shall be classified as hard Murom

The classification of various, strata met with during excavation will be decided
by the Executive Engineer and his decision shall be final and binding on the contractor.

Rock referred to above would include blast. Trap granite, Quartzite, Gneiss
literate and other types.

The use of explosive in excavation will not be considered as a reason for other
classification than the above unless clearly necessary in the opinion of Executive
Engineer.

Mode Of Measurement And Payment :

On completion of excavation work as per the agreement , shall be measured in length,


width, depth method i.e. in volume base cum. The payment shall be made at 70% of
scheduled rate for work measured and remaining 30% shall be released as soon as site is
cleared to the satisfaction of engineer in charge. Payment shall be made on m3 basis.

Item No.2 Providing and supplying HDPE specials suitable to HDPE at store or
site of work including freight, loading, unloading, stacking insurance
and all taxes etc. complete

400 / 200 / 250 mm dia.

M.S. / H.D.P.E. Specials

Providing H.D.P.E. moulded 6/10 kg/cm2 specials (as per IS standard) such as
Tees, bends etc. complete suitable for H.D.P.E. pipe, as approved by Engineer in charge.

Manufacture, supply and delivery of M.S. flange, Tee, bends, tail piece, reducers,
air valve raiser pipes or any other specials suitable for use with G.I., AC, PVC, H.D.P.E.
pipes and delivery of specials is to be made or supply to site of work any where in
Gujarat including all taxes, loading, unloading, carting, stacking, insurance, inspection
charges, octroi etc. complete.

2|Page
Manufacture, supply and delivery of C.I.D. joints with Rubber Rings of standard
quality or any other specials suitable for use with M.S., AC, D.I. and PVC pipes and
delivery of specials is to be made to site of work any where in Gujarat including all
taxes, loading, unloading, carting, stacking, insurance, inspection charges, octroi etc.
complete.

The H.D.P.E. specials shall be of the same material used for PVC, H.D.P.E. pipes
and should be best quality approved by Engineer-In-Charge.

It shall be of best quality as per IS specification and rate shall be including


loading, unloading, carting, insurance and labour charge etc. complete.

M.S. specials of required thickness with 3 coats of approved make epoxy paint
with inside and outside.

The necessary MS specials required during the lowering and laying of


MS/AC/HDPE and PVC pipe shall be supplied by the agency and shall be as per standard
specification.

MS specials included Air valves raisers, Flanges, Tailpiece etc.

It shall be of best quality as per requirement rate shall be including loading, unloading,
carting, insurance etc. complete.

The payment shall be made on No. basis for H.D.P.E. specials and kg. basis for M.S.
Specials.

Item No.3 Providing and supplying at store or site of work PVC Specials as per
requirement including , freight ,loading ,unloading, stacking, insurance
& all taxes etc. comp.

PVC SPECIALS:

The standard specification covers the general requirements for materials , size
method of test and inspection of various types of molded/fabricated PVC fitting for
jointing with solvent cement to the PVC pipes as per specifications mentioned in I.S.(I)-1
to 10. The pipes or molecules used for manufacturing specials shall conform for
material’s specifications for PVC pipe as per IS 4985 – 1981 & of 6Kg/cm2

The size of fittings shall be designated by the nominal dimensions of the pipes
given in the IS 4985 – 1981. The socket length of any fitting shall be minimum L=0.5D +
6 mm. And tolerance minimum diameter shall be 0.007D or 0.2 mm. The testing shall
conform to Appendix “A” of I.S. 10124 – 1982. The fittings withstand a pressure of 4.2 +
0.2 times the working pressure.

MEASUREMENT AND PAYMENT:

The measurement shall be taken per no. bases and paid accordingly at 70% of
the stipulated item rate for non-fixed materials and remaining payment shall be made
after hydraulically tested and found satisfactory.

3|Page
Item No.4 Providing and supplying ISI mark C.I. / D.F. sluice valve, butter fly
valves and reflux valves of following class and diameter including all
taxes insurance, transportation, freight charges, octroi , inspection
charges , loading , unloading , conveyance to departmental stores ,
stacking etc. complete.

500 / 400 / 350 / 250 / 200 / 150 mm dia. Sluice Valve PN – 1.0

250 / 200 / 150 mm dia. Reflux Valve

General :

The cast iron sluice valve up to and including 300 mm. Size shall conform to I.S.
780 of 1969 or latest revision thereof. From 350 mm. to 1200 mm. Size confirming to
IS 2906 of 1969 or latest revision thereof for sluice valves used for water supply
purpose.

Classification :

Sluice valves from 60 mm. to 300 mm. Size shall be two – class test pressure and
maximum working pressure for the classes shall be as follows.

Class Test Pressure in Kg / CM2 Maximum Working

Body Seat Pressure Kg/Cm2

Class – I 20 10 10

Class – II 30 15 15
Sluice valves from 300 mm. to 1200 mm. Size shall be two – class test pressure and
maximum working pressure for the classes shall be as follows.

Class Test Pressure in Kg / CM2 Maximum Working

Body Seat Pressure Kg/Cm2

Class – I 8 5 5

Class – II 16 10 10
Class – III 24 15 15

Materials :

Cast Iron :

Cast iron for body , dome , covers , stuff box, thrust plate, hand wheel wedge, gland ,
and cap shall be of quality not less than grade 20 of IS 210 – 1978 specifications having
gray iron casting.

Nonferrous Metal :

High Tensile Press Of Aluminum Bronze :

The spindle may be manufactured from any of the nonferrous metal shall be
machined from rolled extrudes of forged high tensile brass aluminum bronze. The
tensile strength of the rolled , extrudes of forged metal shall not be less than 55
kg/CM2 with a minimum elongation of 20% in a gauge length of 5 cm.

4|Page
Leaded Gun Metal :

The rings and spindle nut may be manufactured from any of the nonferrous
materials Leaded Gun Metal shall have a tensile strength not less than 22 kg/Cm2
elongation not less than 12% on gauge length of 5 CM.

Ferrous Metal :

Bolt and nuts shall be of mild steel unless otherwise specified and shall confirm
to IS 226 – 1975 for structural steel.

Jointing Materials :

The jointing materials used between the flanges of component / parts of valve
shall be compressed fiberboard or rubber of thickness between 1.5 mm. to 3.0 mm. The
rubber and insertion material shall be as per I.S. 638 – 1965. Its weight per Sq. Meter
shall not be less than 112 grams per mm. Thickness.

Dimensions :

The nominal dimensions for body , flange, seat, spindle , hand wheel , stuffing
box, etc. shall be as specified in the relevant IS.

Optical Feature :

Locking arrangement, valve gate position indicator , IS mark , manufactured by,


etc. shall have indicated with suitable design letters embossing.

Inspection :

The Engineer – in – Charge or his authorized representative shall have free


access so the works for inspection at any stage of manufacture and to reject any
materials which does not confirm to the specified requirements. & also inspected by TPI
authorized board approved.

Testing :

The manufacturer shall arrange to supply all labour and appliance or the tests, if
the testing is to become at his work. Each valve shall be subjected to the hydraulic
tests and shall show no sign of leakage under these tests.

The manufacturer shall guarantee that if any defects changeable to faulty


workman ship, design or material are found in the valves within a period of one year of
dispatch, be shall replace any part or parts that above defective free of charge, at the
place where dispatched.

Mode Of Measurement And Payment :

The 70% rate shall be paid per number the measurement shall be for the number of
valve, 30% amount with held till satisfactory test after fixing and
commissioning.

Item No.5: Providing and supplying C.I. Air valves of approved make & quality of
following class and diameter including all taxes, insurance ,
transportation , freight charge , octroi , inspection charges , loading

5|Page
, unloading , conveyance to departmental stores , stacking etc.
complete.

25 mm dia. Single Acting Air Valve (S1) Type

For Air Valve:


General :
The Air valve shall conform to the ISS as and when published and shall be of
approved make and quality. The standard applies to air valves used for water and
sewerage mains. The details given below briefly cover the requirement for materials ,
dimensions and tests for air valves.

Classification :

Air valve shall be of two types:

Single Air Valve :

Single air valve shall have single small or large orifice for releasing air during
pipe filling and ventilation the pipe during emptying. Air valves up to 40 mm dia. directly
shall be screwed on the main.

Double Air Valve :

Double air valve shall have two ball chambers on outlet of bulk large capacity
shall be provided for admission and releases of bulk volume of air during emptying and
filling of the main, another of small outlet type for the escape of smaller quantities of
air accumulating under pressure. They shall be of flanged type.

Materials :

Cast Iron :

Cast iron for bodies pressure covers space covers glands, caps joints support
rings shall be best gray iron of selected grade 20 of IS 10 – 1970 specification for gray
iron castings.

Gum Metal :

Gum metal shall be of mixture of 88% of copper , 10% thin 2% sink having
excellence wearing qualities , Ball guides of small orifice units are outlet bushes of large
orifice valve shall be of gum metal.

Mild Steel :

Bolts, nuts, flanges etc. shall be of mild steel unless otherwise specified and
shall confirm to IS 226 – 1975 specification for structural steel.

Material For Balls :

The balls shall be of rubber covered. The rubber shall have a smooth and hard
surface. If shall be as per IS 638 – 1965 specification for rubber and insertion jointing.

Dimensions :

Small orifice air valve having single rubber ball is available in the following sizes
12 mm to 20 mm, 25 mm large orifice single air valves are available in following sizes.

6|Page
40 mm , 50 mm, 80 mm , 100 mm , 150 mm

Double air valves are available in size.

50 mm , 80 mm , 100 mm , 150 mm , 200 mm.

Air valve up to 40 mm size shall be of screwed type fitted with Nipples.

Inspection And Testing :

The Engineer – in – charge or his authorised representative shall have free


access to the works for inspection at only stage of manufacture and to reject any
materials , which does not confirm to the specified requirements.

Manufacture’s Guarantee :

The manufacture shall guarantee that if any defect chargeable to faulty


workmanship, design or materials are found in the valve within a period of one year of
dispatch shall be replace any part the prove defective free of charge at the place where
dispatched.

Mode Of Measurement And Payment :

The measurement shall be for the number of valve provided and fixed. 70% rate shall be
paid per number of valves provided. Remaining 30% amount shall be released after
fixing and satisfactory testing and commissioning.

Item No.6 Lowering, laying and jointing H.D.P.E. pipes and specials of following
class and diameter (By butt fusion welding method) including cost of
conveyance from stores to site of works including cost of labour
material giving satisfactory hydraulic testing as per ISI code etc.
complete.
400 / 355 / 200 mm dia.
Welding
HDPE pipes are jointed by BUTT fusion welding method with the help of electric
heat (Mirror) and hydraulically operated welding jack.
Precautions
Since critical parameters for sound welding joint are temperature and pressure,
welding methods should insure proper temperature and pressure by using proper
equipments. The welding area has to be protected from adverse weather condition like
rain water, moisture, rough wind , dust and low ambient temperature (less than 50 C.)
Primary inspection of pipes should be done for ensuring defect free pipe before
striating welding.
Welding Procedure
Two ends of pipe to be welded are to be cut perpendicular to the pipe axis and
then cleaned and planed by using proper planning tool. The pipes are fixed in welding jack
and aligned properly in axial direction. The pipes then are pressed against a hot plate
(Called heating mirror or s imply mirror) till a bead of molten material is formed. The
mirror is electrically heated by in-built electric resistance heating coil. The heating
should be uniform all around mirror plate on both sides. The mirror should be provided
with a temperature control service so that during welding the surface temperature is
7|Page
automatically maintained within the required limit i.e. 200 + 100 C. Proper Teflon cloth
covering should be provided on mirror surface to avoid sticking of melted HDPE
materials on plate surface.
After attaining the welding temperature of 200 C on mirror surface the pipe
ends are simultaneously brought in contact with the heating surface of mirror. This is
done by using hydraulically operated welding jack. Initial contact pressure is applied
which is maintained till the uniform ring of molten bead is achieved. Then the contact
pressure is reduced until proper fusion takes place.
After proper fusion, the welding mirror is removed carefully without damaging
the head. The time of removal of the mirror should be as short as possible. After
removal of mirror, pipe ends are brought immediately to contact with each other under
initial welding pressure which is gradually increased to final welding pressure. This
pressure depends on the total welding surface of pipe.
The final welding pressure is maintained to be applied till the joint is cooled
down to ambient temperature naturally. Artificial cooling such as wrapping with wet
cloth, spraying of water etc. are not allowed.
Inspection of Joints.:
The visual inspection of each joint should be done to ensure correct bead
formation. Weld joint should be checked for axial alignment of welded pipes.
Laying of Pipes:
The required length of HDPE pipes are made alongside the trench. The pipe is
lowered into the trench carefully avoiding damage to pipe and joints.
Trench:
Since the welding of pipe is done outside of trench, the width of trench should
be kept as minimum as possible, Normally pipe O.D. plus 300 mm width should be
sufficient for laying. The depth of trench will be as per the requirement of client
depending on level survey (L.S.) Here in our case the earth cover of average 1.2 mtr. On
top of pipe is to be provided. Hence the depth of trench will be pipe O.D. plus 1.2 mtr.
The trench should be made as straight as possible wherever necessary, the
trench can be made with smooth curve but not below allowed bending radius of HDPE
pipe, which is 25 times of O.D.
The bottom of trench should be properly dressed and made free from any sharp
objects.
Laying and Backfilling:
Laying of pipe lengths to be done carefully from one end without giving any
impact on pipe. After laying of pipe, trench should backfilled with the layers of good
earth of dug soil as available. Extra soil will be embedded on trench which will be
compacted by curing with water.
Hydro Testing:
The pipeline to be tested with fitted with metal blind flange at both ends with
the help of sub end (pipe end), These blind flanges are fitted with necessary
arrangement for supplying water into pipeline, air valve for air drain and pressure guage.
After filling the water into pipeline, pressurized water is supplied with the help of
pressure pump. When the required test pressure (i.e. 6 kg/cm2 in our case) is achieved,
pressure pump is stopped and valve is closed.
This pressure will be kept for 30 minutes and there should not be any drastic
drop in pressure whole pipeline route under test is inspected for checking any leakage.
8|Page
If there is no leakage, the pressure of 6 kg/cm2 will remain same and it test is believed
to be satisfactory. Please note that there could be slight deep in pressure due to
leakage from flange / valve or due to expansion of HDPE pipe under pressure. This drop
upto 0.5 kg/cm2 is normally not considered.
Connection of HDPE to M.S.pipe
This connection will be made by using metal flanged. We shall provide flange at
the end of HDPE pipe by using HDPE stub end. Matching flange connection from M.S.Pipe
will be made by M.S. Pipe agency to which flange of HDPE pipe line will be connected by
bolting and proper rubber gasket packing.
Air Valve fixing :
Suitable size of air valve will be installed on HDPE with the help of metallic
saddle. Metallic flange for air valve will be provided on upper part of saddle for fixing
air valve. Valve chamber of suitable size with top cover will be made for each air valve.
The scope for the Item cover:
Cost of additional excavation required for jointing clearing the site of all scrub,
bushes and trees and dewatering when necessary
Labour for laying pipe in trenches to correct alignment required depth with
tools, including cutting of pipe and specials if required for laying of pipes including
connecting pipes to specials end appurtenances. Cost of the scaffolding tools and plant
ropes etc.
Protection of existing works from damage and cost of repair to the damages
carried out to th existing structure, sewerage line, telephone line, electrification cable ,
electric line, gase pipeline, irrigation pipeline etc.
The pipe laying across the state highways , national high way etc. will have to be
done either throght open cut method or through push through method depending upon
the requirement to be prescribed by the sectioning authority. How ever mostly eat
would be push through method.
GWSSB will not able to provide water for testing the pipeline and water
containers of the project. This shall have to be manage by the contractor at his cost and
risk.
Labour for making joints including jointing materials for joints tools as well as
test. Testing of pipe for leakages under water pressure and flushing the pipe after
testing and construction work shall have to be arranged by the contractor at his own
cost.
Method of measurement and Payment:
The measurement shall be recorded in running meter of pipeline length laid along
the center line of axis of pipeline including tees, enlarges, reducers and bends, correct
up to 0.01 meter length. No payment shall be made for the over lap etc. The payment
shall be made after completion whole item as mentioned in price bid on running meter
basis and 30% shall be with held of satisfactory hydraulic testing.

Item No.7 Lowering, laying and jointing PVC pipes and specials of following class
and dia. Including cost of conveyance from store to site of work
including cost of labour materials except cement solvent, giving
satisfactory hydraulic testing as per ISI code etc. comp.

90 mm dia. PVC 6 kg/cm2

9|Page
Lowering , laying and jointing PVC pressure pipes with specials as tees, bends,
reducers, valves, F H etc. including necessary lighting guarding etc. comp. including
testing (excavation refilling and cost of detachable joints, No deduction shall be made
for running meter measurement of vavles)

PVC pipes of required dia meter and Qty. with coupler & count cement shall be
supplied by the department free of cost as per schedule ‘A’.
Pipe shall be lowering in trench in proper line & level without any deviation in
individual pipe.
Solvent cement an free of pipe & an coupler shall be properly applied as per
instruction of EIC.
Ends of the pipe line shall be conventary of foreign materials in the pipe line.
Common specification of pipe line work attached separately or in vague shall be
followed for general instruction.
Untested pipeline shall be paid at 70% of tendered rate. Hydraulic test shall be
given double the working pressure or working pressure plug 30 m. O head whichever is
more limited to test pressure of pipe line.
Any free of cost material lost or broken by the contractor shall be recovered at
the prevailing issue rate division or market rate whichever is more and decision of
executive engineer regarding its cost shall be linal and binding.
The rate shall be paid M. length of pipeline laid and tested.

Item No. 8 Lowering , laying and jointing pipeline with specials such as tees,
bends, reducer including cost of specials guarding , barricading
testing etc. complete. (excluding excavation and refilling no deduction
to for S.V.) 80 mm dia. G.I. Pipe.

General
Galvanized iron pipes shall conform to IS 1239-1968, Part-I or latest revision of
ISS for mild steel tubes part-I used for conveying water. The tern tube is synonymous
with the term ‘Pipe’.
Preparation Of Pipes :
The pipes shall be brushed throughout to remove any soil deposited or stone
therein. Cutting of pipes shall be done in workman like manner.

Laying And Jointing :

Before laying and jointing the complete layout of pipe work shall be studied well
and got approved from the engineer in charge. The pipe shall be laid in plumb, straight
and parallel lines under directed.

The threading of pipe shall be done by the contractor with his tool as per
threads of the other pipes and specials at his own cost. The threads of the pipe
specials, coupling etc. are cleared properly before they are jointed. A few turns of fiber
of hemp yarn smeared with white zinc shall be taken over the threaded end and then
jointed and tightened with the help of pipe wrench. when two pipes are jointed , the
ends of them shall be tough each other and coupling shall cover equally half of both pipe.
When pipes are to be fixed on wall it shall be fixed with standard brackets, slips or
holder.

10 | P a g e
The wastage shall not be paid separately. If the pipeline is laid in detached
section and not in continuous length due to any reasons, the contractor shall see that no
ends of pipes are kept open. The shall be immediately plugged with G.I. plug without any
extra claim, accommodate specials or fittings coming along the alignment.
Payment :
The rate shall be for one meter of pipe laid including all specials and fitting. The
length shall be measured not on the straight and curves along the center line over the
pipes correct upto one centimeter. Payment of untested section shall be made @ 70% of
the tendered rate. Remaining payment shall be made on giving satisfactory hydraulic
test by the contractor.

Item No.9 Lowering laying and jointing R.C.C. Pipes in C.M. 1:11/2 of following
diameters in proper position, grade and alignment as directed by
Engineer-in-charge including conveyance from stores to site of work
labour, giving hydraulic testing as per ISI code etc. complete.
Including cost of jointing materials.
R.C.C. NP3 Class Pipes 225 mm dia.
Laying :
Before laying, the trench section shall be got checked to designed levels. And grades,
and finished with proper bedding as directed. The contractor shall have to provide and
maintain site rails and bounding rods, of required length whenever required, till the
completion of work. The pipe shall be laid in reasonably dry condition and under no
circumstance; they shall be rest on slushy, murrum bedding. The pipe shall be lowered by
means of manually
Caulking :
The mixture 30 prepared shall be rammed and well packed and pressed with a caulking
tool into the annular space. Wooden wedges, if necessary shall be used for the job. The
caulking shall be so firm that it shall be difficult to drive the point of pen knife into it.
The joints shall be finished off with a fillet sloping 45º along with the length of pipes. It
shall be finished smooth with cement slurry.
Payment :
The rate shall be for one meter of pipe laid including all specials and fittings. The length
shall be measured not on the straight and curves along the center line over the pipes and
specials correct up to one centimeter. Payment of untested section shall be made @ 70%
of the tendered rate. Remaining payment shall be made on giving satisfactory hydraulic
test by the contractor.
Item No.10 Lowering , laying and jointing in position following C.I. D / F reflex
valves, butterfly valves, sluice valves and air valves including cot of
all labour , jointing materials , incl. nuts, bolts and giving
satisfactory hydraulic testing etc. complete.

80 mm dia.

For Sluice Valve :

Supply Of Materials :

Cast iron double flanges sluice valve with two tail pieces suitable to pipe shall be
carted by the contractor at his own cost from the department store or any other store

11 | P a g e
as directed . The rate shall include loading, unloading and stacking at site. The sluice
valves and tailpieces shall be examined before laying for graces and other flaws, they
shall be undamaged in all respect. The sluice valve shall be test operated before laying.
All grits and foreign material shall be removed.

The tightening of gland shall be checked with a proof in side. Clappers cleanse
between the top of the stuffing box and the underside of the gland shall be uniformed
all the sides.

Jointing Materials :

The contractor shall provided all necessary jointing materials such as nuts, bolts,
rubber packing white zinc jute lead wood etc. All roofs and plate required for
installation of sluice valve shall be provided By the contractor.

All jointing materials shall be got approved from The Engineer in charge before
used. The nuts and bolts shall conform to Item No.17 for specification of materials. The
rubber packing shall conform specification as narrated in Item No.17 for specifications
of materials.

Installation :

The sluice valve shall be lowered in the trench carefully, so that no part is
damaged during lowering operation. All pieces shall be fitted with sluice valve first out
side the trench and than lowered. The packing shall be of full diameter of the flange
with necessary holes and the sluice valve bore. If the flange faces found free, thin
fibers of lead wool shall be used to fill up. after placing the packing, nuts and bolts shall
be inserted and tightened to make the joint. The valve shall be inserted in such a way
that the spindle shall remain truly vertical position. The rate includes cost of Extra
excavation required for facility of lowering and fitting.

Testing :

After installation of sluice valve, the same is tested for 1½ times the working
pressure. The joints of sluice valve shall with stand at test pressure of pipeline. Defect
noticed at the time of operation shall be rectified by the contractor at his own cost
other than manufacture.

Mode Of Measurement And Payment :

The measurement shall be taken per number of sluice valve of specified size. The rate
shall be per number fitted in pipeline for non-tested sluice valve 30% with held till
testing given.

For Air Valve:

General :

The Air valve shall conform to the ISS as and when published and shall be of
approved make and quality. The standard applies to air valves used for water and
sewerage mains. The details given below briefly cover the requirement for materials ,
dimensions and tests for air valves.

Classification :

12 | P a g e
Air valve shall be of two types:

Single Air Valve :

Single air valve shall have single small or large orifice for releasing air during
pipe filling and ventilation the pipe during emptying. Air valves up to 40 mm dia. directly
shall be screwed on the main.

Double Air Valve :

Double air valve shall have two ball chambers on outlet of bulk large capacity
shall be provided for admission and releases of bulk volume of air during emptying and
filling of the main, another of small outlet type for the escape of smaller quantities of
air accumulating under pressure. They shall be of flanged type.

Materials :

Cast Iron :

Cast iron for bodies pressure covers space covers glands, caps joints support
rings shall be best gray iron of selected grade 20 of IS 10 – 1970 specification for gray
iron castings.

Gun Metal :

Gum metal shall be of mixture of 88% of copper , 10% thin 2% sink having
excellence wearing qualities , Ball guides of small orifice units are outlet bushes of large
orifice valve shall be of gum metal.

Mild Steel :

Bolts, nuts, flanges etc. shall be of mild steel unless otherwise specified and
shall confirm to IS 226 – 1975 specification for structural steel.

Material For Balls :

The balls shall be of rubber covered. The rubber shall have a smooth and hard
surface. If shall be as per IS 638 – 1965 specification for rubber and insertion jointing.

Dimensions :

Small orifice air valve having single rubber ball is available in the following sizes
12 mm to 20 mm, 25 mm large orifice single air valves are available in following sizes.

40 mm , 50 mm, 80 mm , 100 mm , 150 mm

Double air valves are available in size.

50 mm , 80 mm , 100 mm , 150 mm , 200 mm.

Air valve up to 40 mm size shall be of screwed type fitted with Nipples.

Inspection And Testing :

The Engineer – in – charge or his authorised representative shall have free


access to the works for inspection at only stage of manufacture and to reject any
materials , which does not confirm to the specified requirements.

13 | P a g e
Manufacture’s Guarantee :

The manufacture shall guarantee that if any defect chargeable to faulty


workmanship, design or materials are found in the valve within a period of one year of
dispatch shall be replace any part the prove defective free of charge at the place where
dispatched.

Mode Of Measurement And Payment :

The measurement shall be for the number of valve provided and fixed. 70% rate
shall be paid per number of valves provided. Remaining 30% amount shall be released
after fixing and satisfactory testing and commissioning. Payment shall be made for
fixing of sluice valve No. basis.

Item No.11 Construction of valve chamber in brick or bela stone masonry, locally
available in C.M. 1:6 , foundation concrete 150 mm thick in C.C.
1:4:8 of trap metal size 25 mm to 40 mm thick, inside cement
plaster in C.M. 1:3 and cement painting outside in C.M. 1:3 and top
cover of precast RCC slab 100 mm thick (With key hole in two
parts ,each with handles or MS Bar) etc. complete as given upto
1.00 mt depth from G.L. to pipe invert level incl. compl. civil work
but excluding cost of excavation and refilling with cast in situ RCC
slab in one single piece with fixing of CI-MH frame and cover
(excluding cost of CI-MH frame and cover) with 23 mm thick brick
masonry wall in C.M. 1:6 with precast slab in two parts 15 mm.
Size 0.60 x 0.60 x 1.0 M
General :

The construction work of chambers shall be carried out as specified in the item
description , size given, and instructions issued by The Engineer in charge on site as per
site situation. The other specifications shall be as under.
Materials :
Bricks :
Commonly burnt clay building bricks with all requirement of IS 1077 – 1976 or
it’s latest revision shall be used. The size of conventional bricks may very from 9” x 4¾”
x 3” to 9” x 4½” x 3”. Only bricks of standard quality and size shall be used in the work.
The crushing strength of brick shall not be less than 35 kg/cm2. The average water
absorption shall not be more than 20% by weight.
Sand :

The sand shall be used of required grade as specified in Engineer-In-Charge.

Metal :

The metal shall be used of required grade as specified in Engineer-In-Charge.

Cement :

The metal shall be used of required grade as specified in Engineer-In-Charge.

Mild Steel :

Bolts, nuts, flanges etc. shall be of mild steel unless otherwise specified and
shall confirm to IS 226 – 1975 specification for structural steel.

14 | P a g e
Construction :

The masonry chamber shall be constructed as per drawing from invert of pipe to
atleast 5 cm. High than natural ground. As per line and level and size of chamber, the
chamber pit shall be excavated as directed by The Engineer in charge. The foundation
concrete 150mm. Thick below pipe invert in C.C. 1:4:8 shall be as per drawing and as
instructed by The Engineer in charge. Brick masonry wall 23 cm. thick in Cement Mortar
1:6 shall be constructed as per drawing and as instructed by The Engineer in charge. The
masonry wall shall be plastered inside with cement mortar 1:3 including niru finishing ,
and out side joints struck with cement mortar 1:3 as per drawing and as instructed by
The Engineer in charge. For covering to portion R.C.C. slab with concrete mix proportion
1:2:4 of 100 mm. Thickness shall be cast in two piece with M.S. reinforcement as per
drawing and as instructed by The Engineer in charge having necessary arrangement for
handles or M.S. bars and key hole in center.
Curing :

The masonry and concrete work shall be initially protected from external
damage and covered with wet sacking canvas shall be kept continuously wet by sprinkling
water at least seven days.

Mode Of Measurement And Payment :

The chambers shall be measured in number bases as constructed with all


materials and labour, curing, finishing etc. complete. And payment shall be made
accordingly after completed in all respect.

Item No. 12 Providing C.C. M. 100 for encasing pipes using trap metal size 12 mm
to 50 mm including form work curing consolidating etc. complete.
General :

The construction work of encasing pipes shall be carried out as specified in the
item description, size given, and instructions issued by The Engineer in charge on site as
per site situation proportion of encasing of c.c. 1:3:6 as per concrete work sub estimate
No. 3 item No. 4 payment shall be made on M3 basis. By volume of conc. & deduction of
volume of pipe and work shall be carried out safely for do not damage of pipeline.

Item No.13 Refilling the pipeline trenches from the available selected excavated
stuff or to be brought from out side if required and disposal of
surplus excavated stuff as directed.

Within a lead of 3 Km.

General :

The refilling will generally refer to refilling of foundation or trenches up to


plinth level or ground level with excavated stuff or selected soil or murrum brought
from out side.

Materials :

15 | P a g e
The selected soil, sand or murrum brought from out side shall be cleared of all
rubbish large size stones, brickbats, big clods etc. And shall be got approved before
filling.

Refilling :

Refilling shall be done in a systematic manner by the contractor , before


refilling starts, the contractor shall got checked the foundation / trenches ready for
refilling.

All space between foundation masonry, concrete , pipe line and the sides of
excavation and / or bottom of foundation shall be refilled to the original surface or up
to plinth level with earth or selected materials in layers of 15cm. to 20 cm. well watered
and rammed. Each layer shall be well watered and compacted with heavy rammers before
the upper layer is laid, till the final level reached to form a thoroughly compacted base.

Measurement And Payment :

The measurement shall be taken for total volume filled up. It includes loading,
unloading, carting, breaking clods etc. It also includes the cost of bringing selected
materials from out side as directed by The Engineer in charge. The payment shall be
made according to refilled volume measured in Cubic meter.

Item No. 14 Providing, supplying & fixing ISI mark G.I. pipes with coupling of
following class and diameter including all taxes ,insurance ,
transportation ,freight charges, octroi, inspection charges, loading,
unloading, conveyance to departmental stores stacking etc. comp.

80 mm dia. G.I. Pipe

General :
Galvanized iron pipes shall conform to I.S. 1239 – 1968 part-I or latest revision
of I.S.S. for mild steel tubes Part-I used for conveying water. The tern tube is
synonymous with the term “Pipe”.

The details given below briefly cover the requirement for dimensions , and test
for G.I. pipes.

Classification :
The pipes shall be classified as light medium and heavy depending on the wall
thickness. The pipes may be screwed, socketed and plain ended.

Socket or coupling shall be either welded or seamless as agreed to between the


purchaser and the manufacturer.

Dimensions And Weights :

The dimensions and weights of light , medium and heavy black tubes shall be as
per table-1. The dimension of sockets shall be as per table-2 of relevant specifications.
Tubes or pipes shall be supplied in random lengths from 4 to 7 m.

16 | P a g e
Tolerance On Thciness And Weight :

The following manufacturing tolerance shall be permitted on the tubes and


sockets.

(a) Thickness :
(1) Butt light welded : - Not limited
8 percent.
Medium and heavy tubes - Not limited
10 percent.

(2) Seamless tubes - Not limited.


- 12.5 percent.
(b) Weight :

(1) Single tube irrespective - 10 percent


of the quality - 8 percent

(2) For quantities of 150 m - 4 percent


and over of one size. - 4 percent
Joints :
All screwed tubes or pipes and sockets or couplings shall be supplied with pipe
threads conforming to I.S. 554-1964. Unless otherwise specified, screwed tubes shall
have taper threads and sockets shall have parallel threads. Each tube shall be supplied
with one socket. The ends of sockets shall be chamfered internally to prevent damage to
the leading threading.

Hydraulic Test :
Each tube shall be hydraulically tested at the manufacturer’s works weather
before or after galvanizing.

Marking :
The different classes of tubes shall be distinguished by color bends, which shall
be applied as follows before the tubes leave the manufacture’s works.

Light tubes - Yellow


Medium tubes - Blue
Heavy tubes - Red
All long random length shall each have 75 mm. Bends one near each end, all other
length shall each have one 75 mm. bend.
Payment :
The rate shall be for one meter of pipe supplied at store or site of work. The
length shall be measured on the straight and curves along the center line over the pipes
correct up to one centimeter. Payment of untested section shall be made @ 70% of the
tendered rate. Remaining payment shall be made on giving satisfactory hydraulic test by
the contractor.

17 | P a g e
Item No.15 Providing & supplying ISI standard R.C.C. Pipe in standard length of
following class and diameter suitable for either collar joints or
rubber ring joints including all taxes, insurance, transportation,
freight charges, octroi, inspection charges, loading. unloading,
conveyance to departmental stores, stacking etc. complete.
R.C.C. NP3 class pipe 225 mm dia.
General:
The pipes shall confirm to I.S. 458-1971 or the latest revision of I.S.
specifications for concrete pipes (with and without reinforcement) for use in water
mains sewers, culverts and irrigation. The details given below briefly cover the
requirements for R.C.C. pipes with circular section only.
Classification:
For the purpose of this standard, concrete pipes shall be classified as under:-
class description Conditions where normally Used
NP-1 Unreinforced concrete For drainage and irrigation use, above

non pressure pipes. ground or in shallow trenches.

NP-2 Reinforced concrete light For culverts carrying light Traffic


duty, non pressure pipes. .

NP-3 Reinforced concrete heavy For drainage and irrigation use for
duty non- pressure pipes. culverts carrying very heavy traffic, such
as Railway loading prescribed by the
Ministry of Railways, Govt. of India.
Un-reinforced and reinforced concrete non-pressure pipes shall be capable of
with standing a test pressure 0-7 Kg./Cm². (7 m. Head)

Materials :
Cement :
Cement used for the manufacture of Un-reinforced and reinforced concrete
pipes shall conform to I.S. 269-1967 or I.S. 455-1967 or I.S. 1469-1967.
Aggregates :
The aggregates to be used shall conform to I.S. 383-1970. They shall be well
graded and shall be from crushed or broken stone.
Reinforcement :
Reinforcement used for R.C.C. pipes shall conform to I.S. 432-1966 (Part-I) and
shall be of tested quality of not less than grade-I or hard drawn steel wire conforming
to I.S. 432-1966 (Part-II) where soft grade wire is used. It shall conform to I.S. 280-
1962.
The manufacturer shall produce a test certificate if desired by The Engineer in
Charge.

Concrete :
Concrete shall conform to I.S. 456-1978 code of practice for plain and
reinforced concrete for general building constructions. Compressive strength test shall
be conducted on 15 Cms. cubes as per I.S. 516-1959. The pipe shall be supplied by agency
with testing & Inspection by authorized manufacturer without claiming extra cost.

18 | P a g e
Payment :
The rate shall be for one meter of pipe provided as per IS and with all
certificates required. The length shall be measured center line over the pipes and
correct up to one centimeter. Payment of shall be made @ the tendered rate.
Item No.16 Making job connection for old pipes in connecting the pipe line with
existing main and inserted of specials including cost of excavation ,
carting of pipes , dewatering, testing , refilling etc. complete.
including all jointing materials etc. complete. (Excluding cost of
specials pipe and fitting) job work in cement joints only

Working Criteria :

1. Excavation for pipeline trenches on both ends.


2. Opening of existing pipeline or pipe line end.
3. Cleaning , cutting , and adjusting the required space.
4. Making connection with line.
5. Testing of joint.
6. Refilling the trench.

Making Connection :

Excavation of pipeline trench shall be carried out for required length, width and
depth for working. Opening of both side ends or pipes at the point to be connected.
After opening, both side ends / pipes shall be washed and cleaned for the job. Adjusting
the measurements required for inserting the specials and cutting the pipe from point
placed. The connection shall be made with required materials such as pipe piece, bend ,
tee, reducer , valve etc. including making vata for preventing leakage. The specials
required shall be provided by the dept.

After connecting job over , the joint shall be tested for required line pressure
within stipulated time limit as directed by the engineer in charge.

Mode Of Measurement And Payment :

On completion of connection work as per the agreement, shall be measured in No.


base.

Item No.17 Removing of existing pipeline including removal of specials, valves


jointing materials including carting and stacking of removed materials
from site of work to the departmental stores as directed excluding
excavation and refilling.
The removing existing laid pipe line work shall be carried out as per description of the
item and as directed by the Engineer – in – charge of the work.
Stacking of Material
The removed quantity of pipes and specials shall be loaded, carted, unloaded and stacked
proper from site to on departmental store by the contractor at his own cost.
Pipes shall be lifted in whatever length removed from the trench.
Each pipes and specials shall be arranged length wise by the side of the excavated
trench without causing any obstructions to the traffic.

19 | P a g e
The removed pipes specials jointing materials and other materials shall be returned to
the Board’s Stores as specified by the Engineer – in – charge or as specified in Schedule
– A of the tender.
Every care shall be taken by the contractor to minimize wastage.
Mode of Measurement & Payment
The rate shall be for one meter of pipe line removed including all specials and fittings
and jointing materials, cutting ends wastage shall not be paid separately.

The payment should be made on running meter basis of the pipe removed satisfactory.
The length of specials will be included.
Item No.18 Manufacture, supply and delivery of 80 mm to 700 mm dia cast iron
plain ended specials complete as per IS: 5531-1977 (Part- I to III)
or its latest revision if any, suitable for use with A.C. Pressure pipes
manufactured as per IS: 1592-1989 or its latest revision for various
dia meter and classes. The delivery of specials is to be made to
GWSSB store or sites any where in Gujarat States including all
taxes, loading, carting, unloading, stacking, insurance, octroi,
inspection charges etc. comp.
General :

The specials shall conform to I.S. 1538 – 1976 or latest revision of I.S.S. for
cast specials suitable standard applies to specials with sockets for load joints, or rubber
joints or flanges.

The details given below briefly cover the requirements for dimension and tests
for C.I. specials.

Manufacture :

The metal used for the manufacture of fittings shall be of good quality, gray
cast iron as per I.S. 1387 – 1967. The fittings shall be stripped with all precautions
necessary to avoid warping or shrinking defects. The fittings shall be free from defects,
other then unavoidable surface imperfections, which result from the method of
manufacture and which do not effect the jointing of fittings. The fittings shall be such
that they could be out drilled or machined. In case of spigot and socket joints, the
socket shall be with or without the centering ring. In case if flanged joints the flanged
joints the flanges shall be at right angles to the axis of the joint and machined on face.
The bolt-holes shall be drilled. The two flanges of the fittings shall be correctly aligned.

Dimension :

The dimension on external diameter of the barrel the internal diameter and the
depth of the socket for lead joints and rubber joints shall be as follows.

20 | P a g e
Dimension Nature of Nominal Tolerance
Joint Diameter (DN) mm.

External dia. Rubber All diameters + 4.5 + 0.001

of Barrel (DE) Joints - 5 (DN)


Internal dia. Rubber 80 mm. + 4.5

of socket (DI.) Joints -0


Over 80 mm. up to & +5

including 600 mm.


Over 600 mm. up to & +5=0

including 1000 mm.


750 mm. up to +6

including 600 mm. -0


Depth Lead or Over 600 mm. up to & + 10

Socket Rubber Including 1000 mm.


Jointing
Over 1000 mm. up to & +5
including 1800 mm.

Where Dn is the nominal diameter of the fittings in millimeters and ‘F’ is the
caulking space of the joint in millimeters and equal to 9.00 + 0.003 DN. The maximum of
minimum jointing space resulting from these tolerances is such that the jointing of pipes
and fittings is not adversely affected.

Tolerance Are On Thickness :

The tolerance on the wall thickness and flange thickness of fittings are limited
as follows:

Dimensions
Tolerance mm.

Wall thickness - (2 + 0.05 e)

Flange thickness + (3 + 0.05 e)

Where e= the standard thickness of the wall in millimeters.

b= the standard thickness of the flange in millimeters.

Tolerance Of Lengths :

The tolerance on lengths of fittings normally manufactured are as follows.

Type of fittings Nominal diameter Tolerance mm.

Flanged fittings All diameters + 10

Weights :

21 | P a g e
The standard weights shall be as shown in Part-II to part-XXXII of I.S.
1538 – 1976. The masses have been calculated by taking the design % C.I. of 7.15
kg/cm2.

(A) Tolerance fittings except of bends fittings with more


than one branch and non-standard fittings + 8 percent.

(B) Tolerance for bends fitting with more than one branch
and non-standard fittings. + 12 percent.

Fitting of a heavier weight than the maximum are accepted provided they comply
the requirements of this standard.

Making :

The following information shall be marked on each fittings.

Trade mark of manufacture.

Nominal diameter weight and class of fittings.

Last two digits of the years of manufacture.

Mode Of Measurement & Payment :

The measurement and payment of fittings shall be as per kilogram basis. of the
item rate. The rate shall include the cost of fittings with railway freight, loading,
unloading, carting, stacking as directed load, taxes insurance etc.

22 | P a g e
“Missing Link” Programme
PARIEJ REGIONAL WATER SUPPLY SCHEME

Ta. :- Matar. Dist:.:- Kheda


Sub Estimate No. 2
Constructing R.C.C. U/G. Sump 2,00,000 ( Dethali ), 1,00,000
( Bamangam) & 30,000 ( Chanor ) Lit. Capacity (Contractor’s Own
Design)
The tender being invited with contractor’s own design. The tenderer
shall prepare and submit along with the tender an “Inspection Note” on design in the
same cover of the tender. He shall also indicate the approximate quantity of cement and
steel as per his design. The successful tenderer shall submit the detailed design and
drawings within 30 days of issue of acceptance letter including soil bearing test report
of the destination where the structure shall be constructed.
ANNEXTURE

Design Requirement of R.C.C. U/g Sump

Sr Parameters At Village At Village At Village


Site Site Site

1 Village Dethali Bamangam Chanor

2 Taluka Matar Matar Matar

3 District Kheda Kheda Kheda

4 Constructing Structure U/G. Sump U/G. Sump U/G. Sump

5 Capacity 2,00,000 1,00,000 30,000


Liters Liters Liters

6 Container Shape Cylindrical Cylindrical Cylindrical

7 Finished ground level 100.00 100.00 100.00

8 Bottom level of U/G. Sump 97.00 97.00 98.00

9 Height of structure ( HMGL) in M.R.L. 100.60 100.60 100.60

10 Minimum water level in the container (m) 97.10 97.10 98.10


R.L.

11 Maximum water leveling the container (m) 100.30 100.30 100.30


R.L.

23 | P a g e
12 Water Depth 2.50 to 2.50 to 2.00 to
3.00 3.00 2.50

13 Free Board 0,30 0,30 0,30

14 Inlet pipe (Size in mm) Horizontally 80 80 80


extended up to atleast 1.00 to 1.50 mt
from shaft wall.

15 Out let Pipe cum Wash out-- do -- -- do - 80 80 80

16 Overflow pipe – do -- -- do -- 80 80 80

17 Structure { Shape & Concrete Grade } As per As per As per


Design M- Design M- Design M-
250 250 250

18 Entire structure except PCC M-250 M-250 M-250

19 Soil Bearing Capacity Kg/cm Kg/cm Kg/cm²


² ²
CRITERIA FOR PREPARTION OF DESIGN OF R.C.C. U/G. SUMP PRIVATE AGENCY
REQUIREMENTS :
Sesmic Zone:
The R.C.C. U/G. SUMP shall be designed to with stand earthquake effect of III
zone as per IS 1893 – 1984 or it’s latest revision. Criteria for structure design as per
guideline by the expert group of Government of India, Ministry of Urban affairs &
employment, published by building materials & technology promotion council.
Cyclone/ Wind Intensity/ Wind Storm Protection:
As per IS 875 (3) – 1987 or it’s latest revision latest edition “Code of Practice
for Design loads for building and structure Part – 3 wind loads”. For structural safety
improving wind/ cyclone resistance of building’s guide line by the expert group of
Government of India, Ministry of Urban affairs & employment, published by building
materials & technology promotion council 1998.
Shape of U/G. SUMP.:
Shape of U/G. SUMP should be good looking with the acceptable architectural
effect consistent with the surrounding site conditions and economy.
General Note:
The contractor shall quote the rates in “Schedule B” for the complete work of
constructing R.C.C. U/G. SUMP to be carried out as per his own design based on above
data i.e. he shall tender the rate in “Schedule B” for
construction of U/G. SUMP reservoir of different capacity liters including
providing and fixing pipes, lighting conductor, C.I. manhole frame & cover, water level
indicator, ventilators etc. complete with contractor’s own design and drawing.
The contractor shall submit the name, qualification and experience of design
engineer, who has or will prepared the detailed R.C.C. design and drawing with
calculations including SBC report on acceptance of the tender.
Soil Bearing Capacity Test

The detailed soil foundation investigation for the work of U/G. SUMP and
underground sump is to be carried out as per I.S. Standards as per site conditions by
agency. Minimum depth 10.00 mt shall be checked. Results of soil bearing capacity shall

24 | P a g e
be calculated and given for every 3.00 mt depth. The rules and methods described in
relevant IS/manual/hand book shall be strictly followed during taking samples and
testing. Water table met with shall be observed and clearly mentioned in the report.
The foundation of structures should be designed on this foundation soil investigation
data. SBC shall be carried out by the agency. In any circumstances, stability of
foundation should be disturbed and found fault in S.B.C. results, the agency will be held
fully responsible for the same.

The contractor should have to submit design on base of got S.B.C. through
Zone / Board approved paneled design engineer and same to submit to zone office
through proper channel for cross verification to zone / Board design engineer.

The design of lowest tender or any other tenderer, whose tender is proposed
to be finally accepted, will be subject to through check by The Superintending Engineer,
Public Health Design Circle, Gujarat W. S. & S. Board, Gandhinagar. The tender
agreement will be executed only on approval of design.
The necessary scrutiny charges or the centage charges towards the approval
of design & drawing of R.C.C. U/G. SUMP will have to be born by the tenderer.
The design engineer will be required to attend the office approving authority
for preliminary discussion for scrutiny remarks etc. whenever required with all
reference data, books i.e. specifications etc. at his own cost.
It will be duty of the design engineer of contractor to clarify, modify, redesign
and finalize and submit the design and drawing as per scrutiny remarks offered by the
authority within 30 day’s of the issue of acceptance letter.
On approval of design, contractor shall supply five sets of approved design
drawings duly signed by designer and approving authority free of cost for use of
committee.
The instructions contained in criteria for design of R.C.C. U/G. SUMP shall be
strictly followed and the tenderer shall submit his design based on acceptance of these
criteria. The designer shall have to modify his design as per the criteria without any
change in the tender cost submitted. Earnest money of the tenderer stand forfeited if
he fails to modify his design as per above criteria. The tendered amount filled up by the
tenderer shall be considered as final cost for completing the whole construction work
including designing plans, and got approved by the competent authority.
Actual work order for construction will be given only after approval of design
of R.C.C. U/G. SUMP
The detailed design calculations and detailed drawings should be submitted
within 30 days of the issue of acceptance letter. In case of non submission of detailed
design within 30 days the tender shall be rejected and earnest money deposit shall be
forfeited.
GENERAL
Capacity of the container of the U/G. SUMP shall be the value of the water it
can store between the designed full supply level (FSL) and lowest supply level (LSL) i.e.
the level of the Top of the outlet, pipe. Due allowance shall be made for 20 mm thick
plastering the tank from inside while calculating the capacity of the tank.
Free board is the vertical distance between FSL and soffits of covering slab or
dome or beam supporting the cover In any case the free board shall not be less than
200 mm.

25 | P a g e
Height of the staging or height of the tower shall be the vertical difference
between L.S.L. of the U/G. SUMP and the average ground level at the site of U/G. SUMP
Dead storage shall be the storage capacity of water below L.S.L. Depth of dead
storage shall be the vertical distance between the tip outlet level and wash out level.
The washout pipe level shall be at the lowest portion of the container.
Minimum depth of water for dead storage shall be 100 mm even for flat bottom
slab
Water depth in the U/G. SUMP shall be the vertical distance between L.S.L. and
F.S.L. of tank.
The detailed soil foundation investigation for the work of U/G. SUMP and
underground Sump up to 10 mt. depth by augur drilling is to be obtained out by agency
with the help of recognized soil investigation laboratory at his own cost without claiming
any extra cost. The foundation and structures should be designed on this soil
investigation data.

Not withstanding anything mentioned above regarding S.B.C. whenever the


Engineer-in-charge of design directs that bearing capacity shall be determined by
carrying out actual soil exploration and tests due to conditions as mentioned in para 2.0
of IS 1992-1969. The same shall be carried out by a Government laboratory or any
other approved laboratory of GWSSB Authority not below the rank of S.E. at the cost
of contractor and allowable bearing capacity so arrive shall be taken as the basic of
design. The factor of safety adopted in case of actual test shall be as per clause 6.1 (A)
of IS 6403 - 1971.

GENERAL REQUIREMENTS:

Cement concrete shall be in accordance with IS 456-1978 & fine and coarse
aggregate shall be confirming to IS 383-1963 or its latest revision. The selection of
the type of fine and coarse aggregate to be actually used shall be as directed by the
Engineer-in-charge.

For parts of the U/G. SUMP in contact with stored water and closing vapor
above FSL shall be in concrete grade M250 or in richer grade.

Inlet, Out let, Overflow and Washout pipe:

Materials:

LA Cast iron flanged pipe of appropriate class shall only be used.

Inlet Pipe: The size of inlet pipe shall be as per annexure

Out let pipe: The out let cum washout arrangement pipe shall be as per annexure.

Over flow pipe: The size of overflow pipe shall one diameter higher than that of inlet
pipe.

Detailed drawing showing all the pipes, duck foot bends, chamber, sluice valves
and other necessary connection shall be furnished in the plan. Plain concrete block in M-
15- for duck foot bends shall be of minimum depth of 600 mm. The width of the block
shall have an offset minimum of 150mm.

A water level indicator shall be provided for the tank reading depth of water in
meters with least count of 10 cm. The system shall consist of un corrosion able material

26 | P a g e
and shall be simple and easy to maintain. The water level indicator shall be provided and
fixed as approved and directed by the engineer-in-charge.

Access to roof for an entry to the inside of the tanks shall be provided. At
roof level of the tank the access to roof manhole from the ladder or stair shall be
properly provided with parapet or railing. At ground level or at walkway level the access
forgoing up shall be provided with a door and locking arrangement. Railing at roof level
and at gallery level shall be provided.

If not specified in data sheet at least one manhole with frame and cover of CI
medium type shall be provided with ladder for entering into the

container for maintenance purpose. The size of manhole frame shall be 0.9 x 0.6
meter 75 kg weight.

Cowl type ventilators of 100 mm. dia. having standard dimensions and weight
shall be provided as per design.

The roof of the tank shall be ventilated by providing cowls or ventilators with
mosquito proof met for ventilators. They shall be fixed with proper framing. Ventilation
are shall not be less than of

(A) 0.04% of the free water surface when cowl type ventilators are provided

(B) Cross sectional area of the inlet pipe.

(C) Cross sectional area of the outlet pipe.

All tanks shall be checked for seismic forces confirming to IS 1893-1975 or its
latest revision

Water U/G. SUMP in vicinity of mines, galleries and blasting sites or in areas
which may be subjected to blasting sites or in areas which maybe subjected to blast or
shock shall be designed for the dynamic forces developed due to blast equipment.

Members of towers, which are primarily subjected to dynamic stresses, shall be


checked for ductility of the members at the joint.

Staircase and all columns shall be tied together just above foundation level by
structural members such as a braced or a tie ring beam.,

Following shall be the minimum thickness of various members of the tank


container.

Roof Slab/ dome 100 mm

Bottom slab 200 mm

Vertical wall including shaft wall 150 mm

Error up to 0.25 % in weights, forces, moments etc. in the design calculation


may be neglected.

DESIGN

General

Shape of the structure shall be as directed by Engineer-in-charge and shall be


selected depending upon site condition from the standard shape.

27 | P a g e
General description and salient feature as mentioned below of the design shall
be not approved by the Engineer- in- charge and shall be mentioned in the design before
detail design calculations starts.

Sketch showing dimensional section, elevation with plan shall be given. The
safety against over turning of structure shall be computed quite accurately. Design shall
be based on the worst possible combination of various loads, moments, shears and
resultant stress in the tank for the following two cases.

“A” U/G. SUMP full

‘B” U/G. SUMP empty.

U/G. SUMP full means depth of water inside the container up to full height of
the container without consideration of free board.

Safe bearing capacity of soil based on actual soil investigation report of the
laboratory including Position of sub soil water level.

Chemical analysis if sub soil water and soil, where possibility of brackish / saline
water is ascertained.

The location of site shown on index plan in respect to latitude and longitude.

Design shall be based on accepted basis and methods of design as well as the
provision of IS 3370-1965, IS 4546-1978, IS 1843-1960,IS 2210-1962,IS 2204-1962
etc. and their latest revision. However methods based on experimental investigation as
mentioned in Para 18.2% “C” in IS 456-1978 shall not be entertained.

The parts of the structure neither in contact with the liquid on any face more
enclosing the space above the liquid as the case of stages of a tower shall be designed
on working stress method on accordance with the requirement of Is 456-1978. Staging
may be designed on limit method as per IS 456-1978.

Design of members other than these excluded by above (i.e. roof, walls, floor
etc. of the contractor ) shall be based on consolidation of adequate resistance of
cracking as well as adequate strength calculation of stresses shall be para as per 3.2.2
of IS 3370 ( part-II) 1965 or its latest revision.

GENERAL CONDITION FOR WORK


BREAK UP OF PAYMENTSCHEDULE FOR UNDER GROUND SUMP
Sr. Stage of work Amount
No Admissible
payment

1 On approval of design and on submission of Six sets Including SBC test, 3.00 %

2 On completion of excavation and concreting of base slab/Raft 30.00 %


Foundation. completion of concreting

3 Full container structure including column, wall, ring beam and completion 30.00%
of top slab/dome, fixing M.H. fame & cover, cowl type ventilator etc.
complete.

4 Procurement and fixing of Inlet, Outlet. Washout, Overflow pipe valves 20.00%
specials chambers, and specials as site.

28 | P a g e
5 Water level Indicator, plaster, painting of letters, M.S ladder, pipe 7.00%
railing and all miscellaneous items such as snowcem paints in three coats
etc.

6 Hydraulic testing, Defect liability One month’s performance 10.00%

Total 100.00 %

ANNEXURE
1. Acceptance :
Intimation of acceptance of tender shall be given by registered post to the address
given below the signature of the tenderer in the tender.
2. Details of works:
The tenderer shall state in his tender the name of the contractor in case the agency
shall be other than him self from whomever the purposes to obtain the centering. He
shall also state by what method he purposes to effect the same. The designs of
centering with type shall be got approved by the Engineer before its erection.
3. Examination of plans and Locations :
Statements as to the condition under which work is to be performed includes plans
surveys, relevant dimensions calculations estimates bearing etc are made to furnish a
basis for comparison of tenders and the Village W. & S. Committee do not guarantee or
represent that they are even very approximately correct. The contractor shall satisfy
himself by all conditions affecting the work to be and done and labor materials needed
and shall make his bid in sole reliance thereon.
4. The work included in this contract shall be carried out in accordance with the
specification rules and regulations as laid down in the books mentioned below in order of
the priority (i) P.W.D. Hand Book Vol. I & II 1949 edition if the reference quoted above
fall short for the items in schedule of contract, reference shall be made to Indian
specifications for the latest edition. If any of the items of this contract are not
covered by the reference books quoted above, details and specification as directed by
the Engineer of Village W. & S. Committee shall be final. This shall depend upon the
standard specifications allowed in different countries of the work for the items
concerned.
PROGRAMME:
The Engineer may at any time give direction as to the order and manner in which the
several part of the work shall be carried out and the contractor shall strictly observe
such direction.
5. Method of Carrying out the work:
The contractor shall furnish for the approval of the Engineer a schedule giving the
program of the work giving details for the method of execution proposed to be adopted.
No work shall be carried by other method except the one approved by the Engineer. The
Engineer may suggest suitable modification in the program and method prepared by the
contractor. Adoption of any such changes shall not entitle the contractor for claiming
any extra rates.
6. Relation with public Authorities :

29 | P a g e
The contractor shall comply with all powers and legal order and directions given from
time to time by any local or public authorities and shall pay out of his own money, the
fees or charges to which he shall be liable.
7. The contractor shall at his own expense obtain such license as may be necessary
storing and using explosives. The Village W. & S. Committee shall incur no responsibility
whatsoever in connection with the storage of explosive on the site or any accident or
occurrence whatsoever in connection there with. All operations of the contractor on
which explosives are employed being at the risk of the contractor and upon his sole
responsibility and the contractor hereby given to the Village W. & S. Committee an
absolute indemnity in respect thereof.
8. RETURNS :
1 The contractor shall furnish the Engineer every day during the progress
of the works classified weekly return of the number of people employed on the work
during the week the report of skilled and unskilled labor shall be given in prescribed
from. The contractor if directed by the Engineer shall increase or decrease the
strength of the labor both skilled and unskilled. The contractor shall also furnish the
following returns:
A weekly medical report showing the health of the Contractor’s camp and the number of
persons ill. OR
2. A report of any accident which may have occurred within 24 hours of its
occurrence.
9. OCCUPATION OF ADDITIONAL LANDS :
In case when it becomes necessary for the fulfillment of the contract for the
contractor to occupy land outside the Village W. & S. Committee limits, the contractor
shall make his own arrangement with the land owners and pay such rents as may be
mutually agreed between them.
The Village W. & S. Committee afford the contractor all possible assistance to enable
him to obtain land for such purpose.
10. CONTROLLED MATERIALS :
As regards controlled materials, Village W. & S. Committee will help to arrange for the
permits as far as possible and help the contractor himself. Though the G. W. S. & S.
Board will help to arrange for the permits as far as possible in obtaining the materials it
shall not accept any responsibility for any delay or loss on account of delay or loss on
account of delay caused. Contractor shall submit the monthly return in the prescribed
forms for the receipts and actual use of the controlled materials during the month to
the Engineer on close of every calendar month.
The contractor shall permit the Engineer or his representatives to inspect the stock of
the controlled materials stored by him at any time whenever engineer or his
representative desires.
11. Permit and licenses :
The contractor shall procure at his sole expenses all permits and licenses and pay all
charges and fees for lawful execution of the work.
12. Permit devices Materials and processes :

30 | P a g e
Whenever the contractor desires to use any design devices materials or process covered
by the letters patent or copy right permission for such use shall be secured by the
suitable legal agreement with the patentee or owner and copy of agreement shall be
filled with Engineer.
13. Temporary Quarters :
The contractor will be required to make his own arrangement for housing of all his staff
and working people during the execution of the work. The contractor shall maintain at
his own expenses efficient staff as may be required by the Engineer. Suitable fire
preventive measures to the satisfaction of the Engineer shall be taken by the
contractor.
14. Plant :
The contractor shall with his own expenses supply sound part plant for the whole of the
works sufficient to perform the work within the time agreed upon in the contract and
keep the same in good condition. He shall also at his own expenses, repair or improve it
when required by written request of the Engineer or his representative.
All unused materials and all plants and equipment not removed by the contractor within
two months of the completion date of the works or any extension granted thereof by
the Engineer shall become the property of the Village W. & S. Committee and contractor
shall not be entitled to any payment or compensation whatsoever in respect thereof.
Conditions regarding medical and sanitary arrangements to be provided for labor
employed in the construction by the contractor.
(a) The contractor shall follow rules regarding public Health and sanitary
arrangements to be provided in labor camp as per paragraph 258 of Gujarat P.W.D.
Manual Vol.1 and appendix in that regard.
(b) The contractor shall make arrangements for all anti malarial measures to
be provided for the labor employed on the work. The anti malarial measures shall be as
directed by the Assistant Director of Public Health.
15. Sub letting of work
The contractor will not be permitted to sublet any of the works without permission of
the Engineer-in-charge. If he gives permission for any part of the work to sublet, the
main contractor shall take full responsibility for the quality of work. Before ordering
subletting of the work the contractor shall submit the names of the subcontractors
proposed for the approval for Engineer-in-charge and shall afterward send the two
copies of the order for the work proposed to be sublet when submitting the names of
the sub contractors for the approval it must be stated as to whether the firms
proposed are the actual manufacturers of makes, if not the names of the makes shall
also be submitted. The sublet orders shall contain all necessary information given in the
specification to enable the sub contractor or supplier to work in accordance therewith.
The sublet order shall also contain the time in which the delivery of the materials will be
given for the completion of the work. The contractor shall be held responsible for non
delivery or non completion in stipulated time given in his tender for the completion of
the whole contract.
16. Foreman, Watchman and Workers

31 | P a g e
Competent foreman and watchman shall be employed by the contractor. The Village W. &
S. Committee shall be at all times have the right to remove from the work any foreman,
watchman or man who gives irresponsible response of misbehaves or misconduct.
17. Co-ordination of specifications, plant and special provisions the standard
specification the plans and all supplementary documents are essential parts of the
contract and requirement occurring in one shall be as binding as though occurring in all
the various documents. Specification and special provisions shall over side both the plans
and the standard specifications. Figured dimensions shall prevail over scaled dimensions
if any. Other variations shall be decided by the Engineer.
18. Inspection of work and materials :
1. For Resident Engineer, Agent and Employees on the work, the contractor
provides safe and proper facilities for inspection.
2. The inspection of the work shall not relieve the contractor of his obligations to
fulfill the terms of the contract as herein prescribed by the plans and
specifications.
3. The contractor shall furnish written information to the Executive stating the
original sources of supply and dates of manufacturing of all material brought or
manufactured away from the actual site of the work.
4. The contractor shall furnish the Engineer every facility and assistance for
ascertaining whether or not the work performed is in accordance with the
requirements and instructions of the plans and estimates and the specifications.
If so, directed the contractor at any time shall comply and after acceptance of
the work remove or uncover any portions of the finished work considered
necessary for fresh inspection at his own cost.
5. In order to ensure a proper time sequence for required inspection and approval,
the information shall be furnished at least two weeks or (otherwise) as directed
by the Engineer in advance of the use or incorporation in the work of any such
materials and this shall be given in writing by the contractor.
6. The contractor shall obtain from Village W. & S. Committee a statement of the
places where it is permitted for him to deposit the materials excavated. The
contractor shall accept the entire site as he finds it any work that may be
necessary to carry out contract shall be provided for in his contract price.
19. Setting out :
The contractor shall be responsible for the true and proper setting out of the works and
or the correctness of the position levels, dimensions and alignment of all parts of the
works and for the provisions of all necessary instruments applicable and labor in
connection there with. If at any time during the progress of the works any error shall
appear or arise in the positions, levels, dimensions or alignments or any part of the
works, the contractor is required to discuss with the Engineer and rectify such errors
to the satisfaction of the Engineer. The checking of any setting out or of any line or
level by the Engineer or his representative shall not relieve to the contractor of
responsibilities for the correctness thereof.
20. No quarrying or blasting operations shall be permitted in the riverbed in the
proximity of the bridge for the purpose of taking out materials required for the work
except where the sites are demarcated by the Engineer for this purpose. The
32 | P a g e
contractor shall be personally responsible for any damage or accident cause by such
operations.
21. An order book shall be provided and maintained by the contractor on the work
and the contractor shall sign the order given by the Department and shall carry out
them. Work Order Book is the property of the Village W. & S. Committee supervisory
staff on site. The compliance shall be carried out promptly and approved by the Engineer
in short time so that works can be checked.
22. No materials should be stacked anywhere on the entire formation width of the
road while carrying out the work. These materials should be stacked on the open ground
area of the land width on both sides of the road. Only in exceptional circumstances with
only written permission of the Engineer such materials can be stacked on shoulders of
the road surface.
23. During the working period, day and night all weather diversion shall have to be
provided by the contractor without extra cost of Govt. The diversion shall be maintained
in good conditions as directed by Engineer-in-charge until completion of work. During the
night time for the safety of traffic, red lamps, etc. Shall be provided without any extra
cost.
24. The contractor shall have must to provide required test certificates as per
P.W.D. rules. If failed, it will be carried out by concerned officials and recovered from
the bill with all expenses for taking samples, curing, transportation and obtaining results.
The payment shall be withheld till receipt of result. The contractor shall not entitle to
claim for time consumed of testing the materials.
25. ROYALTY:
The contractor shall pay the royalty to the competent authority / local body as per
rules. The contractor shall furnish quarterly the statement showing quantity of quarried
materials, from whom purchased (with full address of the seller) and copies of bills for
purchase to the District officer of the Mining and Geology Department or authority
competent to levy royalty in the area of work. Copy of such statement shall be furnished
to the Executive Engineer also. Contractor shall also furnish such additional information
as regards royalty payment to the Executive Engineer and the Royalty authority as may
be called for. The royalty charges paid shall be borne by the contractor and shall not be
reimbursed by the Executive Engineer.
Stress & Strength
PERMISSIBLE STRESS IN CONCRETE FOR RESISTANCE TO CRACKING
For calculations relating to the resistance of members to cracking the permissible
stresses in tension ( direct and due to bending ) and shear shall confirm the values
specified in Table-I of IS 3370 ( part –II 1965 )
The permissible tensile stresses due to bending apply to the fact of the member in
contact with the liquid. In members less than 225 mm thick, and in contact with the
liquid on one side. These permissible stress in bending apply to the face remote from
liquid.
FOR STRENGTH CALCULATION :
In strength calculation, the permissible concrete stresses shall be accordance with
para-44 of Is 456-1978. Where the calculated shear stress in concrete alone exceeds

33 | P a g e
the permissible value reinforcement acting in conjunction with diagonal compression in
the concrete shall be provided to take the whole of the shear.
Permissible compressive stress ( Directly only ) in sheels ( i.e. Top Dome, Conical Wall
and shall be reduced by 43% for 10 cm thick walls. For thickness more than 30 cm, the
compressive stress shall be reduced by 50% and for inter media thickness 20 cm. To 30
cm. Linear interpolation shall be done.
PERMISSIBLE STRESSES IN STEEL :
For resistance to cracking the steel and the concrete are assumed to act together. For
checking the tensile stresses in un cracked concrete for avoidance of cracks, the tensile
stress in the steel shall be the products of the modular ratio and the corresponding
allowable tensile stress in concrete as per IS 3370(part-II) 1965 or its latest revision.
Modular ratio “M” for different concrete mix shall be taken as under
Grade of Concrete Modular Ratio “M”
M-150 19
M-200 13
M-250 11
For strength calculation (concrete assumed to be cracked), the permissible stresses in
reinforcement shall be as per Table – 2 of IS 3370 (part – II) 1965 or its latest
revision. For steel, the stresses shall be as per IS 1966 or its latest revision
The analysis of staging of the tank shall be done by using any established method such
as portal method etc. The staging shall be analyzed from combination of dead, dead live
loads and wind seismic loads. The effect of continuity of beams of the junction shall be
properly accounted and column reaction worked out, for different condition of loading,
axial force, shear force, bending moments.
Modules of elasticity of concrete MEC shall be taken as 5700/FC where equal
of characteristic cube strength of concrete in N/m2 as per IS 456-1976.

Water Tower in seismic zone (II) of IS 1393-1975 twin diagonal (crossed)


backing of steel in vertical plane in addition to the horizontal braking may be provided.

FOUNDATION :

Trial pit at sit of elevated tanks shall be taken, SBC of the soil or allowable
bearing pressure on soil shall be established on the basis of actual strata met with

The permissible increase in bearing pressure for different types of foundation


shall be as per table – I of IS 1893-1965 or its latest revision. When seismic forces are
considered and for wind forces it shall be as per IS 1904-1966 or its latest revision.

For the purpose of the design of foundation the loading data shall be given the
magnitude of vertical load, lateral lad and moments at top of footing (Foundation) level.
The date shall be made available, for both the cases as per para 3.3.2

The foundation area, door, individual column footings, combined footings,


angular rafts and solid rafts shall be worked out on the basis of lower most value of the
safe bearing capacity or allowable bearing pressure values as derived from IS 1904-
1978,IS 9403-1971,IS 8009-1976 or their latest revision.

34 | P a g e
In case of purely cohesion and CI pipe of soil particulars attention should be
given to IS 1903-1978 clause 6 & 7. Settlement shall be calculated as per IS 8009
( part-I) 1976 for foundation.

In case of purely cohesion less soil, foundation shall be design for safe bearing
capacity and shall be checked for permissible total as well as differential settlement
values as given in relevant IS.

If the foundation consists of individual columns footing, minimum clear


distance between center of column shall be equal to twice the width of footing and clear
distance between the edge of footing shall be not less than width of footings.

In case of soil beneath the footings, are not of the same characteristics the
footing shall be designed for the soil having lowest SNC or ANP as per case may be. In
such conditions the permissible limits of total as well as differential settlement shall be
limited to 75% of the permissible limit given in ISS.

For special type of foundation like well foundation under beam pipe foundation
etc., decision of Superintending Engineer, Public Health Design Circle shall be final and
binding to the designer.

Classification of soil and all characteristics of soil relevance to BSBC and APB
shall be as per the soil in investigation reports of Government stipulation, Government
approved investigators.

For the design of foundation angular or solid raft type, the “ PLACE THEORY “
shall be adopted.

In normal circumstances minimum 100 mm thick plain cement concrete with 100
mm projection around in Grade M 100 with coarse aggregate as metal shall be provided
as leveling course. Where injurious soil progressive water is expected the leveling
course shall be grade not weaker than M 250 and if necessary sulphate resisting or the
special cement shall be used. The ground level within the foundation area of the
structure shall be consolidated properly with a suitable slope to drain out rainwater
outside the foundation.

DETAILING :

MINIMUM REINFORCEMENT FOR WATER RETAINING MEMBER :

The minimum reinforcement in walls, floors, roofs, in each of two directions at


right angle shall have an area of 0.3% of the concrete selection in that direction for
sections up to 100.00 mm thick. For section for thickness greater than 100 mm and less
than 450 mm thick minimum reinforcement each of two directions shall be nearly
deducted from at 0.3%. For 100 mm thick sections or greater two layers of reinforcing
steel shall be place one near each face of the section to make up to minimum
reinforcement specified in this clause.

The minimum reinforcement specified in this 5.1 above may be decrease by 20


% in case of high yield strength bars confirming to IS 1976 or IS 139-1978.

Minimum clear cover to reinforcement under normal conditions shall be as per


para 25.4 or IS 456-1978.

35 | P a g e
For liquid faces of parts of members either in contact with the liquid or
enclosing the space above the liquid shall be as per para 7.2 IS 3370 ( part – I 1965).

In case of Raft Foundation, the cover to reinforcement shall be as per 4.6.2 of


IS 295 ( part – I) 1973.

In case of “ SHAFT “ the cover to reinforcement shall be as under

Vertical 25 mm

Vertical 25 mm

Horizontal 25 mm

For members of structure in contact with water, effective cover shall not be
more than 60 mm. Even bars subjected to bending stress, or bars subjected to tension
due pure tension in the member the effective cover shall not more than 75 mm.

Spacing of reinforcement shall be as per para 25.3 IS 456 – 1978.

Spacing of lateral ties for column shall satisfying provision of para 25.3.2 ’ C ’ of
IS 456 – 1978.

The additional suggested criteria for reinforcing steel which accounts for
existing moments, tension etc. I.e. Other than temperature or binding steel shall
comprise of minimum 8 mm for deformed or 10 mm mild steel bars.

The spacing between two para in main reinforcement shall distribution steel,
stirrups, links etc. Shall not exceed 30 cm.

For members of the container, the maximum diameter of reinforcement in


tension shall not exceed as given below depending upon the geometrical percentage of
reinforcement. ( Ratio of tensile steel to gross is concrete.)

Up to 1.0 % 16 mm dia

Up to 1.5 % 22 mm dia

Up to 2.0 % 25 mm dia

Notes :

In case of dispute regarding in to partition of any above clause, the decision of


the Superintending Engineer, Public Health Design circle, Gandhinagar will be binding to
the Designer.

In case of any clause not included in the above criteria the decision of the
Superintending Engineer, Public Health Design circle, Gandhinagar will be binding to the
Designer.

FOR CI PIPE:

The pipes shall be CI/DF pipe heavy duty and as per IS 1239 the rates includes
providing and fixing including all kind of fittings and such as bends, tees, plugs taper.
Which ever required the rates includes also cuttings and bending into shape. Necessary
heavy duty clamps at internal of 3 m at all the required joints of pipes without any extra
cost. Necessary excavation shall be carried out for laying pipeline and same shall be
refilling when the work at all required joints of pipes without any extra cost. Necessary

36 | P a g e
excavation shall be carried out for laying pipeline and same shall be refilling the when
the work is completed and pipeline tested.

All pipes and fittings shall be rectified or replaced without any extra cost. The
item includes providing necessary tools and jointing materials such as which zink spun
yarn, nut and bolts and rubber backing jointing as flanges etc, complete without extra
claim

R.C.C. U/G. SUMP 2,00,000, 1,00,000 & 30,000 Lit. Cap. (Contractor’s Own
Design)

COMMON CONDITION
General:
The general conditions for this work shall be as specified in general conditions.

WATER :

1. Portable water shall be used for CMCC & during testing for other purposes
GENERAL
Specifications laid down in Bombay P.W.D Hand Book, Vol. 1 & 2 for relevant
items of work given in schedule “B” of tender shall be strictly observed unless the some
is repentant to the detailed specification given with the tender of work specific
instructions issued by the interest of the work necessary site clearance and jungle
cutting shall be carried out by the contractor at his own cost. Additional amount for
such work shall not be paid by the department.
For unsatisfactory hydraulic testing of pipe lines 30% payment of plaster items,
C.C. items and pipe line item shall be with held

COMMON SPECIFICATION FOR LAYING, JOINTING PIPES AND SPECIALS AT


DIFFERENT DIAMETERS
Providing & fixing flanged steel cylinder reinforced concrete or C.I. pipes vertically for
R.C.C. U/G. SUMP including providing clamps at every 3mt. including jointing materials
such as nuts, bolts, rubber packing, hydraulic testing and necessary scaffolding etc.
Complete.
General:
The pipes shall conform to I.S. 1537-1975 (first revision) or latest revision of
I.S.S. for vertically cast iron pressure pipes. The standard applies to pipes suitable for
lead joints or rubber joints or flanged joints.
The details given below briefly cover the requirements for dimensions,
tolerance on dimension, and tests for C.I. pipes.
Classification:
The pipes have been designated in accordance with the series adopted in I.S.
1536-1976. Where pipes have been classified LA, A & B according to their thickness,
class LA pipes have been taken as the basis for evolving the series of pipes, class “A”
allows a 10% increase in thickness over class LA. Class “B” allow a 20% increase in
thickness over class LA. For vertically cast pipes class LA has been taken as standard.
Manufacture:

37 | P a g e
The metal used for the manufacture of pipes shall be got good quality cast
iron. The pipes shall be free from defect, other than any unavoidable surface
imperfections which result from the method of manufacture and which do not affect
the use of pipes. By agreement between the manufacturer and the purchaser minor
defects may be rectified. The pipes shall be such that they could be cut, drilled or
machined. In case of flanged pipes, the flanges
shall be as right angles to the axis of the pipe and machined on face. The bolt
holes shall be drilled.
Dimensions:
The dimensions of pipes, sockets spigot and flanges shall be as per table II to
VIII of I.S. 1537-1976. For S & S pipes, the standard length shall be 3.66, 4, 4.88, 5,
5.5 meters.
Tolerance Thickness:
The tolerance of the wall thickness and flange thickness of pipes are as
follows

Dimension Tolerance
Wall thickness -(1 + 0.05 e)
Flange thickness +(2 + 0.05 b)
Where e = thickness of wall in mm.
b = thickness of flange in m.
Weight:
The standard weights of pipes shall be as per Table-II to IX of I.S. 1537-
1976. The tolerance on standard weight shall be + 5 percent. The pipes of a heavier
weight than the maximum may be accepted provided they comply in every other respect
with the requirement of I.S. 1537-1976.
Marking:
Each pipe shall have the trade mark of the manufacturer, nominal dia., class of
pipe weight and the last two digits of the year of manufacture suitable marked on it.
Marking may be done on the outside of the socket or towards the ends of the barrels of
pipes.
Materials:
The jointing materials i.e. compressed fibber or rubber sheet and bolts nuts
shall be brought by the contractor at his own cost. The thickness of fibber or rubber
sheet packing shall be between 1-5mm. to 3.00mm. They shall be flexible and capable of
with standing vibration. Rubber packing and bolts and nuts of standard length and
thread suitable for pipe size shall of mild steel, they shall confirm to material
specification for.
Preparation of pipes:
The pipe shall be brushed through to remove any soil deposited or stone
therein. Particularly each end of pipe inside or outside shall be carefully cleaned where
joints is to be done. The pipes shall be of exact length with flanges truly at right angle
to its end plans to avoid cutting.
Laying:
The pipes shall be lowered by means of chain pulley black and tripod stand or
with the help of ropes and suitable size of wooden bullies slowly into the trench. They
shall be brought to the required local by giving packing with wooden sleeper pieces and

38 | P a g e
ultimately with well-consolidated hard murrum if required. The chain pulley black and
tripod stand must be got approved by the engineer in Charge. Under no circumstances,
pipes shall allowed to be thrown into the trenches. Each bolt shall be taken or a little at
a time tacking care to frighten diametrically opposite bolts alternatively. The practice
of fully lightening the bolts, one after anther is highly undesirable. In case of vertical
line, the flanges shall be truly horizontal i.e. vertical line shall be in exact plump. In
horizontal line the flanges shall be truly in vertical line.
Testing:
After each section of pipeline is completed, it shall be tested for water
tightness before being covered in. This can be done by closing each end by means of
valve, blank flange, cap or plug and filling the pipe with water. The contractor shall have
to arrange for water to be filled in a pipeline at his own cost. The pressure shall then be
raised gradually by means of a small hand forced pump till it registers at least the
double the working pressure. The joint shall be absolutely water tight under the test
leakage test. (To be conducted after the satisfactory completion of the pressure test)
at a pressure to be specified by the authority for a duration of two hours. The test
pressure shall be ascertained by means of a reliable gauge. If any leakage or sweeping in
the pipe joints, on surface of pipe itself specials, valve etc. are observed during testing
of section the contractor shall be reapplied until no further leakage, are detected.
COMMON CONDITIONS :

DECLARATION :

The contractor shall made declaration as under :-

“ I have made myself thoroughly conversant conditions as regards the


availabilities or otherwise of all construction materials skilled and unskilled labour on
which. I have quoted my rates for this work. The specifications, drawing and design of
this work have been careful studies and are understood by me before the submission of
this tender.
Before starting the work the site shall be cleared of all shrubs, grass and other
vegetation including large and small bushes, all stamps removal of roots cutting and
disposal of small trees up to 300mm girth etc. (The girth shall be measured at a height
of 1.5 meters above ground level).

The site to be cleared shall consist of the entire area required to be cut down
to accommodate the reservoir.
The bidder shall make themselves familiar with the local rules and regulation
and/ or those governing the land clearance industry special requirements of forest areas
wherever applicable and the work shall be carried out in strict accordance there with.
EXCAVATION :
The side slopes of the cutting shall generally have the following slopes for
stability :
(A) 1:1 slope for excavation in earth, murrum boulders etc.
(B) 0.5:1 slope for excavation in hard murrum and soft rock.
(C) 0.25:1 slope for excavation in hard rock. If however, the strata met with
can sustain safely steeper slopes then those mentioned above, such steeper slopes may
be permitted with the prior written permission of the Engineer in charge of the work
Dewatering or pumping :

39 | P a g e
If pumping or draining of water is required to be done at any time during
excavation. The bidder shall arrange for such draining by excavating channels, pumping
or otherwise and shall maintain such arrangements to the satisfaction of the dewatering
pumps shall be conveyed. The discharge of the dewatering pumps shall be conveyed
either to drains and shall not be allowed to be spread in the vicinity of work site. All
cost for such arrangements including pumping shall be borne by the bidder and no extra
payment shall be admissible for such operation.

Shoring :
Open cuttings shall be suitable shored sheeted and braced. If required by the
Engineer or by site conditions or to meet local laws for protecting life property of the
work. Adequate shoring and strutting shall be provided by the bidder at their own cost,
wrapped or deformed timber shall not be used. The shoring shall project at least 150mm
above ground level and shall extend to a suitable depth below the bottom. Wherever
necessary the planks or struts shall be driven by compressed air pile drivers. The planks
shall be fixed close enough to avoid any running in of sand or earth through the joints.
The shoring materials shall not be of sizes less than those specified below
unless steel sheet piling is used or unless approved by the Engineer in writing.
(A) Planks 5 cm thick
(B) Walling pieces 10 cm × 20 cm
(C) Struts 15 cm × 20 cm
For walling pieces round timber shall not be allowed. In a vertical plane, there
shall be at least three struts or more as directed by the Engineer. They shall rest on
walling pieces. The spacing of the struts shall be as per the requirements. At the bottom
extra struts shall have to be provided if ordered by the Engineer.

The excavated material shall be transported by the contractors and stacked


and / or spreaded at suitable places within the lead of 500m as directed by the
Engineer. The stacks shall be made outside the area of excavation and shall not
endanger the work in any way and shall avoid the obstruction to footpaths, road,
driveways, hydrants access, the properties and work sites. Gutter shall be kept clear,
Natural water coarse shall not be obstructed. Separate stacks shall be formed for
(a)rubble considered suitable for masonry work or road work (b)rubble of inferior
quality and boulders (c)soft rock, earth murrum (d)rock spoils up to 150mm size.

Coarse aggregate depending upon their sizes. The fine aggregates are those
which pass through I.S. sieve No. 480 and the coarse aggregates are those which are
retained on I.S Sieve No. 480.
The aggregate both fine and coarse shall be hard strong durable clean free
from veins and adherent coatings. The use of flaky and elongated pieces of aggregates
shall be prohibited.
The aggregates shall not contain deleterious materials such as iron pyrite, coal,
alkali, soft fragments sea shells organic impurities etc. in such quantity as to affect the
strength or durability of concrete or the reinforcement embedded in such reinforced
concrete.
The maximum quantities of deleterious materials that may be permitted shall
confirm to the following limits by weight.
Deleterious Fine Aggregates Coarse Aggregate(%)
Substances. (%) by weight
40 | P a g e
By weight (Max).
(Max)
(1) (2) (3) (4) (5)
(1) Coal and lignite 1.00 1.00 1.00 1.00
(2) Clay lumps. 1.00 1.00 1.00 1.00
(3) Soft fragments - 3.00 -
(4) Material passing 3.00 3.00 3.00 3.00
through 75 micron sieve
(5) Shale 1.00 - - -
The total of various deleterious materials occurring in any sample, in no case
exceed 5%.
Sampling and testing of aggregates shall be carried out in accordance with the
requirement of the appropriate section of I.S. 2386. (Methods of test for aggregate
for concrete) The tenderers shall satisfy the Engineer that the aggregate to be
supplied shall not give rise to an alkali reaction with the cement.

If the aggregate supplied is unclean it shall be washed. It is not properly


graded, it shall be various sizes proportioned to get the required grading. Storing of
aggregates on dusty, muddy, and grassy spots shall be avoided. They shall be stored on
the works in such manner as to prevent intrusion of foreign matter, and shall be
protected from exposure to dust. They shall be placed in stock piles in individual units of
suitable sizes and in suitable layers to prevent aggregation. They shall not be allowed to
run down slopes.
(1) Sand or fine aggregates :
The sand shall be taken from a source approved by the Engineer. The sand or
fine aggregate shall confirm to the latest I.S. No. 388-1970. “Coarse and fine aggregate
form natural sources for concrete”. If the Engineer considers it necessary it shall be
washed and/or screened before use at the expenses of the contractors. The sand shall
have a fineness modulus of not less than 2.5 and not more than 3.00 and the grading
shall conform as far as possible to the following analysis
I.S Sieve No. Percent Natural Passing crushed
Sand or crushed stone
Gravel
4.75mm 95-100 90-100
2.36mm 70-95 60-90
1.18mm 45-85 40-80
600micron 25-60 20-50
300micron 5-30 5-30
250micron 0-10 0-15
The specific gravity of sand shall not be less than 2.6. In no case shall fine
aggregate be accepted containing more than 2% by dry weight not more than 3.5% by
dry volume, not more than 5% by wet volume of clay, loam or silt. If any samples of fine
aggregate shows, more than 5% of clay, loam silt in one hour’s settlement after shaking
in an excess of water the material represented by the sample shall be rejected.
The following two fields tests are recommended for ascertaining the
percentage of clay lumps and impervious organic material, and the contractors shall
carry out the same, of the Engineer deems fit.

41 | P a g e
(1) Test for determining silt in sand :
Fill a calibrated tumbler with sand to be tested to half its volume and added
water there to until the tumbler is three quarter full. Shake up the mixture vigorously
and allow it to settle for about an hour. The volume of silt visible on top of the sand shall
be measured. If the volume of the silt standing over the sand exceeds 5% of total
volume of sand the sand shall be rejected.
(2) Calorimetric test for organic impurities :
The sample of sand shall be mixed with equal volume of 3% solution (about
30gms in a liter of water) of caustic soda sodium hydroxide taken in a plain glass and the
mixture shall be allowed to stand for 24 hours.
The liquid standing above the sand shall not be darker than light shade (Pale
yellow) color is marked yellow or brown the test would indicate presence of organic
material in excessive amount.
In case suitable sand is not available in adequate quantities with in a reasonable
and economical limit the contractors may be allowed to use of crushed or pulverized
stone or gravel either alone or mixed with natural sand in parts. The stone or gravel
shall be clean sharp and free from dust etc. and shall confirm to the latest I.S. 383.
The percentage of crushed stone to be mixed with sand shall be such as to obtain the
fineness modulus of the blended sand within the limit specified above, and / or as
approved by the Engineer after laboratory tests.
(ii) Coarse Aggregates :
All coarse aggregates used in concrete works shall consist of crushed rock,
gravel or other approved inert material. Broken or crushed rock from sound blue basalt
or black trap free from zeolite or other common impurities shall be used in the concrete
as coarse aggregate. The particles of aggregates shall be clean, hard, tough, and durable
free from deleterious substances and shall not contain soft, flat or elongated pieces.
The coarse aggregate shall have specific gravity not less than 2.6 and the water
absorption measured after being immersed for 24 hours in water shall not be more than
5% by weight. The maximum of deleterious materials in the coarse aggregate shall not
exceed 5% by weight in the aggregate when tested in conformity with I.S. No.383. 1970.
coarse fine aggregate from natural sources for concrete.
The nominal size of the coarse aggregate for reinforced concrete work shall be
20mm. Larger coarse aggregate up to 40mm. size may be used if approved by the
Engineer in plain concrete work. The maximum size of coarse aggregate shall be as large
as possible within the limits specified but in no case shall be greater than one quarter of
the minimum thickness of the member, provided that the concrete can be placed in the
form work without difficulty so as to surround all reinforcement thoroughly and to fill
the corners of the form work. The minimum size of coarse aggregate shall be as
mentioned (90%-95% maximum) on I.S. Sieve No. 480.
The aggregate shall be screened and, if necessary blended to give the required
grading when testing in the laboratory at contractors cost by means of standard mesh
Sieves, the grading shall fall with in the following limits.
Sieve Size Percentage Retained by wt.
Plain C.C R.C.C.
40mm ------ ------
25mm 10 to 15 ------
20mm 35 to 40 5 to 10
42 | P a g e
10mm 75 to 80 100 to 80
4.75mm 90 to 100 100 to 95
The percentage given above are only for guidance and the Engineer reserves the
right to modify the same to any other lower or higher value if considered necessary by
him, in consonance with the requirements of the work.
In the event of undesirable segregation occurring in coarse aggregates in two
or more suitable fractions as directed by the Engineer, who shall set up such as to give a
dense water-tight concrete of specified proportion and strength and required
consistency.
The Engineer shall have the right and authority to carry out routine control
tests and analysis of the broken rock at any stage of the work processing and / or
concreting operations and the contractors shall give all necessary facilities in respect of
such testing. The sampling and testing shall be carried out as per standard I.S practices
at the entire cost of the contractor.
Water
The water used for the preparation of concrete, for washing sand etc. and for
curing shall be clean and free from objectionable quantities of silt, organic material,
acid, alkali, salts oil and other deleterious impurities and it shall be obtained from the
sources approved by the Engineer. Potable water shall be generally be acceptable. The
quantity of water to be added for making concrete shall be properly measured and
controlled. Suitable water cement ratio for the different mixes and uses shall be
determined in consultation with Engineer and shall generally not be exceeding 0.5 the
exact value being fixed after taking account all relevant factors such as strength
required, weather condition, water absorbed by material, workability and slump required
consistent with the work requirements, methods of compacting etc. 0.5% of the tender
cost will be charged for supplying water to use in construction shall be charged and also
Rupees 5 per 1000 liters will be charged for the water to be used for testing of water
retaining structures.
Cement Concrete (Plain or reinforce ) (ordinary) :
All cement concrete whether used in R.C.C work or plain concrete work shall be
designated in grades (by the strength it acquires at the age of 28 days M. 100M – 150,M
– 200 and M-250 where refers to the mix and the number 100, 150, 200 and 250
represent the specified 28 days workable compressive strength of the mix under
reference, expressed in Kg./Sq. cm. The cement concrete to be used in the construction
of works covered under this specification can be broadly classified as
(i) ordinary concrete and (ii) controlled concrete.
The concrete to be used in the structural work of the reservoir or any part of
water retaining structures viz. the roof slab, side walls and divide wall, columns, column
footings and the top layer of the reservoir floor and partition walls in each
compartment, control room substation shall be controlled concrete while that used in
the structural work of appurtenant structures, viz. the stair cases outside the
reservoir, etc. mass concrete working anchor blocks, thrust blocks, concrete to be used
in the leveling courses or foundation concrete etc. shall be ordinary concrete. All cement
concrete to be used in the work shall confirm to be used in the leveling courses or
foundations concrete etc. shall be ordinary concrete. All cement concrete to be used in
the work shall confirm to the requirements of I.S. 456-1978 code of practice for plain
and reinforced concrete, Cement concrete used in any water retaining structure shall in
43 | P a g e
addition to I.S 456 – confirm to I.S. 3370 – code of practice for concrete structures
for storage of liquids.

(Part I & II (1963)


(Part III & IV (1967)
Though the use of controlled concrete is specified for the construction of the
reservoir proper control room and substation it may be extended to other parts of the
work covered by this contract if so directed by the Engineer.
In the concrete used in water retaining structure, the minimum quantity of
cement used be 330 / Kg./M³ of the concrete produced.
(i) Ordinary cement concrete :
Ordinary cement concrete is that cement concrete which is not required to be
designed by preliminary test and is produced by mixing the various ingredients of
concrete designated below shall generally consist of quantities as given in the table
below per bag of cement.

Table 1 : Concrete mix proportions for ordinary concrete


Grade of Total quantity of dry aggregate Quantity of water/ Concrete (fine and
coarse) by volume per 50Kg. 50Kg. of
cement. cement.
(Max. in liters) (Max. in liters)
M. 100 300 34
M. 150 220 32
M. 200 160 30
M. 250 100 27
The proportion of fine aggregate to coarse aggregate for the various mixers
listed above shall generally be 1:2 by volume but variation from 1:1.5 to 1:3 depending
upon the grading of the aggregates may be permitted by the Engineer, the total quantity
of fine and coarse aggregates, however shall not in any case exceed the quantity in the
above table 1. For the purpose of this tender the ordinary concrete specified by
strengths as m100, m150, m200, shall be considered to be equivalent to nominal mixes
specified as 1:3:6, 1:2:4 and 1:1.5:3 respectively, and any mention to these mixes under
one system of nomenclature the strength requirements for 28 days and 7 days test
under both the system of nomenclature shall be in conformity with those in table(2) &
(3) given here in after. The cement concrete shall be tested for compressive strength
at the age of 28 days on 15 cm. cubes in accordance with the latest I.S. 516 – 1959.
Methods of test for strength of concrete and the strengths developed for all
types of concrete shall not be less than those given in table – 2.
Table 2 : Strength requirement of concrete :
Grade of concrete Minimum compressive strength of
15cm. cubes at 28 days, in 1 gs/cm.
Preliminary test : works test
M 100 135 100
M 150 200 150

44 | P a g e
M 200 260 200
M 250 320 250
For quick results, the contractors shall carry out compression tests on
representative 15cm. cubes cast in accordance with relevant I.S. at 7 days in addition to
the normal 28 days compressive strength. The 7 days strength of the various concrete
mixes shall not be less than the values given in the Table No.3 below.
However the 28 days compressive strength along shall be the criterion for
acceptance or rejection of the concrete, unless the Engineer is satisfied of the relation
between the 7 days compressive strength and the 28days compressive strength,
established by carrying out a number of tests in which case he may relax the test
frequency of 28 days compressive strength specified here in after.
Table 3 : Optional works test requirements of concrete:
Grade of concrete Minimum compressive strength of
15cm. cubes at 7 days, in kgs/cm².
M 100 70
M 150 100
M 200 135
M 250 170
All test strength specified above are exclusively for 15cm. size cubes & they
shall be adequately modified to suit the requirement of 15cm. dia. and 30cm. long
cylinder, the strength values obtained should be multiplied by 1.25 to obtain the
equivalent cube strength.
Controlled concrete :
Controlled concrete when used in plain and reinforced concrete structure shall
be in grades M100, M150, M200, M250, M300 and M400. In controlled concrete the
determination of the proportions of cement, aggregate and water to attain the required
strength shall be made with the preliminary test by designing the concrete mix.
The concrete mix shall be designed to have an average strength corresponding
to the values specified for preliminary tests in Table – 4. The proportions chosen should
be such that the concrete is of adequate workability for the conditions prevailing on the
work in question, and can be properly compacted with the means available.
The maximum total quantity of aggregate by weight per 50kg of cement shall
not exceed 450kg except where otherwise specifically permitted by the Engineer.
Except where it can be shown to the satisfaction of the Engineer that supply
of properly graded aggregate of uniform quality can be maintained over the period of
work, the grading of aggregate in different sizes and blending them in the right
proportions when required, the different sizes being stocked in separate stock piles.
The material should be stock piled for several hours preferably a day before use. The
material should of coarse and fine aggregate should be checked as frequently as
possible, the frequency for a given job of being determined by the Engineer, to ensure
that the suppliers are maintaining the grading uniform with that of the samples used in
the preliminary tests.
In proportioning concrete, the quantity of both cement and aggregate should
be determined by weights. Where the weight of cement is determined by accepting the
maker’s weight per bag, reasonable number of bags should be weighted separately to
check the net weight where the cement is weighed on the site and not in the bags it

45 | P a g e
should be weighed separately from the aggregate. Water should be either measured by
volume in calibrated tanks or weighed. All measuring equipment should be maintained in a
clean serviceable condition, and their accuracy periodically checked.
It is most important to maintain the water cement ratio constant at its
correct value, to this end determination of moisture contents in both fine and coarse
aggregates should be made as frequently as possible the frequency for a given job being
determined by the Engineer according to weather conditions. The amount of the added
water should be adjusted to compensate for any observed variation in the aggregate,
IS:2386 – (Part.III) 1963 Methods of tests for aggregates for concrete Part – III
specific gravity, density voids, absorption and bulking may be referred to. To allow for
the variation in weight of aggregate due to variation in moisture content, suitable
adjustment in the weight of aggregate should also be made.
No substitution in materials used on the work or alternations in the
established proportions, except as permitted in the above paragraph, shall be made
without additional tests to show that the quality and strength of concrete are
satisfactory.
Workability of the concrete should be checked at frequent intervals. The
slump test, or where facilities exist, the compacting factor test in accordance with
I.S. : 1199 –1959 Method of sampling and analysis of concrete may be adopted for this
purpose.
A competent person should be employed whose first duty will be to supervise
all stages in the preparation and placing of the concrete. All works test specimens should
be made and site test carried out under his direct supervision in order to get a
relatively quicker idea of the quality of concrete or compressive strength test at 7 days
may be carried out in addition to 28 days compressive strength test. In all cases the 28
days compressive strength specified in table –4 should alone be the criterion for the
acceptance or rejection of the concrete. If however, from tests carried in a particular
job over a reasonably long period it has been established to the satisfaction of the
Engineer that a suitable ratio between 28 days compressive strength and compressive
strength at 7 days may be accepted, the Engineer may suitably relax the frequency of
28 days compressive strength test specified in table – 8, provided the expected
strength values at the specified early age are consistently met. For this purpose the
value given in table – 5 may taken for general guidance in the case of concrete made of
ordinary cement. For detailed specification regarding preliminary and work test relevant
paragraphs are reproduced from I.S :1199 – 1959. Method of test for strength of
concrete and I.S. 516 – 1959 Methods as sampling and analysis of concrete as given
below.
Table – 4 :Strength requirements of concrete :
(All values in kg./cm2)
Grade of Compressive strength of 15 cm cubes at 28 days
concrete After mixing in accordance with
I.S. : 516 – 1959
Preliminary Test Works test
Min. Min.
M 100 135 100
M 150 200 150
M 200 260 200
46 | P a g e
M 250 320 250
M 300 380 300
M 350 440 350
M 400 500 400
Note :
(A) Preliminary test :
A test conducted in a laboratory on the trial mix concrete produced in the
laboratory with the object of :
(1) Designing a concrete mix before the actual concreting operation start.
(2) Determining the adjustment required in the design mix when there is a change
in the materials used during the execution of work or
(3) Verifying the strength of concrete mix.
(B) Work Test :
A test conducted either in the field or in a laboratory on the specimens made
on the works out of the concrete being used on the works.

Note :
Size of cubes :
In the works test with the approval of the Engineer 10cm cubes may be used in
place of 15cm cubes provided the maximum nominal size of aggregate does not exceed
20mm. Even the use of 15cm cubes should normally be restricted to concrete having a
maximum nominal size of aggregate not exceeding 40mm. where concrete with aggregate
larger than 40mm is required to be tested, the size of cubes should be specified by the
Engineer keeping in view that generally the length of side of the cubes should be about
four times the maximum nominal size of aggregate in the concrete constituting the cube
specimen.
Strength in relation to size of the cubes :
where 10cm cubes are used the values obtained from tests on 10cm cube shall
be reduced to the extent established by comparative preliminary tests, with 10 & 15 cm
cubes in the absence of such comparative tests by 10% of the value determined from
the test, in order to give the equivalent strength for 15 cm cubes where cubes larger
than 15 cm are adopted, generally no modification is necessary unless otherwise
specified by the Engineer.
Note 3 :Cylinder Strength
Comparative strength tests may, with the approval of the Engineer be
conducted on 15cm diameter and 30cm high cylinders in accordance with I.S 516-1959
instead on cubes. Where cylinder strength modified according to the formula.
Minimum cylinder compressive strength required = 0.8 compressive strength
specified for 15 cm cubes.
The central Road Research Institute, New Delhi has carried tests with a view
to establishing a relation between water – cement ratio and the compressive strength of
concrete using ordinary Portland cements manufactured in the country in accordance
with I.S.:269-1976 ordinary and low heat Portland cement.
As a result of these, it has been considered advisable to give graphs showing
the relationships between the compressive strength of the concrete mixes with
47 | P a g e
different water cement ratios and the seven days compressive strength of cement
tested in accordance with I.S.:269 – 1976. The Road Research Institute graphs (design
curves) may be referred. As they would be of some assistance in obtaining the water-
cement ratio for trial mixes of concrete.
Table–5 optional works test requirements of concrete : (All values in kg/cm²)
(All test conducted in accordance with I.S. 516-1959)
Grade of Compressive Module of rupture by beams test Min. at
Concrete strength on 72 + 2 Hr. At 7 days.
15 cm cubes
Min at 7 days
(1) (2) (3) (4)
M 100 70 12 17
M 150 100 15 21
M 200 135 17 24
M 250 170 19 27
M 300 200 21 30
M 350 235 23 32
M 400 270 25 34
Note : Notes 2 & 3 under Table – 4 are also applicable to Table 5
Table 6 Concrete Mix proportions:
Grade of Total quantity of dry aggregates Proportion of fine Quality of
concrete by volumes per 50kg. of cement aggregate to coarse water per
to be taken as the sum of the aggregates 50kg of
individual volumes of fine and cement
coarse aggregates Max.
Max.
Liters Liters
M 100 300 Generally 1:2 for fine 34
M 150 220 aggregate to coarse 32
M 200 160 aggregate by volume 30
M 250 100 but subjected to a 27

upper limit or 1:1:5 and


a lower limit of 1:3
Note :
1. The proportion of the aggregates should be adjusted from upper limit to lower
limit progressively as the grading of fine aggregate becomes larger. Example: for an
average grading of fine aggregate (that is, zone II of I.S : 383-1963) the
proportion shall be 1:1:5, 1:2 & 1:3 for maximum size of aggregate 10mm and 40mm
respectively.
2. it may be noted for general guidance that m 100 and m 250 of ordinary concrete
correspond approximately to 1:3:6, 1:2:4, 1:1:5:3 and 1:1:2 nominal mixes of ordinary
concrete currently used in the country.
Table 7. Surface water carried by average aggregate
AGGREGATE APPROXIMATE QUANTITY OF SURFACE WATER
Very wet sand 120
Moderately wet sand 80
Moist sand 40
48 | P a g e
*Moist gravel or crushed rock 20 & 40
*coarse aggregate, less the water it will carry
Control and testing of concrete
The work of controlled concrete shall be carried out under the strict supervision
of the Engineer the contractors shall employ qualified competent persons for executing
this work following tests shall be carried out at site whenever required by the engineer
in accordance with I.S : 516-1956.

Methods of test for strength of concrete (latest)


(1) preliminary tests – 7 days and 28 days compressive strength test
(2) works test - 7 days and 28 days compressive strength test
(3) consistency test –
(4) moisture contents in aggregates
(5) unit weight of concrete
(6) Procedure and Guidance for testing for concrete
Preliminary Test :
Preliminary test cubes or cylinders for controlled concrete shall be made in the
laboratory prior to the commencement of the work in the manner and at frequencies laid
down in the latest I.S.:456 – 1978 Code of practice for plain and reinforced concrete.
The testing shall be carried out at the GERI laboratory at Baroda or at any other
approved laboratory at contractor’s cost.
Work Test :
During concreting operations, samples of concrete as placed in the work shall be
taken every day and a set of 6 cubes or cylinders their compressive strength. The
consistency (slump) test shall also be made and the slump recorded.
All concrete cubes or cylinders shall be tested for compressive strengths as
specified in I.S 456 and 516 at the field testing laboratory of at any approved material
testing laboratory. The above specifications cover concrete mixes of grades m100 and
above ordinarily it is not necessary to test the compressive strengths of mix grade
m100 as it is generally used for nonstructural purposes. However where this mix (M 100)
is used extensively on works (i.e. more than 75 m³ in one work) it shall be tested in the
same manner as other grades of concrete used for structural purpose. The minimum
strengths of various grades of concrete both at the age of 7 days and 28 days are given
in table 2 & 3.
In the case of concrete of mix m 150 and above the Engineer may not insist on
the testing of concrete if the quantity of concrete, if the quantity of concrete to be
paid on any particularly day is less than 10cm, if however the quantity exceeds 10cm.
test specimens must be taken and sent to the field testing laboratory or at any
approved laboratory for testing.
6 specimens are made for every sample and three of them tested for 7 days
strengths as mentioned earlier the 28 days strengths of concrete shall along form the
criterion for acceptance or rejection of the concrete.
With this point in view the concrete samples shall be tested both for 7 days
strength as well as 28 days strength at the start of the work and continued till the
Engineer is satisfied that a proper relation between the 7 days compressive and the 28
days compressive strength is established in which case be may decide to relax the
frequency if testing the concrete cubes for the 28 days compressive strength.

49 | P a g e
If the average strength of specimen tested at the age of 7 days 28 days is
not less than the strength specified in table 2 & 3, then the test shall be considered
that only out of 3 consecutive tests may give value less than specified strength but not
less than 90% of the specified strength.
If the tests are unsatisfactory, the contractors shall take immediate steps and
carry out remedial measures as may be directed by the Engineer in their own modules.
The contractors shall pay usual testing fees carried out in the approved laboratory.
These fees may vary from should arrange to bring their own moulds for taking samples.
Consistency and slump test :
The workability of concrete shall be checked at frequent intervals. The slump
test shall be carried out in accordance with the standard method given under. I.S.
specification mentioned above. The slump shall be as less as practicable consistent with
the efficient working and compacting of concrete. The slump shall not exceed 64mm but
the Engineer may, under exceptional conditions, permit greater slump up to a limit of
150mm. The standard consistency test shall be applied at least once in a day while the
concreting is in progress.
Moisture contents in the Aggregates :
The moisture contents in the aggregates shall be determined in the field in
accordance with the latest I.S. No. 2386 – 1963 (Part-3). In methods of tests for
aggregates for concrete. Method of test for aggregates for concrete.

Unit weight of concrete


It shall be determined by placing representative samples of concrete in a unit
measure capacity and vibrating it externally by small vibrator or hand compacting to
represent actual placing condition. The top of the concrete shall then be made truly
flush with the top of the mould and the weight of concrete per cum determined after
curing and drying. The weight of dry concrete shall not be less than 2.4 tones per cum. A
complete record regarding various tests carried out at site and in the laboratory shall
be kept by the Engineer. The contractors shall provide at their own cost all facilities for
labour, material, transport etc. required for the proper execution of the above tests.
Any concrete which does not comply with the above requirements shall be liable
for rejection by the Engineer.
Procedure and guidance for testing of concrete.
Making and curing compression test specimens in the laboratory. The procedure
for making and curing compression test specimens of concrete in the laboratory where
accurate control of the quantities of materials and test conditions are possible and
where the maximum nominal size of aggregate does not exceed 38mm. The method is
especially applicable to the making of preliminary compression test to ascertain the
suitability of the available materials or to determine suitable mix proportions.
Sampling of materials :
Representative samples of the materials of concrete for use in the particular
concrete construction work shall be made of a small portion taken from each of a
number of bags on the site. Test samples of aggregate shall be taken from larger lots of
quartering.
Preparation of materials. :
All materials shall be thoroughly mixed dry either by hand or in a suitable mixer
in such a manner as to ensure the greatest possible blending and uniformity in the
50 | P a g e
material. Care being taken to avoid the intrusion of foreign matter. The cement shall
then be stored in dry place, preferably in air tight metal containers, samples of
aggregates for each batch of concrete shall be of the desired grading and shall be in an
air dried condition. In general, the aggregate shall be separated in to fine & coarse
fractions and recombined for each concrete batch in such a manner as to produce the
desired grading. I.S. sieve 48 shall be normally used for separating the fine and coarse
fractions, but where special grading is being investigated both fine and coarse fractions
shall be further separated in to different sizes.
Proportioning :
The proportions of the materials, including water in concrete mixes used for
determining the suitability of the materials available, shall be similar in all respects to
those to be employed in the work, where the proportions of the ingredients of the
concrete as used on the site are to be specified by volume, they shall be calculated from
the proportion by weight used in the test cubes and the weights of the materials.
Weighting :
The quantities of cement, each size of aggregate and water for each batch shall
be determined by weight , to an accuracy of 0.1 percent of the total weight of batch.
Mixing concrete:
The concrete shall be mixed by hand, or preferably, in a laboratory batch
mixer, in such a manner as to avoid loss of water or either materials, each batch of
concrete shall be such a size as to leave about 10 percent excess after modeling the
desired number of test specimens. The specifications and mechanism used specified in
sub Estimate No. 1’s item No. 2.
Workability :
Each batch of concrete shall be tested for consistency immediately after
mixing, by one of methods described in I.S : 1199 – 1956. method of sampling add
analysis of concrete. Provided that care is taken to ensure that no water or other
material is lost, the concrete used for the consistency test may be mixed with the
remainder of batch before making the test specimens. The period of re-mixing shall be
as short as possible yet sufficient to produce a homogenous mass.
Size of test specimens :
Test specimens cubical in shape shall be 15 * 15 cm. If the largest nominal size
of the aggregate does not exceed 2cm. 10cm. cubes may be used as an alternative
cylindrical test specimens shall have a length equal to twist the diameter. They shall be
15cm in diameter and 30cm. long smaller test specimens shall have a ratio of diameter of
specimen to maximum size of aggregate of not less than 3 to 1. except that the
diameter of the specimen shall be not less than 7.5cm for mixtures containing aggregate
more than 5 percent of which is retained on IS sieve 480.
Molds :
Cube molds :
The molds : shall be metal, preferably steel or cast iron, and stout enough to prevent
distortion. It shall be constructed in such a manner as to facilitate the removal of the
molded specimen without damage & shall be so machined that when it is assembled ready
for use the dimensions and internal faces shall be accurate within the following limits ;
the height of the mould and the distance between opposite faces shall be specified size
+0.2mm. The angle between adjacent internal faces and between internal faces and top
and bottom planes of the mould shall be 90+0.5. The interior faces of the mould shall be
51 | P a g e
plane surface with a permissible variation 0.03mm each mould shall be specified size +
0.2 mm. The angle between adjacent internal faces and between internal faces and top
and bottom planes of the mould shall be 90+0.5. The interior faces of the mould shall be
plane surfaces with a permissible variation of 0.03mm each mould shall be provided with
a metal base plate having a plane surface. The base planate shall be of such dimensions
as to support the mould during the filing without leakage and it shall be preferably
attached to the mould by springs of screws.
The parts of the mould when assembled shall be positively and rigidly held
together, and suitable methods of ensuring this both during the filling and on
subsequent handling of the filled mould shall be provided in assembling the mould for use
the joints between the section of moulds shall be thinly coated with mould oil shall be
applied between the contact surfaces of the bottom of the mould and the base plate in
order to ensure that no water escapes during the filling. The interior surfaces of the
assembled mould shall be thinly coated with oil to prevent adhesion the concrete the
contractor shall have at least 6 cube moulds at time site to enable test cubes to be
taken at any time. The cube moulds shall be of standard make by reputed manufactures
(like Lawrence & mayo etc.)
Tampering bar:
The tamping bar shall be steel bar 16mm in diameter 0.6m long and bullet
pointed at the lower end.
Compacting:-
The test specimens shall be made as soon as practicable after mixing, and in
such a way as to produce full compaction of the concrete with neither segregation nor
excessive laitance. The concrete shall be filled in to the mould in layers approx. 5 cm
deep. In placing each scoop full of concrete, the scoop shall be moved around the top
edge of the mould as the concert within the mould. Each layer shall be compacted either
by hand or by vibration as described below
After the top layer has been compacted, the surface of the concrete shall be
finished level with the top of the mould using a trowel and covered with a glass or metal
plate to prevent evaporation.
(I) When compacting by hand, the standard tamping bar shall be used and the
storks of the bar shall be distributed in a uniform manner over the cross section of the
mould. The number of the strokes per layer required to produce specified conditions will
very according to the type of concrete. For cubical specimens in no case shall concrete
be subjected to less than 35 strokes per layer for 15cm cubes or 25 strokes per layer
for 10cm cubes. For cylindrical specimens the no. of strokes shall penetrate in to the
under laying and the bottom layer shall be robbed throughout its depths where voids are
left by the tamping bar. The side of the mould shall be tapped to close the voids.
Compacting by vibration:-
When compacting by vibration each layer shall be vibrated by means of an
electric or pneumatic hammer or vibrator or by means of suitable vibrating table until
the specified condition is attained.
Note :
The mould and quantum of vibration of the laboratory specimen shall be as
nearly the same as those adopted in actual concreting operations.
Capping specimens :

52 | P a g e
The ends of all cylindrical test specimens that are note plane within 0.05mm
shall be capped. Capped surfaces shall not depart from a plane by more than 0.05 and
shall be approx. at right angles to the axis of the specimens. Caps shall be made thin as
practicable and shall not flow or fracture when the specimen is tested. Capping shall be
carried out according to one of the following methods.
(I) Neat cement :
Test cylinders may be capped with a thin layer of stiff, neat Portland cement
paste after the concrete has ceased setting in the moulds, generally for two to four
hours or more after molding. The cap shall be formed by means of glass plate not less
than 6.5mm. in thickness or a machined metal plate not less than 13mm. in thickness and
having a maximum surface dimensions atleast 25mm larger than the diameter of the
mould, it shall be worked on the cement paste until its lower surface rests on the top of
the mould. The cement coping shall be mixed to a stiff paste for about two to four hours
before it is to be used in order to avoid the tendency of the cap to shrink. Adhesion of
late paste to the capping may be avoided by coating the plate with a thin coat oil or
grease.

(II) Sulphur :
Just prior to testing, the cylindrical specimens may be capped with a sulphur
mixture consisting or 1 part sulphur 2 to 3 parts of inert filler, such as fiercely. The
specimens shall be securely held in a special jig so that the caps formed have true plane
surfaces. Care shall be taken to ensure that the sulphur compound is not over heated as
it will not then develop the required compressive strength. Sulphur caps shall be allowed
to harden for atleast 2 hours before applying the load.
(III)Hard Plaster :
Just prior to testing, specimens may be capped with hard plaster having a
compressive strength of atleast 420 kg/sq. cm. in one hour. Such plasters are generally
available as proprietary material. The cap shall be formed by means of a glass plate not
less than 13mm. in thickness, having a minimum surface dimensions at least 25mm. larger
than the diameter of the mould. The glass plate shall be lightly coated with oil to avoid
sticking.
Note:
Ordinary plaster will not serve the purpose of the capping materials due to its
low compressive strength.
(IV) As soon as possible after the concrete is mixed, a mortar shall be gauged using a
cement similar to that used in the concrete and sand which passes IS Sieve 30 but is
retained on IS Sieve 15. The mortar shall have a water cement ratio not higher than
that of the concrete of which the specimen is made, and shall be of stiff consistencies.
If an excessively wet mix of concrete is being tested, any free water which has
collected on the surface of the specimen shall be removed with a sponge, blotting paper
or other suitable absorbent material before the cap is formed. The mortar shall then be
applied firmly and compacted with a towed to a slightly convex surface above the edges
of the mould, after which the capping plate shall be pressed sown on the cap with a
rotary motion until it makes complete contact with the rim of the mould. The plate shall
be left in position until the specimen is removed from the mould.
(V) Curing :
53 | P a g e
(a) The test specimens shall be stored in a place free from vibration, in moist air at
a temperature of 27 +- 20 C for 24 hours +- ½ from the time of addition of water to the
dry ingredients. After this period, the specimens shall be marked and removed from the
mould and, unless required for test within 24 hours, immediately submerged in clean,
fresh water or saturated lime solution in which the specimens are submerged shall be
renewed every day and shall be maintained at a temperature of 27oC +/- 20oC. The
specimens shall not be allowed to become dry at any time until they have been tested.
(b)Making and curing compression test specimen in the field.
The procedure for making and curing compression test specimens of concrete
sample during the progress of construction where the nominal maximum size of the
aggregate does not exceed 38mm. Size of test specimen, apparatus to be used and
procedure to prepare specimens shall be the same as specified earlier.
Apparatus :
Testing Machine :
The testing machine may be any reliable type of sufficient capacity for the
tests and cable of applying the load at the rate specified in 5.5. The permissible error
shall be not greater than +2 percent of the maximum load. The testing machine shall be
equipped with two steel bearing plates (preferably the one that normally will bear on the
upper surface of the specimen) shall be fitted with a ball seating in the form of portion
of a sphere, the center of which coincides with the central points of the face of the
plate. The other compression plate shall be plain rigid bearing block.
The bearing faces of both plates shall be atleast as large as and preferably
larger than the nominal size of the specimen to which the load is applied. The bearing
surface of the plates, when new, shall not depart from a plane by more than 0.01m at any
point, and they shall be maintained with a permissible variation limit of 0.02mm. The
movable portion of the spherically seated compression plate shall be held on the
spherical seat, but the design shall be such that the bearing face can be rotated freely
and tilted through shall angles in any direction.
AGE TEST :
Tests shall be made at recognized ages of the test specimens, the most usual
being 7 and 28 days. Ages of 13 weeks and one year are recommended if tests at
greater ages are required. Where necessary to obtain the early strengths, tests may be
made at the ages 24 hours +/- ½ hour and 72 hours +/- 2 hours. The ages shall be
calculated from the time of addition of water to the dry ingredients.
Number of specimens :
At least three specimens preferably from different batches shall be made for
testing at each selected age.
Note :
When a full investigation is being carried out it is advisable for three separate
batches to be made for given variable. An equal number of specimens for each variable
should be made.
Procedure :
Specimens stored in water shall be tested immediately on removal from the
water and while they are still in the wet condition. Surface water and grit shall be wiped
off the specimens and projecting fins removed. Specimens when received dry shall be
kept in water for 24 hours before they are taken for testing. The dimensions of the
specimens to the nearest 0.2mm and their weight shall be noted before testing.
54 | P a g e
Placing the specimens in the Testing Machine :
The bearing surface of the testing machine shall be wiped clean and loose sand
or other material removed from the surface of the specimen which are to be in contact
with the load shall be applied to opposite sides of the cubes as cast, that is not to the
top & bottom, the axis of the specimen shall be carefully aligned with the center of
thrust of the spherically seated plate. No packing shall be used between the faces of
the test specimen and steel plate of the testing machine. As the spherically seated
block is brought to bear on the specimen, the load shall be applied without shock and
increased continuously at a rate of approximately 140 kg/sq. cm/min. until the resistance
of the specimen to the increasing load breaks down and no greater load can be sustained.
The maximum load applied to the specimen shall then be recorded and appearance of the
concrete and any unusual features in the type of failure shall be noted.
CALCULATION :
The measured compressive strength of the specimen shall be calculated by
dividing the maximum load to the specimen during the test by the sections (see also
4.5.1 of IS 1199-1959)methods of sampling and analysis of concrete and shall be
expressed to the nearest Kg./sq.cm. Average of three values shall be taken as per the
representative of the batch provided the individual variation is not more than the +/-
15% of the average. A correct factor according to the height / diameter ratio of the
specimen after copping shall be obtained from the curve shown in fig. 1. The product of
this correction factor and the measured compressive strength shall be known as
corrected compressive strength. This being the equivalent cube strength of the
concrete shall be determined by multiplying the corrected strength by 5 / 4 .
Report :
The following information shall be included in the report on each test specimen.
(A) Identification mark
(B) Date of test
(C) Age of specimen
(D) Curing condition, including date of manufacture of specimen in the field.
(E) Weight of specimen
(F) Dimensions of specimen
(G) Cross-sectional area
(H) Maximum load
(I) Compressive strength
(J) Appearance of fractured faces of concrete and type of fracture if these are
unusual.
(K) Sampling of Fresh concrete in the Field.
This method specifies the procedure to be followed in the field for obtaining
representative samples of fresh concrete directly from the mixer or from concrete at
the time and place of deposition.
Sample :
The composite sample shall be truly representative of the batch and shall not
less than 0.02mm in volume. It shall be composed of a mixture of portions taken from
different points in the batch. When continuous mixers used a batch shall be regarded as
the discharge from the mixture during the minute.
Procedure :
From Mixers :
55 | P a g e
At least three approximately equal sample increments totaling (2m shall be
taken from a batch during its discharge and each sample increment shall be collected by
passing a clean and dry receptacle across the stream of concrete. This receptacle shall
be constructed of non absorbent material, preferably of metal and shall be such that
the sample retained is not segregated. A flat surface without retaining sides will not
fulfill this purpose. Where there sample increments are taken they shall be taken at
about the time when one-quarter on half and there quarters of the concrete have been
discharged from the mixer and if marathon three are taken they shall be at
corresponding shorter, but equally spaced, intervals.
From concrete at the Time and place of Deposition :
The sample shall be taken while a batch of concrete is being or immediately
after it has been, discharged on the site. The sample shall be collected from not less
than five well – distributed positions, avoiding the edges of the mass where segregation
may have occurred.
Mixing the composite sample :
The composite sample obtained by either of the methods described above, shall
be mixed on a non-absorbent base either in such a manner as to ensure uniformity. The
sample thus obtained shall be used immediately for the purpose of carrying tests. Care
shall be taken to protect the sample from the weather.
Recording of samples :
The following information regarding the sample shall be recorded
(A) Date and time of sampling
(B) Method of sampling
(C) Mix proportions (Proportion of ingredients including water, admixtures, etc.
(D) Mixtures from which delivered (if more than one issued)
(E) The location of the sampled batch after placing, and
(F) Temperature and weather conditions
Slump Test:
The method of test specified the procedure to be assorted, either in the
laboratory or during the progress of work in the field, for determining, by the slump
test, the consistency, of concrete where the nominal maximum size of the aggregate
does not exceed 38mm.
(A) Mould :
The mould for the test specimen shall be in the form of the frustum of a cone
having the following internal dimensions :
Cm
Bottom diameter 20
Top diameter 10
Height 30
The mould shall be constructed of metal (brass of aluminum shall not be used)
of at least 1.6mm.(or16 BC) thickness and the top and bottom shall be open and at right
angle to the axis of the cone. The mould shall have a smooth internal surface. It shall be
provided with suitable foot pieces and also handles to facilitate lifting it from the
molded concrete tests specimen in vertical direction as required by the test. A mould
provide with a suitable guide attachment may be used.
(B)Temping rod :

56 | P a g e
The tamping rod shall be of steel or other suitable material, 16mm in diameter,
0.6m long and rounded at one end.
Note :
To facilitate the lifting of the mould in a vertical direction. It is recommended
that suitable guide attachment be provided any rivets used in the construction of the
mould shall be countersunk flush on the inside of the cone. Attachments should
preferably be welded to the mould.
Sampling :
If this test is being carried out in the field, the sample of freshly mixed
concrete shall be obtained as described in 3. In the case of concrete containing
aggregate of maximum size more than 38mm. the concrete shall be wet-sieved through
1.5 in screen to exclude aggregate particles bigger than 38mm.
Procedure :
The internal surface of the mould shall be thoroughly cleaned and free from
superfluous moisture and set concrete before commencing the test. The mould shall be
placed as a carefully leveled metal plate, the mould being firmly held in place while it is
being filled.
The mould shall be filled in four layers, each approximately one-quarter of the
height of the height of the mould. Each layer shall be temped with twenty-five strokes
of the rounded end of the tempering rod. The strokes shall be distributed in uniform
manner over the cross-section of the Mould and for the second and subsequent layers
shall penetrate into the underlying layer. The bottom layer shall be temped throughout
its depth. After the top layer has been rodded, the concrete shall be shrunk off level
out between with a trowel or the temping rod, so that the mould is exactly filled. Any
mortar which may be leaked out between the mould and the base plate shall be cleaned
away. The mould shall be removed from the concrete immediately by raising it slowly
And carefully in a vertical direction. This allows the concrete to subside and the
slump shall be measured immediately by determining the difference between the height
of the mould that of the highest point of the specimen being tested. The above
operations shall be carried out at a plate free from vibration or shock and within a
period of two minutes after sampling.
Slump :
The slump measured shall be recorded in terms of millimeters of subsidence of
the specimen during the test. Any slump specimen which collapses or shears off laterally
gives incorrect result and if this occurs the test shall be repeated with another sample.
If in the repeat test also, the specimen should shear, the slump be measured and the
fact that the specimen sheared, shall be recorded.
Note :
Some indication of the cohesiveness and workability of the mix can be obtained,
if after the slump measurement has been completed, the side of the concrete is tapped
gently with the tamping rod, a well proportioned concrete which has an appreciable slump
will gradually slump further but if the mix has been badly proportioned, it is likely to fall
apart.
Gauge Boxes :
Gauge boxes of approved type shall be used for measuring sand and coarse
aggregates in required proportion whenever concrete is allowed to be prepared by
mixing the aggregates on volumetric basis. Such boxes shall be of seasoned timber or
57 | P a g e
steel and shall be of such size as and shape and shall be used in such a manner as to
enable the proportion of the material to be checked readily. The cement used in
concrete however, shall not be used by measuring it in gauge boxes but it shall be
measured by weight whatever may be the type of concrete.

Storage of materials :
Cement, fine and coarse aggregates shall be stored separately at the site of
work in such manner as to prevent any deterioration or contamination or admixture of
foreign materials. Any material which has been damaged or is considered defective by
the Engineer shall not be used on the works and shall be removed immediately from the
site of work.
ITEMWISE SPECIFICATION

DETAILED SPECIFICATION :

Detailed specification given here shall be treated as extension or partial


modifications to the specifications of respective items given in the volume of
specification published by Gujarat Water Supply and Sewerage G. W. S. & S. Board.

C.C.M. 100 BASE CONCRETE FOR LEVELLING COARSE :

For all practical purpose and in absence of proportioning of concrete on base


of preliminarily tests, C.c. 1:3:6 may be provided as a leveling course i.e. one part to
cement three parts of sand and six parts of black trap kapachi. Specification for
various ingredients of concrete such as sand, cement, kapachi, water shall be as these
given in specification for C.Cm.15.

While laying base concrete for leveling course the concrete shall not be
dumped from above but shall be carried out to the bottom and gently placed from a
height not exceeding 1.5 meter. If concrete is transported by chutes, then the same
shall be remixed at bottom of chutes to overcome any segregation that might have
occurred.

C.C. M. 150/ M. 200/ M. 250 :

As far as possible the preparation of various ingredients of concrete shall be


determined on the bases of preliminary tests as per ISS using the actual materials to
be used on site. However in absence of such preliminary tests the volumetric proportion
of 1;2:4 may be adopted i.e. one part to cement, two parts of sand and four parts of
Kapachi, water just sufficient to attain desired workability may be added. However the
aim while proportioning should be to fix the proportion of aggregation and water cement
ratio shall be always sufficiently low enough to get desired strength.

C.C. M 200 & M:250 :

Specification for C.C. M. 200 & M:250 shall be same as those for C.C.M.150
except that grade of concrete to be produce shall be M- 200. If arbitrary volumetric
proportioning is to be followed then the proportion of cement, sand and kapachi shall be
1:1/2:3 respectively. Since M – 200 mix is normally used in water retaining parts of
container where the aim is not to get dense. Strong and watertight concrete, special
care shall be exercised in controlling proportion of aggregate, water cement ratio,
compaction and curing

58 | P a g e
Manufacture and placement of concert
(1) Batching
Whether controlled concrete or ordinary concrete is to be mixed the quantity
of cement shall be determined by weight if the makers weight per bag is to be used the
same shall be certified by weighing separately a reasonable number of bags.
Whenever direct use of bagged cement is allowed, one jute bag of cement shall
be considered to contain 50kg. of net weight of cement. This shall, however be verified
at site by weighting. For which the contractors shall provide an accurate weighing
apparatus on work site.
Having once designed the mix, the Engineer may permit further mixing of the
aggregate to be used done on volumetric basis for a particular batch stock of
aggregates which has been used in the design of the mix.
The water shall be either measured by the volume in calibrated tanks or
weighed, in controlled concrete, the quantity of fine and coarse aggregates shall be
determined by weight. While in ordinary concrete, they may be determined by volume.
For volumetric measurements gauge boxes used for approved type as described earlier
shall be used for measuring the fine and coarse aggregates in required proportion.
(ii) Mixing of concrete :
The concrete shall be mixed in a mechanical and/or weight mixer of adequate
capacity. The ingredients shall be added to each batch of mix by weight, volume or both
as the case may be so as to ensure accurate proportioning, water for each batch of
concrete shall be measured in a standard container so as to ensure the same amount of
water being used each time and shall be added prior to during and following mixer
charging operation. The mixing of each batch shall be done for a period of not less than
two minutes or shall continue until there is a uniform distribution of material, having the
mass uniform in colour and consistency. Every care shall be taken to ensure that there is
no segregation while unloading the mixer.
Mixing shall be done as near the place of placement as possible and adequate
shed shall be constructed over the mixer to protect the discharged concrete from the
effect of direct sun rays small additional amount of water, if necessary, shall be allowed
to be added to the mixer to compensate for any anticipated evaporation losses during
transport. The quantity of water to be added shall be sufficient to allow a workable mix
being made tamped and vibrated into all parts of the mould and between the
reinforcement.
Permission for starting the concrete work :
The contractors shall get the surface whether concrete of rock or form work
etc. previously approved by the Engineer, who shall, then issue the permission for
starting the work. Any concrete work done without such permission shall be cut and
removed at the cost of contractors.
No concreting shall be started unless the surface of the foundation is inspected
and approved by the Engineer as stated above. If concreting is to be done on concrete
shall cleaned with wire brushed and all laitance removed to expose the original surface
of metal and sand particles etc. It shall, then be covered with a 7mm. thick layer of
cement mortar (1:2) before laying fresh concrete.
Transporting and depositing concrete :
Concrete shall be placed within 30 minutes after mixing and shall be
transported from the mixer to its final placement as rapidly as practicable, taking care
59 | P a g e
to see that no segregation of loss of ingredients takes place. In case segregation occurs
the concrete shall be remised. Dropping of concrete from an excessive height or running
or working it along forms will not be permitted. Any concrete which before placement
has begun to set has become stiff shall be rejected.
Concrete shall be properly compacted by use of vibrators or by rotting and
spading as directed by the Engineer. Tamping as above shall be continued until all the
entrained air is removed and the concrete has become compacted and completely fills
the form. The sides of the formwork shall be gently tapped by spades during concreting.
All controlled concrete shall be invariably compacted by mechanical vibrators
irrespective of the positions. It shall be compacted by needle vibrator or screed
vibrator as the case may be and the work of vibrating the concrete by mechanical means
shall be paid for under the relevant item. Compacting by rotting or spading however shall
not be paid for separately and the rates for concrete shall be demeaned to cover the
cost thereof.
Internal type vibrators when used shall be inserted into the uncomplicated
concrete vertically and at regular intervals. Where the uncomplicated concrete is in a
layer above freshly compacted concrete. The vibrator shall be allowed to penetrate
vertically for a few cms. in to the previous layer. In no circumstances shall the
reinforcement or form work nor shall they be withdrawn quickly from the mass of
concrete but shall be drawn back slowly so as to leave no voids. Internal type vibrators
shall not be placed in the concrete in a random or haphazard manner not shall concrete
from one part of the work to another by means of the vibrator. The duration of
vibration shall be limited to that required to produce satisfactory compaction without
causing segregation. Vibration shall on no account be continued after water or excess
grout has appeared on the surface face.
Curing of concrete :
All concrete work shall be protected from direct rays of the sun. The exposed
surface shall be kept wet for a minimum period of 10 days or such longer periods as may
be directed by the Engineer. All concrete laid shall not be distributed and shall be
suitably protected from any injury, until completely set : particular care shall be taken
at all corners and edges of the members. All horizontal concrete surfaces shall be kept
constantly wet pounding or otherwise in the manner approved by the Engineer, till the
time of next pouring regardless of time. Concrete surfaces shall be cured either by
sprinkling or by spraying water or by adopting any other method to keep the areas moist.
Flat or vertical surfaces may be covered with damp gunny bags and watered frequently.
Water used for curing shall be clean and free from any excessive amount of silt, coloring
matter of other impurities which may stain the finished work. In order to ensure
adequate quantities of water for curing, the contractors shall make necessary
arrangements such as providing sufficient lengths of temporary pipelines of suitable
sizes, storage of water in tanks and / or use of blisters at their cost.
Defective concrete :
The defective concrete shall be cut out and the work reconstructed with fresh
concrete of required quality in the presence of the Engineer. The concrete thus cut out
shall not be re-used under any circumstances, should any concrete become permanently
damaged due to cracking or is broken or damaged from whatever cause, or should any
concrete be found defective in quality due to honey – combing or bad workmanship, it

60 | P a g e
shall be removed forthwith and replaced by concrete of required quality at the cost of
the contractors to the satisfaction of the Engineer.
The authority reserves the right to carry out any further test like electronic
ultrasonic tests and such other non-destructive test to verify. The quality of concrete
done by the contractor should it become to notice at that time that some work is
required to be redone, the same shall be attended to by the contractor at his own cost,
irrespective of the fact that the same has been passed and paid for.
FORMWORK :
Formwork fixing and general :
All formwork shall be constructed of timber, sheet metal or other approved
material. For work, Which are of respective nature such as roof slab, column capital,
floors, etc. for reservoir, the formwork shall be fabricated out of steel plates and
structures to obtain uniform finish throughout the work. All formwork shall be firmly
supported, adequately strutted, braced and tied to withstand the placing and vibrating
of concrete and the effect of weather. The tolerance on line and level shall not exceed
3mm.
The Tenderers / contractors shall be responsible for the calculations and
designs for the formwork, and, if required, shall submit them to the Engineer for
approval before any construction. In all case the formwork shall be inspected and
approved by the Engineer before any concreting is started. On formwork to external
faces, which will be permanently exposed, all horizontal and vertical formwork joints
shall be so arranged that joint lines will form a uniform pattern on the face of the
concrete.
Where the tenderers / contractors propose to make up to formwork from
standard sized manufactured formwork panels, the size of such panels, shall be
approved by the Engineer before they are used in the construction of the works. The
finished appearance of the entire elevation of the structure and adjoining shall be
considered when planning the pattern of joint lines caused by formwork and by
construction of horizontal and vertical lines.
Face of formwork in contact with concrete shall be free from adhering foreign
matter, projecting nails and the like, splits or other defects and all formwork shall be
clean and free from standing water, dirt shavings chipping or other foreign matter.
Joints shall be sufficiently watertight to prevent the escape of mortar or the formation
of line or other blemishes on the face of the concrete.
Opening for inspection of the inside of the formwork and for the removal of
water used for washing down shall be provided and so formed as to be easily closed
before placing concrete. Before placing concrete all bolts, pipes or conduits or any other
fixtures which are to be built in shall be fixed in their correct positions, and cores and
other devices for forming holes shall be held fast by fixing to the formwork or
otherwise. Holes shall not be cut in any concrete without the approval or the Engineer.
No ties or bolts or other device shall be built into the concrete for the purpose
of supporting formwork without the prior approval of the engineer. The whole of part of
any such supports shall be capable of removal so that no part remaining embedded in the
concrete shall be nearer than 50mm from the surface in the case of reinforced
concrete & 150mm in case of reinforced concrete. Holes left after removal of such
supports shall be neatly filled with well rammed dry-pack cement sand mortar in
proportion of 1:3 at tenderers / contractors cost.
61 | P a g e
Formwork in contact with the concrete shall be treated with a suitable non-
standing mould oil to prevent adherence of the concrete except where the surface in
subsequently to be rendered. Care shall be taken to prevent the oil from coming in
contact with concrete at construction joints.
Defects in formed surfaces :
Workmanship in formwork and concreting shall be such that concrete shall
normally requires no making good, surfaces, being perfectly compacted and smooth.
If any blemishes are revealed after removal of formwork the Engineer’s
decisions concerning remedial measures shall be obtained immediately.
These measures may include, but shall not be limited to the following fins,
pinhole bubbles; surface discoloration and minor defects may be rubbed down with
sacking immediately after the formwork is removed. Abrupt and gradual irregularities
may be rubbed with carborendum and water after the concrete has been fully cured.
These and any other defects shall be remedied by methods approved by the Engineer
which may include using a suitable bituminous resin or where necessary, cutting out to a
regular dovetailed shape atleast 75mm deep and refilling with concrete over steel mesh
reinforcement souring in to the dovetail. No extra payment for rectification work will be
made.
Holes to be filled :
Holes formed in concrete surfaces by formwork supports of the like shall be
filled with dry-pack mortar made from one part by weight of ordinary cement and three
parts fine aggregate passing I.S. sieve 1.18mm. The mortar shall be mixed with only
sufficient water to make the materials strike together when being molded in the hands.
The tenderers / contractors shall thoroughly clean any hole that is to filled
with dry-pack mortar and where the surfaces has been damaged the tenderers /
contractor shall break out any loose, broken or cracked concrete or aggregate. The
concrete surrounding the hole shall be dried so as to leave a small amount of free water
on the surface.
The surface shall then be dusted lightly with ordinary Portland cement by
means of small dry brush until the whole surface that will come into contact with the
dry-pack mortar has been covered and darkened by absorption of the free water by
cement. Any dry cement in the hole shall be removed. The dry-pack material shall then
be placed and packed in layers having compacted thickness not greater than 15mm in
thickness the compaction shall be carried out by use of a hard-wood stick and a hammer
and shall extend over the full area of the layer, particular care being taken to compact
the dry-pack against the sides of the hole. After compaction the surface of each layer
shall be scratched before further loose material is added. The hole shall not be over
filled and the surface shall be finished by laying a hardwood block several times. Steel
finishing tools shall not be used and water shall not be added to facilitate finishing.
Removal of formwork :
In no circumstances, shall forms be struck until the concrete reaches adequate
strength has required or without obtaining permission of the Engineer. All formwork
shall be removed without any shock or vibration such as would damage the concrete.
Before the soffits are removed the concrete, surface shall be exposed where necessary
in order to ascertain that the concrete has sufficiently hardened. The responsibility for
the removal of the formwork whether whole or part shall rest entirely with the
Tenderers /Contractors who must never them shall be guided by the opinion of the
62 | P a g e
Engineer in this regard. The work of striking and the removal of formwork shall be
conducted in the presence of the Engineer and under personal supervision of competent
foremen in the employment of the contractors.
Normally, the form shall be struck after the expiry of following periods :
1. Vertical surfaces of wall ……1 day
2. Columns and vertical sides of beam ……2 days
3. Slab bottoms with props left under ……2 days
4. Beam bottom and bottoms of column strip in a flat with prop left under ……7 days
5. Removal of props under span up to 4.5m ……7 days
span above 4.5m ……14 days
6. Removal of props to span up to 6m beam/arches. ……21 days
Surface treatment and finish :
When the formwork is struck, all the faces of concrete shall be smooth and
sound, free from voids and air holes. Any roughness or irregularity on the exposed
surface shall be immediately filled up while the concrete is still green, with cement
grout, cement wash and / or 1 : 1.5 cement mortar, properly trawled and finished. Such
patching of the concrete face shall be carried only with the permission of the Engineer.
If the concrete is found honey combed the portion and whatever surrounding concrete
that may be considered unsatisfactory by the Engineer shall be dismantled and fresh
concrete of proper quality shall be reinstated at contractors cost.
Faces of concrete which are to be either in contact with water of are exposed
to water vapors such as in roof slab, and columns, col. footing, R.C.C floor internal
staircase, etc shall be treated as described below immediately after the formwork is
struck.
All projecting imperfections shall be first rubbed down flush, with carborendum
stone or by any other approved means. The grit and dust resulting these from shall be
thoroughly washed off clean water. The surface shall then be given a wash of cement,
and Cico solution made up to a consistency of thick milk by mixing Cico (i) and water in
proportion 1:10 applied with brush. The treated surface shall be cured with water spray
for a period of 10 days minimum. The Engineer may at his discretion, allow the contract
to substitute CICO by any other approved material, of equivalent quality. In the case of
any other concrete except for the reservoir proper and control room used in the
construction on other structure such substation, external stair cases, parapet walls, etc.
the concrete surface exposed when the form are struck off shall be finished as
specified below : All exposed external R.C.C surfaces, including soffits edges, faces etc.
shall be finished with sand faced plaster 1:3 or medium smooth plaster 1:4 as the case
may be consistence with the finish of the adjoining masonry work as per specifications
or as directed by the Engineer.

REINFORCEMENT
General
Requirement specified here in provided for reinforcing work complete as
indicated, specified and required and including supply and delivery of reinforcing bars,
and mesh, bending, wire brushing and cleaning, steel fixing and the attendance of a
fitter during concreting, to inspect fixed reinforcing bars and maintain bars in correct
position at each four locations. Whenever mention of I.S. code is made, the latest
editions thereof shall be applicable.
63 | P a g e
Quality Assurance :
Code requirement
Unless otherwise stated herein all work specified herein and as shown on the
drawings shall conform to be applicable requirement of IS-456-latest edition. In case of
water retaining structure IS-3370 Part-I and IV shall be applicable.
Standards :
Steel for reinforcing shall be of the following kinds as may be specified in the
drawings. Mild steel plain bars conforming to IS:432-1960 and it’s latest edition. High
yield deformed bars conforming to IS:1139-1966 and it’s latest edition.
Field quality control :
All continuous inspections shall be performed by the Engineer-in-charge’s
representative or his authorized
Materials :
Reinforcing bars :
Reinforcing bars shall have to be brought by the contractor as laid down in the
tender condition.
Welded Wire mesh :
Mesh reinforcement, where specified shall conform to IS:1566-1967.
Binding Wire :
Steel fixing shall be by 1.65 mm dia soft annelid wire.
Supports and Accessories :
Supports, cover or spacer for reinforcement shall be provided by precast
mortar [1:2] blocks made with embedded wire ties. The cover blocks shall be made so as
to provide the exact specified cover to reinforcement. Stays, blocks, ties, spacers or
other supports as approved by Engineer-in-charge shall be provided at appropriate
intervals to avoid sagging of bars between supports. Broken stones, bricks pieces,
wooden blocks shall not be allowed.
Dowels :
Where and as designated on the drawings, steel bars dowels shall be provided
for anchorage to previously cast concrete for anchorage where shown or required to
existing construction, and approved non-shrink bituminous type grout or approved
deferred bolting devices shall be used.
Bending :
Unless otherwise indicated or specified bars shall be bent and fixed in
accordance with the provisions of IS: 2502. All bending shall be done with the use of an
approved bending tool. Re-bending of incorrectly bent bars shall not be permitted.
Cleaning :
Before placing reinforcement and again before concrete is placed,
reinforcement shall be wire-brushed and cleaned of loose mill scale, oil, or other coating
that might destroy or reduce bend.

Concrete cover :
Cover over reinforcing bars shall be as indicated. Correct concrete cover to
reinforcement shall be maintained with the aid of approved cover blocks. Top
reinforcement in slabs shall be maintained in position by means of chairs made out of
mild steel, the diameter and quantity bending sufficient to ensure security of the
reinforcement in shape and position.
64 | P a g e
Securing in place:
All reinforcement shall be securely and accurately fixed in positions shown on
the drawings, care being taken to prevent contract with coated shuttering and forms.
All intersection of bar should be secured with approved clips or with wire, the ends
being turned into the body of concrete.
Splices shall be wired contract lap splices unless otherwise indicated or
approved. Splices at points of maximum tensile stress shall be avoided and shall be
staggered elsewhere, lap length and other provisions shall conform to Is:456. splicing of
vertical bars in concrete be at be a approved positions.
Unless otherwise shown in case of horizontal bars lap splices shall be made with
at least one continuous bar between adjacent splices, where double mats of bars occur in
walls, lap splices in opposite mats shall offset at least 1.5 m .
Welding :
When permitted or required, joints of reinforcement bars shall be welded so as
to transmit their full stresses. Welded joints shall preferably be located at points when
steel will not be subjected to more than 75% of the maximum permissible stresses and
welds so staggered that at any one section not more than 20% of the rods are welded.
Only electric welding using a process which excludes air from molten and conforms to
any or all other special provisions for the work shall be accepted. Suitable means shall
be provided for holding bars securely in position during welding. It shall be ensured that
no voids are left in welding and when welding is done sin tow or three stages, previous
surface shall be cleaned properly. Ends of the bars shall be cleaned of all loose scale,
rust, grease, paint and other foreign matter before welding. Only competent welders
shall be employed on the work. The M.S. electrodes used for welding shall conform to
IS:814. Welded pieces of reinforcement shall be tested. Specimen shall be taken from
the actual site and their number and frequency of test shall be as directed.
WOODEN WATER LEVEL INDICATOR :

A wooden water level indicator of approve size and type shall be provided and
fixed by the contractor. It shall consist of wooden plank of 250 mm x 40 mm.

The division on water level indicators shall show distance of 10 cm. clearly. A
copper or PVC float of 500 mm dia and 50 mm height shall be provided along with steel
wires pulleys etc. The entire arrangement shall be first got approved the Engineer –in –
charge of work. Letter and marking shall be painted with approved enamel paint.

COPPER LIGHTING CONDUCTOR :

Copper lighting conductor with size of strip 20 mm x 3 mm with clamps and


screw and copper plate of 600 mm x 600 mm x 6 mm and copper red as per specification
no. 120 of PWD Hand book Vol. I ( ISS – 2309 ) shall be provided and fixed by the
contractor. It shall consist of copper arrestor at top, copper conductor from top up to
GL and copper earthing plate shall be 1 m. deep below GL and filled with salt and
charcoal to transmit the current to earth, minimum dimension of these part shall
confirmed relevant ISS height of the arrestor shall be such as to enclose the entire
structure with imaginary cone generated by inclined at 60o degrees with vertical at top.

Providing and fixing C.I., flanged pipes and special such as duck foot bends,
crippling flanges bell mouth piece etc. for inlet outlet overflow and washout.

65 | P a g e
Diameter and length of above pipes shall be as given in Appendix – A. CI
flanged pipes shall be vertically cast double flanges and shall be confirm to relevant
ISS. They shall be first get approved by the Engineer –in – charge of work.

Rate shall include providing all specials such as crippling flanges, and duck feet
bends etc. as may be required on site.

The rates shall also include cost of all jointing materials such as nuts, bolts,
rubber packing, white zink or pig lead or lead wool if required.

Pipes shall be fixed perfectly vertical and straight.

Before fixing in position pipes shall be coated with two coats of anticorrosive
paint.

The pipes and specials shall be tested hydraulically. Leakage if found shall be
repaired without extra cost.

PROVIDING AND FIXING CI SLUICE VALVE :

Diameter of C.I. sluice valve shall be as shown in Appendix – A. C.I. sluice valve
shall be of class – 1 confirming to I.S. – 780 – 1980.

The rate includes providing and fixing C.I. sluice valves with tailpieces including
jointing materials such as nuts, bolts, rubber packing zink etc. The rate includes giving
hydraulic test to the satisfaction of Engineer –in – charge of work

Sluice valve shall be supplied with necessary spindle or wheel for operating the
same.

PROVIDING AND FIXING C.I. M. H. FRAME AND COVER :

One number of C.I.M.H. frames and cover shall be provided and fixed in top
slab of container. The dimensions and weight shall be as shown in Appendix – A. The
C.I.M.H. frame and cover shall be first got approved by the Engineer –in – charge. The
coats of anticorrosive paints shall be applied before fixing them in position.

C.I. COWL TYPE VENTILATORS :

The cowl type ventilator should be of 100 mm dia shape with flanged and
roughing screen shall be as per Appendix – A. The rate includes providing and fixing C
I.C. cowl type ventilator as per Appendix – a including cost of all jointing materials such
as nuts, bolts, white zink rubber packing etc. two coats of anticorrosive paints shall be
applied to the surface before they are fixed in position. They shall be first for
approved by the Engineer –in – charge.

PROVIDING AND FIXING ANGLE IRON LADDER INSIDE CONTAINER:

Structural steel flat or angle sections conforming to I.S. 226-1975 and I.S.
straight and shall be free from loose mill scales, rush pits or other defects affecting
strength and durability. Stringers shall be kept 45cms. or 50cms. apart clearly between
the inner edges of the stringers and shall extend atleast 75cms. above the top of the
tank with the curved top. The size shall be taken as specified in the Item. Mild steel
bars conforming to I.S. 432-1960 or its latest revisions shall be clean and free from
dirt, oil paints, grease, mill scales, rust. Steps shall be placed at 25cms. or 30cms.
center to center. As specified in the item above. Stays shall be provided at 3 meters

66 | P a g e
interval and stays shall be of adequate length with at least 15cms. bearing in the walls of
the container and as directed by the Engineer in Charge.
CONSTRUCTION OF VALVE CHAMBER:

Number and size of valve chamber shall be as per Appendix – A. or


otherwise it shall be 1.3 x 1.3 x 1.0mt, inside. Specification of various items such as B.
B. masonry cement plaster, C.M. (1:3) and C.C. (1:3:6) at bottom. . RCC 1:2:4 etc. shall be
as these given in column of specification published by G.W.S.& S G. W. S. & S. Board and
as those prevailing in Division.

Rate shall be including cost of all material and labour for constructing valve
chamber as above.

PAINTING LETTERS :

Words shall be painted on the container for showing the capacity of tank as
per departmental specifications and as per instruction of E.I.C.

The letters shall be 45 cm high and the black ground of suitable color shall be
provided. Approved enameled paint shall only be used for painting letters and
background. Entire work shall be carried out as per instruction of Engineer –in – charge.
Rate includes providing paint and labour for painting letters and also providing
scaffolding etc for painting.

Plaster :
Inside plaster :
Cement plaster shall be of 15mm thick with cement mortar 1 : 3 (1 cement : 3
fine sand )
Scaffolding -
Wooden bellies, bamboos, planks, treaties and other scaffolding shall be sound.
These shall be properly examined before erection and use. Stage scaffolding shall be
provided for ceiling plaster which shall be independent of the walls.
Preparation of Background – The surface shall be cleaned of all dust, loose
mortar droppings, traces of algae, efflorescence and other foreign matter by water or
by brushing. Smooth surface be roughened by wire brushing it it is not hard and hacking
if it is hard. In case of concrete surface, if a chemical retarder has been applied to the
form work, the surface shall be rough3ned by wire brushing and all the resulting dust
and loose particles cleaned off and care shall be taken that none of the retarders is left
on the surface. Trimming of projections on brick/concrete surfaces where necessary
shall be carried out to get an even surface.
Raking of joints in case of masonry work where necessary shall be allowed to
dry out for sufficient period before carrying out the plaster work.
The work shall not be soaked but only damped evenly before applying the
plaster. If the surface becomes dry, such areas shall be moistened again.
Outside plaster :
Providing and applying 20mm thick sand faced cement plaster walls up to height
10 meters above ground level consisting of 12 mm thick backing coat of C.M. 1 : 3 [1
cement : 3 sand] and 8mm thick finishing coat in C.M. 1 : 1 [1 cement : 1 sand] etc. comp.
The work shall be carried out in two coats. The backing coat [basecoat] shall be
12mm thick in C.M. 1:3. The relevant specifications of ITEM No.14 shall be followed

67 | P a g e
except the thickness of back coat shall be 12mm average and the proportion shall be of
cement mortar 1:3 [1 cement : 3 sand]
Before the first coat hardens its surface shall be beaten up by edges of
wooden tapers and close dents shall be made on the surface subsequent coat shall be
applied after this coat has been allowed to set for 3 to 5 days, depending upon the
weather conditions. The surface shall not be allowed to dry during this period.
The second coat shall be completed to 8mm thickness in C.M. 1:1 as described
above, including raising sand facing by bushing. The sample of sand face shall be got
approved before the work is started. The whole work shall be carried out uniformly as
per sample approved.
For external plaster, the plastering operation shall be started from top floor
and carried downwards. For internal plaster, the plastering operations may be started
wherever the building frame and cladding work are ready and the temporary supports of
the ceiling resting on the wall of the floor have been removed. Ceiling plaster shall be
completed before starting plaster to walls.
I.P.S FLOORING :
I.P.S flooring shall be 40mm thick in cement concrete 1:2:4 (1cement : 2 coarse
sand : 4 stone aggregate 20mm. nominal size ) with a floating coat of neat cement.
The cement concrete flooring of 40mm thick (average) is to be laid as per the
site conditions. The concrete shall be mixed in a mechanical mixer at the work. Hand
mixing may be allowed for smaller quantities of work and in case of failure of
machineries or as permitted by the Engineer-in-charge. It shall be carried out on a
water tight platform and care shall be taken to ensure that mixing is continued until the
mass is uniform in colour and consistency. However, in such cases 10% more cement than
otherwise required shall have to be used without any extra cost. The mechanical mixing
shall be done for a period of 1.5 to 2 minutes. The quantity of water shall be just
sufficient to produce a dense concrete of required workability for the purpose. Flooring
of specified thickness shall be laid in accordance with the approved pattern or as
directed. Finishing operation shall start shortly after the cessation or beating and shall
be spread over a period of one to six hours depending upon the temperature and
atmospheric conditions. The surface shall be left for some time till moisture mixed with
water to form thick slurry and spread over the surface while the concrete is still green.
Use of dry cement or cement and sand mixture sprinkled on this surface to stiffen the
concrete or absorb excessive moisture shall not be permitted. The cement slurry shall
then be properly pressed twice by means of iron floats, once when the slurry is applied
and the second time when cement starts setting and finished floated smooth. The
surface shall be marked with string or B.R.C fabric jali to make the surface non-slippery
as and when directed. The junction of floors with wall plaster, dado or skirting shall be
rounded off where so required up to 25mm radius flooring in lavatories and bath rooms
shall be laid after fixing of water closet and squatting pans and floor traps which shall
be plugged while laying the floors and opened after the floors are completed. Any
damage done to the water supply or sanitary fittings during execution of work shall be
made good.
After the final set, the concrete shall be kept continuously wet, if required by
pounding for a period of not less than 7 days from the date of placement.

68 | P a g e
The form work shall be provided if necessary as directed by the Engineer-in-
charge. Concreting shall be done as per alternate bay method with necessary centering
either by mastic or cement mortar as directed.
FILLING WITH EXCAVATED EARTH :
The earth to be used for filling shall be free from salts, organic or other
foreign matter. All clods of earth shall be broken.
As soon as the work in foundation has been completed and measured the site of
foundation shall be cleared of all debris, brick bats, mortar dropping etc. and filled with
earth in layers not exceeding 20 cms. Each layer shall be adequately watered, rammed
and consolidated before the succeeding layer is laid. The earth shall be rammed with
iron rammers where feasible and with the butt ends of crowbars, where rammer cannot
be used.
The side slopes of reservoir shall be similarly filled with earth in layers not
exceeding 20 cms adequately watered and consolidated by ramming with iron or wooden
rammers. When filling reaches finishing level, the surface shall be flooded with water
for at least 24 hours and allowed to dry and then rammed and consolidated.
The finished level of filling shall be kept to shape intended to be given to floor.
The excavated stuff of the selected type shall be allowed to be used in filling the
trenches and plinth. Under no circumstances black cotton soil be used for filling the side
slopes and trenches.
SNOWCEM, DISTEMPER, OIL PAINT :
General :
Preparation of surface & priming coat :
The surface shall be thoroughly brushed free from motor dropping and other
foreign matter and sand papered smooth.
A priming coat of whiting shall be applied over the prepared surface in case of
water-bound distempering and distemper primer or cement primer shall be applied in the
case of oil bound distemper. No white washing coat shall be used as a priming coat for
distemper.
Application :
After the primer coat has dried for at least 48 hours, the entire surface shall
be coated uniformly with proper distemper brushes in horizontal strokes, immediately
followed by vertical ones which together shall constitute one coat.
Scaffolding :
Where scaffolding is necessary it shall be erected in such a way that as far as
possible no part of scaffolding shall rest against the surface to be white or colour
washed. A properly secured strong and well tied suspended platform (zoola) may be used
for white washing. Where ladders are used, pieces of old gunny bags shall be tied at top
and bottom to prevent scratches to the floors and walls. For white washing of ceilings,
proper stage scaffolding shall be erected where necessary.
Snowcem :
Finishing wall with water proofing cement paint (snowcem) on undecorated wall
surface )three coats) to gives and approved brand and manufacture and required shape
even shade after thoroughly brushing to surface to remove all dirt and remains of loose
powdered materials.
The surface shall be thoroughly scrapped cleaned finishing walls shall be
completely cleaned before applying snowcem or water proof cement paint. The shade and
69 | P a g e
quality must be approved by Engineer-in-charge of the work before starting the work.
The snowcem shall be applied with the fine brush and allowed to set before second coat
is applied. The rate shall include necessary scaffolding, tools and plants and sufficient
watering etc. complete.
The work shall be carried out to the entire satisfaction of the Engineer-in-
charge of the work and in best workmanship like manner as per specification of
manufacturer or as directed.
Oil paint :
All doors, windows, ventilators, shutters, railing, all fabricated items, motors,
pumps, all interconnecting piping above ground level etc. shall be colored with two coats
of approved make oil paint strictly as directed by Engineer-in-charge.
Distempering :
Distempering shall be of the oil or water bound type as specified.
Material :
Dry distemper or oil bound washable distemper of approved brand and
manufacture for water bound and oil bound respectively conforming to IS:428 shall be
used. The proportions of the mix shall be as per the approved manufacturer’s
instructions.
a) The dry distemper shall be stirred slowly in clean warm water using 0.6
liter of water per kg. of distemper or as specified by the approved makers. The mixture
shall be well stirred before and during use to maintain an even consistency.
b) Thinner as stipulated by approved manufacturer shall be used in case of
distemper for oil bound type.
c) Dry distemper shall not be mixed in larger quantity than is actually
required for one day’s work.
G.I Railing :
The railing shall be fabricated from G.I pipes generally conforming to IS. They
shall consist of horizontal pipes welded at a spacing of not more than 450mm to vertical
balustrade pipes of 40mm dia. The vertical pipes shall be spaced at
1m c/c. The fabricated railing shall be installed using 6 mm thick M.S base plate
and 12mm dia M.S ‘J’ bolts. The exposed faces shall be painted with 2 coats of enamel
paint of approved quality.
M.S Ladder :
The M.S ladder shall be used where access to elevated area is essential for
operation and maintenance. It shall be fabricated from M.S angles and channel section.
The span of the ladder shall be not less than 60 cms. The angles used shall not be less
than ISA 25 × 25 × 6 mm. A chequered plate of thickness 6mm shall be provided for
every step. For ease in climbing the pitch of ladder shall be restricted to 60 degree.
The rise of the steps shall be restricted to 25 cm. All M.S surfaces shall be coated with
bituminus to prevent the corrosion. The railing for the ladder shall be fabricated from
25mm GI pipes.
WATERPROOF CEMENT PLASTER :

The cement mortar shall consist of two parts of fine river sand free from any
dust and other organic matter and one part of approved quality of cement. The mortar
shall be properly mixed on watertight platform. The mortar shall be used within half an

70 | P a g e
hour after mixing. The water proofing materials weighting 1.5 kg of powder in one bag
of cement shall be added.

The plaster shall be applied in uniform thickness of 20 mm and shall be


properly smoothened with wooden & finished with cement finishing of required. The
curing shall be done at least for week by sprinkling the water over the wall. The wall
shall be tested for water proof- ness. The rate includes the cost of waterproofing
materials. The test for water proof-ness shall be carried out by the contractor at his
own cost by filling the contractor with water and it shall be checked out that there is no
percolation of water from the wall. Payment shall be made per sq. m. of plaster done.

BRICK PITCHING :

The brick shall be of proper quality, standard size, uniform in color, well burnt
and free form crack work of brick pitching shall be carried out in C.M. 1:6. It shall be
laid as per the drawing and directed by the Engineer –in – charge. The bricks shall
properly soaked before being using in work. No brickbats shall be use except the bricks.
The joint shall be racked out 20mm depth. Every day at the end of the days work the
cement pointing in C.M. 1:2 shall be carried out by line as directed by the Engineer –in –
charge. The excavation required for bricks pitching shall have to be carried out by the
contractor as directed including necessary temping consolidation etc complete.

After completion & testing of work the contractor shall have to provide & fix
Marble “ Takti “ of required size with necessary writings, as directed by the Engineer –
in – charge.

RCC work of shaft, container and staircase should be of well finished condition
if the same is not satisfactory than contractor since have to finish the surface with 12
mm thick plaster C.M without any extra cost.

The contractor shall have to make arrangement for testing of steel bars
brought on site and concrete cubes, for different mix at different stage like
foundation, shaft, column, and cube should be cast on site and send Govt. approved
laboratory for compressive strength at 28 days. Results must be produced in office
before taking payment of work done. Testing charge must bear by contractor.

GENERAL DISCRIPTION

(1) The contractor will required to approved to the specification of he Executive


Engineer a fully qualified and experienced engineer of building of engineer of
Building or Engineer work and also will be always available on site of work during
the progress of work and the Executive Engineer has full powers to remove such
engineer from the work within 24 hours giving notice to contractor who will
immediately thereon appoint another qualified Engineer. The contractor shall
provide office accommodation for him
(2) The contractor shall give to the Municipality police and other authority notice
etc. that may be required by law and obtain requisite license sewer water pipe
etc. and other authorities and also being bouring properties where necessary.
The contractor shall make good and damage to adjoining premises, whether police
or private and provide nightlights etc. as maybe required on site. They shall also
construct peren clousure and faces for the protection and connivance of the

71 | P a g e
working people and public. During the progress of work & perfectly rest the
adjoining ground up to completion of work.
(3) No claim of contractor for any extra work shall be entertained unless the extra
work done in clearly without under order of Engineer in charge
(4) The contractor shall engage in experienced and qualified supervisor as his
authorized agent for this work. He shall be responsible for taking free from
the time order regarding work from the Engineer in charge any carrying the
promptly.
(5) The contractor shall maintain a work order book on work site & signed carryout
promptly the orders given by the Engineer in charge. This work order book shall
be submitted to the Dept. on completion of the work.

(6) The contractor shall have to clean the site of work before commencing work and
after completion of work without any extra claim

(7) The contractor shall provide at his own cost, all labour, materials & adequate
facilities of lining.

(8) The contractor shall materials regular account of his respect and use controlled
materials purchased by him.

(9) The contractor shall provide at his one cost necessary accommodation water
supply and sanitary arrangement for his staff and labour and shall pay dirt to the
authorities concern all rate taxes royalties and other charges. He shall be
comply with the requirement of the Health Dept. as regards ant malaria
measures etc.

(10) The water required excavation of the work shall have to be supplied by
contractor at his own cost.

(11) Dewatering of trenches foundation etc. shall be done by the contractor at his
own cost during executing of all items of this work till completion all respect.

(12) The contractor shall provide his own made of conveyance for carting of pipes,
specials etc. to the supplied by department & surplus excavated stuff from to
site of work.

(13) The contractor shall provide deviation to the existing read if required as
directed by Engineer in charge

(14) The quantities given in schedule – ' B ' are approximately. The contractor shall
have to claim for a safe in excess of his tendered rate for any varied to any
extent in quantities.

(15) For laying & locating pipes specifications attached here to shall be followed.

(16) Any time not covered in the schedule – ' B ' but required to be executed shall be
carried out by the contractor at the rate for such items available in division
schedule of the in force.

(17) The limit for completion of this work shall be months from the date of work
order.

THE CONTRACTOR SHALL MAKE DECLARATION AS UNDER

72 | P a g e
( 1) I have made myself thoroughly convergent with the local conditions as regards
availability of otherwise of all construction materials, studies and understood the
specifications drawings and designs of this work & have passed my rates
accordingly."

(2) The contractor at his own costs shall have to provide a temporarily shed of area
about 20 sq. m. at site of work for use as office for discussion of the work. The
same shall be removed by the contractor after the work is completed.

(3) The hydraulic test of water bearing structures shall have to be given by the
contractor as per instruction of Engineer in charge without any extra cost 10%
of the containers items cost of the structure will be with held. If the hydraulic
test is not given by the contractor or there is any damage to the structure.

SPECIFICATION FOR PLAIN & REINFORCED CONTRETE WORK:

(1) The work shall be carried out as per specification no 160 appearing on page 395
to 406 of PWD Hand book Vol. I 1949 edition & specification detailed hereafter.

(2) Proportion of the various ingredients of concrete shall be as per description of


item.

(3) Volume of one sound bag of cement weight in 50 kg. shall be consider i.e. 4.77
cft. for volumetric purpose.

(4) Cement shall be stacked on water tight platform raising atleast 30 cm. above
floor in a sound store room in such a way that it can be easily counted. No
deteriorated cement shall be allowed for in use and the same shall reject at cost
of the contractor. Double locking arrangement shall be adopted for cement
store.

(5) Clean hard, strong durable and well- graded river sand shall be used. It shall not
contain clay slot or any detritus foreign materials. The sand shall be sounded
and washed if required as per instruction of Engineer in charge. Sand shall be
stored in a clean platform.

(6) Coarse aggregate made from block trap stone shall be used and the same is clean
hard tough durable and cubical in slope. If shall not contain any soft flaky or
elongates piece. It shall be well graded the maximum size specified to give
minimum percentage of void. Necessary test of materials shall have to be given
by the contractor & when desired by the Engineer in charge. The coarse
aggregate shall be stored in clean platform.

(7) Water to be used for preparing concrete shall be clean & potable. Quantity of
water to be used for preparing shall be as specified by the Engineer in charge.
No assuring apparatus shall be provided as per instruction of Engineer in charge.

(8) Precast C.C. block or cement mortar block with wired reinforcement shall
provided between form work and reinforcement and tied to the letter as
directed by the Engineer in charge to provide necessary cover to the
reinforcement.

(9) Hand mixing shall be done on a sufficiently large water platform. First cement
sand in required quantity shall be mixed by turning the mixture al least three

73 | P a g e
time. After the mixture contains uniform coarse aggregate shall be added and
whole mix shall be turned over. The specified quantity of water shall be carried
out simultaneously until whole batch attains uniform color.

(10) The formwork shall be just moisture before placing concrete. The concrete shall
be placed in position within 20 minutes after water is added. It shall be slowly
placed in position and not thrown from a height. It shall not cast in layers

(11) The concrete shall be well cured for 20 days after it placed in position by means
of the gunny bags for pounding.

(1) Side of beams after 4 days

(2) Bottom of beams after 21 days

(3) Bottom of slab after 10 days

(4) Vertical side of wall after 7 days

(5) Vertical side of column 7 days.

(12) Necessary facilities shall be provided by the contractor for inspection of various
stages of concrete work by the Engineer in charge of Sub-divisional officers of
Executive Engineer. Concreting RCC chambers shall be done only after order to
affect is given in work order by the Engineer in charge or sub divisional officer
in important work.

(13) Finishing of concrete faces shall be done as provided in the description of item
concerned. It shall consist of 3 coats of wash if it is not specified in the site.

(14) Item shall be laid on the rate quoted by the contractor in schedule – "B"

(15) The payment shall be paid as per the payment schedule.

APPENDIX B
R.C.C. U/G. SUMP 2,00,000, 1,00,000 & 30,000 Lit. Cap. (Contractor’s Own
Design)
Cement Consumption Statement

Sr. Particulars of Item to be included Qty. as per Rate of Total Total


No. in Work by contractor contractor’s cement cement cement
own design consumption required
per unit in No. of in M. Tone Begs

APPENDIX C
R.C.C. U/G. SUMP 2,00,000, 1,00,000 & 30,000 Lit. Cap. (Contractor’s Own
Design)
Tenderer’s and Contractor’s Certificate
I/ We hereby declare that, I/ We have pursued in details and examined closely the
specifications in the tender documents.
I/ We agree to be bound by and comply with all such specifications for this agreement.
I/ We executed with the Village Water and sanitation Committee.

Date :

74 | P a g e
Name of Tenderer or Contractor :

Address of Tenderer or Contractor :

APPENDIX D
R.C.C. U/G. SUMP 2,00,000, 1,00,000 & 30,000 Lit. Cap. (Contractor’s Own
Design)
Tenderer’s and Contractor’s Certificate

I/ We hereby declare that, I/ We have pursued in details and examined closely the
specifications in the tender documents.

I/ We agree to be bound by and comply with all such specifications for this agreement.

Date :

Name of Tenderer or Contractor :

Address of Tenderer or Contractor :

Missing Link
PARIEJ REGIONAL WATER SUPPLY SCHEME
TA. MATAR, TARAPUR, SOJITRA DIST. KHEDA
Const. Staircase for R.C.C. Ele. Reservoir of 3.00 & 6.00 Lit. cap.
25 Mt.Ht. at Luvakuva & sayala. & Repairing of ESR.

Sub Estimate No. 3

Item No.1: Demolition of existing scrape of staircase column and steps in side
the shaft up to level. Removing and clearing the surface without
disturbing existing structure and surrounding as directed.

The demolition of unserviceable materials for staircase column and steps in side
this shaft up to level shall be carried out in such a way that other components are root
damage. The demolition work shall be carried out up to excavation level in such a way. So
that the demolition material does not fall inside excavation. The material shall be
disposed out side the working area with lead up to 90.0mt. as per instruction of
Engineer-In-Charge.

Item No.2 Drilling holes in shaft wall at regular intervals for fixing M.S. plates
to support and spike the tie beams without disturbing and damaging
the existing structure and surrounding.

75 | P a g e
Drilling holes in shaft wall at regular intervals for fixing M.S. plates to support
and spike the tie beams without disturbing and damaging the existing structure and
surrounding and as per instruction of Engineer-In-Charge.

Item No.3 Excavation for pipe line tranches including all safety provisions using
site rails and stacking excavated stuff up to a lead of 90 m clearing
the site etc. comp. for lift and strata as specified in all sorts of
soil and soft murrum upto 1.50 m. depth.

General:
This specification same as per Sub-Estimate No.1 Item No. 4

Item No.4 Providing and casting in situ mass cement concrete in grade M-100
(Approximate corresponding to proportion 1:3:6) using granite
quartzite trap metal of 12 mm to 25 mm including consolidating
curing. etc. complete.
General :
Specification cover the requirement of ordinary or controlled cement concrete
of specified proportion for plain and cement concrete works. Specials requirement for a
particulars, item shall be laid down in the specifications as per I.S. 456-1979. For
deviation laid down in the specifications for liquid retaining structure, narrated in I.S. :
3370-1971 shall apply.

Materials :
Specifications for the materials required in the item shall be specified as under.
Aggregate :
Two types of aggregates shall be used in the concrete work described as under.
1. COURSE:
Course aggregate of black trap stone conform all general requirements specified
in I.S.:383-1970 or it’s latest revision. Course aggregate shall be of machine crushed
stone of free in skin and coating likely to prevent proper adhesion of mortar. It shall be
free form injuries amount of disinfected stone, soft, faulty or elongated particles, salt ,
alkali, vegetable table matters and others deleterious substances. In the case of
reinforced cement concrete the maximum limit may be restricted to 6mm. Less than the
minimum lateral clear distance between bars or 6mm. less than the cover whichever is
smaller. The percentage may be varied some what by the Engineer in charge when
considered necessary for obtaining better density and strength of concrete. The
grading test shall be taken in the beginning and at the change of course materials. The
necessary test indicated in various I.S. shall have to be carried out to ensure the
acceptability.

2. FINE:
The sand shall comply all general requirements of fine aggregates as specified in
I.S. 383-1970 or it’s latest revision. Sand shall be natural sand,durable and gritty
particles free form injuries amount of dust, clay, kankar modules of or flaky particles,

76 | P a g e
shale , alkali, salts, organic matter loam ,mica or other deleterious substances and shall
be got approved form The Engineer in charge as a specified in I.S..:383-1970 with
module varying form 1.4 to 2.6 as per requirements fitness. The sand shall be stacked
carefully on a clear hard surface. and got approved for quality form The Engineer In
charge.

CEMENT
The cement used shall be ordinary Portland cement or rapid hardening Portland
cement conforming to I.S..:269-1958 or Portland pozzolone cement conforming to
I.S.:1489-1976 or high alumna cement of approved specifications.

WATER:

Water used for both mixing and curing shall be free from injurious amount of
deleterious materials. Potable waters are generally considered satisfactory for mixing
and curing concrete. In case of doubt, the suitability of water for mixing concrete shall
be ascertained in accordance with I.S.: 516-1959 and I.S.: 4031-1968. The “pH” value of
water shall generally be between 6 to 8.

Storage Of Materials :

All materials shall be so stored as to prevent deterioration or intrusion of


foreign matter and to ensure the preservation of their quality and fitness for the work.
Any material, which has deteriorated or has been damaged or is otherwise considered
defective by The Engineer in charge shall not be used for the concrete.

Grade Of Concrete :

The concrete shall be in seven grades designated as M100, M150, M250, M350,
and M400. The mix of concrete shall be adopted as specified in the item. The
determination of the proportions of cement, aggregates and water to attain the
required strength shall be made by one of the following.

A) With preliminary tests by designing the, concrete mix.. Such concrete shall
be called. ‘controlled concrete’.
B) Without preliminary tests by adopting nominal concrete mixes. Such
concrete shall be called ‘ordinary concrete.
As far as possible, controlled concrete should be used on all concrete works the
maximum total quantity of aggregate by weight per 50kg. of cement shall not be exceed
450kg. except where otherwise specifically permitted by The Engineer in charge any
extra cost. Cement and sand shall be first mixed dry then aggregate added, and whole
furred-over three times dry and then turned over four times wet. Measured quantity of
water shall be applied through a rose. A fairly wet mixture shall be used.

Laying :

Before starting the concrete work, The contractor shall have to clear the
foundation, remove dirt’s, clods, or any type of foreign matter from pit, level the pit,
and got approved form The Engineer in charge.

77 | P a g e
The concrete shall be placed in to it’s final position, compacted and finished
within 30 minutes of mixing the water and before setting commences and should not be
subsequently disturbed. The method of placing shall be such as to avoid segregation and
balanced load on formwork. The concrete shall be deposited in continuous horizontal
layer, not exceed 30 cm. in thickness. As far as possible, the joints should be avoided in
the concrete work. Unless and otherwise shall be made only where mentioned in the
plans or approved by The Engineer In Charge. The concrete shall be thoroughly complete
compacted during the operation by means of tools and/or mechanical vibrator as
directed by The Engineer In Charge.

Curing :

Curing shall be done by creating compartments, using lime/mud-sand mixtures, it


shall be done for minimum 21 days.

Finishing :

All exposed faces of the concrete shall be finished with C.M. 1:2 and neat
finishing without claiming any extra cost.

Testing :

Testing for strength required of the concrete for R.C.C. E.S.R. work, contractor
shall arrange for taking cube test for preliminary test if required and work test as per

Strength Requirement Of Concrete :

Grade of Compressive Strength of 15 cm. Cubes after


mixing conducted concrete in accordance with IS : 516
---1959 All values in Kg/CM2 Preliminary At 28 days.
At 7 days. Work test
Min. Min.
Min.

M100 70 135 100


M150 100 200 150

M200 135 260 200


M250 170 320 250

M300 200 380 300


M350 235 440 350

Mixing Of Concrete :

The concrete shall be mixed in proportion of Six parts of aggregate, Three


parts of sand and One part of cement by volumes as per discretion of Item. The
materials for concrete shall be carefully and accurately measured for every batch. The
aggregate and sand shall be measured by wooden or iron boxes made for the purposed.
The mixing shall be carried out by machine mixture or by hand as directed by The
Executive Engineer or his agent. In case of C.C. higher proportion than 1:5:10 shall be
mixed in the mixture only.

Machine Mixing :

78 | P a g e
The quantity of materials mixed should not exceed the rated capacity of the
machine. After all the materials are loaded into drum the concrete shall be mixed until
it is uniform in color and consistency but for not more than 1.5 to 2 minutes. About 15 to
18 revolutions per minute are generally considered sufficient.

Hand Mixing :

To be done on a clean paved area or water tight platform at least 2 m. x 4 m. or


a 3 meter square with strips fastened along three sides to prevent the materials being
washed or shoveled off during mixing. Additional 10 percent cement over and above the
specified proportion shall be used when hand mixing is resorted to, without claiming
clause 5 of I.S.: 456-1964. Results for the same shall have to be communicated to the
Divisional officer , through and in charge.

Measurements And Payment :

The measurements for work done only shall be taken as per Item’s units
specified in the “Schedule B”. 90% payment shall be made till the satisfactory results
are obtained for the sample cubes taken from and visual test on site. 10% amount will be
withheld from each item which are meant to require finishing.

Item No.5 Providing and casting in situ mass cement concrete in grade M-200
(Approx. corresponds to proportion 1:1.5: 3) using granite quartzite
trap metal of size 12 mm to 20 mm and or 6 mm to 12 mm for
R.C.C. work including scaffolding centering form work, needle
vibrated, consolidating curing and hydraulic testing etc. comp. up to
6.00 mt. ht. average GL for RCC ESR.

General :
All specification for the concrete work including materials required in the work
as specified in the item and shall conform the specification as per Item No.2 except
size of aggregate and proportion for grade of concrete. The aggregate and proportion
shall be kept as per Item description.
Scaffolding :
Scaffolding will be double or single as is wanted for the particular work. The end
of poles, if required to be rested on the brick for work shall be located at convenient
place. Scaffolding shall be erected with bullies, steel sections, pipes, or bamboo of
adequate strength as to be safe for all dead, live and impact loads likely to come on
them due to construction operations. The contractor shall take all measures to ensure
the safety of the work and the working persons. The contractor shall be entirely
responsible for any damage to work, property, or injury to persons, resulted from the
scaffolding, defective ladders, and materials , or other problems arising out of any
default in this respect. Proper and sufficient scaffolding shall be provided for easy
approach to the tail of work.

Centering :
The term “Centering” shall include all forms, molds, sheeting , shuttering,
planks , posts, shores struck , ties, uprights and all other temporary supports to the
concrete during the process of setting. The centering shall be such dimensions and so
constructed as to remain rigid during laying, tempting and setting of concrete. The

79 | P a g e
joints must be tight so as to prevent leakage. The centering must be arranged, so that
the portion below the slab can be removed first, then the sides of beams and finally
that below the beams.

All debris, saw-dust, etc. shall be removed from the shuttering before any
concrete is placed and should be taken to see that the shuttering is not likely to absorb
water from the concrete laid. On common works, wet the form immediately before
placing the concrete. The forms can also be given a coat of crude oil or grease thinned
with paraffin or soft soap and water or white wash in order to prevent adhesion of
concrete oiling shall be done before the reinforcement is placed in order for prevent
greasing the steel. Where it intended to plaster the concrete, oil or grease shall be used
it prevent the adhesion of plaster. Centering has to be got approved before laying the
concrete.
Placing Of Reinforcement :
All bars shall be accurately placed in the exact position shown on the drawing or
as directed, care shall be taken that they are not displaced during the process of placing
the concrete around them. Soft wire shall be used for binding the bars.

Measurement And Payment :


The work done shall be measured as specified and paymet shall be made in m3
basis.

Item No.6 Supplying ,cutting, bending & binding , and placing in position steel as
per plan and design and as per ISS 2502 including cost of steel and
binding wires for reservoirs only including lift up to 6.00 mt.
ht.depth below g.l. for all diameters

General :

The item provides for the supply of mild steel bars, cutting, bending, binding
with galvanized iron wire and placing in position for reinforcement in various R.C.C. work.

Materials :
Mild Steel Bars :
Mild steel bar’s reinforcement for R.C.C. work shall conform to I.S. 432- 1966
and shall be of tested quickly. It shall also comply with relevant part of I.S.
4456 – 1964. All the reinforcement shall be clean and free from dirt, oil, paint, grease,
mill scale of loose or thick cast at the time of placing. Substitution of reinforcement
bars shall not be made without the approval of the Engineer-In – Charges. The
reinforcement shall mote the size, shape and spacing as per the drawing issued by the
Engineer-In-Charge.

Reinforcement steel shall be stored such as to avoid distortion and sags of long
length and shall be protected as far as possible from surface deterioration. All bars of
the same designation shall be stacked separately as far as possible and distinctly
marked.
For the purpose of payment the bar shall be measured correct up to 10 mm.
Length and weight payable worked-out.
(1) 6 mm. 0.22 Chg./Rmt. (2) 8 mm. 0.39 Chg./Rmt.
(3) 10 mm. 0.62 Chg./Rmt. (4) 12 mm. 0.89 Chg./Rmt.

80 | P a g e
(5) 14 mm. 1.21 Chg./Rmt. (6) 16 mm. 1.58 Chg./Rmt.
(7) 18 mm. 2.00 Chg./Rmt. (8) 20 mm. 2.47 Chg./Rmt.
High Yield Strength Steel Deformed Bars :

High yield strength steel deformed bars shall be either cold twisted or hot
rolled and shall confirm to I.S.: 1986 – 1966 and IS: 1139 – 1966 respectively or as
revised form time to time. Other provisions and requirements shall confirm to
specification as above for mild steel bars.

Mild Steel Binding Wire :

The mild steel wire shall be of 1.63 mm. or 1.22 mm. (16 or 18 gauge) diameters
and shell conform to IS.: 280 – 1962 or as revised form time to time. The use of black
wire will be permitted for binding reinforcement bars. It shall be free form rest, oil
paint, grease loose will scale or any other undesirable coating which may prevent
adhesion of cement mortar.

Fabrication :

Reinforcing steel shall be thoroughly cleaned of all coatings of any character


that would destroy or reduce the bond. Bending reinforcement shall confirm accurately
to the dimensions and shapes shown on the plans or as directed by The Engineer In
Charge. Bars shall be bent cold to the shape and dimensions shown on the drawings or as
directed by the Engineer in writing. Reinforcing bars shall be bent. in accordance with
procedure specified in IS.: 2502 – 1963. Code of practice for bending and fixing of bars
for concrete reinforcement bar bender may be used to attain proper radius of bends
and shapes. Bars which may bent during transport or handling shall be properly
straightened before being placed in the work without heating them. Bending bar by
heating to cherry red heat, not exceeding 8450 c (about 15000 F) may be allowed for
bars larger than 25 mm. (about 1 inch.) diameter except for bars which depend for their
strength on cold working. Hot bars shall not be cooled by quenching. Details of lengths,
size, laps and bending diagram shall be got approved by The Engineer In Charge.
Substitution Of Bars Size :

In order to accommodate the available size of bars, use of bar sizes other than
those shown on the drawings may be permitted by the Engineer.

Placing & Binding :

All reinforcement shall be accurately placed in position with spacing and cover as
shown in the plan and firmly held so during the placing and setting of concrete. Bars
shall be tied at all intersections. Binding wire of 1.63 mm. or 1.22 mm. (about 16 or 18
gauge) diameter shall be used. Alternatively, spacing of bars shall be maintained by
means of stays, block tiles, spacers hangers or other approved supports at sufficiently
close intervals so that bars will not sag between supports not be displaced during
placing, vibrating or compacting concrete or by any other operation. Layers of bars shall
be separated by precast cement mortar blocks , spacer bars or other approved devices.
Special care shall be taken to prevent any disturbance of the reinforcement after being
placed in position shall be maintained in a clean condition till it is completely embedded in
the concrete.

Item To Include :

81 | P a g e
1 Cost of labour, material, use of tools, plant and tackle and other items to
complete the work include the item specified.
2 Supplying, conveying, cleaning, cutting, bending, binding in position with 1.63 mm.
or 1.22 mm. dia. (16 or 18 gauge.) wire and maintaining, cleaning it and in position
till the concrete is laid.
3 Cost of sampling and testing shall be born by the contractor for entire
satisfaction of Engineer.
Measurement :

The rate shall be on weight basis for 1 kg. / Quintal / M. Ton of M. S. bars
reinforcement. The weight of steel reinforcement incorporated in the concrete, shall be
measured in quintals base, on the total computed weights for the size and lengths of
bars as shown on the plan or ordered by the Engineer. The lengths of the bars shall be
measured correct to two places of decimals in meters and the weight payable would be
worked out on the basis of I.S. standards and shall be correct up to 0.10 Kg.

Item No.7 R.C.C circular spiral stair case with central circular column in M-150
as per type design incl. M.S. reinforcement, centering, curing, form
work and finishing with scaffolding incl. providing and fixing
balusters, hand rails and necessary joints with columns at intervals
of 2.50 m (Work below G.L. for column and footing will be paid
extra) for step of 80 mm. radius and 20 cm. rise.
General :
All the specifications applied as specified in the Item No. 4 & 5 above except
proportion.

In addition to above, the contractor shall have to provide M.S. iron frame for casting
the steps on site having standard dimensions specified in the item and drawing. Item
also include casting , curing, and finishing them as specified in Item No. 15 of this Sub
Estimate No.3
Payment shall be made on No. basis.
Item No.8 Purchasing & supplying at site of works, with railway freight, loading,
unloading, carting, etc. complete such as joints , channels, angles, iron
rails etc. M.S. plate 600 x 600 x 8 mm size.

I. The size and length of the R.S. joints shall be as specified in schedule “B”. or
as directed by the engineer in charge.
II. The steel R.S. joints shall be free from scales, blister, surface flaws,
cracked edge and defects or any sort and shall comply with latest standard
specification for structural steel in all respect.
III. General specification of P.W.D. Hand Book, Volume-1, latest edition shall
be followed as far as possible in this case. Weight calculated on the standard
weight per meter tabulated in hand book for structure.
IV. He ends shall be embedded in cement concrete books after making sufficient
holes in the masonry. The cement concrete for blocks shall be 1:2:4. This shall be
done without any extra cost. It shall be rigidly fixed in the block and that there
is no possibility of the ends being distributed sue to specified coming on the
gurder.
82 | P a g e
V. The gurder shall be tested for load, vibrations etc. after they are fixed as
directed by the engineer in charge without claiming any extra cost.
VI. Payment shall be as per Qtl. basis.

Item No.9 Labour charges for lowering, laying , fixing various size of
M.S.section such as joints , channels, angles, plates etc. comp.
M.S. rails 600 x 600 x 8 mm size.

Cutting holding assembling, painting, erection and fixing in concrete shall be


carried out in accordance and as directed by the engineer. The payment shall be made as
per Qtl. basis for job work.

Item NO.10 Brick work using common burnt clay building brick having crushing
strength not less than 35 kg/sq.cm. in foundation and plinth in
cement mortar 1:6 (1 Cement : 6 Fine sand)

Conventional

General:

Before starting the brick work, The contractor shall have to clear the
foundation , remove dirt’s, clods or any type of foreign matter from foundation , level
the base and got approved form The Engineer in charge.

All materials required for the brick work shall be present on the site. Required
strength of labours shall also be present.

Materials:

Bricks:

The bricks shall be of information size (9” x 4.5” x 2.5) unless otherwise
specified and thoroughly well burnt and sound ringing clearly when struck with a trowel
comply with all the requirements specified in I.S.: 1077 – 1976 or it’s latest revision
having crushing strength not less than 35 kg/cm2. The average water absorption shall
not be more than 20% by weight. No difficulty shall Aries on this account in laying of
uniform course of layers.

Fine Aggregate:

Natural sand or sand prepared from crushed stone, gravels, or such other inert
materials conforming to I.S.: 383 – 1963 or I.S.: 515 – 1959 or it’s latest revisions. And
also conform to I.S.: 2116 – 1965 or it’s latest revisions. The fineness modules shall not
exceed 3.00.

Cement :
The cement used shall be ordinary Portland cement or rapid hardening Portland
cement conforming to I.S..:269-1958 or Portland pozzolone cement conforming to
I.S.:1489-1976 or high alumna cement of approved specifications.

Water:

Water used for both mixing and curing shall be free from injurious amount of
deleterious materials. Potable waters are generally considered satisfactory for mixing
83 | P a g e
and curing concrete. In case of doubt, the suitability of water for mixing concrete shall
be ascertained in accordance with I.S.: 516-1959 and I.S.: 4031-1968. The “pH” value of
water shall generally be between 6 to 8.

Storage Of Materials:

All materials shall be so stored as to prevent deterioration or intrusion of


foreign matter and to ensure the preservation of their quality and fitness for the work.
Any material, which has deteriorated or has been damaged or is otherwise considered
defective by The Engineer in charge, shall not be used for the concrete.

Mortar:

The proportion of mortar shall be as specified in Schedule “B”. I.e. one part of
cement and size part of fine aggregates, thoroughly dry mixed on platform before
adding water. The mix shall be prepared in such quantity , that it will be used within
half-hour before setting time of cement.

Soaking:

The bricks shall be properly soaked in water before they are put into the work
at least 12 hours.

Laying:

The bricks shall be laid flushed in mortar in such bond to avoid joints in same line
and as may be directed, and shall be thoroughly grouted. The whole work executed in a
good and workman like manner.

Work shall be carried up regularly in all cases, when the nature of the work will
admit it Not leveling any part 8’-o” lower then another but when circum’s angles render
if necessary to carry on the same section of a building at different levels, the breaks
shall be stepped so as to give batter and uniform level and an effectual bond. All
necessary scaffolding shall be provided by the contractor.

Face Work:

As far as practicable brick of a uniform color are to be selected for the face
work.

Joints:

The bricks shall be laid in leveled layers, and in required English bond to prevent
displacement of joints as directed by The Engineer in charge. The bed-joints shall not
exceed 0.5” thick.

Bats:

No bats or half bricks shall be used in the work unless absolutely necessary as
closer.
Curing:
The masonry be kept well wetted , while in progress and for at least 10 days
after completion.
Finishing:

84 | P a g e
All the brick work shall be washed down on completion and al stains removed
from the face. and also all rubbish shall be removed by the contractor, unsightly holes
or pits leveled up and the whole surrounding of the work left neat and clean.
Measurement And Payment:
The brick work shall be measured in unit specified in schedule B. Payment shall
be made according to measurements.
Item No.11 Providing 15 mm thick cement plaster in single coat on brick concrete
walls for interior plastering up to floor two level and finished even
and smooth in Cement Mortar 1:3 (1 Cement : 3 Sand) including
finishing with floating coat of neat cement slurry.

General :

This specification lay down the requirement of cement plaster to be applied on


concrete, stone or brick masonry surface in cement mortar of specified proportion and
thickness. The work shall conform to IS: 1661-1960.
Materials :

The materials required for brick work, such as brick , sand, cement, water etc.
shall conform the I.S. & specifications specified in Specifications for the materials
required in the item shall be specified as under.
Cement Mortar :

Cement mortar shall have the proportion of cement to sand as mentioned in the
working of the item or in special provisions and shall comply with item No.3 above for
cement mortar for plaster.
Preparatory Work :
Smooth surface of concrete old plaster etc. must suitably roughened to provide
necessary bond for the plaster. The exposed materials of concrete shall be removed by
using chisel and make plain leveled surface, all dirt, soot oil paint or any other material
that might interface with satisfactory bond shall be removed.
While preparation of cement mortar of specified proportion as per Item
description, the approved quality water proofing compound at the rate of 1.00 Kg. per
one bag of cement or as per manufactures instructions shall be added in the mortar
while mixing in dry condition. The contractor shall bring the water, proofing compound to
the site in it’s original packing, and shall be got approved by The Engineer-In-Charge.
Plastering :
In all plaster work the mortar shall be firmly applied with some what more than
the required thickness and well pressed into the joints and on the surface and rubbed
and leveled with a flat wooden rule to give required thickness. Long straight edges shall
be freely used to ensure a perfectly plane and even surface. All corners shall be finished
to their true angles or rounded as directed by The Engineer. The surface shall be
finished to plane or curved surface as shown on the plan or as directed by the Engineer
and shall present a neat appearance.
The mortar shall adhere to the masonry / concrete surface intimately when set
and there should be no hollow sound when struck. Cement plastering shall be done. in
square or strips as directed , plastering shall be done from top to down ward.

Finishing :

85 | P a g e
In any continuous face of a wall, finishing treatment of any type shall be carried
out continuously and day to day breaks made to coincide with architectural breaks in
order to avoid unsightly junctions.

Watering :

All plasterwork shall be kept damp continuously for a period of 14 days. To


prevent excessive evaporation on the sunny of or windward side of the buildings in hot,
dry weather matting or gunny bags may be hung over on the outside of the plaster in the
beginning and kept moist.

Item To Include :

1. Erecting, dismantling and removing the scaffolding as and when necessary.


2. Preparing the surface to receive the plaster.
3. Providing cement plaster of the specified average thickness with specified
number of costs.
4. All labour , material, use of tools, and equipment to complete the plastering as
per specifications.
5. Curing for 14 days.
Any molding work, if shown on the drawings or as specified unless separately
provided in the tender.

Measurement And Payment :

The contact rate shall be per square meter of plastering of specified thickness. All work
shall be measured in square meters. Dimensions shall be measured and quantity worked
out correct up to two places of decimals in square meter and paid at accordingly.

Item No.12 Providing and fixing M.S.Grills of required pattern to wooden frames
of window etc. (Iron doors, window) with M.S.frame alround square
or round bars with round bolts and nuts or by screw Plan Grill.

General:

The steel doors, windows and cupboards in building shall conform the Indian
Standard Specifications No. 1038 – 1975 or it’s latest revision.

Structural Steel:

The structural steel such as angles, tees, girders, plates , channels etc. Conform
relevant IS. as under.

* IS : 226 – 1962 Structural steel third revision.

* IS : 961 – 1962 High tensile Structural steel revision.

* St 44 – 0 or IS :1977 – 1962 Structural steel ordinary.

* IS : 2062 – 1962 Structural steel Fusion Welding Quality.

Revit Steel:

All rivet steel used in general building construction work shall comply with
appropriate Indian Standard specification as under.

• I.S. : 1148 – 1957 Rivet bars for structural purpose.

86 | P a g e
• I.S. : 1149 – 1957 High tensile Rivet bars for structural purpose steel.
Bolts And Nuts:

All bolts and nuts shall conform to IS : 1367 – 1961 Technical supply condition
for threaded fasteners, and IS: 1608 – 1960 for tensile testing of steel products. The
threaded fasteners shall have a tensile strength not less than 44 kg/cm2 and a million
elongation of 23% on engage length of 5.65

Electrodes:

Mild steel electrodes shall comply with the requirements of IS: 814 – 1957
specification for covered electrodes for Metal Arc Welding of mild steel. High tensile
steel electrode shall comply with the requirements of IS: 1442 – 1959 specification for
covered electrodes for Metal Arc Welding of high tensile structural steel.

Standard Dimensions , Form And Weight:

The dimensions, Form, Weight, tolerance of all rolled shapes and other members
used in any structure shall, when ever possible , conform to the latest appropriate
Indian Standards, wherever available.

The dimensions, Form, Weight, tolerance of all rivets, bolts, nuts, studs, etc.
shall conform to the requirements of latest appropriate Indian Standards, wherever
available.

Manufacturing:

The frames, both fixed and opening frames shall be constructs of sections,
which have been cut to length and miters. The corners shall be electrically flush welded
to form a solid and true right angle. The type of window and door shall be as shown in
drawing or as directed by The Engineer in charge.

Finishing:

The joints of doors and windows frames with masonry or concrete shall be
finished neatly with cement mortar and niru.

Oil Paint:

The doors, windows , which are not dip Zinc coated shall be finished with two
coats of oil paint of approved quality and shade on a primer coat of red lead. The
contractor shall have to provided oil paint of recognizes and reputed company with
required shade as approved and instructed by The Engineer in charge.

Measurement And Payment:

The measurement shall be taken as per unit shall be made according to


measurement.

Item No.13 Applying any approve quality of cement paint in three coats including
cleaning washing etc. complete for ESR Only.

General:

Snowcem paint shall confirm to I.S. 427 – 1953 and I.S. 428 – 1953 or its latest
revision. It shall be oil bond, washable, and of desired color and shade. The sample shall

87 | P a g e
be got approved before use. It shall be of approved brand and manufacture. All
instructions as given by the manufacture shall be obeyed, while using the same.

The item refers to providing and applying washable Snowcem Paint or washable
oil bond Snowcem. Paint as specified in item in one, two, or three coats as specified to
surface. The work shall be carried out as per I.: 6278 – 1971 or its latest revision.

Scaffolding :

This shall be as per specification narrated in as per Engineer-In-Charge.

Preparation of surface :

The surface to be Snowcem Painted shall be cleaned and all crack, holes and
surface defects shall be repaired with gypsum and allowed to set hard. All irregularities
shall be sand papered and wiped clean. The surface so prepared must be dry and free
from dust before Snowcem Painting is commenced.

Application:

Priming Coat :

The priming coat shall be applied over in the manner recommended by the
makers in case of patent Snowcem Paint. When no priming coat is specified by the
manufacturer, a finely powered chalk mixed with a thin solution of glue be applied to
prepared a good, hard background.

Snowcem Paint :

Snowcem Painting shall not be mixed in a larger quantity than is actually required
for a day’s work. Hot water shall be used for preparing mixture. Snowcem Paint shall be
applied with a broad stiff brush in long parallel strokes. The treated surface shall be
allowed to dry and harden. The next coat of Snowcem Paint shall be laid on in exactly
the same manner as the first one. The brushes used should never be allowed to rest on
the bristle and after the use they should be carefully and thoroughly cleaned. Atleast
two coats of Snowcem Paint on priming coat shall be applied.

Measurement:

The contract rate shall be per square meter of area, where Snowcem Paint is applied.
The measurements shall be taken as per P.W.D. manual and as per IS 1200 – 1976 (Part
XIII).

Item No.14 Filling available excavated earth (excluding rock) in trenches plinth,
sides of foundation etc. in layers not exceeding 20 cm. in depth
consolidating each layer by ramming and watering.
General :

The refilling will generally refer to refilling of foundation or trenches up to


plinth level or ground level with excavated stuff or selected soil or murrum brought
from out side.

Materials :

88 | P a g e
The selected soil, sand or murrum brought from out side shall be cleared of all
rubbish large size stones, brickbats, big clods etc. And shall be got approved before
filling.

Refilling :

Refilling shall be done in a systematic manner by the contractor , before


refilling starts, the contractor shall got checked the foundation / trenches ready for
refilling.

All space between foundation masonry, concrete , pipe line and the sides of
excavation and / or bottom of foundation shall be refilled to the original surface or up
to plinth level with earth or selected materials in layers of 15cm. to 20 cm. well watered
and rammed. Each layer shall be well watered and compacted with heavy rammers before
the upper layer is laid, till the final level reached to form a thoroughly compacted base.

Measurement And Payment :

The measurement shall be taken for total volume filled up. It includes loading,
unloading, carting, breaking clods etc. It also includes the cost of bringing selected
materials from out side as directed by The Engineer in charge. The payment shall be
made according to refilled volume measured in Cubic meter.

Item No.15 Providing and laying cement concrete flooring 1:2:4 (1 Cement : 2
coarse sand : 4 graded stone aggregate 20 mm nominal size) and laid
in one layer finished with a floating coat of neat cement. 50 mm.
Thick.

General :

All the specification applied as specified in the Item No. 2, & 7 of this Estimate
above including aggregate except proportion, laying and finishing , as specified below.

Laying :

Before laying the concrete , the sub-grade shall be passed by The Engineer in
charge. The sub-grade shall be formed to proper levels and slopes well compacted and
cured.

The surface of sub-grade shall be cleaned of all loose materials and moistened
immediately before laying the concrete floor. The flooring shall be laid in alternative
bags not exceeding 6 Sq.mts. each. The edges of each panel into which the floor is
divided shall be supported by flat bars of steel or wood duly oiled to prevent sticking.
The thickness of floor shall be as specified in the item the supporting bars shall
removed before filling in jointing panel.

Finishing :

When the rendering is some what stiff , neat cement may be sprinkled on the
surface and rubbed lightly to give smooth polished ordinary cement colored surface.

Curing :

89 | P a g e
Curing shall start on the next day after finishing and shall continued for 14 days.

Mode Of Measurement And Payment :

The rate shall be per square meter of the flooring thickness as specified in item the
linear measurement shall be measured between plastered walls of square meter and paid
accordingly.

Item No.16 Providing & fixing 50 cm. wide M.S. ladder fabricated from M.S.
Flats 10mm x 60 mm with 20 mm. dia. steel bar steps @ 30 cm.
C/C. The item include stays of 10 mm. x 60 mm. flats fixed at 3
meter C/C.

Material And Dimension :

Stringers :

Structural steel flat or angle sections conforming to I.S. 226 – 1975 and I.S.
straight and shall be free from loose mill scales, rush pits or other defects affecting
strength and durability. Stringers shall be kept 45 cms. or 50 cms. apart clearly
between the inner edges of the stringers and shall extend atleast 75 cms. above the top
of the tank with the curved top. The size shall be taken as specified in the item.

Step :

Mild steel bars conforming to I.S. 432 – 1960 or its latest revisions shall be
clean and free from dirt, oil paints, grease, mill scales, rust. Steps shall be placed at 25
cms. or 30 cms. center to center.

Stays :

As specified in the item above. Stays shall be provided at 3 meters interval and
stays shall be of adequate length with at least 15 cms. bearing in the walls of the
container and as directed by The Engineer in charge.

Rivet Bars :

Rivet bars shall conform to I.S. 1148 – 1957 or its latest revision. Welding is to
be done instead of the rivet bars for oxyacetylene welding in structural steel work,
filler roads shall conform to I.S. 1278 – 1972 or its latest revision and shall be free
from oxidation and shall be in a clean condition.

Size & Dimension :

Size: Stingrays Flat Sections 60 x 10 mm.

Angle Sections 40 x 40 x 5 mm.

65 x 65 x 6 mm.

Step Single bar 20 mm. dia.

Double bars 13 mm. dia.

Stays Flat 50 x 10 mm.

Fabrication :
90 | P a g e
Fabrication work shall be done in the approved method and of the best
workmanship. The shape of the ladder.

Shall conform to the to the drawings or as ordered by The Engineer in Charge.


Fabrication work shall be done at the site of work. If done at the supplier’s workshop, it
shall have to be transported at the works-site.

Anticorrosive Painting :

The ladder shall be painted with a case cost or red lead and two coats of good
anticorrosive oil paints of approved shade.

Oil Paint :

During the transportation, handling and fixing the ladder, the oil painting to the
ladder is damaged in any way, it shall have to be remade by the contractor at his own
cost. The materials of oil paints shall conform to relevant I.S. of the specification of
the materials and shall be supplied by the contractor at his own cost.

Fixing :

The whole ladder shall be clean off the foreign matter such as dirt, dust , grit,
mud, etc. and shall be so placed in side the tank as to keep the curved top of the
stringers at least 750 mm. above the top of the tank. The last step shall be 300 mm.
below the top of the tank. The stringers after the curve shall extend up to the top of
the tank.

The lower end of the ladder with hold fast of at least 100 mm. long shall be
embedded into a block of 1:2:4 cement concrete 600 x 600 x 600 mm.

Item To Include :

The contractor shall supply all necessary labour, material, use of tools and
equipment necessary for the satisfactory completion of the item.

Mode Of Measurement & Payment :

The contractor rate shall be for one meter length of the ladder. The length shall
be measured from the ground or floor along the ladder up to the top of the tank correct
up to 50 mm. If any damage is found or observed to the adjoining structure already
constructed while fixing the ladder, it shall be remade good by the contractor at his own
cost as per instructions of The Engineer in Charge.

Item No.17: Gunniting the surface in C.M. 1:2 having thickness of 40mm to 50mm for
beam, braces, column and container slab incl. chiseling and scraping loose concrete
cleaning the surface with water and air under pressure and including providing and fixing
in position steel wire square mesh 75 x 75mm as per IS 1966 – 1982 3.15mm Wt./Sqmt.
1.64 Kg. with spot welding where ever necessary with main reinforcement incl. tying
binding with wire incl. scaffolding centering staging all equipment and materials etc.
complete incl. labour and testing of the container.
General:

91 | P a g e
Specification cover the requirement of ordinary or controlled cement concrete
of specified proportions for plain and cement concrete works. Special requirement for
particulars, item shall be laid down in the specifications as per I.S.:456-1979. For
deviation laid down in the specifications for liquid retaining structure, narrated in
I.S.:3370-1971 shall apply.
Materials:
Specifications for the materials required in the item shall be specified as under.
Fine:
The sand shall comply all general requirements of fine aggregates as specified in
I. S.: 383-1970 or it’s latest revision. Sand shall be natural sand, durable and gritty
particles free form injuries amounts of dust, clay, kankar modules of or flaky particles,
shale alkali, salts organic matter loam, mica or other deleterious substances and shall be
got approved form The Engineer in Charge. Sand to be used for concrete work shall be
of grades as a specified in I. S.: 383-1970 with module varying from 1.4 to 2.6 as per
requirements fineness. The sand shall be stacked carefully on a clear hard surface. and
got approved for quality form The Engineer In Charge.
Cement:
The cement used shall be ordinary Portland cement or rapid hardening Portland
cement conforming to I.S.:269-1958 or Portland pozzolone cement conforming to
I.S.:1489-1976 or high alumna cement of approved specifications.
Water:
Water used for both mixing and curing shall be free from injurious amount of
deleterious materials. Potable waters are generally considered satisfactory for mixing
and curing concrete. In case of doubt, the suitability of water for making concrete shall
be ascertained in accordance with I. S.: 516-1959 and I.S.:4031-1968. The “pH” value of
water shall generally be between 6 to 8.
Storage of materials:
All materials shall be so stored as to prevent deterioration or intrusion of
foreign matter and to ensure the preservation of their quality and fitness for the work.
Any material, which has deteriorated or has been damaged or is otherwise considered
defective by The Engineer in Charge shall not be used for the concrete.
Grade of concrete:
The concrete shall be in seven grades designated as M100, M150, M200, M250,
M300, M350, and M400. The mix of concrete shall be adopted as specified in the item.
The determination of the proportions of cement, aggregates and water to attain the
required strength shall be made by one of the following.
A) With preliminary tests by designing the concrete mix. Such concrete shall be
called ‘controlled concrete’.

B) Without preliminary tests by adopting nominal concrete mixes. Such concrete


shall be called ‘ordinary concrete’.

As far as possible, controlled concrete should be used on all concrete works the
maximum total quantity of aggregate by weight per 50Kg. Of cement shall not be exceed
450Kg. except where otherwise specifically permitted by The Engineer in Charge.

92 | P a g e
Strength requirements of concrete:
Grade of Compressive strength of 15cm. Cubes after mixing concrete conducted
in accordance with IS : 516 - 1959.
All values in Kg/CM²
At 7 days. At 28 days.
Min. Preliminary Work test
Min. Min.
M100 70 135 100
M150 100 200 150
M200 135 260 200

M250 170 320 250


M300 200 380 300
M350 235 440 350

Scaffolding :
Scaffolding will be double or single as is wanted for the particular work. The end
of poles, if required to be rested on the brick for work shall be located at convenient
place. Scaffolding shall be erected with bullies, steel sections, pipes, or bamboo of
adequate strength as to be safe for all dead, live and impact loads likely to come on
them due to construction operations. The contractor shall take all measures to ensure
the safety of the work and the working persons. The contractor shall be entirely
responsible for any damage to work, property, or injury to persons, resulted from the
scaffolding, defective ladders, and materials, or other problems arising out of any
default in this respect. Proper and sufficient scaffolding shall be provided for easy
approach to the tail of work.
Centering :
The term “Centering” shall include all forms, molds, sheeting, shuttering, planks,
posts, shores, struck, ties, uprights and all other temporary supports to the concrete
during the process of setting. The centering shall be such dimensions and so constructed
as to remain rigid during laying, tempting and setting of concrete. The joints must be
tight so as to prevent leakage. The centering must be arranged, so that the portion
below the slab can be removed first, then the sides of beams and finally that below the
beams.
All debris, saw-dust, etc. shall be removed from the shuttering before any
concrete is placed and should be taken to see that the shuttering is not likely to absorb
water from the concrete laid. On common works, wet the form immediately before
placing the concrete. The forms can also be given a coat of crude oil or grease thinned
with paraffin or soft soap and water or white wash in order to prevent adhesion of
concrete oiling shall be done before the reinforcement is placed in order for prevent
greasing the steel. Where it intended to plaster the concrete, oil or grease shall be used
it prevent the adhesion of plaster. Cantering has to be got approved before laying the
concrete.
Placing of reinforcement:

93 | P a g e
All bars shall be accurately placed in the exact position shown on the drawing or
as directed, care shall be taken that they are not displaced during the process of placing
the concrete around them. Soft wire shall be used for binding the bars.
Mixing of concrete:
The concrete shall be mixed in proportion of Two parts of sand and One part of
cement by volumes as per discretion of Item. The materials for concrete shall be
carefully and accurately measured for every batch. The aggregate and sand shall be
measured by wooden or iron boxes made for the purpose. The mixing shall be carried out
by machine mixture or by hand as directed by The Executive Engineer or his agent. In
case of C.C. higher proportion than 1:5:10 shall be mixed in the mixture only.
Testing:
Testing for strength required of the concrete for R.C.C. E.S.R. work, contractor
shall arrange for taking cube test for preliminary test if required and work test as per
clause 5 of I. S.: 456-1964. Results for the same shall have to be communicated to the
Divisional officer, through and in charge.
Mild Steel Binding Wire
The mild steel wire shall be of 1.63 mm. Or 1.22 mm. (16 or 18 gauge) diameters
and shell conform to IS 280-1962 or as revised from time to time. The use of black wire
will be permitted for binding reinforcement bars. It shall be free from rest, oil paint,
grease loose will scale or any other undesirable coating which may prevent adhesion of
cement mortar.
Fabrication :
Reinforcing steel shall be thoroughly cleaned of all coatings of any character
that would destroy or reduce the bond. Bending reinforcement shall confirm accurately
to the dimensions and shapes shown on the plans or as directed by The Engineer In
Charge. Bars shall be bent cold to the shape and dimensions shown on the drawings or as
directed by the Engineer in writing. Reinforcing bars shall be bent in accordance with
procedure specified in IS 2502-1963. Code of practice for bending and fixing of bars
for concrete reinforcement bar bender may be used to attain proper radius of bends
and shapes. Bars which may bent during transport or handling shall be properly
straightened before being placed in the work without heating them. Bending bar by
heating to cherry red heat, not exceeding 845ºc (about 1500ºF) may be allowed for bars
larger than 25 mm. (about 1 inch.) diameter except for bars which depend for their
strength on cold working. Hot bars shall not be cooled by quenching. Details of lengths,
size, laps and bending diagram shall be got approved by The Engineer In Charge.
Substitution of bars size :
In order to accommodate the available size of bars, use of bar sizes other than
those shown on the drawings may be permitted by the Engineer.
Item to include :
1. Cost of labour, material, use of tools, plant, and tackle and other items to complete
the work included under the item specified.
2. Supplying, conveying, cleaning, cutting, bending, binding in position with 1.63 mm. or
1.22 mm. dia. (16 or 18 gauge) wire and maintaining, cleaning it and in position till the
concrete is laid.

94 | P a g e
3. Cost of sampling and testing shall be borne by the contractor for entire satisfaction
of Engineer.
Measurement :
The rate shall be made on amount of work measured per square meter basis.

Missing Link
PARIEJ REGIONAL WATER SUPPLY SCHEME

95 | P a g e
TA. MATAR, TARAPUR, SOJITRA DIST. KHEDA
Constructing of new Pump house, Repairing of Pump house of different
places & compound wall
Sub Estimate No. 4

Item No.1 Excavation for foundation up to 1.5 mt. depth including sorting out
and stacking of useful materials and disposing of the excavated stuff
up to 50 m. lead. In loose or soft soil.

General:
This specification same as per this Sub-Estimate Item No.1, Item No.11

Item No.2 Providing and laying cement concrete 1:3:6 (1 cement: 3: courser
sand : 6 hand broken) stone aggregate 40 mm nominal size) and
curing etc. comp. excluding cost of form work in foundation and
plinth.
General :
Specification cover the requirement of ordinary or controlled cement concrete
of specified proportion for plain and cement concrete works. Specials requirement for a
particulars, item shall be laid down in the specifications as per I.S. 456-1979. For
deviation laid down in the specifications for liquid retaining structure, narrated in I.S. :
3370-1971 shall apply.
Materials :
Specifications for the materials required in the item shall be specified as under.
Aggregate :
Two types of aggregates shall be used in the concrete work described as under.
3. COURSE:
Course aggregate of black trap stone conform all general requirements specified
in I.S.:383-1970 or it’s latest revision. Course aggregate shall be of machine crushed
stone of free in skin and coating likely to prevent proper adhesion of mortar. It shall be
free form injuries amount of disinfected stone, soft, faulty or elongated particles, salt ,
alkali, vegetable table matters and others deleterious substances. In the case of
reinforced cement concrete the maximum limit may be restricted to 6mm. Less than the
minimum lateral clear distance between bars or 6mm. less than the cover whichever is
smaller. The percentage may be varied some what by the Engineer in charge when
considered necessary for obtaining better density and strength of concrete. The
grading test shall be taken in the beginning and at the change of course materials. The
necessary test indicated in various I.S. shall have to be carried out to ensure the
acceptability.
4. FINE:
The sand shall comply all general requirements of fine aggregates as specified in
I.S. 383-1970 or it’s latest revision. Sand shall be natural sand,durable and gritty
particles free form injuries amount of dust, clay, kankar modules of or flaky particles,
shale , alkali, salts, organic matter loam ,mica or other deleterious substances and shall
be got approved form The Engineer in charge as a specified in I.S..:383-1970 with
module varying form 1.4 to 2.6 as per requirements fitness. The sand shall be stacked

96 | P a g e
carefully on a clear hard surface. and got approved for quality form The Engineer In
charge.
CEMENT
The cement used shall be ordinary Portland cement or rapid hardening Portland
cement conforming to I.S..:269-1958 or Portland pozzolone cement conforming to
I.S.:1489-1976 or high alumna cement of approved specifications.
WATER:
Water used for both mixing and curing shall be free from injurious amount of
deleterious materials. Potable waters are generally considered satisfactory for mixing
and curing concrete. In case of doubt, the suitability of water for mixing concrete shall
be ascertained in accordance with I.S.: 516-1959 and I.S.: 4031-1968. The “pH” value of
water shall generally be between 6 to 8.
Storage Of Materials :
All materials shall be so stored as to prevent deterioration or intrusion of
foreign matter and to ensure the preservation of their quality and fitness for the work.
Any material, which has deteriorated or has been damaged or is otherwise considered
defective by The Engineer in charge shall not be used for the concrete.
Grade Of Concrete :
The concrete shall be in seven grades designated as M100, M150, M250, M350,
and M400. The mix of concrete shall be adopted as specified in the item. The
determination of the proportions of cement, aggregates and water to attain the
required strength shall be made by one of the following.
C) With preliminary tests by designing the, concrete mix.. Such concrete shall
be called. ‘controlled concrete.
D) Without preliminary tests by adopting nominal concrete mixes. Such
concrete shall be called ‘ordinary concrete.
As far as possible, controlled concrete should be used on all concrete works the
maximum total quantity of aggregate by weight per 50kg. of cement shall not be exceed
450kg. except where otherwise specifically permitted by The Engineer in charge any
extra cost. Cement and sand shall be first mixed dry then aggregate added, and whole
furred-over three times dry and then turned over four times wet. Measured quantity of
water shall be applied through a rose. A fairly wet mixture shall be used.
Laying :
Before starting the concrete work, The contractor shall have to clear the
foundation, remove dirt’s, clods, or any type of foreign matter from pit, level the pit,
and got approved form The Engineer in charge.
The concrete shall be placed in to it’s final position, compacted and finished
within 30 minutes of mixing the water and before setting commences and should not be
subsequently disturbed. The method of placing shall be such as to avoid segregation and
balanced load on formwork. The concrete shall be deposited in continuous horizontal
layer, not exceed 30 cm. in thickness. As far as possible, the joints should be avoided in
the concrete work. Unless and otherwise shall be made only where mentioned in the
plans or approved by The Engineer In Charge. The concrete shall be thoroughly complete
compacted during the operation by means of tools and/or mechanical vibrator as
directed by The Engineer In Charge.

Curing :
97 | P a g e
Curing shall be done by creating compartments, using lime/mud-sand mixtures, it
shall be done for minimum 21 days.
Finishing :
All exposed faces of the concrete shall be finished with C.M. 1:2 and neat
finishing without claiming any extra cost.
Testing :
Testing for strength required of the concrete for R.C.C. E.S.R. work, contractor
shall arrange for taking cube test for preliminary test if required and work test as per
Strength Requirement Of Concrete :

Grade of Compressive Strength of 15 cm. Cubes after


mixing conducted concrete in accordance with IS : 516
---1959 All values in Kg/CM2 Preliminary At 28 days.
At 7 days. Work test
Min. Min.
Min.

M100 70 135 100


M150 100 200 150

M200 135 260 200


M250 170 320 250

M300 200 380 300


M350 235 440 350

Mixing Of Concrete :

The concrete shall be mixed in proportion of Six parts of aggregate, Three


parts of sand and One part of cement by volumes as per discretion of Item. The
materials for concrete shall be carefully and accurately measured for every batch. The
aggregate and sand shall be measured by wooden or iron boxes made for the purposed.
The mixing shall be carried out by machine mixture or by hand as directed by The
Executive Engineer or his agent. In case of C.C. higher proportion than 1:5:10 shall be
mixed in the mixture only.

Machine Mixing :

The quantity of materials mixed should not exceed the rated capacity of the
machine. After all the materials are loaded into drum the concrete shall be mixed until
it is uniform in color and consistency but for not more than 1.5 to 2 minutes. About 15 to
18 revolutions per minute are generally considered sufficient.

Hand Mixing :

To be done on a clean paved area or water tight platform at least 2 m. x 4 m. or


a 3 meter square with strips fastened along three sides to prevent the materials being
washed or shoveled off during mixing. Additional 10 percent cement over and above the
specified proportion shall be used when hand mixing is resorted to, without claiming
clause 5 of I.S.: 456-1964. Results for the same shall have to be communicated to the
Divisional officer , through and in charge.

Measurements And Payment :

98 | P a g e
The measurements for work done only shall be taken as per Item’s units
specified in the “Schedule B”. 90% payment shall be made till the satisfactory results
are obtained for the sample cubes taken from and visual test on site. 10% amount will be
withheld from each item which are meant to require finishing.
Item No.3 Brick work using common burnt clay building brick having crushing
strength not less than 35 kg/sq.cm. in foundation and plinth in
cement mortar 1:6 (1 Cement : 6 Fine sand)

Conventional

General:

Before starting the brick work, The contractor shall have to clear the
foundation , remove dirt’s, clods or any type of foreign matter from foundation , level
the base and got approved form The Engineer in charge.

All materials required for the brick work shall be present on the site. Required
strength of labours shall also be present.

Materials:
Bricks:
The bricks shall be of information size (9” x 4.5” x 2.5) unless otherwise
specified and thoroughly well burnt and sound ringing clearly when struck with a trowel
comply with all the requirements specified in I.S.: 1077 – 1976 or it’s latest revision
having crushing strength not less than 35 kg/cm2. The average water absorption shall
not be more than 20% by weight. No difficulty shall Aries on this account in laying of
uniform course of layers.

Fine Aggregate:

Natural sand or sand prepared from crushed stone, gravels, or such other inert
materials conforming to I.S.: 383 – 1963 or I.S.: 515 – 1959 or it’s latest revisions. And
also conform to I.S.: 2116 – 1965 or it’s latest revisions. The fineness modules shall not
exceed 3.00.

Cement :
The cement used shall be ordinary Portland cement or rapid hardening Portland
cement conforming to I.S..:269-1958 or Portland pozzolone cement conforming to
I.S.:1489-1976 or high alumna cement of approved specifications.

Water:

Water used for both mixing and curing shall be free from injurious amount of
deleterious materials. Potable waters are generally considered satisfactory for mixing
and curing concrete. In case of doubt, the suitability of water for mixing concrete shall
be ascertained in accordance with I.S.: 516-1959 and I.S.: 4031-1968. The “pH” value of
water shall generally be between 6 to 8.

Storage Of Materials:

All materials shall be so stored as to prevent deterioration or intrusion of


foreign matter and to ensure the preservation of their quality and fitness for the work.
Any material, which has deteriorated or has been damaged or is otherwise considered
defective by The Engineer in charge, shall not be used for the concrete.

99 | P a g e
Mortar:

The proportion of mortar shall be as specified in Schedule “B”. I.e. one part of
cement and size part of fine aggregates, thoroughly dry mixed on platform before
adding water. The mix shall be prepared in such quantity , that it will be used within
half-hour before setting time of cement.

Soaking:
The bricks shall be properly soaked in water before they are put into the work
at least 12 hours.
Laying:
The bricks shall be laid flushed in mortar in such bond to avoid joints in same line
and as may be directed, and shall be thoroughly grouted. The whole work executed in a
good and workman like manner.
Work shall be carried up regularly in all cases, when the nature of the work will
admit it Not leveling any part 8’-o” lower then another but when circum’s angles render
if necessary to carry on the same section of a building at different levels, the breaks
shall be stepped so as to give batter and uniform level and an effectual bond. All
necessary scaffolding shall be provided by the contractor.
Face Work:
As far as practicable brick of a uniform color are to be selected for the face
work.
Joints:
The bricks shall be laid in leveled layers, and in required English bond to prevent
displacement of joints as directed by The Engineer in charge. The bed-joints shall not
exceed 0.5” thick.
Bats:
No bats or half bricks shall be used in the work unless absolutely necessary as
closer.
Curing:
The masonry be kept well wetted , while in progress and for at least 10 days
after completion.
Finishing:
All the brick work shall be washed down on completion and al stains removed
from the face. and also all rubbish shall be removed by the contractor, unsightly holes
or pits leveled up and the whole surrounding of the work left neat and clean.
Measurement And Payment:
The brick work shall be measured in unit specified in schedule B. Payment shall
be made according to measurements.
Item No.4 Filling available excavated earth (Excluding rock in trenches plinth
sides of foundation of etc. in laid not exceed 20 cm in depth
consolidating each disposing it layer by ramming and watering.

General :

This specification same as per this Sub-Estimate- 1, Item No.13

100 | P a g e
Item No.5 Brick work using common burnt clay building brick having crushing
strength not less than 35 kg/sq.cm. in foundation and plinth in
cement mortar 1:6 (1 Cement : 6 Fine sand)

Conventional including extra for super structure above plinth level up


to floor two leve.

General :

This specification same as per this Estimate , Item No.3

Item No.6 Providing and fixing M.S. Grills of required pattern to wooden frames
of window etc. with M.S. flats at required spacing and frame all
round square or round bars with round handed bolts and nuts or by
screw Plan Grill

General:

The steel doors, windows and cupboards in building shall conform the Indian
Standard Specifications No. 1038 – 1975 or it’s latest revision.

Structural Steel:

The structural steel such as angles, tees, girders, plates , channels etc. Conform
relevant IS. as under.

* IS : 226 – 1962 Structural steel third revision.

* IS : 961 – 1962 High tensile Structural steel revision.

* St 44 – 0 or IS :1977 – 1962 Structural steel ordinary.

* IS : 2062 – 1962 Structural steel Fusion Welding Quality.

Revit Steel:
All rivet steel used in general building construction work shall comply with
appropriate Indian Standard specification as under.
• I.S. : 1148 – 1957 Rivet bars for structural purpose.
• I.S. : 1149 – 1957 High tensile Rivet bars for structural purpose steel.
Bolts And Nuts:
All bolts and nuts shall conform to IS : 1367 – 1961 Technical supply condition
for threaded fasteners, and IS: 1608 – 1960 for tensile testing of steel products. The
threaded fasteners shall have a tensile strength not less than 44 kg/cm2 and a million
elongation of 23% on engage length of 5.65
Electrodes:
Mild steel electrodes shall comply with the requirements of IS: 814 – 1957
specification for covered electrodes for Metal Arc Welding of mild steel. High tensile
steel electrode shall comply with the requirements of IS: 1442 – 1959 specification for
covered electrodes for Metal Arc Welding of high tensile structural steel
Standard Dimensions , Form And Weight:

The dimensions, Form, Weight, tolerance of all rolled shapes and other members
used in any structure shall, when ever possible , conform to the latest appropriate
Indian Standards, wherever available.

101 | P a g e
The dimensions, Form, Weight, tolerance of all rivets, bolts, nuts, studs, etc.
shall conform to the requirements of latest appropriate Indian Standards, wherever
available.

Manufacturing:

The frames, both fixed and opening frames shall be constructs of sections,
which have been cut to length and miters. The corners shall be electrically flush welded
to form a solid and true right angle. The type of window and door shall be as shown in
drawing or as directed by The Engineer in charge.

Finishing:

The joints of doors and windows frames with masonry or concrete shall be
finished neatly with cement mortar and niru.

Oil Paint:

The doors, windows , which are not dip Zinc coated shall be finished with two
coats of oil paint of approved quality and shade on a primer coat of red lead. The
contractor shall have to provided oil paint of recognizes and reputed company with
required shade as approved and instructed by The Engineer in charge.

Measurement And Payment:

The measurement shall be taken as per unit shall be made according to


measurement.

Item No.7 Providing and laying cement concrete 1:2:4 (1 cemnet : 2 course sand : 4
graded 20 mm nominal size and curing comp. excluding cost of form work
and reinforcement for cement concrete. (Coping) payment shall be made
on m3 basis.

Item No.8 Providing and laying ordinary cement concrete 1:2:4 (1 cement :2 coarse
sand :4 graded stone aggregate 20 mm nominal size) for R.C.C. lintel
including finishing smooth with curing etc. comp. including the cost of
from work but excluding the cost of reinforcement. (Lintel) payment
shall be made on m3 basis.

Item No.9 Providing and laying cement concrete 1:2:4 (1 cement :2 coarse sand :4
graded stone aggregate 20 mm nominal size) for reinforced concrete
CHAJJAS not exceeding 10 cm thickness up to floor two level including
finishing the exposed surfaces with cement mortar 1:3 (Chhajja)
payment shall be made on m3 basis.

Item No.10 Providing and laying ordinary cement concrete 1:2:4 (1 cement :2 coarse
sand :4 graded stone aggregate 20 mm nominal size) exposed work with
curing etc. comp. including the cost of form work but excluding the cost
of reinforcement for R.C.C. work in slabs having more than 10 cm and up
to 13 cm. thickness. (Slab) payment shall be made on m3 basis.

102 | P a g e
General :

Specification cover the requirement of ordinary or controlled cement concrete


of specified proportion for plain and cement concrete works. Specials requirement for a
particulars, item shall be laid down in the specifications as per I.S. 456-1979. For
deviation laid down in the specifications for liquid retaining structure, narrated in
I.S.:3370-1971 shall apply.
Materials :

The materials required for brick work, such as brick , sand, cement, water etc.
shall conform the I.S. & specifications specified in Specifications for the materials
required in the item shall be specified as under.
Aggregate :

Two types of aggregates shall be used in the concrete work described as under.

Centering :

The term “Centering” shall include all forms, molds, sheeting, shuttering, planks ,
posts, shores struck , ties, uprights and all other temporary supports to the concrete
during the process of setting. The centering shall be such dimensions and so constructed
as to remain rigid during laying, tempting and setting of concrete. The joints must be
tight so as to prevent leakage. The centering must be arranged, so that the portion
below the slab can be removed first, then the sides of beams and finally that below the
beams.

All debris, saw-dust, etc. shall be removed from the shuttering before any
concrete is placed and should be taken to see that the shuttering is not likely to absorb
water from the concrete laid. On common works, wet the form immediately before
placing the concrete. The forms can also be given a coat of crude oil or grease thinned
with paraffin or soft soap and water or white wash in order to prevent adhesion of
concrete oiling shall be done before the reinforcement is placed in order for prevent
greasing the steel. Where it intended to plaster the concrete, oil or grease shall be used
it prevent the adhesion of plaster. Centering has to be got approved before laying the
concrete.

Item No.11 Providing mild steel reinforcement for R.C.C. work including bending and
binding and placing in position complete up to floor two level.

General :

The item provides for the supply of mild steel bars, cutting, bending, binding
with galvanized iron wire and placing in position for reinforcement in various R.C.C. work.

Materials :
Mild Steel Bars :
Mild steel bar’s reinforcement for R.C.C. work shall conform to I.S. 432- 1966
and shall be of tested quickly. It shall also comply with relevant part of I.S.
4456 – 1964. All the reinforcement shall be clean and free from dirt, oil, paint, grease,
mill scale of loose or thick cast at the time of placing. Substitution of reinforcement
bars shall not be made without the approval of the Engineer-In – Charges. The

103 | P a g e
reinforcement shall mote the size, shape and spacing as per the drawing issued by the
Engineer-In-Charge.

Reinforcement steel shall be stored such as to avoid distortion and sags of long
length and shall be protected as far as possible from surface deterioration. All bars of
the same designation shall be stacked separately as far as possible and distinctly
marked.
For the purpose of payment the bar shall be measured correct up to 10 mm.
Length and weight payable worked-out.

(1) 6 mm. 0.22 Chg./Rmt. (2) 8 mm. 0.39 Chg./Rmt.


(3) 10 mm. 0.62 Chg./Rmt. (4) 12 mm. 0.89 Chg./Rmt.
(5) 14 mm. 1.21 Chg./Rmt. (6) 16 mm. 1.58 Chg./Rmt.
(7) 18 mm. 2.00 Chg./Rmt. (8) 20 mm. 2.47 Chg./Rmt.

High Yield Strength Steel Deformed Bars :

High yield strength steel deformed bars shall be either cold twisted or hot
rolled and shall confirm to I.S.: 1986 – 1966 and IS: 1139 – 1966 respectively or as
revised form time to time. Other provisions and requirements shall confirm to
specification as above for mild steel bars.

Mild Steel Binding Wire :

The mild steel wire shall be of 1.63 mm. or 1.22 mm. (16 or 18 gauge) diameters
and shell conform to IS.: 280 – 1962 or as revised form time to time. The use of black
wire will be permitted for binding reinforcement bars. It shall be free form rest, oil
paint, grease loose will scale or any other undesirable coating which may prevent
adhesion of cement mortar.

Fabrication :

Reinforcing steel shall be thoroughly cleaned of all coatings of any character


that would destroy or reduce the bond. Bending reinforcement shall confirm accurately
to the dimensions and shapes shown on the plans or as directed by The Engineer In
Charge. Bars shall be bent cold to the shape and dimensions shown on the drawings or as
directed by the Engineer in writing. Reinforcing bars shall be bent. in accordance with
procedure specified in IS.: 2502 – 1963. Code of practice for bending and fixing of bars
for concrete reinforcement bar bender may be used to attain proper radius of bends
and shapes. Bars which may bent during transport or handling shall be properly
straightened before being placed in the work without heating them. Bending bar by
heating to cherry red heat, not exceeding 8450 c (about 15000 F) may be allowed for
bars larger than 25 mm. (about 1 inch.) diameter except for bars which depend for their
strength on cold working. Hot bars shall not be cooled by quenching. Details of lengths,
size, laps and bending diagram shall be got approved by The Engineer In Charge.
Substitution Of Bars Size :

In order to accommodate the available size of bars, use of bar sizes other than
those shown on the drawings may be permitted by the Engineer.

104 | P a g e
Placing & Binding :

All reinforcement shall be accurately placed in position with spacing and cover as
shown in the plan and firmly held so during the placing and setting of concrete. Bars
shall be tied at all intersections. Binding wire of 1.63 mm. or 1.22 mm. (about 16 or 18
gauge) diameter shall be used. Alternatively, spacing of bars shall be maintained by
means of stays, block tiles, spacers hangers or other approved supports at sufficiently
close intervals so that bars will not sag between supports not be displaced during
placing, vibrating or compacting concrete or by any other operation. Layers of bars shall
be separated by precast cement mortar blocks , spacer bars or other approved devices.
Special care shall be taken to prevent any disturbance of the reinforcement after being
placed in position shall be maintained in a clean condition till it is completely embedded in
the concrete.

Item To Include :

4 Cost of labour, material, use of tools, plant and tackle and other items to
complete the work include the item specified.
5 Supplying, conveying, cleaning, cutting, bending, binding in position with 1.63
mm. or 1.22 mm. dia. (16 or 18 gauge.) wire and maintaining, cleaning it and in
position till the concrete is laid.
6 Cost of sampling and testing shall be born by the contractor for entire
satisfaction of Engineer.
Measurement :

The rate shall be on weight basis for 1 kg. / Quintal / M. Ton of M. S. bars
reinforcement. The weight of steel reinforcement incorporated in the concrete, shall be
measured in quintals base, on the total computed weights for the size and lengths of
bars as shown on the plan or ordered by the Engineer. The lengths of the bars shall be
measured correct to two places of decimals in meters and the weight payable would be
worked out on the basis of I.S. standards and shall be correct up to 0.10 Kg.
Item No.12 Providing and fixing 25 mm thick shutter for cup board etc. including
anodized aluminum butt hinges with necessary screws, Indian teak wood
including frame fully paneled.

General:

The item covers the requirement of preparation doors, windows, and ventilators with
teak wood frames and panels fully paneled of fully glazed or partly paneled and partly
glazed with all type of fixtures and fastenings and fixing is position.

The timber frame of doors, windows, and ventilators shall conform to I.S. 1976 – or its
latest revision.

The timber paneled and glazed shutters for doors, windows and ventilators shall
conform to I.S. 1003 ( Part I & II ) 1977 and 1966 respectively or their latest revision.

The installation of timber door and windows shall conform to I.S. 4913 – 1968 or its
latest revision.

Materials:

Shutters :-

105 | P a g e
Timber paneled shutters shall be constructed in the form of timber frame work of
stiles and rails with panel inserts of timber, plywood block board particle board
venecred particle board, hand board, or asbestos cement sheet. As specified in the item.

The panel shall be fixed by providing grooves in the stiles and rails. The stiles and rails
shall be joined to each other by mortise and ten on joints at right angles.

All members of the door or window shutters shall be straight without any wrap or bow
and shall have smooth well planed faces at right angels to each other.

Timber panels shall be fixed only with groves but additional beading may be provided
either on one side or both sides as directed.

Stiles and rails of shutters shall be prepared out of one piece only.

Timber paneling the thickness of timber panel shall be as specified in the item. When
made from more than one piece the pieces shall be jointed with a continuous tongued and
grooved joint. Glued together and reinforced with metal dowels the panel shall be
framed into grooves to the full depth of groove, leaving on air space of 1.5mm and faces
shall be closely fitted to the sides of the groove. molding to the edges of panel opening
shall be scribed of the joint the panel shall be so designed that no single panel exceeds
0.5ml. area. Beading may be done as said before.

Plywood paneling.

If specified in the item plywood panels shall be made. They shall be made of plywood not
less than 10mm thickness of two or more panel construction and 12mm thickness for
single panel construction.

Particle board paneling

If specified in the item particle board shall be used for paneling the thickness of board
shall be so far plywood paneling said above. They shall be fitted in grooves as per timber
paneling .

Hard board paneling

If specified hard board shall be use for panels the work shall be carried out as narrated
for particle board paneling.

Asbestos panels

If specified asbestos cement sheet shall be used for paneling the work shall be carried
out as per particle board paneling.

Glass paneling

For glazed window etc. glass paneling shall be provided as specified in the item. The
glass panels of size shown in drawing or as directed shall be embedded in putting and
secured to the rebate by wooden or molding of shape and size approved with brass
counter sunk screws of suitable size.

Fixtures and fastening

All fixture and fastening as per scale laid down in table attached shall be fixed with
appropriate screws in sound manner to ensure case in operation. The shall be appropriate
positioned.

106 | P a g e
M . S. Bard and flats shall be fixed as per drawing and as directed.

Finishing

The joints of the frame with the wall shall be made nearly with pointing or plaster as the
case many be to fit into the groom left in the frame for the purpose. The wood work
shall be finished by French polishing or varnishing or oil painting as mentioned in the
item the varnishing or French polishing shall be done as per item oil painting shall be
done in three coats of approved shade of paint as specified in item WSP 18. The iron
bars if provided shall be finished with two coats of oil paint of approved share as
specified in item no WSP – A – 18 .

The type of wood

Teak wood best quality or any other shall be got approved before work starts.

The sizes of different ports of timber frames and shutters shall be as per respective
I.S.S. or as per drawing or as directed.

The ventilator shall be either hung type or swing type as per drawing or as directed. In
swing type the ventilator shall swing about a central horizontal axis of a pair of brass
pivots in sockets.

The shutter shall be single shutter or double shutter as specified in the item.

The 16mm diameter m. s. bars shall be fixed in ventilator or window or door shutter
frames 10cms c/c. or as per drawing or as directed. The shall be passed through mild
steel flats of 40mm x 6mm size after drilling holes the flats shall be fixed iron screw.

Incase of partly glazed and partly paneled doors and windows, upper for panels shall be
glazed as per drawing or as directed. The steel and rails shall be rebated 10mm wide on
inside to receive the glass sash bars shall be molded on out side and inside rebated
10mm to receive glass.

If specified doors or window with partly ventilated shall be provided with upper part
fixed with ventilators as per drawing or as directed.

The blended shall be 90mm wide and 10mm thick and shall over lap about half their
width. Blades shall be rounded edges or molded. The blades shall be accurately and
securely fixed to the operating stanchion by brass hings the stanchion shall be of
finished size 25 x 20mm and shall be molded.

Then glass louvers are specified in the item they shall be provided of obsecured / wired
glass as mentioned the shall be fixed in grooves cut into the frame wooden beads shall
be screwed.

Measurement

The rate shall be for a unit of one square meter of the clear opening of the door or
window and ventilation when doors are combined with ventilators, the height shall be
measured between the un rebated opening between the sill of the door and the head of
the ventilators and the width between the un rebated opening between the posts. Then
doors are combined with windows they shall be measured separately for their respective
clear un rebated opening. Payment will be made on m2 basis.

107 | P a g e
Item No.13 Providing 15 mm thick cement plaster in single coat on brick concrete
walls for interior plastering up to floor two level and finished even
and smooth in Cement Mortar 1:3 (1 Cement : 3 Sand) including
finishing with floating coat of neat cement slurry.

General :

This specification lay down the requirement of cement plaster to be applied on


concrete, stone or brick masonry surface in cement mortar of specified proportion and
thickness. The work shall conform to IS: 1661-1960.
Materials :

The materials required for brick work, such as brick , sand, cement, water etc.
shall conform the I.S. & specifications specified in Specifications for the materials
required in the item shall be specified as under.
Cement Mortar :

Cement mortar shall have the proportion of cement to sand as mentioned in the
working of the item or in special provisions and shall comply with item No.3 above for
cement mortar for plaster.
Preparatory Work :

Smooth surface of concrete old plaster etc. must suitably roughened to provide
necessary bond for the plaster. The exposed materials of concrete shall be removed by
using chisel and make plain leveled surface, all dirt, soot oil paint or any other material
that might interface with satisfactory bond shall be removed.

While preparation of cement mortar of specified proportion as per Item


description, the approved quality water proofing compound at the rate of 1.00 Kg. per
one bag of cement or as per manufactures instructions shall be added in the mortar
while mixing in dry condition. The contractor shall bring the water, proofing compound to
the site in it’s original packing, and shall be got approved by The Engineer-In-Charge.

Plastering :

In all plaster work the mortar shall be firmly applied with some what more than
the required thickness and well pressed into the joints and on the surface and rubbed
and leveled with a flat wooden rule to give required thickness. Long straight edges shall
be freely used to ensure a perfectly plane and even surface. All corners shall be finished
to their true angles or rounded as directed by The Engineer. The surface shall be
finished to plane or curved surface as shown on the plan or as directed by the Engineer
and shall present a neat appearance.

The mortar shall adhere to the masonry / concrete surface intimately when set
and there should be no hollow sound when struck. Cement plastering shall be done. in
square or strips as directed , plastering shall be done from top to down ward.

Finishing :

In any continuous face of a wall, finishing treatment of any type shall be carried
out continuously and day to day breaks made to coincide with architectural breaks in
order to avoid unsightly junctions.

Watering :

108 | P a g e
All plasterwork shall be kept damp continuously for a period of 14 days. To
prevent excessive evaporation on the sunny of or windward side of the buildings in hot,
dry weather matting or gunny bags may be hung over on the outside of the plaster in the
beginning and kept moist.

Item To Include :

Erecting, dismantling and removing the scaffolding as and when necessary.


Preparing the surface to receive the plaster.
Providing cement plaster of the specified average thickness with specified number of
costs.
All labour , material, use of tools, and equipment to complete the plastering as per
specifications.
Curing for 14 days.
Any molding work, if shown on the drawings or as specified unless separately
provided in the tender.

Measurement And Payment :

The contact rate shall be per square meter of plastering of specified thickness.
All work shall be measured in square meters. Dimensions shall be measured and quantity
worked out correct up to two places of decimals in square meter and paid at accordingly.
Item No.14 Distempering (two coats) with oil bound washable distemper of
approved brand and manufacture and of required shade on wall
surface to give an even shade over and including a primer coat with
alkali resistance primer of approved brand after thoroughly brushing
the surface to give an even shade free from mortar droppings and
other foreign matter and also including preparing the surface even
and smooth.

General :

Distemper shall conform to I.S. 427 – 1953 and I.S. 428-1953 or its latest
revision. It shall be oil bound , washable, and desired color and shade. The sample shall
be got approved before use. It shall be of approved brand and manufacture. All
instructions as given by the manufacturer shall be obeyed, while using the same.

The item refers to providing and applying washable distemper or washable oil
bond distemper as specified in item on one, two or three coats as specified to surface.
The work shall be carried out as per IS. 6278 – 1971 or its latest revision.

Scaffolding :

Scaffolding will be double or single as is wanted for the particular work. The end
of poles, if required to be rested on the brick for work shall be located at convenient
place. Scaffolding shall be erected with bullies, steel sections, pipes, or bamboo of
adequate strength as to be safe for all dead, live and impact loads likely to come on
them due to construction operations. The contractor shall take all measures to ensure
the safety of the work and the working persons. The contractor shall be entirely
responsible for any damage to work, property, or injury to persons, resulted from the
scaffolding, defective ladders, and materials , or other problems arising out of any

109 | P a g e
default in this respect. Proper and sufficient scaffolding shall be provided for easy
approach to the tail of work.

Preparation Of Surface :

The surface to be distempered shall be cleaned and all cracks, holes and surface
defects shall be repaired with gypsum and allowed to set hard. All irregularities shall be
sand papered and wiped clean. The surface so prepared must be dry and free from dust
before distempering is commenced.

For old surface , which has earlier been distempered, the surface shall be
cleaned of grease, dirt’s etc. The flaking of previous coating shall be taken off. In case
surface are colored or white washed, the wash must be removed., thoroughly.
Application :
Priming Coat :
The priming coat shall be applied over in the manner recommended by the
makers in case of patent distempers. When no priming coat is specified by the
manufacturer, a finally powered chalk mixed with a thin solution of glue be applied to
prepared a good , hard background.

Distempering :

Distempering shall not be mixed in a larger quantity than is actually required for
a day’s work. Hot water shall be used for preparing mixture. Distemper shall be applied
with a broad stiff brush in long parallel strokes. The treated surface shall be allowed to
dry and harden. The next coat of distemper shall be laid on in exactly the same manner
as the first one. The brushes used should never be allowed to rest on the bristle and
after the use they should be carefully and thoroughly cleaned.

Measurement :

The contract rate shall be per square meter of area, where oil bound distemper
is applied. The measurements shall be taken as per P.W.D. manual and as per IS 1200-
1976 (Part XIII).

Item No.15 Providing and laying cement concrete 1:3:6 (1 cement: 3: courser
sand : 6 hand broken) stone aggregate 40 mm nominal size) and
curing etc. comp. excluding cost of form work in foundation and
plinth.
General :

This specification same as per above this Estimate , Item No.2

Item No.16 Providing and laying Cement concrete flooring 1:2:4 (1 cement : 2
course sand : 4 graded stone aggregate 20 mm nominal size black
stone laying in one layer finished with floating coat of neat cement
50 mm thick.

General :

All the specification applied as specified in the Item No. 2, & 7 of this Estimate
above including aggregate except proportion, laying and finishing , as specified below.
110 | P a g e
Laying :

Before laying the concrete , the sub-grade shall be passed by The Engineer in
charge. The sub-grade shall be formed to proper levels and slopes well compacted and
cured.

The surface of sub-grade shall be cleaned of all loose materials and moistened
immediately before laying the concrete floor. The flooring shall be laid in alternative
bags not exceeding 6 Sq.mts. each. The edges of each panel into which the floor is
divided shall be supported by flat bars of steel or wood duly oiled to prevent sticking.
The thickness of floor shall be as specified in the item the supporting bars shall
removed before filling in jointing panel.

Finishing :

When the rendering is some what stiff , neat cement may be sprinkled on the
surface and rubbed lightly to give smooth polished ordinary cement colored surface.

Curing :

Curing shall start on the next day after finishing and shall continued for 14 days.

Mode Of Measurement And Payment :

The rate shall be per square meter of the flooring thickness as specified in item the
linear measurement shall be measured between plastered walls of square meter and paid
accordingly.

Item No.17.: Providing and fixing AC soil down take pipe with necessary bends etc.
comp. 75 mm dia.
General:
Materials:
The P.V.C. pipes shall conform to relevant I.S. and it’s latest revision for use as
rain water pipe.
Manufacture:

The standard specification covers the general requirements for materials , size
method of test and inspection of various types of molded/fabricated PVC fitting for
jointing with solvent cement.

The pipes shall be straight and the ends of pipe shall be finished square to their
exist. Inner and outer surface of the pipe shall be truly smooth, sound and practicable
concentric. The pipes shall be marked with manufacturers trademark , size , and date of
manufacture.

Jointing and Fitting:

The pipes and fitting shall be fixed as instructed by The Engineer in Charge. The
fitting and jointing work shall be carried out with full care to avoid any damage to
humans and materials. Item includes the cost of fixing materials like steel clamps,
cement mortar, spun yarn, nails and other required materials.
Measurement & Payment:

111 | P a g e
The measurements for work done shall be taken in running meter, i.e. pipes
fixed, and paid accordingly.
Item No.18 Providing and fixing M.S. fan clamp of shape and size as specified in
existing R.C.C. slab including cutting, fixing and making good.

Work of this item shall be conform the specifications laid down in sub-estimate
no.5 item no.6 for materials and fixing. The place / point for clamp shall be placed in
center of room or as instructed by The Engineer-In-Charge during execution of top slab.
The clamp shall be of suitable size’s M.S.bar in particular shape or ready made suitable
clamp shall be provided and placed by the contractor.
Measurement and Payment :
The payment for this item shallbe made on No. Basises as provided and fixed in
the slab.

Item No.19: Providing light point fitting using 0.12 mm2 copper wire in PVC batten
fitting including all specials, anchor or comet make switches, plug
point, two / three pin combined half point with switching
arrangement, item also includes to provide wiring from GEB fuse to
boards including main switch room fuse and blank sheet with boards
and full earthing arrangements etc.complete.
The work shall be carried out as per instruction given by the engineer in charge.
The material like switch boards, wires plugs holders, Fitting materials shall be got
approved from the engineer in charge first. The plug points shall treated as half point.

Materials:
Wires:
The wires shall be used to standard quality. The copper wires of size 1/18 and
3/20 having standard insulation and brand shall be used in fitting as instructed by the
engineer in charge.
Switch, Plug, Socket, Holder:
The materials of wiring such as switch, plug, sockets, holders main switch, fuse
etc. of standard make and capacity not less than 5 amp. Shall be used in fittings as
instructed by the engineer in charge.
Fitting materials:
PVC conduit pipe or box pipe of specific or required size and strength shall be
used and fixing in copper line, Level and as required for the work in shortest length as
per instructions of the engineer in charge.
Fitting:
The light point fitting work shall be carried out by the contractors as instructed by the
engineer in charge. The points shall be provided as per requirement. Proper fixing of
pipes of battens, wires and other fixtures shall be done. No wire or fitting shall be kept
open. The contractor’s test report for the point wiring carried out.

The measurements shall be taken for total points wiring made. Plug points shall be
measured as half points. The payment shall be made on No. Bases according to
measurements.

112 | P a g e
Item No.20 Purchasing & supplying at site of works with railway freight loading,
unloading, carting etc. comp. such as joints channels, angles iron rails
etc. Comp.

M.S Rails 200 x 100 x 6 mm. size.

VII. The size and length of the R.S. joints shall be as specified in schedule “B”. or
as directed by the engineer in charge.
VIII. The steel R.S. joints shall be free from scales, blister, surface flaws,
cracked edge and defects or any sort and shall comply with latest standard
specification for structural steel in all respect.
IX. General specification of P.W.D. Hand Book, Volume-1, latest edition shall be
followed as far as possible in this case. Weight calculated on the standard
weight per meter tabulated in hand book for structure.
X. He ends shall be embedded in cement concrete books after making sufficient
holes in the masonry. The cement concrete for blocks shall be 1:2:4. This shall
be done without any extra cost. It shall be rigidly fixed in the block and that
there is no possibility of the ends being distributed sue to specified coming on
the gurder.
XI. The gurder shall be tested for load, vibrations etc. after they are fixed as
directed by the engineer in charge without claiming any extra cost.
XII. Payment shall be as specified.

Item No.21 Supplying C.I.Manhole Frame & Cover Light duty weight 50 to 75
kg.wt. for water supply.

General :

Cast iron manhole frames and covers shall confirm to I.S. 1726 – 1974 (Part – I
to VIII) or latest revision of I.S. for cast iron manhole covers and frames intended to
use in drainage and water works.

The details given briefly cover the requirements for materials, dimensions etc.
For cast–iron manhole covers and frames.

Grades & Types :

Heavy duty denoted by the letter H.D. circular solid type for use in heavy
vehicular traffic condition, double triangular solid type may be also be used where 80
desired for their load conditions.

Medium duty denoted by the letter MD solid type for use under light traffic
conditions such as in footpaths and cycle tracks.

Light duty demoted by the letter LD rectangular and square types for use in
domestic promises or other place where they are not subjected to walked traffic loads.

Materials :

Manhole frames and covers shall be of Grey cast iron confirming to the relevant
I.S. as specified in Item.

Workmanship :

113 | P a g e
Frames and shall be clearly cast and they shall be free from air and sand holes
cold shuts and warping which are likely to impair the utility of the castings. Cover shall
have a raised checkered design to provide an adequate non slip grip the rise of the
checker shall be not less than 4 mm. Key holes and keys shall be as indicated in fig. 1
given in I.S. 1726 – Part-I 1974. Looking devices such as galvanized chain or lock, a
combination of both, may be provided if directed.

Coating :

Manhole frame and covers shall be coated with material having base with a block
bituminous composition. The coating shall be smooth and tenacious.

Marking :

Each manhole frame and cover shall have cast on then the following information.

A) Manufacturer’s name or trade mark.


B) Grade donated by abbreviation such as HD, MD or LD.
Dimensions :

Heavy Dut Circular Type :

Dimensions of circular type manhole covers and frame shall be as per table I of
I.S. 1726 (Part – II) 1974 on its latest revision. The standard sizes are 500 mm. dia. 560
mm. dia.

The minimum weights of manhole frame and covers shall be as given below.

Clear opening Weight of Weight of

mm. Frame in Kg. Cover in kg.

500 85 85

560 100 108

Light Duty Rectangular Type :

There shall be two patterns of light as rectangular type manhole covers and
frame as shown in figures in I.S. 1726 – (Part – VI section-1) 1974. This is style seal type
and dimensions of these shall be as table-I and table-II given in I.S. the standard
size is 410 mm. x 455 mm. The minimum weights of manhole frame and covers shall be as
given below.

Cover Weight Frame Weight

Part-I 34 Kg. 15 Kg.

Part-II 15 Kg. 10 Kg.

Measurement And Payment :

The measurement for supply of C.I. manhole frame and cover shall be
taken in weight (mass) bases, and shall be paid accordingly as unit specified in
the schedule “B”.

Item No.22 Fixing all types of C.I. Frame & Cover in CC 1:2:4 including carting etc.
complete. Excluding cost of C.C.

114 | P a g e
General :

The item pertains to fixing all types of C.I. manhole frame and cover whether
rectangular to circular, heavy or lightweight in C.C. 150 of roof slab or on manhole
chamber in water supply and sewerage system. The rate also includes the carting of C.I.
manhole frame and cover from source of supply to the site of work including loading,
unloading, stacking as directed. The contractor shall have to take care for any damage
during transit of materials from store to site.

Materials :

The manhole frame and cover shall be fixed in cement concrete M. 150. The
cement, sand and coarse aggregate for cement concrete M-150 shall comply with the
respective I.S. specification of the materials, and a specified in Item No.2.

Construction :

Manhole frame and cover shall be fixed as per the detailed drawing and as
directed by the Engineer in charge. The surface where the manhole frame is to be fixed
shall be roughened and watered before placing the frame in position. The frame shall be
placed horizontally and cement concrete M-150 shall be laid all around the frame so that
base of the frame shall be covered properly with cement concrete. If possible, the
frame shall be placed in the slab, while concreting. The frame and cover shall be painted
with the bituminous paints in two coats.

Measurement And Payment :

The measurements shall be total number of manholes frame and covers fixed.
The rate shall be paid per number of manhole frame cover of specified type and size
fixed.

Item No.23: Labour charges for lowering, laying , fixing various size of M.S.
section such as joints , channels, angles, plates etc. comp.
M.S. rails 150 x 75 x 6 mm size.
Cutting holding assembling, painting, erection and fixing in concrete shall be
carried out in accordance and as directed by the engineer. The payment shall be made as
specified.

Item No. 24 Filling in plinth and foundation with murrum or selected soil in layers
of 20 cm. thick including watering, ramming and consolidating etc.
comp.
General :

The refilling will generally refer to refilling of foundation or trenches up to


plinth level or ground level with excavated stuff or selected soil or murrum brought
from out side.

Materials :

The selected soil, sand or murrum brought from out side shall be cleared of all
rubbish large size stones, brickbats, big clods etc. And shall be got approved before
filling.

Refilling :

115 | P a g e
Refilling shall be done in a systematic manner by the contractor , before
refilling starts, the contractor shall got checked the foundation / trenches ready for
refilling.

All space between foundation masonry, concrete , pipe line and the sides of
excavation and / or bottom of foundation shall be refilled to the original surface or up
to plinth level with earth or selected materials in layers of 15cm. to 20 cm. well watered
and rammed. Each layer shall be well watered and compacted with heavy rammers before
the upper layer is laid, till the final level reached to form a thoroughly compacted base.

Measurement And Payment :

The measurement shall be taken for total volume filled up. It includes loading,
unloading, carting, breaking clods etc. It also includes the cost of bringing selected
materials from out side as directed by The Engineer in charge. The payment shall be
made according to refilled volume measured in Cubic meter.

After connecting job over , the joint shall be tested for required line pressure
within stipulated time limit as directed by the engineer in charge.

Mode Of Measurement And Payment :

On completion of connection work as per the agreement, shall be measured in No.


base. The payment shall be released as soon as site is cleared to the satisfaction of
engineer in charge.

Item No.25 Demolition of brick work and stone masonry including stacking of
serviceable materials and disposal of unserviceable materials with all
lead and lift. In cement mortar.

The demolition of unserviceable materials for brick work and stone masonry
including stacking of serviceable materials The demolition work shall be carried out up to
excavation level in such a way. So that the demolition

material does not fall inside excavation. The material shall be disposed out side
the working area as per instruction of Engineer-In-Charge. & all lead & lift.

Item No.26 Demolition including stacking of serviceable materials and disposal of


unserviceable materials with all lead and lift. R.C.C. work slab/Beam

Demolition including stacking of serviceable materials and disposal of


unserviceable materials with all lead and lift. R.C.C. work slab/Beam. The material shall
be disposed out side the working area as per instruction of Engineer-In-Charge. & all
lead & lift.

Item No.27 Providing and fixing rolling shutters of approved make made of 80
mm wide M.S. Laths inter-locked together through their entire
length and jointed together at the ends by end locks mounted on
specially designed pipe shaft with bracket plates, guide channels and
arrangements for inside and outside locking with push pull operation
complete including the cost of hood cover and spring etc. comp. @
Pariej H/W store (i) Shutters having width above 3.5 M.

116 | P a g e
Payment shall be made on m2 basis.

Item No.27b Providing and fixing 27.5 cm long wire spring grade no. 2 of approved
make for rolling shutters.
Payment shall be made on No.basis.

Item No.27c Providing and hood cover for rolling shutters (a) shutters having
width 3.5 meters and above. Payment shall be made on m2 basis.

General:

The collapsible steel gate shall be in one or two leaves and size as per approved
drawing or as specified. The gate shall be fabricated from best quality mild steel
channels, flats etc. either steel pulleys or ball bearing shall be provided in every double
channel. Unless otherwise specified the particulars of collapsible gate shall be as under.

( A ) Pickes : - These shall be of 20mm M.S. channel or heavy section unless


otherwise shown on drawings. The distance centre to centre of pickets shall be 12cms.
An opening of 10cms.

( B ) Pivoted MS flats shall be 20 x 6mm.

( C ) Top and bottom guides shall be from tee or flat iron approved size.

( D ) The fittings like stoppers, fixing fold, locking cleats, brass handless and
cast iron rollers shall be of approved design and size.

The rolling shutter shall e of steel and of approved make as design and shall be suitable
for fixing in position ordered i.e. outside inside on or below lintel or between
jambs. The shutter shall be of the manually operated pull or push up type
with ball bearing for easy operation.

The shutter shall be constructed with curud slabs or laths from mild steel sheets of the
specified gauge generally 18/20 gauge. The lathes shall be machine molded
and strengthened with an effective depth of 16mm. These slats shall slide
into one another forming a continues hinge throughout their length and shall
be fitted with alternating end lock side guides and bottom rails shall be
build up from mild steel rolled sections but in the case of small shutters,
they may be of pressed steel. The size of these members shall be as shown
on drawing. The guides shall be generally 6cm.

Rolling spring shall be manufactured from tested unbreakable high tensile tempered
spring steel wire or strip adequate strength to balance the shutter to all
position.

The spring assembly shall be supposed on mild steel or malleable cast iron brakes shaped
to fit the lintel. The shutter when coiled up shall be housed in a bar of 17
gauge sheet metal.

117 | P a g e
Locking arrangement shall be provided of the bottom of the shutter shall be opened
from outside. The shutter shall be complete with door suspension shafts,
locking arrangement, pulling hooks, handles and their accessories.

Measurement shall be taken at the unit specified in schedule B and payment shall
be made accordingly.

Item No.28 Providing and laying cement concrete 1:2:4 (1 cement : 2 course sand
:4 graded stone aggregate 20 mm nominal size) and finishing smooth
with curing etc. comp. including cost of form work but excluding the
cost of reinforcement for reinforced cement concrete work in slab
more than 10 cm. and up to 13 cm. thickness.
General:

The specification shall be same as above Sub-Estimate No.1 Item No.6

Item No.29 Providing and fixing iron door, window & cupboards etc. including
using the frames of channels , angles and flats and M.S.Sheet as
per design include, riveting or welding and fixing in concrete block,
include iron fixtures & fastening with one coat of primer and painting
3 coats.

General:

The steel doors, windows and cupboards in building shall conform the Indian
Standard Specifications No. 1038 – 1975 or it’s latest revision.

Structural Steel:

The structural steel such as angles, tees, girders, plates , channels etc. Conform
relevant IS. as under.

* IS : 226 – 1962 Structural steel third revision.

* IS : 961 – 1962 High tensile Structural steel revision.

* St 44 – 0 or IS :1977 – 1962 Structural steel ordinary.

* IS : 2062 – 1962 Structural steel Fusion Welding Quality.

Revit Steel:

All rivet steel used in general building construction work shall comply with
appropriate Indian Standard specification as under.

• I.S. : 1148 – 1957 Rivet bars for structural purpose.


• I.S. : 1149 – 1957 High tensile Rivet bars for structural purpose steel.
Bolts And Nuts:

All bolts and nuts shall conform to IS : 1367 – 1961 Technical supply condition
for threaded fasteners, and IS: 1608 – 1960 for tensile testing of steel products. The
threaded fasteners shall have a tensile strength not less than 44 kg/cm2 and a million
elongation of 23% on engage length of 5.65

Electrodes:

118 | P a g e
Mild steel electrodes shall comply with the requirements of IS: 814 – 1957
specification for covered electrodes for Metal Arc Welding of mild steel. High tensile
steel electrode shall comply with the requirements of IS: 1442 – 1959 specification for
covered electrodes for Metal Arc Welding of high tensile structural steel.

Standard Dimensions , Form And Weight:

The dimensions, Form, Weight, tolerance of all rolled shapes and other members
used in any structure shall, when ever possible , conform to the latest appropriate
Indian Standards, wherever available.

The dimensions, Form, Weight, tolerance of all rivets, bolts, nuts, studs, etc.
shall conform to the requirements of latest appropriate Indian Standards, wherever
available.

Manufacturing:

The frames, both fixed and opening frames shall be constructs of sections,
which have been cut to length and miters. The corners shall be electrically flush welded
to form a solid and true right angle. The type of window and door shall be as shown in
drawing or as directed by The Engineer in charge.

Finishing:

The joints of doors and windows frames with masonry or concrete shall be
finished neatly with cement mortar and niru.

Oil Paint:

The doors, windows , which are not dip Zinc coated shall be finished with two
coats of oil paint of approved quality and shade on a primer coat of red lead. The
contractor shall have to provided oil paint of recognizes and reputed company with
required shade as approved and instructed by The Engineer in charge.

Measurement And Payment:

The measurement shall be taken as per unit shall be made according to


measurement. Payment shall be made on Kg. basis.

Item No.30 Supplying ,cutting, bending & binding , and placing in position steel as
per plan and design and as per ISS 2502 including cost of steel and
binding wires for reservoirs only including lift up to 6.00 mt.
ht.depth below g.l. for all diameters
The specification shall be same as above Sub-Estimate No.3 Item No.6

Item No.31 Providing and fixing 1.20 meter high fencing with 2.0 meter long
M.S. angle posts 40 mm x 40 mm x 6 mm and oil painting 3 coats
fixed at 2.5 m c/c with five horizontal lines and two diagonals of
galvanized steel barbed wire weighing 9.38 kg per 100 meter.
Strained and fixed to posts in ground with G.I. staples.

General:

119 | P a g e
Providing and fixing 1.20 meter high fencing with 2.0 meter long M.S. angle posts
40 mm x 40 mm x 6 mm and oil painting 3 coats fixed at 2.5 m c/c with five horizontal
lines and two diagonals of galvanized steel barbed wire weighing 9.38 kg per 100 meter.
Strained and fixed to posts in ground with G.I. staples as per Engineer-In-Charges.

Materials:

Seven stand twisted G.I. fencing wire No. 4 shall be used it shall be usual commercial
type barbed wire shall conform to I.S. 278 – 1951 or its latest revision. Mild steel angle
iron of 40 x 40 x 6mm or tee of 40 x 40 x 6mm shall confirm to item No. MSP – 18 the
length shall be as specified in the item.

G. I. straining bolts 30cm long and 10mm dia shall be of the standard commercial type.

Erecting :

The posts shall be pre cast type of size as mentioned in the item and shall be fixed to
2.3 to 2.6 centers c/c.

45 x 45 x 45cms. Pits of or of dimensions as given in drawings, shall be excavated for


foundation of RCC pre cast posts. The posts shall be held in the correct position in the
pit and 1:4:8 C.C. poured round it and consolidated and cured to from the foundation
block for the full depth of the pit the flange of the tee or one side of the angle shall
face out side.

The dimensions of RCC post shall be 10cms. Square at top and 15cms square at the
ground.

Holes shall be drilled into the wet of the tee or in the leg or angle at right angles to the
out side leg for passing the wire through or tying wire with staples of U shape or closed
staples. Holes shall be left into the RCC posts for passing the wire or tying with staples
while casting.

The hole shall be at 22cms. c/c leaving 22cm. from the ground level and leaving 10cm at
the top or as directed by the Engineer.

The posts at every 30meter and at corners and angles shall be suitably strutted on
either side of the posts.

These struts shall be of angle iron and shall have foundation of 1:4:8 C.C. like vertical
post. This strut shall be fixed at 450 and be fixed at the top most wire.

After the concrete has set the fencing wire shall be fixed through holes made in the
post and strained with streining bolts. Alternatively a G. I. staples shall be used for
fixing barbed wire the nas of raws shall be as specified in the item. The steel post shall
be painted with a priming coat of red lead and three coats of good oil paint of approved
shade. Painting shall conform to item WSP – A – 18 (i).

Measurements :

The rate shall be for one running meter or fencing completed as specified. The
measurement shall be for the length measured from the out side face of the first post
to the out side post of the end. At angle the measurement shall be at the center lines of
the posts.

120 | P a g e
Executive Engineer,

Public Health Works Division,


Gujarat W/S. & S. Board,

Nadiad.

121 | P a g e

Potrebbero piacerti anche