WEEKLY PROGRESS REPORT

(2nd December, 2009 - 8th December, 2009)

for

MRF Limited
Medak, AP

By

JONES LANG LASALLE MEGHRAJ


WEEKLY PROGRESS REPORT # 13
Project Name: Proposed Manufacturing Plant at Medak Area in Sqft: 400,000 Target Start Date: 1-Sep-09

Project Lead: Anantharaman J Target End Date: 1-Mar-10

Objective / Scope of Work: Project Monitoring for MRF Limited Purpose of the Facility: Manufacturing Plant

Reporting Date: 9-Dec-09


Actual Start Date 4-Sep-09
Original Operational Date: 1-Mar-10
Revised Operational Date: 4-Mar-10 LEGENDS
Original Duration: 180 Days GREEN Normal
Revised Duration: 180 Days AMBER Action Required
Duration Covered: 96 Days RED Critical to Project

WORKS SCHEDULE STATUS (Inclusive of Radial,


Easy, Banbury, RM Godown, Roads, Drains, Planned Completion 67%
Ancilliary Buildings PEB Works & Structural Steel 67%
Actual Completion 55%
Works) 55%

NCCL (Includes Radial, Easy, Banbury, RM Godown, Planned Completion 41%


41%
Roads, Drains, Ancilliary Buildings) 28%
Actual Completion 28%

Planned Completion 97%


KIRBY (Including Drawing, Design, Supply, Erection) 97%
Actual Completion 77%
77%

Planned Completion 62%


ICIC (Supply, Fabrication, Erection only) 62%
Actual Completion 52%
52%

Safe Man Hours of the Week 78,240


SAFE MAN HOURS
Total Safe Man Hours (Cumilative) 533,750

CRITICAL ISSUES CRITICALITY RESPONSIBILITY SUPPORTED BY


KIRBY is yet to appoint a quality engineer with sufficient control over the painting and erection
AMBER KIRBY
process. This has affected quality of painting

The structural members required for the 2 nos. lean-to roof in Radial Tyre Plant and 2 nos. lean-
to roof in Easy Tyre Plant are yet to be produced in the KIRBY factory. KIRBY commits to
AMBER KIRBY
manufacture them and bring them to site on 7 Dec. 09. Any delay in erecting lean-to portion will
further delay the roofing in the contiguous area in the main building (18 m. x 9 m.)

Page 2 of 30
WEEKLY PROGRESS REPORT # 13
KIRBY is yet to increase number of supervisors to follow up on work to complete as per
AMBER KIRBY
schedule and avoid mistakes in painting and bolt fixing.
ICIC yet to start erection work in old Banbury and RM Godown. The scheduled start date is 27
AMBER ICIC
Nov. 09. Commits to complete work as per schedule.
In the Progress Review Meeting held on 26 Nov. 09, NCCL committed to mobilise their
equipment for VDF on 28, 29 and 30 Nov. 09 and start work on 1 Dec. 09. The equipment have AMBER NCCL
been mobilised but the work has not commenced.

A recent communication from the architect instructing KIRBY to completely change the
sequence of wall and roof sheeting even in areas where work has already been
RED MRF
completed could seriously impact the end date of the entire project. This could also
impact the VDF work as a water-tight roof is a requirement for commencing this activity.

Area handing over to NCCL for construction of 163.80 m. of compound wall on Western
boundary was done on 6 Oct. 09. Neighbouring farmer on Western side who had cultivated in
RED MRF
land which was later purchased by MRF wants work to be executed after harvest of his crops.
NCCL has been prevented by the farmer from entering the area.
RISKS CRITICALITY RESPONSIBILITY SUGGESTED MITIGATION PLAN
Shortage of building materials like cement, sand and aggregate during the execution of vacuum NCCL to stock sufficient quantities of materials required for VDF. If
de-watered flooring (VDF) will affect the progress of work as consumption of these materials for AMBER NCCL there is any shortage of sand as claimed by NCCL then sand will have
VDF will be huge and the work will be going on continuously. to be stocked in bulk at the site.

No clearance has been given to NCCL for starting the construction of compound wall for fenced Survey to be organised as soon as possible in order to resolve the
portion on Eastern side since joint survey of land with neighbours is yet to be done. This will RED MRF dispute and provide work front to NCCL without resulting in major
impact the schedule for construction of compound wall. delay.

Slippage in areas in which both NCCL and KIRBY will be working together could result in the Close monitoring & coordination and adherence by NCCL and KIRBY
AMBER JLLM / NCCL / KIRBY
jointly agreed schedule not being maintained. to agreed schedule.

SCHEDULE
Key Milestone Dates Scheduled Start Date Actual Start Date
Start date of civil works for Radial Plant - Zone 1 4-Sep-09 4-Sep-09
Start date of civil works for Radial Plant - Zone 2 15-Sep-09 12-Oct-09
Start date of civil works for Radial Plant - Zone 3 10-Sep-09 14-Sep-09
Start date of civil works for Easy Plant - Zone 1 & 2 2-Sep-09 2-Sep-09
Start date of civil works for Easy Plant - Zone 3 1-Sep-09 4-Sep-09
Start date of civil works for new Banbury Building & RM
16-Sep-09 25-Sep-09
Godown
Start date of structural work in new Banbury 9 Nov. 09
Start Date of PEB works in Radial Tyre Plant Zone 1 1-Oct-09 1-Oct-09
Start Date of PEB works in Easy Tyre Plant Zone 1 & 2 2-Oct-09 24-Oct-09
`
WORK DONE THIS WEEK
Package Description
Concreting of machine foundations in Zone 1 of Radial Tyre Plant.
Brick masonry for walls in Zone 1 & 2 of Easy Tyre Plant.
Concreting of machine foundations in Zone 1 & 2 of Easy Tyre Plant.
Civil & PEB Works
Page 3 of 30
WEEKLY PROGRESS REPORT # 13
Completion of roof and wall sheeting in Zone 1 & 2 of Easy Tyre Plant from Grid 14 to Grid 9.
Civil & PEB Works
Start of work on retaining wall in Northern boundary.
Foundations for ancillary buildings in Radial & Easy Tyre Plants.
Erection of structural steel members for new Banbury / RM Godown and old Banbury / RM Godown.
Commencement of rubble masonry for drain near southern boundary.

`
WORK SCHEDULED FOR THE NEXT WEEK
Package Description
VDF flooring in Zone 1 of Radial Tyre Plant.
Wall and roof sheeting in balance portion of Zone 1 & 2 of Easy Tyre Plant.
Erection of columns, lattice girders and trusses in old Banbury / RM Godown and new Banbury / RM Godown.
Concreting of retaining wall in Northern boundary.
Civil & PEB Works
Concreting of machine foundations in Zone 1 and Zone 3 of Radial Tyre Plant and Zone 1 & 2 of Easy Tyre Plant.
Wall sheeting in Zone 2 and Zone 3 of Radial Tyre Plant.

Page 4 of 30
MRF LIMITED, MEDAK : MILESTONE SCHEDULE AND ACTUAL DU
7-Dec-09
Area
Completion
Handing
Scheduled Date From
Type of Scheduled Over Date
Description of Milestone Completion Area
Work Start Date - Actual OR
Date Handing
Anticipated
Over Date

Radial Tyre Plant : Zone 1

Completion of Column foundation with


bolts, Plinth beams, stub columns and back
GBW 1-Sep-09 4-Sep-09 30-Sep-09 4-Oct-09
filling etc. and handing over of area for PEB
erection

Completion Machine Foundations,


trenches, pits and flooring, etc. including
GBW brick wall with plastering, windows & doors 7-Nov-09 30-Nov-09 10-Jan-10 3-Feb-10
etc. and handing over of area for
equipment erection

Erection of PEB including Roof sheeting,


PEB wall cladding, gutters, & down take pipes 1-Oct-09 1-Oct-09 12-Nov-09 12-Nov-09
etc. and handing over of area for flooring

Radial Tyre Plant : Zone 3

Completion of Column foundations with


bolts including deep foundations, plinth
GBW 10-Sep-09 10-Sep-09 25-Oct-09 25-Oct-09
beams, stub columns and back filling etc.
and handing over of area for PEB erection

Completion of Machine Foundations, curing


trenches, pits and flooring etc. including
GBW side brick wall with plastering, windows & 24-Nov-09 20-Dec-09 15-Feb-10 14-Mar-10
doors etc. and handing over of area for
equipment erection
Erection of PEB including roof sheeting,
PEB wall cladding, gutters, and down take pipes 26-Oct-09 26-Oct-09 28-Nov-09 28-Nov-09
etc. and handing over of area for flooring

Radial Tyre Plant: Zone 2

Completion of Column foundations with


bolts, plinth beams, stub columns and back
GBW 15-Sep-09 15-Sep-09 7-Nov-09 7-Nov-09
filling etc. and handing over of area for PEB
erection

Completion of Machine Foundations,


trenches, pits and flooring etc, including
GBW side brick wall with plastering, windows and 10-Dec-09 16-Dec-09 9-Feb-10 16-Feb-10
doors, etc. and handing over of area for
equipment erection

Erection of PEB including Roof sheeting,


PEB wall cladding, gutters, & down take pipes 19-Nov-09 16-Nov-09 12-Dec-09 12-Dec-09
etc. and handing over of area for flooring

Easy Tyre Plant Zone 1 & 2

Completion of Column foundations with


bolts, plinth beams, stub columns and back
GBW 1-Sep-09 2-Sep-09 30-Sep-09 1-Oct-09
filling etc. and handing over of area for PEB
erection

Completion of Machine Foundations,


trenches, pits, and flooring, etc. including
GBW side brick wall with plastering, windows and 5-Nov-09 30-Nov-09 20-Dec-09 14-Jan-10
doors etc. and handing over of area for
equipment erection

Erection of PEB including Roof sheeting,


PEB wall cladding, gutters, & down take pipes 2-Oct-09 2-Oct-09 13-Nov-09 13-Nov-09
etc. and handing over of area for flooring

Easy Tyre Plant Zone 3

Completion of Column foundations with


bolts, plinth beams, stub columns and back
GBW 15-Sep-09 15-Sep-09 20-Oct-09 20-Oct-09
filling etc. and handing over of area for PEB
erection
Completion of Machine Foundations, curing
trenches, pits and flooring etc. including
GBW side brick wall with plastering, windows and 22-Nov-09 20-Dec-09 20-Jan-10 18-Feb-10
doors etc. and handing over of area for
equipment erection

Erection of PEB including Roof sheeting,


PEB wall cladding, gutters, & down take pipes 4-Nov-09 26-Oct-09 26-Nov-09 18-Nov-09
etc. and handing over of area for flooring

Full Completion of GBW (General Building


Works) - Radial Tyre Plant, Easy Tyre
GBW by
Plant, new Banbury & RM Godown, all 1-Sep-09 3-Mar-10
NCCL
Ancilliary Buildings, Roads, Culverts and
Drains within project site

Full completion of PEB in Radial Tyre Plant


PEB by
& Easy Tyre Plant (Excluding Liner Panel, 1-Oct-09 20-Dec-09
KIRBY
False Ceiling Supports & Pipe Racks)

Banbury (new)

Completion of Column foundations with


bolts, plinth beams, stub columns and back
GBW 1-Sep-09 16-Sep-09 30-Sep-09 15-Oct-09
filling etc. for 50% of plinth area and
handing over of area for structural erection

Completion of Column foundations and


machine foundations, pits, etc. for balance
GBW 1-Oct-09 16-Sep-09 30-Oct-09 15-Nov-09
50 % of plinth area and handing over of
area for structural erection

Completion of Machine Foundations,


trenches, pits and flooring etc. including
GBW side brick wall with plastering, windows and 31-Dec-09 12-Dec-09 28-Feb-10 10-Feb-10
doors etc. and handing over of area for
equipment erection
Procurement, fabrication, erection,
Structural
alignment, painting, roof sheeting,
Stell By 4-Sep-09 15-Nov-09 8-Feb-10 8-Feb-10
installation of decking sheets, wall cladding,
ICIC
rain water pipe lines

R.M. Godown (new)

Completion of Column foundations with


bolts, plinth beams, stub columns and back
GBW 1-Sep-09 16-Sep-09 30-Sep-09 15-Oct-09
filling etc. for 50% of plinth area and
handing over of area for structural erection

Completion of Column foundations and


machine foundations, pits, etc. for balance
GBW 1-Oct-09 16-Sep-09 30-Oct-09 15-Nov-09
50 % of plinth area and handing over of
area for structural erection

Completion of Machine Foundations,


trenches, pits and flooring etc. including
GBW side brick wall with plastering, windows and 31-Dec-09 28-Feb-10
doors etc. and handing over of area for
equipment erection

Procurement, fabrication, erection,


Structural
alignment, painting, roof sheeting,
Steel By 4-Sep-09 8-Feb-10
installation of decking sheets, wall cladding,
ICIC
rain water pipe lines
LE AND ACTUAL DURATION OF GBW & PEB WORKS

Planned
Anticipated Actual
Delay Duration
Completion Completion Remarks
(days) As Per
Date Date
PO (days)

The work of back-filling of foundation pits


was not done as per specification by NCCL.
NA 54 30 27-Nov-09 They were asked to re-do this work by
removing the filled up soil and compacting in
layers with earth rammers

Excavation and PCC for machine foundation


under progress since 22 Nov. 09. RCC for
3-Feb-10 0 65 Under progress
foundation of Roller Die Calendar was done
on 29 Nov.09.

In the meeting at HO, MRF on 6 Nov. 09,


KIRBY committed to hand over Grid 20 to
Grid 17 on 20 Nov. 09 and Grid 17 to Grid
13 on 30 Nov. 09. The same was
committed in the site meeting on 14 Nov.
NA 18 43 30-Nov-09
09.
KIRBY handed over Grid 20 to Grid 17 on
25 Nov. 09 and Grid 17 to Grid 13 on 30
Nov. 09.

The work of back-filling of foundation pits


was not done as per specification by NCCL.
NA 20 46 14-Nov-09 They were asked to re-do this work by
removing the filled up soil and compacting in
layers with earth rammers

The area handing over date mentioned is


the anticipated date. As of now no delay is
14-Mar-10 NA 84 Under progress
anticipated. NCCL has started work on
curing trench.
The anticipated delay has been calculated
20-Dec-09 22 34 Under progress assuming that the work will be completed on
20 Dec. 09.

NA 4 53 11-Nov-09

16-Feb-10 NA 62 Yet to start Yet to start

20-Dec-09 8 24 Under progress The anticipated delay is 8 days.

NA 66 30 6-Dec-09

KIRBY has handed over Grid 14 to Grid 10


25-Jan-10 11 45 Under progress on 30 Nov. 09 and Grid 10 to Grid 9 on 2
Dec. 09.

It is anticipated that Grid 9 to Grid 6 will be


10-Dec-09 27 43 Under progress handed over on 10 Dec. 09. The anticipated
delay is 27 days.

NA 16 35 5-Nov-09
The area handing over is anticipated based
18-Feb-10 NA 60 Yet to start
on KIRBY's anticipated completion date.

Work under progress. A delay of 32 days is


20-Dec-09 32 23 Under progress
anticipated.

NCCL had started work in RM Godown on


NA 31 30 15-Nov-09 22 Oct. 09
This area is from Grid 1 to Grid 3.

Entire Banbury / RM Godown area was


NA 11 30 26-Nov-09 handed over on 4 Sep. 09 but revised
drawings were issued on 16 Sep. 09.

ICIC was instructed to hand over Grids 1 to


3 (5 grids) on 25 Nov. 09. Later ICIC
committed to hand over this area on 30 Nov.
09. In the Progress Review Meeting held on
10-Feb-09 NA 60 Yet to start
26 Nov. 09 ICIC commits to hand over on 6
Dec. 09. Due to changes made in the
design ICIC now commits to hand over this
area on 12 Dec. 09.
Erection work under progress. Erection work
8-Feb-10 0 157 Under progress commenced on 15 Nov. 09. As per
conditions in PO the end date is 8 Feb. 09.

Yet to be NCCL have started work in RM Godown on


4-Dec-09 50 30
completed 22 Oct. 09

Entire Banbury / RM Godown area was


Yet to be
20-Dec-09 35 30 handed over on 4 Sep. 09 but revised
completed
drawings were issued on 16 Sep. 09.

28-Feb-10 NA 60 Yet to start Yet to start.

8-Feb-10 NA 157 Erection work commenced 4 Dec. 09.


MRF LIMITED, MEDAK : MILESTONE SCHEDULE AND ACTUAL DURATION OF EXPANSION
7-Dec-09
Area
Handing Scheduled
Type of Scheduled
Description of Milestone Over Date Completion
Work Start Date
- Actual OR Date
Anticipated

Expansion Of Banbury (Old)

Completion of column foundations with bolts,


GBW by plinth beams, stub columns and back filling
17-Sep-09 6-Oct-09 29-Jan-10
NCCL etc.and handing over of area for structural
erection

Procurement, fabrication, erection,


Structural
alignment, painting, roof sheeting,
Steel by 4-Sep-09 27-Nov-09 9-Jan-10
installation of decking sheets, wall cladding,
ICIC
rain water pipe lines

Expansion Of RM Godown (Old)

Completion of column foundations with bolts,


GBW by plinth beams, stub columns and back filling
17-Sep-09 6-Oct-09 29-Jan-10
NCCL etc.and handing over of area for structural
erection

Procurement, fabrication, erection,


Structural
alignment, painting, roof sheeting,
Steel by 4-Sep-09 26-Nov-09 9-Jan-10
installation of decking sheets, wall cladding,
ICIC
rain water pipe lines

Compound Wall - Western, Northern & Eastern Boundaries - NCCL

WESTERN BOUNDARY - Clearance given


for retaining wall and compound wall from 0
6-Oct-09
m. chainage to 163.80 m. chainage.
Total length on western side is 324 m.

NORTHERN BOUNDARY - Clearance


given on 26 Nov. 09. for 160 m. from north-
western corner out of a total length of 317 26-Nov-09
m.
EASTERN BOUNDARY - 383 M.

Compound Wall - Southern Boundary - J.D. Construction

Retaining Wall / Compound Wall 28-Aug-09 5-Sep-09 27-Oct-09

Approach Road Along Eastern Boundary - NCCL

Length of road 710 m. 6-Oct-09 15-Oct-09 12-Dec-09

Note : The anticipated completion date has been used to calculate the delay for works under progress.
URATION OF EXPANSION OF EXISTING BANBURY / RM GODOWN, COMPOUND WALLS AND APPROACH R

Completion
Anticipated Planned Actual
Date From
Completion Delay (days) Duration As Completion
Area Handing
Date Per PO (days) Date
Over Date

18-Feb-10 28-Feb-10 10 135 Under progress

9-Jan-10 9-Jan-10 127

18-Feb-10 28-Feb-10 10 135 Under progress

9-Jan-10 9-Jan-10 127

12-Dec-09 Under progress

67
67

4-Nov-09 7-Dec-09 33 60 Under progress

21-Dec-09 21-Dec-09 67 Under progress

progress.
OWN, COMPOUND WALLS AND APPROACH ROAD

Remarks

Back filling under progress. Anticipated date of complete


handing over to ICIC for erection is 6 Dec. 09. Half the area
has been handed over to ICIC on 26 Nov. 09.

Area was handed over to ICIC on 27 Nov. 09. Erection work


under progress. End date for ICIC as per PO is 9 Jan. 10.
Back filling by NCCL is expected to be completed by 9 Dec.
09.

Back filling of foundation except around lift pit was completed


on 25 Nov. 09.

Area was handed over to ICIC on 26 Nov. 09. Erection work


under progress.
Back filling by NCCL is expected to be completed by 9 Dec.
09.

Work cannot be continued beyond 123 m. chainage as the


farmer who had cultivated crops before sale of land to MRF is
refusing entry of NCCL into the field till the crop is harvested.
Work front yet to be given for portion beyond 163.80 m.
chainage.

Work under progress from 0 chainage to 160 m. chainage.


Joint survey on fenced portion and permission from
neighbours for portion with existing compound wall (part of
Eastern boundary) is required for start of work. NCCL unable
to give schedule as start date is not fixed.

Eastern half completed. Work under progress in western half.

Work under progress.


TRACKER FOR RUNNING BILLS PAYMENT (KIRBY) - Target Number Of D

Checks
Quantites. Approves
Certifies.

Bill Amount Submission of Plant


Running Plant Civil
Sl. No. Vendor PO Ref NO. Inclusive Of All Bill by Engineering
Bill No. Engineer
Taxes Contractor Manager

2400027540 Planned 13-Nov-09 17-Nov-09 18-Nov-09


1 KIRBY dt. 28 Aug. 09 3,81,26,170.00 1
Actual 13-Nov-09 13-Nov-09
Planned 1-Dec-09 5-Dec-09 6-Dec-09
2 KIRBY 2400027540 6,64,84,020.00 2
dt. 28 Aug. 09 Actual 1-Dec-09 3-Dec-09 5-Dec-09
Planned 1-Dec-09 5-Dec-09 6-Dec-09
3 KIRBY 2400027540 65,64,255.00 3
dt. 28 Aug. 09 Actual 1-Dec-09 3-Dec-09 5-Dec-09
BY) - Target Number Of Days From Submission Of Bill - 13 Days

Certified
Service Checks.
Bills Checks Sends E-
Entry Sheet Countersigns. Approves. Releases
Received By funds. Send Approves mail To
Created On Sends E-mail. Sends To Payment.
Accounts To VPF. PAM.
SAP MD.
Dept.

HO Finance No. Of Days


Plant Civil Plant Plant Accounts
- GM Plant VPF MD VPF PAM For
Engineer Accounts Manager
Accounts Payment

19-Nov-09 21-Nov-09 22-Nov-09 23-Nov-09 23-Nov-09 24-Nov-09 25-Nov-09 26-Nov-09 13


16-Nov-09 16-Nov-09 16-Nov-09 20-Nov-09 20-Nov-09 25-Nov-09 12
7-Dec-09 9-Dec-09 10-Dec-09 11-Dec-09 11-Dec-09 12-Dec-09 13-Dec-09 14-Dec-09 13
5-Dec-09 7-Dec-09 7-Dec-09
7-Dec-09 9-Dec-09 10-Dec-09 11-Dec-09 11-Dec-09 12-Dec-09 13-Dec-09 14-Dec-09 13
5-Dec-09 7-Dec-09 7-Dec-09
TRACKER FOR RUNNING BILLS PAYMENT (NCCL, ICIC, JDC & JLLM) - Target Nu

Checks
Quantites. Approves
Certifies.

Bill Amount Submission of Plant


Running Plant Civil
Sl. No. Vendor PO Ref NO. Inclusive Of All Bill by Engineering
Bill No. Engineer
Taxes Contractor Manager

2400028297 Planned 10-Oct-09 17-Oct-09 18-Oct-09


1 NCCL dt.11 Sep. 09 86,64,097.00 1
Actual 10-Oct-09 14-Oct-09 14-Oct-09
2400028384 dt. Planned 12-Oct-09 19-Oct-09 20-Oct-09
2 JDC 15 Sep. 09 46,48,820.00 1
Actual 12-Oct-09 15-Oct-09 15-Oct-09
2400029904 dt. Planned 23-Oct-09 30-Oct-09 31-Oct-09
3 JLLM 23 Oct. 09 15,66,761.87 1
Actual 23-Oct-09
2400029904 dt. Planned 12-Nov-09 19-Nov-09 20-Nov-09
4 JLLM 23 Oct. 09 5,32,699.00 2
Actual 12-Nov-09
2400028213 Planned 11-Nov-09 18-Nov-09 19-Nov-09
5 ICIC 5,33,78,884.00 2
Actual 11-Nov-09 12-Nov-09
2400028297 Planned 14-Nov-09 21-Nov-09 22-Nov-09
6 NCCL dt.11 Sep. 09 2,28,02,216.00 2
Actual 14-Nov-09
3000060153 dt. Planned 14-Nov-09 21-Nov-09 22-Nov-09
7 NCCL 17 Sep. 09 15,71,668.00 1
Actual 14-Nov-09
2400028357 dt. Planned 14-Nov-09 21-Nov-09 22-Nov-09
8 NCCL 3,81,613.00 1
14 Sep. 09 Actual 14-Nov-09
240029196 dt. Planned 14-Nov-09 21-Nov-09 22-Nov-09
9 NCCL 12,44,255.00 1
6 Oct. 09 Actual 14-Nov-09
2400028384 Planned 17-Nov-09 24-Nov-09 25-Nov-09
10 JDC 29,99,716 2
dt. 15 Sep. 09 Actual 17-Nov-09 23-Nov-09 23-Nov-09
JDC & JLLM) - Target Number Of Days From Submission Of Bill - 18 Days

Certified
Service Checks.
Bills Checks Sends E-
Entry Sheet Countersigns. Approves. Releases
Received By funds. Send Approves mail To
Created On Sends E-mail. Sends To Payment.
Accounts To VPF. PAM.
SAP MD.
Dept.

HO Finance No. Of Days


Plant Civil Plant Plant Accounts
- GM Plant VPF MD VPF PAM For
Engineer Accounts Manager
Accounts Payment

19-Oct-09 23-Oct-09 24-Oct-09 25-Oct-09 25-Oct-09 26-Oct-09 27-Oct-09 28-Oct-09 18


15-Oct-09 16-Oct-09 16-Oct-09 19-Oct-09 27-Oct-09 17
21-Oct-09 25-Oct-09 26-Oct-09 27-Oct-09 27-Oct-09 28-Oct-09 29-Oct-09 30-Oct-09 18
16-Oct-09 16-Oct-09 16-Oct-09 19-Oct-09 27-Oct-09 15
1-Nov-09 5-Nov-09 6-Nov-09 7-Nov-09 7-Nov-09 8-Nov-09 9-Nov-09 10-Nov-09 18
30-Oct-09 30-Oct-09 7
21-Nov-09 25-Nov-09 26-Nov-09 27-Nov-09 27-Nov-09 28-Nov-09 29-Nov-09 30-Nov-09 18
13-Nov-09 13-Nov-09 1
20-Nov-09 24-Nov-09 25-Nov-09 26-Nov-09 26-Nov-09 27-Nov-09 28-Nov-09 29-Nov-09 18
16-Nov-09 16-Nov-09 25-Nov-09 14
23-Nov-09 27-Nov-09 28-Nov-09 29-Nov-09 29-Nov-09 30-Nov-09 1-Dec-09 2-Dec-09 18
23-Nov-09 24-Nov-09 30-Nov-09 2-Dec-09 4-Dec-09 20
23-Nov-09 27-Nov-09 28-Nov-09 29-Nov-09 29-Nov-09 30-Nov-09 1-Dec-09 2-Dec-09 18
24-Nov-09 30-Nov-09 5-Dec-09 21
23-Nov-09 27-Nov-09 28-Nov-09 29-Nov-09 29-Nov-09 30-Nov-09 1-Dec-09 2-Dec-09 18
24-Nov-09 30-Nov-09 5-Dec-09 21
23-Nov-09 27-Nov-09 28-Nov-09 29-Nov-09 29-Nov-09 30-Nov-09 1-Dec-09 2-Dec-09 18
24-Nov-09 30-Nov-09 5-Dec-09 21
26-Nov-09 30-Nov-09 1-Dec-09 2-Dec-09 2-Dec-09 3-Dec-09 4-Dec-09 5-Dec-09 18
24-Nov-09 25-Nov-09 30-Nov-09 2-Dec-09 4-Dec-09 17
KEY EXECUTION CONCERNS/CHALLENGE

Location Description of concern/challenge

Close coordination between NCCL and KIRBY to be done as they are both working in Zone 1.
Changes in location of machinery after excavation of foundation pits could reduce the speed of work.
Poor supervision by Kirby of the execution and painting works due to the absence of dedicated site supervisors for each of the building units.
RADIAL TYRE PLANT
The quality of paint application is very poor. Missed out patches, paint peeling off, improper surface preperation, improper material handling, improper mixing of
paint which results in different shade of paint while doing the correction works are causing unnessary delay due to rework.
Details of Creel Room yet to be received. Concreting of nearby machine foundation on hold. This could delay the VDF in this area.

Bolts tightening at supports to be done immediately after erection of primary members.


Delay in removal of construction debris and levelling of ground next to building by NCCL could lead to delay in wall cladding by KIRBY.
Poor supervision by Kirby of the execution and painting works due to the absence of dedicated site supervisors for each of the building units.
EASY TYRE PLANT
The quality of paint application is very poor. Missed out patches, paint peeling off, improper surface preperation, improper material handlign, improper mixing of
paint which results in different shade of paint while doing the correction works are causing unnessary delay due to rework.
Slow progress of work by KIRBY could lead to them missing even the latest dates committed by them.

Frequent changes in design requiring alteration or replacement of fabricated strucutural members could lead to delays.
BANBURY (new)

Dealy in concreting of walls of DCV pit could lead to delay in work of back filling.
RM Godown (new)

On western side the neighbour is not permitting NCCL to continue work beyond 123 m. chainage as his crops are in the way of the proposed compound wall.
Compound Wall
On parts of northern side and on eastern side joint survey to be done with neighbours.Permission to be obtained to work from their side.
MRF LIMITED

SITE PHOTOGRAPHS

Sheeting Completed In Zone 1 Of Radial Tyre Plant - Northern Side Wall Cladding In Zone 2 Of Radial Tyre Plant - Southern Side

View Of Zone 3 Of Radial Tyre Plant - Southern Side View Of Zone 3 Of Radial Tyre Plant - Northern Side

Wall & Roof Sheeting In Progress In Zone 1 & 2 Of Easy Tyre Plant Zone 3 Of Easy Tyre Plant
MRF LIMITED

SITE PHOTOGRAPHS

Structural Steel Work In Progress In New Banbury Structural Steel Work In Progress In New RM Godown

Foundation Work In Progress For Ancillary Buildings Of Easy Tyre Plant Foundation Work In Progress For Ancillary Buildings Of Radial Tyre Plant

Foundation For Roller Die Calendar Machine In Zone 1 Of Radial Tyre Plant
Foundation Work For Triplex Extruder In Progress In Zone 1 Of Radial Tyre Plant
MRF LIMITED

SITE PHOTOGRAPHS

Concreting Of Retaining Wall In Western Boundary Reinforcement Work For Raft Of Retaining Wall In Northern Boundary

Structural Steel Work In Expansion Of Old Banbury Structural Steel Work In Expansion Of Old RM Godown