Sei sulla pagina 1di 5

LPG Storage and Handling 2X 300 MT

SNO Description UNIT QTY


item code
Customs tariff
A EQUIPMENTS & PIPELINE
1 LPG Compressor No. 1 5%
2 LPG pump No. 2 5%
6 LPG/VPG/utility pipeline L.S. lot 5%
7 ROV/Control valves / Valves L.S. lot 10%
8 Service water pumps & piping L.S. 0 na
9 Loading arms Nos 2 5%
10 Mercaptan dosing equipment L.S. lot 5%
11 Weigh Bridge no 1 5%

B FIRE PROTECTION SYSTEM


1 Water Spray System 5%
a) Bullets nos 2 5%
b) LPG Pump shed nos 1 5%
c) TT Gantry nos 1 5%
2 Deluge valve with accessories L.S. 5 5%
C STORAGE FACILITIES
1 Bullet-Butane L.S. 2 20% 7311.0000.00
2 Bullet-Propane L.S. 0 20% 7311.0000.00

D INSTRUMENTATION
CONTROL SYSTEM inclusive of Consoles
interconnecting cables, Basic system
1 L.S. 1 5%
engineering & interconnection

Tank safety fittings


2 ls 2 5%

3 Pressure Guages L.S. 1 5%


4 Pressure Transmitter L.S. 1 5%
5 Pressure Switches L.S. 1 5%
6 Differential Pressure Instruments L.S. 1 5%
7 Mass Flow Meters L.S. 1 5%
8 Control Valves L.S. 1 10%
9 Thermal Relief Valves L.S. 1 10%
10 Portable Gas Detector with HART Output L.S. 1 5%
11 Self Actuated Pressure Control Valve L.S. 1 10%

E Civil works

1 Bullets foundation and mounding L.S. lot na


2 pump house L.S. lot na
3 PMCC room L.S. lot na
4 weigh bridge foundation L.S. lot na
5 pipe supports etc L.S. lot na
6 Truck gantry L.S. lot na

F Electrical works

1 PMCC L.S. lot 20%


2 Cables L.S. lot 5%
3 Flame proof fittings L.S. lot 20%
4 Other Electrical works L.S. lot na

G Mechanical works

1 Plant piping L.S. 1 na


2 Erection and testing L.S. 1 na
3 Commissioning L.S. 1 na
Description of Items

A facility for increasing the pressure of gas/LPG


A machine for transferring LPG to storage tank

Pipe lines for conducting/transferring gas from one location to another


A facility to allow or disallow flow of product in pipelines and other facilities
A facility and network of pipelines for transferring service water for usage
A facility for loading LPG to road tankers
A facility for injection of chemicals which allows for easy identification of escape of LPG into the atmosphere
A machine for measuring the weight of LPG

Spray nozzles for water for fire fighting


Spray nozzles for water for fire fighting
Spray nozzles for water for fire fighting
Spray nozzles for water for fire fighting
Spray nozzles for water for fire fighting

A cylindrical vessel for storing butane C4


A cylindrical vessel for storing propane C3

A facility for controlling onsite facilities through comntrols in the control room

Facilities for safe operations of the tanks

A facility for measuring pressures


A facility for passing preassure reading across to users
A facility for controlling the reading of pressure by an instrument
A facility for reading and comparing readings of two pressures
A facility for measuring the flow of crude oil

A facility to allow or disallow flow of product in pipelines and other facilities


A facility for bringing pipelines to safe conditions incase of emergencies
A facility for detecting leakage of gas

A self-working facility to allow or disallow flow of product in pipelines and other facilities

A construction for placing bullets (LPG storage) ontop


A facility for keeping pumps

A construction for placing weigh bridge ontop

A packing slot for LPG truck before loading

Elecrical control panel


Electrical cables
electrical fittings
Flow station

description qty Customs tariff


Equipment
inlet manifold 1 10%
hp separator 2 5%
MP Separator 2 5%
lp separator 2 5%
Test separator 1 5%
bath heater/Heater Treater 0 5%
surge vessel 1 5%
KO drum 1 5%

Crude oil Storage tank 10 K BBL 2


Int. Oil Storage tank 3 k BBL 1
Off Spec Storage Tank 3 K BBL 1 5% for
Produced Water Storage Tank 1.2 k BBL 1 plate,20% for
Trated water storage tank 2.5 k BBL 1 structural steel

Flare KO drum 1 5%
Flare System 1 5%

Crude oil export pump 75 Cu. m 2 5%


Crude oil transfer pump 75 Cu. M 2 5%
Produced water transfer pump 2 5%
Flare KO drum transfer pump 2 5%
off spec transfer pump 2 5%
small transfer pumps 10 5%
Chemical injection System(6 set) 1 5%

CBD system 1 5%
Water Treatment and Handling 1 5%
Water Inj pump (Provisional) 0 5%
Gas Compressors- from HP Seperator to Gas
plant
Gas Compressors- from gas plant to export 2 0%
line 2 0%
fuel Gas conditioning System 1 0%
Gas Dehydration Pkg 1 0%

Utilities
diesel generator refurbished 1 5%
gas generator new 1 0%
gas generator refurbished 1 0%
Air Compressor 200cfm,8kg/cm2 2 5%
Air Dryer 1 5%
Service water storage tank 125 BBL 1 local
Service water Pump 2 5%
Bore wells System 1 local
Fire water storage tank 5.5 k BBL 2 5%
Fire water pump 410 cu. M 2 5%
Fire water Hydrant System 1 5%
Sprinklers 1 5%
Foam System 1 5%
Jockey pump 2 5%
Diesel Storage tanks 40 KL 1 local
Diesel Transfer Pumps & piping 2 5%
Nitrogen System 1 local
description qty Customs tariff
Electrical
MCC 1 20%
PDB 1 20%
LDB 1 20%
cables 1 5%
Cable treys 1
earthing and lightning protection 1 5% for copper
lighting 1 20%
UPS 1 10%
FLP fittings 1 20%

Instrumentation
PLC/SCADA 1 5%
cables 1 5%
field instruments 1 5%
fire detection 1 5%
control valves 1 10%
shut down valves 1 10%
ROVs 1 10%
? Level indicators 1 5%
? switches 1 20%
? relief valves 1 10%
flowmeter 4 5%

Pipes & Accessories


pipes 1 5%
flanges 1 20%
fitting 1 20%
valves 1 10%
supports(pipe rack etc) 1 20%
Description
customs duty Description of Items
Pipes 5% Cylindrical conduits for conducting/transferring crude oil from one location to another
Coating/painting Matering for covering pipelines to prevent corrosion arising from contacts with soil
Valves 10% A facility to allow or disallow flow of crude oil in pipelines and other facilities
Flanges & Fittings 20% Connectors for pipelines
Pig launcher/receiver A facility for cleaning pipelines of dirts, solids and other foreign particles that made impede flow
Tie in valves and fittings 20% Connectors for pipelines at a junction or connection to another pipeline/facility
Cables OFC/HDPE conduit na A network of elecrical wires for conducting current
Electrical cable for well head panel A network of elecrical wires for conducting current at the wellheads
CP na A corrosion-prevention facility
LACT/turnine meter A facility for measuring flow of crude oil in a pipeline
Control valves 10% A set of valves for monitoring set conditions
Gauges/RTD A facility for measuring certain conditions of flow of crude oil in a pipeline
Shut down valves 10% A set of valves for bringing the flowstation to safe contions incase of emergencies
Switches 20% A facility for starting or stopping an operation process
Transmitters/receiver A facility for passing and accepting messages via air
Tele communication Means of communicating between operators on site amd in control room
Engineering na A scientific system of verifying the feasibility of a project technically
Route survey/Cadstal Survey/Soil Test na A process of verifying the soil condition and route accessibility before distortion as a result of the project
ROU na A land stirp dedicated for the laying of pipelines
Community compensation @ 40% na Entitlement to communities hosting the ptoject
Installation , Testing & commissioning na Process of assmblage and confirming readiness for operations
Third Party Inspection charges na Amount paid to third parties for services rendered on the execution of the project
Civil works na Construction activities required to be performed onsite
Pipe Supports na Stands overwhich pipelines are laid for rigidity