Sei sulla pagina 1di 16

Issue

03/2003

WIND BLATT
The ENERCON Magazine

On solid
foundations
Report on page 10

Pages 4/5: Luxembourg


Municipal wind farm in the Ardennes
Pages 6/7: More power
Replacing old converters
Page 11: Stress test
Deep foundations for the new E-112
2 WIND BLATT 3/2003

Editorial
Dear Readers,

I am pleased to inform you that the


preparations for series production
of our 4.5 megawatt E-112 converter
are making rapid progress. We
recently upgraded a factory hall
complex in Magdeburg-Rothensee to
meet the job requirements. Moulds
and other working equipment for
production of the rotor blades are
now ready to manufacture the first
E-112 blade in June. Series production
of the nacelle components will also
begin there next year.

This is another demonstration of


ENERCON’s close relationship with
Magdeburg and the Saxony-Anhalt
region. Following the development
of a large number of wind energy
production facilities and the erection
of the world’s largest converter last
year, wind energy is making a vital
Technology
contribution to a federal region where
unemployment is still high.
Graphite and
Yet more service and quality for ENERCON
We are looking forward, with confi-
dence, to good future cooperation
There was plenty of ENERCON’s production manager, Klaus
with the region’s political leaders
Peters, was visibly pleased as he an-
in matters concerning the further innovation to find out about and to
nounced that Meuselwitz Guss from
development of wind energy in admire on the ENERCON stand Thuringia, amongst others, would in
Saxony-Anhalt and by these means
at the Hanover Fair. future be supplying cast main carriers for
hope to be able to create many more
the E-66. This relegates welded seams
jobs in the Saxony-Anhalt region. to the past, and an even stress distribu-

Yours,
C ustomers and interested visi-
tors crowded onto ENERCON’s
stand at the Hanover Fair. They did not
tion is achieved in cast parts (see diagram
above right). This was also achieved in
just take the opportunity for a look inside the past, thanks to ENERCON’s high
the two converters on display, an E-30 demands for quality, but only at the
(300 kW) (see photograph above) and an cost of extensive work on the welded
E-40 (600 kW), but also listened to a seams. The new process now makes this
Aloys Wobben variety of talks about the technological work superfluous. Suppliers have been
Managing Director of ENERCON GmbH innovations at ENERCON. working for a long time on the imple-
3/2003 WIND BLATT 3

Presented at the Hanover Fair: the new cast main carrier. The even stress distribution can be seen here with
a computer simulation.

responsible for the electrical power The portal is currently being tested,
supply at the rotor. Carbon brushes and is expected to be available to
were formerly used to slide on the customers in 2004. It will then not only
slipring casing, but have now been be possible to call up yields, availabi-
replaced by gold spring wire. About lities, usage data and analyses, but
200 wires, each 60 mm long, ensure also to present them in individually de-
that DC current is supplied to the rotor’s signed formats. Customers and other
pole shoes at the tip of the axle journal, interested visitors at the Hanover Fair
and that data transfer can take place. had the chance to try out the portal on

of Carbon brushes wear out after a few


years, which means that the slipring
a remote monitoring computer for the
first time.

Gold casing has to be regularly cleaned. The


new material, however, is subject to
hardly any wear. Gold has a number
customers
of advantages here: it does not wear
easily, giving it a long service life,
mentation of the cast main carrier, using and, at the same time, is a good con-
computer simulations provided by ductor.
ENERCON’s Research Department. The
use of spheroidal graphite cast iron was The E-66 has also passed the inspection.
a crucial point in making the manu- It is not only available as a 1.8 MW
facture possible. One of the material’s converter, but also with a rated power
properties that makes it particularly of 2 MW. Optimum yield can therefore be
suitable for safety-relevant components achieved in combination with the new
is its high tensile strength. For ENERCON 114 m prefabricated towers.
the new E-66 main carriers therefore
represent a further step forward in the Operators can look forward to a new
optimisation of production processes. innovative converter servicing field:
“Service Information Portal”. An inter-
Yet another component will look diffe- net, which permits the analysis and
rent in future: the slipring casing. It is statistical processing of converter data. The new slipring casing with gold spring wire.
4 WIND BLATT 3/2003

Construction of Luxembourg’s largest wind energy converters


amongst blooming mountain meadows.

Municipal wind farm


in the Ardennes
Three E-66 converters for the best wind region in Luxembourg

Luxembourg’s largest wind

energy converters have now


T he trucks had a tough job. Laden
with tower sections, they ground
their way up through the Eifel region’s
A tough time was also crossing the
bureaucratic landscape before the three
E-66 (1.8 MW) converters could be
mountain landscape. But it was not erected. The 99 trucks did not take
been set up in Ösling,
just Luxembourg’s terrain that made life the simplest route through Belgium to
in the Luxembourg Ardennes. difficult for the ENERCON transport team. Luxembourg, but travelled all the way
3/2003 WIND BLATT 5

through Germany to reach their desti-


nation, since the Belgian authorities
require an individual approval procedure
for every single heavy transport. A
process which is always associated
with costs and waiting times. “Only
the nacelles and rotor blades reached
their destination through Belgium. They
could not have been driven through
the narrow, winding roads”, explains
ENERCON project manager, Dipl.-Ing.
Peter Köppel.

But the difficult journey paid off: the des-


tination, Heinerscheid, is the best wind
region in Luxembourg. A wind speed of
more than 5 m/s is measured here at a
height of 30 m. An ideal combination of
nature and technology, because the three
E-66 converters, with their hub height of
98 m, are the largest and most powerful
in this small country. In purely arithmetic
terms, each of these new converters
provides enough power to supply all
the domestic and small business con- Eagerly following the construction of the wind energy converters at Heinerscheid (l. to r.): Paul Schockmel
(SEO), Änder Schanck (President of Wandpark Gemeng Hengischt) and Charles Offermann (SEO).
sumption of the public grid for 1 1/2 days
a year. planning office of the electricity supply The public grid in Luxembourg supplies
company SEO and gives for the positive customers with electric power amounting
And there was another unusual feature. mood in Heinerscheid. A further possible to 4 billion kWh a year. 89 per cent of the
The “Heinerscheid Windpark” project, run reason could be that rights to obtain necessary energy is imported, a high
by Wandpark Gemeng Hengischt S.A., shares were granted to residents in the proportion of it coming from the RWE
does not have a single opponent in the community. “Hëpperdanger Wandenergie grid. At present, renewable energy repre-
Heinerscheid community. In Luxembourg s.à.r.l.”, an association of local wind sents about 3.4 per cent of Luxembourg’s
it is known exactly whether residents are energy interests, owns the lion’s share of electric power. The remuneration for wind
for or against a project because the local 25 per cent of the project. One of its energy converters with a rated power
inhabitants are informed by the respon- shareholders, Mr Änder Schanck, is also above 500 kW is composed of the tariff
sible initiators about any planned projects the president of the wind project’s ope- to be paid by the consumer (the day
at a public meeting. Following this they rating company. He explained: “I am an tariff is 6.4 euro cents per kilowatt
can express any doubts or reservations organic farmer, and I wanted a small wind hour, the night tariff 3.3 euro cents) and
in the course of the approval procedure, energy converter as an ecological source a power premium that depends on
either in writing, or in a personal dis- of energy. The mayor convinced me about the contribution to covering peak load
cussion with the local council. Pierre the construction of larger converters. And, in Luxembourg’s grid. For converters
Heinen, a local landowner, joins the of course, I am now happy about that.” with a rated power of less than 500 kW
collected spectators to watch the con- The second largest share, at 22.5 per 7.88 euro cents for each kilowatt hour is
struction team. “My children convinced cent, is owned by the Heinerscheid mu- paid. On top of these prices, the state
me about the green idea”, he explained. nicipality. It presently holds the shares in pays a premium, based on ecological
For that reason he was happy to lease trust, and proposes to transfer 20 per considerations, of 2.5 euro cents per
some of his land to the wind farm opera- cent of the company’s share capital to kilowatt hour. This arrangement is
tors. “The community was involved in this the community’s residents, and retains based on regulations passed in the
project from the very beginning”, is the 2.5 per cent for itself. The remaining share Grand Duchy in 1994, and is currently
explanation Charles Offermann, from the is distributed amongst four other groups. being revised.
6 WIND BLATT 3/2003

The small one goes


the big one comes
Time for a new generation of converters in Schleswig-Holstein

Large picture: An idyllic view of Hans-Reimer Thiessen’s E-66


converter that has taken the place of two Nordtank units.
Small picture: Operator Thiessen (left) and ENERCON
marketing representative Jan Hanssen in Kronprinzenkoog.
3/2003 WIND BLATT 7

This Vestas converter is now being


replaced by an E-66.

An E-66 has now taken the place of a Tacke (now GE) installation.

The name “Koog” refers to reclaimed are of high capacity. “I decided in favour of
land, obtained by draining the water an ENERCON converter, because at that
time I did not know for definite whether I
from between two dykes. Wind-free
would be allowed to feed the full power into
days are unknown in these regions of the grid. And because it is possible to limit replacing old converters by new ones:
Schleswig-Holstein’s west coast. the output of ENERCON converters to any “It is an excellent opportunity because it
desired power, this was the best option”, encourages further development of the
he prevailing wind conditions are recalls Mr Thiessen. It has now, however,
T so ideal here that the local inhabi-
tants set up the first 55 kW wind energy
become clear that the converter can be
operated at its rated power. Last year, the
wind sector while helping to reduce pres-
sure on the appearance of the landscape.
The new converters also reinforce the
converters in the middle of the 1980s. A 65 m high E-66 yielded 4.5 million kWh. leading role that wind energy must play in
wide variety of converter types were in- Like Mr Thiessen, a large number of “wind- the necessary changes to energy policy.”
stalled here over the years. Some of them mill” operators in the Koog have filed And Voigt already knows how forceful these
have now been in place for nearly 20 years. applications for similar projects. changes will be: “The first estimates indi-
So it is no surprise that operators here, cate that by 2010 something like 1,000 MW
more than in any other region of Germany, In the neighbouring Kaiser-Wilhelm-Koog, of additional power can be installed in
are thinking in terms of replacing old wind at a wind farm belonging to the Windtest Schleswig-Holstein in this way, without
energy converters with new and more firm, the large “Growian” converter drew a having to assign any new suitable areas.”
powerful models. Farmer Hans-Reimer lot of attention in the 1980s. Dipl.-Ing. Jan
Thiessen’s converters were amongst the Hanssen, from ENERCON’s marketing Hermann Albers, chairman of Schleswig-
first in Kronprinzenkoog. “If I was still department in Marne, grew up at Dith- Holstein’s Regional Association for Wind
just a farmer today, then I would have to be marschen in Schleswig-Holstein. “I was Energy, nevertheless fears that the govern-
looking for a new job”, he says, watching familiar with the 3 MW converter”, he re- ment may place obstacles in the path of
pensively as a tractor passes by, white members. Close to the test field, in the wind energy converter operators. Regional
cabbages rolling around its trailer. And Westküste wind energy farm, small con- guidelines for wind energy are at present
now Mr Thiessen, though he might verters from Tacke (now GE), HSW and being revised. Amongst other rules, they
modestly deny it, is again amongst the Adler had to make way for an ENERCON place a limit of 100 m on the total height of
first. This time, it is in the replacement of E-66 converter. A little further on, there is wind energy converters. But Hermann
old converters with a new generation: at a 600 kW Vestas V 42 that is presently Albers takes a different view. “We natural-
the end of 2001 an E-66 (1.8 MW) arrived being replaced by an E-66. ly want to exploit the latest developments
in order to replace two of his Nordtank con- in technology, for instance higher towers
verters, each of which provides 300 kW. As the German Wind Energy Institute and larger rotor diameters.” The govern-
The project was implemented quickly and (Deutsche Windenergie-Institut, DEWI) in ment has, however, made concessions,
without any difficulty, especially because Wilhelmshaven wrote in its report in March and tolerates converters up to 150 m. In
the E-66 was being set up within an of 2003, the installed capacity in 2002 was compensation, however, the distance that
existing wind farm. Only noise and turbu- 22 per cent more than the figure for 2001. the guidelines specify to be maintained
lence reports were required. Mr Thiessen Each new converter, with an average power from residential areas is to be increased.
was lucky that his converters are located of almost 1.4 MW, is nine percent more Whereas in the past converters could be
in a wind energy precedence area, desig- powerful than the average converter power erected within 1 km of the nearest village,
nated some years ago by the regional installed in 2001. According to the DEWI a distance of 1.5 km will in future have to
authorities. Replacing converters outside report, in 2002, 8 new wind energy con- be maintained. Hermann Albers does not
these areas, on the other hand, is only verters, with a total power of 12.7 MW, re- think that is right: “With this requirement,
possible if the municipality concerned placed 16 old units totalling 5.4 MW. the regional government is no longer
agrees to a corresponding development sailing full ahead. Those in power seem
plan. There is, furthermore, the question of Wilfried Voigt, state secretary in Schleswig- to have forgotten that we can do more
whether the necessary grid capacity is Holstein’s Ministry for Industry, Work and for climate protection by using more wind
available when the replacement converters Traffic, has no objections to the plan of power.“
8 WIND BLATT 3/2003

Pure copper
from Hamburg
Suppliers purchase from Norddeutsche Affinerie

Europe’s leading copper producer is at the same


time the world’s largest copper recycler:
Norddeutsche Affinerie (NA), with headquarters in
Hamburg, supplies the raw copper used for ENERCON
generators. In 2002 alone, ENERCON used 8,000 t
of copper in the form of enamel-insulated wire
for the windings of stators and pole shoes.

A copper-coloured Smart takes us


across the huge site of the com-
pany’s refinery in Hamburg-Veddel. Past
of layers, and has a total thickness of
between 98 and 104 µm.
and conveyor belts. As the finely ground
composite materials glide past on con-
veyor belts, natural gas, oxygen and
mountains of wire, some of it brown and All of ENERCON’s supply companies buy cooling water are supplied through the
thick as a finger, while other is bright red their raw copper in Hamburg. And it is pipes, while exhaust fumes travel in the
and extremely fine. Compressed water very probable that after many thousands opposite direction.
pipes and pressed blocks of copper plate of hours of operation in a wind energy
are stacked house-high in front of red- converter, the copper will return to the It is hot in the copper works, and fumes
brick buildings. very same place. The “red gold” might rise here and there above splashing
then find its way into a coin. And so it streams of copper. Anyone who works
Europe’s leading copper producer is at goes on. Because copper can be recycled here soon starts to sweat. Before the pure
the same time the world’s largest copper any number of times without any loss of metal is obtained, both used copper and
recycler. Chairman of the Board, Dr. value or quality. copper concentrates obtained from ores
Werner Marnette, sets the record straight: must pass through a variety of processes.
“Copper is not consumed”. It is simply Norddeutsche Affinerie processed a total They are melted, together with sand
employed for a certain purpose for a of 1.3 million tons of raw materials last to assist slag formation, in the flash
certain time. For the ENERCON ring year, with a copper content of 554,000 t. smelting furnace at above 1,200 degrees,
generator, for instance: 8,000 t of pro- Nearly one million tons of this were forming crude copper and iron silicate
cessed copper wire is purchased by copper concentrates from ores imported slag.
ENERCON each year from a number of from Chile, Peru or Argentina. 355,000 t
different suppliers for the generator of copper from scrap and recycled mate- Blister copper, as it is known, is formed in
windings. ENERCON’s suppliers process rials comes almost entirely from Western the converter; the oxygen will later be
the copper obtained from Norddeutsche Europe. withdrawn from this in the furnace.
Affinerie, converting it to lacquered wire Orange-glowing anode plates, containing
with an insulating coating. It possesses a If we now leave behind the mounds of 99.5 per cent copper, are cast from this
particularly high long-term temperature cable ground to fine dust we reach the copper. In a final step, the anode plates
resistance of 200 degrees Celsius. The part of the company’s site that is domi- are submerged in an electrolytic tank.
lacquer is applied to the wire in a number nated by enormous, intertwined pipes The copper separates here to create
3/2003 WIND BLATT 9

cathodes with 99.99 per cent purity. the electrolytic tank for every ton of
The refinery has been using this electro- copper. At an average production of about
lysis procedure on a large industrial 1,000 tons of copper, this amounts to
scale since 1876. The refinery’s chemist, 300,000 kWh a day. No wonder Dr.
Emil Wohlwill, carried out intensive re- Marnette complains about high electrici-
search in pursuit of this high level of ty prices: “They are damaging Germany’s
purity. economy.” The blame for the high prices,
in his opinion, lies primarily with govern-
The copper comes onto the market in the ment intervention, and with the near mo-
form of continuous cast and rolled wire, nopoly held by a small number of power
continuous cast mouldings, billets, strip companies in what was once a liberalised
and section wires. On top of this, all the market. At the same time, Dr. Marnette
by-products that naturally occur in the calls on the government for competitive
course of copper extraction are also sold, electricity prices to apply also to renew-
from iron silicate stone, which will be able energies. He acknowledges the con-
used to reinforce embankments, through tribution of the largest German manufac-
to gold and silver. turer of wind energy converters: “With
the aid of high-quality copper, the power
Copper processing, and electrolysis in quality is optimised, and the converters
particular, is an energy-intensive under- run efficiently. I think that ENERCON is
Dr. Werner Marnette, Chairman of the Board
taking. 300 kWh of energy is required in pursuing the right policy.” of Norddeutsche Affinerie.
10 WIND BLATT 3/2003

Firmly rooted
ENERCON supports new foundation guidelines

A wind energy converter must these are inspected separately in the nents satisfy the requirements. The DIBt
context of the converter certification. guideline takes particular account of spe-
withstand the force of the wind for
According to the definition in the building cial conditions applying to wind energy
many years. From the tip of the rotor regulations, the machine is supported by converters, and formulates additional
blades to the base of the tower, a structure. The complex dynamics in- regulations.
volved are, however, scarcely considered
its components are designed to in the foundation calculations. By and large, the same rules are applied to
meet this demand. The foundations, the foundations of wind energy converters,
“Wind Energy Converters – Forces and with their special dynamic properties, as
anchored deeply in the ground,
Stability Verification for Tower and Foun- apply to other structures. In other words,
are now to be made even stronger. dations” is the guideline published by safety specifications that have been de-
the German Institute of Construction veloped for conventional, stationary struc-
Engineering (Deutsches Institut für Bau- tures are, in accordance with DIBt, trans-
n Germany, wind energy converters,
I like any other building from a light-
house to an advertising pillar, are in-
technik, DIBt), and has been the basis
for foundation calculations in the wind
energy sector according to German con-
ferred to the wind energy sector.

Under the currently applicable guidelines


spected to ensure compliance with struction regulations since 1993 (second, and standards, an opening of the ground
building regulations. The tower and the revised edition, 1995). The guideline de- joint is permissible both under dynamic
base, together with the foundations, are scribes possible loading situations, wind operating stresses and under rare ex-
subject to this inspection, although the conditions and structural specifications treme loadings. This means that there can
nacelle and the rotor blades are not – required to demonstrate that the compo- be conditions under which the sole plate
3/2003 WIND BLATT 11

of a raft foundation does not have to be in It is always possible that a ground saddle
ground contact over its whole surface will form if the building ground gives
Test loading
(see Fig. 1). In comparison with the other way locally, so that the foundation then of the E-112
components of the wind power converter, wobbles on the remaining supporting deep foundation
the ground joint is very hard to inspect. surface.
The second prototype of the 4.5 MW
Repeated inspections do not allow its
E-112 converter will be erected this
condition to be assessed, and subsequent Some foundations for steel towers will, in
year at the Jade wind farm near
improvements are to all intents and pur- exceptional cases, require an increase in
Wilhelmshaven. The quality of the
poses impossible. the foundation mass of up to 50 per cent
ground calls for a deep foundation
under the modified requirements, where-
Therefore the loading capacity of the foun- consisting of 64 pillars, each of which
as the foundations for heavy concrete
dation according to the currently valid ver- towers, on the other hand, are generally is 14.5 m long.
sion of the guideline is capable of further not going to be subject to any change. This type of pile foundation has not
optimisation. This is confirmed by Prof. been built before. In order to estimate
Horst Bellmer, a structural engineer with “At present, the costs of a foundation its loading capacity, therefore, the
the Bellmer Ingenieurgruppe in Bremen: represent between three and five percent construction company responsible has
“I have indeed seen a few foundations in of the project cost. The additional costs
now carried out trial loadings on two
Germany where the design was only required for this higher level of safety in
piles of the type involved immediately
just adequate. Any construction mistakes foundation construction are entirely rea-
next to the site. The “Franki piles”, as
made at the bottom of such a structure sonable in relation to the total investment
they are known, achieve particular
cannot be compensated for at the top.” involved in a wind farm project”, states
stability through a wide pile base.
ENERCON construction engineer Torsten
In the context of raising safety levels from The force of 1,800 kilonewtons
Jepsen.
the tip of the blade to the foundation, (corresponding to 180 t) on each pile
ENERCON has therefore tightened its own ENERCON is now aiming to introduce the corresponds to the maximum working
requirements for the design of founda- newly calculated foundations immediate- load acting on the E-112. It is reached
tions. ENERCON’s construction engineers ly for all future projects. Jepsen assumes at a wind velocity of about 58 m/s.
have given critical consideration in par- that other manufacturers and project When the corresponding force was
ticular to the capacity of the building planners will follow this example. The applied hydraulically to the test piles,
ground to absorb dynamic loading, and corresponding guidelines will probably be they moved no more than 3.5 mm in
the special case of ground joints that adjusted in the near future. the ground. Doubling the force to
come open. For this reason, ENERCON 3,600 kilonewtons caused the piles
has modified the specifications for foun- Although the DIBt guideline only applies to sink by 9 mm. “That is an out-
dation design so that components are not to Germany, in the light of the higher standing result", was ENERCON pro-
overloaded. This will avoid both tilting of safety level ENERCON will also intro- ject manager Dipl.-Ing. Olaf Kunert’s
the converter and the formation of a duce the new foundations for projects
enthusiastic reaction.
“ground saddle” (Fig. 2). abroad.

Fig. 1: Ground compression resulting in a ground joint that is up to half open. Fig. 2: Foundation on a ground saddle.
12 WIND BLATT 3/2003

A question of safety
Interview with the manager of the Grid Operation Department, Siegfried Grochow

T he maintenance of transformer
and interconnection stations is
frequently offered nowadays by power
serious for those responsible. It is for this
reason that only trained ENERCON staff
work there.
sibility for the equipment in accordance
with DIN VDE 0105. All the switching
operations necessary in operating inter-
companies and specialist engineering connection or transformer stations, e.g.
companies, sometimes at a very high WIND BLATT And what if the operator in the context of extensions, servicing
price. When considering such offers, wants to go into the transformer or inter- work or malfunctions, are coordinated
many operators of wind energy con- connection station, say to to check the by our department. In fact this often
verters simply forget that, provided the supply meter? happens when a wind farm is first
stations were included in the company’s commissioned, although this is usually
overall scope of supply, this service is Grochow: Then he can do so, accompa- managed by the electrical engineers of
already covered by ENERCON through a nied by an ENERCON service electrician. the project management team, and
servicing contract or the ENERCON Part- Electrotechnical instruction, in conformi- agreed with us.
nership Plan. Electrical engineer Sieg- ty with the UVV, by specialist ENERCON
fried Grochow manages the Grid Ope- staff also gives the operator limited WIND BLATT Why is consultation
ration Department. This department is about these switching operations neces-
responsible for the technical operation of sary at all?
the low, medium and high voltage com-
ponents required for the connection of Grochow: It enables us to ensure safety
ENERCON converters to the grid, and for the electricians and for the grid on
developed out of the electrical project site. It is very much like opening a circuit
management area. breaker at home because you want to
install a new lamp. The difference is that
WIND BLATT Herr Grochow, is it real- here we are dealing with a 20,000 volt
ly necessary for ENERCON to have a Grid supply grid instead of a 230 volt house-
Operation Department? Can’t the opera- hold supply, so that even a tiny mistake
tors look after the servicing of the elec- can have enormous consequences.
trical stations themselves?
WIND BLATT And what is the task of
Siegfried Grochow.
Grochow: This is first and foremost a the Grid Operation Department during a
matter of safety. According to the authorisation if he wants to enter the service?
accident prevention regulations (UVV) stations alone. Because of the generally
published by the employer’s liability in- high levels of risk, however, this pro- Grochow: The service electricians on site
surance association, only trained per- cedure is exceptional, and the situa- are given instructions over the telephone
sonnel are allowed to enter transformer tion will be examined in each individual by the Grid Operation Department, telling
or interconnection stations. This also in- case. them how to proceed with the work with-
cludes the transformer stations inte- out putting themselves or the grid at
grated into the tower, such as the WIND BLATT What activities fall with- risk. The entire station, including the
E-module. The law obliges us, as the in the scope of the Grid Operation De- switchgear and the transformer, is first
responsible electrical concern, to ensure partment? thoroughly cleaned. A visual check is
that the equipment operates properly, is made to see, amongst other things,
regularly serviced, and that neither the Grochow: We ensure the smooth and re- whether there are any signs of oil or gas
customer nor our service staff are put at liable operation of the grid connection loss. Functional checks of the switchgear,
risk. If an accident should happen, per- equipment supplied by ENERCON parallel for instance, are also included. So is in-
haps from touching a live component, the to the grid itself, both in Germany and spection of the protective equipment,
consequences can be physically severe abroad. For that reason the process when necessary, to ensure that the grid
for the person concerned and legally always starts with assumption of respon- protection is fully intact.
3/2003 WIND BLATT 13

Following the switching discussion, service


electrician Heinz-Wilhelm Diekmann under-
takes connection of the wind energy converter.
His colleague, Georg Fresenborg, waits outside
the interconnection station during this time, for
reasons of safety.

Peter Schmidt explains to


the service team at the Neer-
moor wind farm what must
be borne in mind to connect
a wind energy converter.

A hotline to service
Peter Schmidt coordinates switching operations in grid operation

Peter Schmidt looks at the clock. It is 11.30, the time agreed already unlocked the door with its yellow “Warning – high-
for the beginning of the “switching discussion”. In the course of voltage” sign, and are standing in front of a series of control
this telephone call, Mr Schmidt will talk to a service electrician panels in the small green-painted concrete hut that houses the
on site at a wind farm, giving instructions for switching off a farm interconnection station. Peter Schmidt now explains what
farm, an individual converter or an interconnection station, has to be done to carry out the service: “Visual check of the
connecting it to the grid, or switching it on again. Today the cable connections.” (Are all the cables really properly con-
two service engineers, Georg Fresenborg and Heinz-Wilhelm nected?) “Earth disconnection.” (In this way all the circuits are,
Diekmann, are in front of the farm interconnection station at for safety reasons, to be considered as electrically live, and can
the newly erected Neermoor wind farm in East Frisia. Wind energy be approved for connection.) “Switch on the power switch.” Mr
converter 6, an E-66 (1.8 MW), is to be switched on for commis- Schmidt has given his instructions, and it is now the service
sioning. engineer’s job to repeat the instructions so that both sides are
certain that nothing has been forgotten or misunderstood. Then
The switching discussion is the life assurance for the two it can start. Mr Schmidt says goodbye and leaves the service
service engineers. A discussion gives them certainty that engineers to their work.
nothing will happen to them while they are working with the
electrical power. Peter Schmidt is also informed as to whether Wearing a helmet, face protection and tightly closed protective
the medium-voltage cable has been properly inspected, in cotton clothing, Heinz-Wilhelm Diekmann enters the intercon-
what sequence the converters are switched on, and whether nection station again, because he knows that the risk of a fault
perhaps a second service team is working at the same time in arc is greatest at the time of initial commissioning. He uses two
another part of the wind farm, and therefore will have to be different versions of the switching handles, specifically designed
informed. for the particular switchgear, for the earth disconnection and for
the connection of the equipment. This prevents any possible con-
Peter Schmidt has now called up the equivalent circuit diagram fusion. The drive mechanisms for the earthing switches are also
of the Neermoor wind farm onto the screen of his PC. He now secured by padlocks, for which only the specially trained
sees precisely how the converters are connected to the farm ENERCON service team has a key. As the conclusion to the
station, and how the current will have to be guided. Georg switching discussion, the two engineers report execution of
Fresenborg dials Peter Schmidt’s number, and is able to say the switching as planned to their colleague Mr Schmidt. Com-
hello a few moments later. The two service electricians have missioning of converter 6 can now begin.
14 WIND BLATT 3/2003

A d d r e s s e s
ENERCON International sales offices
ENERCON GmbH, International Dept.
Otto-Lilienthal-Str. 25
28199 Bremen · Germany
We need
Phone: +49 421 2441520
Fax: +49 421 2441539
e-mail: sales.international@enercon.de
AUSTRIA
Hauptstr. 19A · 2120 Wolkersdorf · Austria
Phone: +43 2245 82828
Fax : +43 2245 82838
e-mail: enercon@vienna.at
following
SWEDEN
c/o Energy Converter AB
Stenåldersgatan 19 · 21376 Malmö · Sweden
BWE president, Dr. Peter Ahmels, on the current
Phone: +46 40 143580
Fax: +46 40 222420
e-mail: mail@enercon.nu
GREAT BRITAIN
Axiom House, Station Road
Stroud, Glos. GL5 3AP · Great Britain
Phone: +44 1493 782018
Fax: +44 1493 789094 The developments in other countries show that
e-mail : info@enercon.co.uk
SPAIN
ENERCON Spain S.A.
this is by no means a foregone conclusion.
c/o València Parc Tecnològic
Av. Juan de la Cierva, 27
E-46980 Paterna Valencia · Spain
In Denmark, thanks to the installation of a
Phone: +34 961 3678-70
Fax : +34 961 3678-75 number of offshore wind farms and a govern-
PORTUGAL
c/o Gellweiler Lda.
Travessa do Alecrim, 3 - 2° ment-supported repowering programme in
1200 Lisbon · Portugal
Phone: +351 21 3420021
Fax : +351 21 3420026 2002, it was just possible to prevent the
e-mail: aesteves@gellweiler.pt
BENELUX
Van Karnebeekstraat 125
wind market from collapsing, while in the USA
8011 JE Zwolle · The Netherlands
Phone: +31 38 4228282
Fax: +31 38 4228010
there has, for years, been a stop-go situation
e-mail: sales@blx.enercon.de
TURKEY that does not allow the wind sector to develop
ENERCON Service Ltd. Sti.
PK.: 23 Kiziltoprak · Istanbul · Turkey
Phone: +90 216 4149202 continuously.
Fax: +90 216 3452959
e-mail: enercon@doruk.net.tr
DENMARK
Bredkaer Parkvej 62 · 8250 Egaa · Denmark
Phone: +45 87 430388 To get to the point, there is no other country
Fax: +45 87 430344
E-mail: kristensen@enercon.de
ITALY in the world that offers such good conditions
ENERCON Service Italia S.r.l.
Via G. Della Casa 7 · 82100 Benevento · Italy
Phone: +39 082 425257
for wind energy as Germany. With 12,000 MW
Fax: +39 082 4336883
e-mail: enerconitalia@tin.it installed, and with 40 per cent of the wind
GREECE
ENERCON S.A.
20, Pentelis Ave. · 15235 Vrilissia power that has been installed in the whole
Athens - Greece
Phone: +30 106838490
Fax: +30 106838489 world, we are in an undisputed number one
e-mail: enerconh@otenet.gr
AUSTRALIA
ENERCON Powercorporation Pty. Ltd.
position.
3406 Export Drive · Trade Development
Zone · Northern Territory
NT 0822 Darwin · Australia
Phone: +61 889470933
Fax: +61 889470925 But we should not fool ourselves: the more
e-mail: mail@pcorp.com.au
EGYPT
c/o Zaki International Trading successful we are, the stronger the headwind.
23 Kasr El-Nil StreetCairo 11111 · Egypt
Phone: +20 2 3923670
Fax: +20 2 4170023 BWE president, Dr. Peter Ahmels.
Industrial sectors that consume large amounts
e-mail: zit@starnet.com.eg
CANADA
Wind Power Inc.
of electrical power complain about the special
Suite # 222 Lebel Manison
696 Kettles Street, Pincher Creek burdens, particularly those created through the
Alberta TOK 1 WO · Canada
Phone: +1 403 6272923
Fax: +1 403 6273239 Dr. Peter Ahmels, president of the German Renewable Energy Law, although the
e-mail: wpi@windpower.ca
INDIA ecology tax and the excessive grid charges in
ENERCON (India) Ltd.
Kolsite House, Plot Nr. 31
Federal Wind Energy Association
Shah Industrial Estate
Veera · Desai Rd., Andheri (West)
fact play a much greater role.
Mumbai 400 053 · India
Phone: +91 22 56924848
(Bundesverband WindEnergie), speaks
Fax: + 91 22 26730085 / 26730089
e-mail: mktg@enerconindia.net
BRAZIL about the goals that have been achieved Particularly at this stage it is therefore important
Wobben Windpower
Industria e Comércio Lda.
Av. Fernando Stecca n° 100
that we clarify the reasons for high electrical
Distrito Industrial CEP and the growing significance of strong
18087450 Sorocaba · Sao Paulo · Brazil power prices. One of our strengths, which will
Phone: +55 15 2283737
Fax: +55 15 2283887
e-mail: wobben@splicenet.com.br representation in the wind energy sector. help to distribute our arguments as widely as
possible, is the decentralised structure of the
I m p r i n t
WINDBLATT MAGAZINE sector. There are a large number of political
Publisher: ENERCON GmbH
ho would have thought it a few years interfaces in the various regions, and these in
Dreekamp 5, 26605 Aurich
Phone: +49 4941 927-0
Fax: +49 4941 927-109
www.enercon.de/english/fs_windblatt_e.html
Editorial office:
ENERCON GmbH Aurich, Nicole Weinhold
W ago: the proportion of wind energy has
now reached almost five per cent of Germany’s
turn can take a positive image back to Berlin.

nicole.weinhold@enercon.de
Printed by: net electricity consumption. Thanks to the wide Altogether, the Federal Wind Energy Association
Steinbacher Druck GmbH, Osnabrück,
Phone: +49 541 95900-0 support for the exploitation of new energies, (BWE) now represents 14,200 companies, firms
The WINDBLATT magazine appears every two
months and is regularly included in the news-
paper “New Energy” – magazine of the
there was a strong enough following wind from and individuals. At this size, the association is
Federal Association for Wind Energy. Phone:
+49 541 350600 or Fax: +49 541 3506030 society for us to achieve a new installation now in a good position to put its ideas and aims
record year after year. into the public arena.
3/2003 WIND BLATT 15

more Info Service


June/ July 2003
wind! 04- 05/06/ Key Account Management
2003
Berlin
in the Electricity Supply Company
Organiser, and information from:
situation of the wind energy sector in Germany Management Circle AG
Tel. +49 (0)6196 4722800
Fax +49 (0)6196 4722888
kundenservice@
Considering the over 200,000 people The association’s magazine NEUE ENERGIE
managementcircle.de
who have participated in German wind (NEW ENERGY) keeps members informed www.managementcircle.de
projects, and the 41,000 jobs in the on a monthly basis of what is going on in
sector, the BWE is nevertheless still a the wind sector. It is also possible to 16-18/06/ Berlin Energy Days 2003
relatively small player. participate in events such as our semi- 2003 Organiser, and information from:
nars at a reduced price. Berlin Berliner ImpulsE-Management,
Thorsten Poppe
The Federal Association is the crucial body Tel. +49 (0)30 21752107
for matters of representation in the wind If the BWE is to continue to generate the Fax +49 (0)30 21752109
energy field. The members of the BWE necessary following wind, it needs the poppe@eumb-poeschk.de
benefit from a broad information exchange backing of a large membership. A www.berliner-energietage.de
taking place within the association. Wind free information pack is available by
16-19/06/ EWEC European Wind Energy
energy converter owners, planners, tech- telephoning +49 (0)541 350600, faxing
2003 Conference
nical experts, legal specialists and manu- +49 (0)541 3506030 or by e-mailing Madrid Organiser, and information from:
facturers have got together within the BWE info@wind-energie.de. There is also Spain European Wind Energy Association
to form committees and working groups, more information on our website at (EWEA)
in order to keep each other informed. www.wind-energie.de. Tel. +32 2 5461940
info@ewea.org
www.ewea.org

Well-informed 25/06/2003 “Yield Improvement Through


Hamburg New Technology” Symposium
about wind energy Organiser, and information from:
smart dolphin GmbH
For many years now, it has been im- present possible future scenarios. At the Martin Tschierschke
Tel. +49 (0)40 40171657
possible to imagine school education same time, the CD-ROM provides a rich
info@windmesse.de
without the topic of environmental pro- resource on the topic of wind energy www.Windmesse.de
tection. Since the Kyoto conference, if (technical and political aspects). Pre-
not before, the changes that human sentation slides ensure that the topics 02/07/2003 The Implementation of
activities are causing to the climate are clearly presented. The CD-ROM Osnabrück Photovoltaic Installations
have also taken a firm place in the “Wissen Windenergie” (Wind Energy Organiser, and information from:
Otti-Energie-Kolleg
curriculum. Knowledge) is available from the BWE
Tel. +49 (0)941 2968829
(tel. +49 541 350 600). Fax +49 (0)941 2968817
For this reason the Federal Wind Energy viola.janik@otti.de
Association (BWE) has now, with the www.otti.de
support of the Environment Ministry,
released a CD-ROM on the topic of 08-09/07/ “Introduction to the Energy
2003 Economy” Seminar
climate protection in science and poli-
Munich Organiser, and information from:
tics, suitable for use in school education. Euroforum Deutschland GmbH
Starting from the current energy situa- Daniela Molicki
tion, considerations are presented in Tel. +49 (0)211 96863434
both German and English as to how Fax +49 (0)211 96864040
info@euroforum.com
energy supply may look in the future.
www.euroforum.de
Energy experts such as Hermann Scheer
WIND BLATT The ENERCON Magazine
artist from Westphalia. “I think
that a wind energy converter
is a beautiful object in itself”,
he announces. “And, in its
usual colours, it fits harmo-
niously into the landscape.”
But once in a while it is also
possible to draw people’s
attention to it, and one way
is through the lighting tech-
nology provided by his com-
pany, Licht-Service. Franz-
mann states: “For me, light is a
form of representational art,
and light can also be used to
create a visual impact”. His
success proves his point: he il-
luminated the cinema complex
for the Harry Potter premiere,
and also turned the spotlight
on the Porsche Centre for the
launch of a new model.

Mr Franzmann is the director


of a number of different firms
grouped under the umbrella
of HWP-Verwaltung GmbH,

Pop art with E-66 based in the village of


Hempsen near Höxter. In fact,
The wind energy converter as an object of light art his family comes from near
Brunsbüttel, he explains, and

T he nacelle glows pink against the


black night sky. Its colour then
slowly changes, glowing in neon yellow,
ideally illuminated from every point of
view. He then alters the colours from a
mixing desk. With the three primary
that is where his passion for renewable
energy began. “It was in 1992, when I was
still doing my community service, that I
and a little later in blue. The wind energy colours yellow, magenta and cyan he is saw a wind energy converter for the first
Windblatt is printed on recycled paper. Printed with Ökoplus printing ink.

converter creates the effect of a piece of able to “mix” any desired colour. He lets time, found out more about it, and
pop art, and seems somehow not to be of an arc of light like a rainbow curve around convinced my father that we should
this world. This is also the impression the converter, and then plunges the implement a wind project ourselves”, he
gathered by the spectators who have wind energy converter into uniform light, remembers. The E-66 that is being lit
collected around the unique piece of lumi- changing from one colour to another. up in colour was finally installed, to-
nous art, attracted by the strange view. Franzmann knows a lot about two things gether with an E-58 (in the Harburg
in particular: wind energy converters and wind farm), last year. Franzmann has
Steffen Franzmann runs backwards and designing with light. This combination planned two more E-66 converters there.
forwards between four special 2,500 watt was the trigger for the light spectacle He is also working with biomass and
lamps, shining up to the nacelle from the staged on this cool April night. At the photovoltaic energy. He has been inter-
foundation of the E-66. The 33 year-old same time it was also a very special ested in wind energy for 12 years, and in
adjusts the lamps so that the nacelle is occasion for the wind pioneer and light light for 17.

Potrebbero piacerti anche