Seismic Upgrades Report

Salem-Keizer School District


August 14, 2014

SKSD Facilities Department Page 1

Auburn Elementary School Added plywood shear panels at exterior walls. 2009
Brush College Elementary School Existing windows removed and replaced with wood
framed shear wall panels in classrooms 1-6 and the
west side of classrooms 16-17
2010
New plywood sheathing on the covered play and
straps, new sheathing over the administration area,
connections made at the front entry corridor.
2011
Candalaria Elementary School Added plywood shear panels at exterior walls and
added concrete shear walls below the Multi-Purpose
Room.
2011
Chapman Hill Elementary School The perimeter of the gym received plywood sheathing
at the roof only.
2009
Cummings Elementary School Remove existing adhesive applied ceiling tiles and
replace with new seismic braced suspended T-Bar grid
and acoustical tiles on the N-S and E-W ceilings of the
classroom wings, south of the main entrance.
2011
At the gym, plywood sheathing on the roof and tension
ties on the sides with added plywood sheathing
installed with roofing project.
2010
Englewood Elementary School New suspended acoustical tile ceiling installed
throughout the 2nd and 3rd story corridors with
current seismic bracing standards.
2010
New plumbing installed with current seismic bracing
standards.
2010
Added interior skeletal structure to support existing
floor and roof, corridor shear walls, strengthen exit
canopies, strengthen exterior fire staircase, demolished
chimney.

2013
Seismic Upgrades Report
Salem-Keizer School District
August 14, 2014

SKSD Facilities Department Page 2

Four Corners Elementary School Shear walls added between new windows to upgrade
seismic.
2010
Grant Elementary School New shear walls at perimeter window wall systems to
withstand lateral movement.
2012
New HVAC unit installed with current seismic bracing
standards.
2012
Added tension ties from roof to parapet walls at gym
and gym entry.
2010
Hayesville Elementary School Two covered play areas, multipurpose room and
walkways received plywood sheathing and tension ties.
Perimeter of building received straps.
2011
Highland Elementary School Added interior skeletal structure to support existing
floor and roof, corridor shear walls, strengthen exit
canopies, strengthen exterior fire staircase, demolished
chimney.
2014
Hoover Elementary School Added plywood shear panels at exterior walls. 2010
Plywood sheathing over the most of building, did not
add over media center wing.
2010
Liberty Elementary School Added plywood sheathing to the building except for
media center and 1964 addition. Added straps at the
perimeter of the building, tension ties at the media
center.
2011
Morningside Elementary School At the south side of classroom wing, both upper and
lower floor levels, existing windows were removed and
replaced with wood framed shear wall panels.
2012
Myers Elementary School Roof straps were added at each of the two covered
play areas.
2011
Rosedale Elementary School Added plywood sheathing, straps at the perimeter of
the building.
2010
Seismic Upgrades Report
Salem-Keizer School District
August 14, 2014

SKSD Facilities Department Page 3

Salem Heights Elementary
School
At the west side of 1957 classroom addition, existing
windows were removed and replaced with wood
framed shear wall panels.
2012
Schirle Elementary School New plumbing and HVAC installed with current seismic
bracing standards.
2011
New wall partitions braced to structure with current
seismic bracing standards.
2011
New mechanical unit anchored to new concrete pad
with current seismic bracing standards. 4. Existing
suspended light fixture bracing was updated to current
bracing standards.
2011
Swegle Elementary School Added plywood shear panels at exterior walls over
main building.
2012
Washington Elementary School Added plywood shear panels at exterior walls over
main building.
2010
Wright Elementary School Added plywood sheathing and perimeter straps over
classrooms, north covered play, multipurpose room.
2011
Judson Middle School Shear walls added between windows for seismic
upgrades in all classroom wings.
2012
Waldo Middle School Shear walls added between windows for seismic
upgrades in all classroom wings.
2010
Walker Middle School Shear walls added between new windows for seismic
upgrade. Settlement issue addressed with drilled in
anchors in all classroom wings.
2011
Added plywood sheathing. Tension ties added at locker
rooms to gym.
2012
Whiteaker Middle School Added tension ties to gym wall.

2010
Seismic Upgrades Report
Salem-Keizer School District
August 14, 2014

SKSD Facilities Department Page 4


McKay High School New Kalwall Skylight / Roof System with current
seismic attachment to substrate support.
2011
New HVAC installed with current seismic bracing
standards.
2011
McNary High School On the first and second floor corridor ceilings, removed
existing suspended spline ceiling time and suspension
system and replaced with new seismic braced
suspended T-bar grid and acoustic tiles.
2011
North Salem High School New plumbing and HVAC installed with current seismic
bracing standards.
2010
The media center received plywood sheathing and
tension ties. The aux gym and boiler room received
plywood sheathing, straps, parapet walls anchored to
roof.
2011
South Salem High School New plumbing and HVAC installed with current seismic
bracing standards.
2010
Sprague High School New HVAC installed with current seismic bracing
standards.
2012
New plumbing and HVAC installed with current seismic
bracing standards.
2012
New chiller anchored to existing pad to current seismic
bracing standards.
2012