CSCI321 Final Year Project

BIT-09-6 Secure House


Project Diary

University of Wollongong
CSCI321 Final Year Project
BIT-09-6 Secure House: A building security tool
Project Diary

Project Supervisor: Mr Adrian Choo

Group no: IT09/1B

Group members: Ching Wei Jie Jojo (3564253)


Hong Wenfeng (3564101)
Fatimah (3564071)
Loh Sze Lee (3564149)

Page 1 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary

Introduction

This project diary consists of a set of documents that are used to keep track of
the project timeline and review on project meetings. It contains the project
plan with milestones and all copies of the minutes conducted by the project
team.

Appendix

Documents Date
Project Plan (Gantt Chart) -

Milestones -

Minutes of Meeting 1 18 Mar 09

Minutes of Meeting 2 27 Mar 09

Minutes of Meeting 3 04 Apr 09

Minutes of Meeting 4 13 Apr 09

Minutes of Meeting 5 19 Apr 09

Minutes of Meeting 6 25 Apr 09

Page 2 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary

Project Plan

Milestones

Page 3 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary

Minutes of Meeting 1

MEETING PRELIMINARIES
Project : BIT-09-6 Secure House
Subject : Meeting 1
Place : SIM Date : 18 Mar 09
Time : 1330 Pages : 2

BOARD MEMBERS:

Ching Wei Jie Jojo (3564253) Present Fatimah Present


(3564071)
Hong Wenfeng Present Loh Sze Lee Present
(3564101) (3564149)

APPROVAL:
Minutes By : Wenfeng Date : 18 Mar 09
Vetted By : Jojo Date : 18 Mar 09
Approved By : Jojo Date : 18 Mar 09

No. Subject Matter Remark

1 APPOINTING OF PROJECT LEADER

Project members agreed and appointed Jojo as the Project Manager to steer this
1.1
project

2 PLANNING FOR PROJECT PROPOSAL

2.1 Discussion was conducted on proposal layout. Format was generated and agreed
by the team.

Proposal layout:
 Introduction
- Project introduction
- Development Stages
 Researches
- Applications and devices
2.2 - Strengths and weaknesses
 Design Specification
- Methodology
- Development tool and language
 Marketing Analysis
- Type of housing
- Targeted audiences

Page 4 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary
No. Subject Matter Remark

3 ALLOCATION OF WORKLOAD

Workload was planned and allocated evenly among the team.


3.1

3.2 Work allocation:


 Introduction – Wenfeng
 Researches – Fatimah, Sze Lee
 Design Specification – Jojo
 Marketing Analysis – Wenfeng

3.2 Dateline was set at 19 Mar 09 for further enhancement and consolidation.

4 CONCLUSION

4.1 Meeting was concluded at 1500.

Page 5 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary

Minutes of Meeting 2

MEETING PRELIMINARIES
Project : BIT-09-6 Secure House
Subject : Meeting 2
Place : SIM Date : 27 Mar 09
Time : 2000 Pages : 1

BOARD MEMBERS:

Ching Wei Jie Jojo (3564253) Present Fatimah Present


(3564071)
Hong Wenfeng Present Loh Sze Lee Present
(3564101) (3564149)

APPROVAL:
Minutes By : Wenfeng Date : 27 Mar 09
Vetted By : Jojo Date : 27 Mar 09
Approved By : Jojo Date : 27 Mar 09

No. Subject Matter Remark

1 ENHANCEMENT ON PROJECT PROPOSAL

1.1 Enhancements are done on 2 sections of the initial proposal. Enhanced sections
included ‘Introduction’ and ‘Researches’ sections.

Inclusion of roles and responsibilities, and project plan (Gantt chart and
Milestones) under the ‘Introduction’ section.
1.2
Additional sources on applications and devices, strength and weaknesses are
provided in the ‘Researches’ section.

1.3 A new version of Project Proposal v1.1 was updated.

2 ALLOCATION OF WORKLOAD

Work allocation:
2.1  Enhancement on Introduction – Wenfeng, Jojo
 Enhancement on Researches – Fatimah, Sze Lee

2.2 Dateline was set at 29 Mar 09.

3 CONCLUSION

Page 6 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary
No. Subject Matter Remark

3.1 Meeting was concluded at 2100.

Minutes of Meeting 3

MEETING PRELIMINARIES
Project : BIT-09-6 Secure House
Subject : Meeting 3
Place : SIM Date : 04 Apr 09
Time : 1500 Pages : 1

BOARD MEMBERS:

Ching Wei Jie Jojo (3564253) Present Fatimah Present


(3564071)
Hong Wenfeng Present Loh Sze Lee Present
(3564101) (3564149)

APPROVAL:
Minutes By : Wenfeng Date : 04 Apr 09
Vetted By : Jojo Date : 04 Apr 09
Approved By : Jojo Date : 04 Apr 09

No. Subject Matter Remark

1 PLANNING FOR PROJECT PROTOTYPE

Discussion was conducted on project prototype. 2 key points of focus:


1.1  Suitable applications
 Layout of prototype

1.2 Applications like JAVA 3D, VB, Flash were shortlisted for further researches.
Any suitable applications can also be added.

1.3 Layout of prototype:


 A combination of 3D house layouts
 Able to simulate from one model to another
 Additional models of security devices as drag and drop features

2 ALLOCATION OF WORKLOAD

2.1 All team members will conduct research on shortlisted applications and any
sample source codes.

Page 7 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary
No. Subject Matter Remark
2.2 Dateline was set at 13 Apr 09 for discussion on researches done.

3 CONCLUSION

3.1 Meeting was concluded at 1700.

Minutes of Meeting 4
MEETING PRELIMINARIES
Project : BIT-09-6 Secure House
Subject : Meeting 4
Place : SIM Date : 13 Apr 09
Time : 2000 Pages : 1

BOARD MEMBERS:

Ching Wei Jie Jojo (3564253) Present Fatimah Present


(3564071)
Hong Wenfeng Present Loh Sze Lee Present
(3564101) (3564149)

APPROVAL:
Minutes By : Wenfeng Date : 13 Apr 09
Vetted By : Jojo Date : 13 Apr 09
Approved By : Jojo Date : 13 Apr 09

No. Subject Matter Remark

1 UPDATES ON PROJECT PROTOTYPE

1.1 Consolidation on finding by each team members. Team members have


presented on researches done.

1.2
Jojo conducted researches on JAVA 3D.
 Setting up of applets
 Using loader to upload models
 Found a sample coding on layout of a house

Wenfeng found a suitable application by Google called ‘Google SkretchUp 7’.


 Able to create 3D models and import models from 3D warehouse
 Research in progress

Fatimah implemented on VB to create a sample prototype.


 Creating a combination of 3D models
 Creating directions mode to act as simulation
 Adding of security devices as drag and drop features

Page 8 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary
No. Subject Matter Remark

Sze Lee works on the project website.


 Creating a blog and template of website
 Constructing the layout for the website

1.3 Team members will continue with enhancements on the prototype.

2 CONCLUSION

2.1 Meeting was concluded at 2130.

Minutes of Meeting 5

MEETING PRELIMINARIES
Project : BIT-09-6 Secure House
Subject : Meeting 5
Place : National Library Date : 19 Apr 09
Time : 1700 Pages : 2

BOARD MEMBERS:

Ching Wei Jie Jojo (3564253) Present Fatimah Present


(3564071)
Hong Wenfeng Present Loh Sze Lee Present
(3564101) (3564149)

APPROVAL:
Minutes By : Wenfeng Date : 19 Apr 09
Vetted By : Jojo Date : 19 Apr 09
Approved By : Jojo Date : 19 Apr 09

No. Subject Matter Remark

1 FINALIZE ON PROJECT PROTOTYPE

Team members finalize on the suitable application after all refining done. Java
1.1 As refer to Meeting 4.
3D was selected for further enhancement.

2 COMPARSION

2.1 Google SkretchUp 7 was good for building models and able to import models
but not able to implement drag and drop security feature.

VB can only act as a prototype template, no simulation and drag and drop

Page 9 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary
No. Subject Matter Remark
security features.

Java 3D was able to setup applets and upload models. Simulation can be done
and, drag and drop feature can be included.

2.2 Team members will conduct more refining on the prototype using Java 3D.

3 PROJECT DOCUMENTATION

3.1 On top of implementation, team members also discuss on various project


documents like technical plan, user manual and project diary.

4 ALLOCATION OF WORKLOAD

4.1 Implementation:
Jojo & Fatimah will focus more on implementing the application.

Project Documentation:
Wenfeng will start with the technical plan and compiling the project diary.

Project Website:
Sze Lee will continue to build on the project website.

5 CONCLUSION

5.1 Meeting was concluded at 1900.

Page 10 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary

Minutes of Meeting 6

MEETING PRELIMINARIES
Project : BIT-09-6 Secure House
Subject : Meeting 6
Place : National Library Date : 25 Apr 09
Time : 1900 Pages : 2

BOARD MEMBERS:

Ching Wei Jie Jojo (3564253) Present Fatimah Present


(3564071)
Hong Wenfeng Present Loh Sze Lee Present
(3564101) (3564149)

APPROVAL:
Minutes By : Wenfeng Date : 25 Apr 09
Vetted By : Jojo Date : 25 Apr 09
Approved By : Jojo Date : 25 Apr 09

No. Subject Matter Remark

1 UPDATES ON PROJECT PROGRESS

Team members provide updates on individual work progression and mark on


1.1 As refer to Meeting 4.
project status.

2 IMPLEMENTATION

2.1  Application created using java 3D


 A prototype external house layout was formed
 Rotation can be done by mouse action or rotate buttons (clockwise or
anti-clockwise)
 Images of security devices loaded (security camera, motion camera,
surveillance camera, alarm)

In-progress
2.2  Constructing internal layout
 Drag and drop function

3 DOCUMENTATION

3.1 Technical plan


 Requirements Specification

Page 11 of 12
CSCI321 Final Year Project
BIT-09-6 Secure House
Project Diary
No. Subject Matter Remark
 Project Proposal
 Design Specification
 Test Document (in-progress)
 Project Review
Project Diary
 Project Plan
 Milestones
 Minutes of Meeting (6 minutes to date)

User manual (in-progress)

4 WEBSITE

4.1 Project website was created and still in progression.


 Company info
 Commercial products
 Uploading of documents

5 CONCLUSION

5.1 Team members will continue on enhancements and update on regular basis.

5.2 Meeting was concluded at 2030.

Page 12 of 12