other city houses the range of iconic projects built on JCT contracts like the capital. In recent years it seems the London skyline has been expanding to the tune of a JCT contract at its foundation. Both the Gherkin and more recently Heron Tower are examp|es of the O|ty fex|ng |ts muscles with JCT at the core. Now, a new glass giant casts a long, sharp shadow over its City neighbours: with the completion of The Shard, it is not just London, but Europe that sees the most iconic building constructed on a JCT contract to date. In a climate where stories are currently centred on constructions decreasing output, the loss of jobs and bus|nesses, The Shard |s a defant splinter. The Shard is a story of bombast, of innovation, of going against the current economic grain to make a cultural statement. Those who saw the recent Channel 4 documentary The Tallest Tower, documenting the construction process, know that many of the approaches taken to deliver this landmark were unprecedented for a UK project. Building a 1016ft (310m) tower comprising 900,000sq ft of space between Guys Hospital and London Bridge station is a daunting, costly and logistically sophisticated task, yet main contractors Mace employed some exceptional techniques to complete this complex build in just four years. One example is the UKs largest ever continuous concrete pour 32 hours in total, during which 5,500 cubic meters (about 750 lorry loads) of concrete was poured to allow the top-down JULY 2012 JCTNEWS THE JCT CONTRACTS UPDATE FOR THE CONSTRUCTION PROFESSIONAL SWEET & MAXWELL 3 4 5 6 8 10 JCTs Essay Competition provides boost to industry with support and opportunities for construction students JCT Contracts Discovery the new education module from JCT improves the understanding of contracts for future professionals Using the Standard Building Contract to manage performance Shona Frame, Partner MacRoberts LLP Ground conditions and JCT contracts Jane Fender-Allison - Dundas & Wilson The Bribery Act and Contractual Anti- Corruption Provisions Neil McInnes, Senior Associate, Barrister - Pinsent Masons LLP Chairmans Letter Government trials the JCT - Constructing Excellence Contract THE SHARD EUROPES TALLEST BUILDING COMBINES INNOVATION, DARING AND JCT CONTRACT EXPERTISE >> Continues on page 2 The Shard JULY 2012 JCTNEWS construction method (whereby work on the foundations and core can progress in parallel) to continue. A big pour on most projects would be around 150-200 cubic meters. Mace did this every hour. As development of the core progressed, a hydraulic jump lift was used to transport mater|a|s to the |ncreas|ng|y d|ffcu|t h|gh working points. The lifts were capable of moving three metres per second as opposed to the half-a-metre per second speed of using traditional hoists, meaning a lot of time could be saved. Perhaps most remarkably, the decision to set a 'foat|ng` crane on top of the core rather than inside it allowed structural work to continue no matter the rate of growth. This was only the second time that such a technique had been employed on a project anywhere. Topping Europes tallest building has to be done in style. The Shards striking feature, its broken glass spire comprises 1300 pieces of glass and 500 tonnes of steel, which had to be prefabricated and winched into place piece-by-piece using Europes largest tower crane, often during challenging weather conditions. The success of The Shard in terms of the level of innovation, design and work by the parties involved can now be clearly seen. However, it seems incredible to think how close this project came to not getting off the ground at all. Originally let on a bespoke construction management contract, works packages for The Shard were a|most fna||sed and let, when the recession caused the funding for the project to be pulled. With orders already placed, the outlook was bleak for the client, with the contractor on the verge of backing away. Private funding from Qatar ultimately saved The Shard project but the operation would have to be rethought, under a fxed-pr|ce scheme with a new contract. The contract that the parties chose was a JCT Standard Building Contract Without Quantities, with Contractors Designed Port|on (spec|fca||y SBO 2005 rev|s|on 1 2007). With enough uncertainty around the project already, and with a lengthy renegotiation having to take place, JCT seemed the natural choice. JCT contracts are well known, familiar and risks can be apportioned fairly. Given the experience of the contractor on projects of this size and the experience of the client, the comprehensiveness of SBC was a key requirement. From Maces point of view, it was the best choice because the contract required needed to have a strong background, a proven history and one that could provide key default positions. It was also the most appropriate form for allocating the risks outlined in the project between the parties. An added beneft was a|so the fex|b|||ty of SBC. The client had already gone a long way with the design team, and using the contract with a Contractors Designed Portion meant that certain elements could be handed over to the contractor for completion, with the client still able to retain overall control of the design. It is perhaps testament to the position of JCTs contracts within the industry that even for a project so contemporary, innovative and complex, JCT, and in particular the Standard Building Contract, remains the go-to form. It adapts with the changing needs of the industry, yet its balance, background and proven history make it an excellent choice for when daring and innovation needs a solid foundation. 2 SWEET & MAXWELL >> The JCT Sustainability Lifecycle Consultation closed in April. Responses are currently being considered by the JCT Sustainability Working Group. We would like to thank those who participated in the consultation. JCT SUSTAINABILITY LIFECYCLE CONSULTATION The Shard, London Bridge Chairmans Letter 3 In the April 2012 edition of JCT News an article by Peter Barnes and Nigel Davies looked at partnering as a means to procure construction work more effectively. They also outlined the use of the JCT - Constructing Excellence Contract (JCT-CE), its key features and why they believe it achieves the greatest success of the various forms of partnering contracts that are available. It is, they suggest, more effective in respect of integration and alignment of partnering team members. What constitutes a partnering contract has always been subject of debate and many years ago JCT went to some lengths to clarify what was being sought by the construction industry and its clients. The traditional approach to contracts was seen by some, especially some w|th|n centra| government, as fawed and a|though the concept of partnering had not been wholly embraced it was right to explore the use of a different model. This resulted in the 2001 publication of Practice Note No. 4 (series 2) on partnering. Following further consultation, in 2006 JCT in conjunction with Constructing Excellence introduced JCT-CE to meet a developing desire, especially in the public sector, for an alternative means of procuring construction work. The public sector sought a relationship that was fair, dealt with risk in a more overt way and reduced costs: these objectives were, it believed, achievable through a partnering relationship. The frst pub||cat|on of JOT-OE was, and the recent|y pub||shed 2011 ed|t|on rema|ns, a refned contract that offers great potential to those who seek to collaborate in achieving the common objective of a successful project outcome. It was subsequently shown to satisfy all the requirements of the OGCs Achieving Excellence in Construction [1] . An increasing number of public sector clients have recognised the potential of partnering but government continues its search for more effective procurement and the means to increase savings beyond those already claimed. ln February th|s year, the Oab|net Offce |ssued a paper Government Construction Construction Trial Projects which sets out three new procurement models [2] , namely Cost-Led, Integrated Project Insurance and Two Stage Open Book which it wanted to trial using what |t cons|dered the best ft standard contract form. JCT is pleased that government has chosen JCT-CE for use on a number of the trial projects. JCT-CE is being trialed on the Two Stage Open Book procurement approach, notwithstanding that the Contract Form Working Party appointed by the Procurement/Lean Client Task Group (PLCTG) recommended that it should be used on the Cost-Led approach [3] . Such deliberation is understandab|e as JOT-OE has an |n-bu||t fex|b|||ty to enable its use in either situation. It can be used with a |ump sum or cost re|mbursement approach. The fex|b|||ty that JCT-CE offers is important as users views on each of these approaches are not constant. Although JCT-CE offers such fex|b|||ty the P|OTG was aga|nst mandat|ng a single form of contract for all of its projects. The outcome of any project trial is dependent upon a range of factors, not least the experience of the process adopted and the skill of those involved. Nevertheless, it is right to carry out trials to investigate the operation of var|ous procurement approaches. l am confdent that JCT-CE through its promotion of early and extensive engagement with the supply chain either in conjunction with a framework agreement or stand-alone can drive innovation, identify waste, deal appropriately with risk and |mportant|y de||ver |ncreas|ng cost benefts. The veh|c|e Operator and Serv|ces Agency (vOSA} found th|s to be case and won the integration and collaborative working award at the National Constructing Excellence Awards when using JCT-CE under a framework contract for its new build and refurbishment work on its operating centres [4] . The contract is also used by the Historic Royal Palaces for its building conservation and improvement programme [5] and provides further proof of the contracts great fex|b|||ty |n terms of accommodat|ng d|fferent types of project. The JCT-CE contract and the JCTs Pre-Construction Services Agreements for use in conjunction with JCTs ma|n contract forms prov|de s|gn|fcant opportun|t|es to explore non-traditional approaches to procurement. Used as intended either of these approaches can provide a better end product on time and deliver major savings. Peter Hibberd Chairman of JCT Peter Hibberd GOVERNMENT TRIALS THE JCT - CONSTRUCTING EXCELLENCE CONTRACT [1] Partner|ng Oontract Rev|ew, September 2008 by Arup Project Management for the Offce of Government Oommerce [2] The Interim Report of the Procurement/Lean Client Task Group January 2012 report acknowledges the procurement models are an evolution of existing practice rather than a radical departure page 2 [3] Interim Report of the Procurement/Lean Client Task Group January 2012 page 45 [4] Reported in JCT News April 2009 (www.jctltd.co.uk/vosa-bristol.aspx) [5] Reported in JCT News April 2009 (www.jctltd.co.uk/Hampton-court-surrey.aspx) JULY 2012 JCTNEWS 4 SWEET & MAXWELL JCTS ESSAY COMPETITION PROVIDES BOOST TO INDUSTRY WITH SUPPORT AND OPPORTUNITIES FOR CONSTRUCTION STUDENTS Education remains a major focus for JCT this year. Having launched our Education and Training Initiative formally last year with the JCT Academic Box set, we have continued to provide education resources and opportunities throughout 2012. In addition to the announcement of JCT Contracts Discovery, our new education module, another key activity was the JCT Student Essay Competition, which ran from January to the beginning of June. The competition was set up to provide opportunities for students studying on construction courses, as well as increase the level of understanding of construction contracts throughout the education system. An important overall objective of JCTs Education and Training Initiative is to improve the understanding of the contract process throughout the supply chain, therefore it was important to encourage entries from as diverse a range of backgrounds as possible. The competition was open to any student studying a degree, professional qua||fcat|on, vocat|ona| course, trade apprenticeship or any other construction- related study programme. Peter Hibberd, JCT chair and chair of the competition judging panel, explained the background to the competition: We wanted to do something to help improve awareness of procurement and contracts in the industry, and appreciation of the impact that actions, or inaction, can have upon the supply chain. If we can begin to increase understanding through our education and training initiative, perhaps we can help reduce the number of future problems and disputes, and assist in making the ||d0s||, wo|| mo|e e//c|e|||,. The task for the competition was to produce an essay of no more than 2500 words on one of the following topics: A vision of the future for construction or The future of construction management in the digital age`. The frst top|c was set up to be deliberately broad, although students could choose to comment on the whole industry, or one particular element (e.g. training or sustainability) within the context of the overall question. The second topic is more contract focused, |ook|ng spec|fca||y at the management of construction contracts and their administration in the digital age. With the wide implication of the competition beyond its primary education remit, JCT has assembled a representative judging panel of experts from the education, law, training and skills and media sectors. The panel includes: Dr Ann Heywood, Principal of the College of Estate Management Mark Farrar, Chief Executive of CITB- Construction Skills Tony Bingham, Barrister and Arbitrator at 3 Paper Buildings, Temple and legal columnist for Building magazine Rebecca Evans, Editor of Construction News Peter Hibberd, JCT Chair Tony Bingham further emphasised the importance of the competition in promoting contracts throughout the supply chain: Encouraging better understanding of contracts down the supply chain is commendable. Many disputes arise at trade level, and a better understanding, especially of the consequences of actions, could help reduce the number of problems and disputes on projects, which cumulatively, could help make the industry run more smoothly, and do me o0| o/ a |oo. The judging process has involved some careful consideration of the entries with judges particularly looking for originality, imagination, creative writing skills, clarity of thought. Other factors that the judges considered in the essays are their shape and structure, the ability of the author to keep to the point and demonstration of care and effort. It is JCTs aim that the competition prov|des a s|gn|fcant boost for construction students, and accordingly the prizes available for winners provide both further development opportunities as we|| as fnanc|a| support. JOT |s prov|d|ng 1,000 prizes for winning entries, with prizes of 250 available for runners-up. In addition, in collaboration with the College of Estate Management, a special overall winner prize will be on offer. The entry that the judges believe to be the best will be awarded a 1,000 a year scholarship by the College of Estate Management to study one of their construction courses. The value of this prize would be 4,000 for one of their full Bachelors degree programmes. This one-off overall award complements the existing prizes on offer, meaning the overall winner could be taking home a prize worth 5,000. Ann Heywood, competition judge and CEM Principal explained CEMs involvement in the prize fund: As a key supporter of JCTs Student Essay Competition, we felt that CEM was uniquely placed to provide an additional opportunity for a student in the form of this scholarship prize. It is in the interest of the whole construction industry to improve the knowledge and skills of its students. By working with JCT on a number of projects we are taking proactive steps to ensure that in future our industry continues to maintain the |||es| s|a|da|ds. A special prize-giving ceremony will be taking place as part of JCTs annual Construction Industry Parliamentary Reception on 12th July. The winners and an extract of the winning essay will be published in the October edition of JCT News. 5 JCT has launched JCT Contracts Discovery, an education and learning modu|e a|med spec|fca||y at educat|on and training providers, independent tutors and in-house training teams to help students gain a comprehensive understanding of JCT contracts and contractual procedures. Th|s |s the frst t|me that JOT has created a product spec|fca||y for the educat|on market, but as part of JCTs wider Education and Training Initiative we recognise the importance of ensuring that students coming through construction- related higher education courses have the best possible grounding in the role contracts play across the construction industry. Delivered in hard copy and as an online distance learning package, the module |s des|gned to be as fex|b|e as poss|b|e, meeting a variety of teaching and learning requirements. It can be used as a stand- alone module on JCT contracts or it can be incorporated into the existing structure of a construction contracts and contractual procedures course. JCT Contracts Discovery supplements a students knowledge of JCT contracts and helps to explain their use in context. It can be used a|ongs|de the study of spec|fc contract documents offering a richer understanding of a particular document. The module is organised so that each section covers a key area of the construction contract process impacted by JCTs range of documents. JCT Contracts Discovery: Explains the major elements of the JCT suite of contracts Goes through how JCT contracts are set up and implemented Looks at the various roles of individuals including contractors, employers, sub- contractors and contract administrators within the contract process Discusses how JCT provisions deal with administrative matters, such as payment, control of the works, and control of time JCT Contracts Discovery is now available to purchase for incorporation into course materials for September. The module is available through JCTs publishers Sweet and Maxwell. For more information, please contact suzanna.wong@thomsonreuters.com Dr Ann Heywood is principal of the College of Estate Management, the leading distance learning provider for the property and construction sector, with 4000 students in 100 countries, worldwide. She was previously in private practice and was elected Green Surveyor of the Year by the RICS in 1998 for her work in balancing the competing environmental, land use and fnanc|a| needs of |and portfo||os. Rebecca Evans joined Construction News in 2010, becoming editor in September 2011. Prior to joining CN, Rebecca had been a journalist for a series of public sector-focused trade magazines, including positions as deputy editor of Health Service Journal and Nursing Times, and news editor of Local Government Chronicle and Inside Housing. Mark Farrar took over as chief executive of CITB-ConstructionSkills, the Sector Skills Council and Industry Training Board responsible for the UK construction industry, in 2008. Mark is a trustee of the Buildings Research Establishment (BRE), a member of the Skills Funding Agency (SFA) advisory board and sits on the board of the Alliance of Sector Skills Councils. He is also a member of the Skills Sub Group to the Green Construction Board and has previously held positions on the board of Women into Science, Engineering and Construction (WISE) and the Institute of Chartered Accountants Public Sector Advisory Panel. Tony Bingham is a barrister and arbitrator at 3 Paper Buildings Temple, and is best-known as the legal columnist for Building magazine, which he has done for the last 25 years, and for his role in the Channel 4 series Dont blame the builder. He was called to the Bar in 1992, completing his pupillage at 3 Paper Buildings, Temple, London, subsequently becoming a full member of chambers, where he has been ever since. He is a visiting lecturer at Reading University, College of Estate Management, and since 1996, he has been training new adjudicators for the CIoA and the Chartered Institute of Building. Peter Hibberd is chairman of JCT. He is a fellow of the Royal Institution of Chartered Surveyors (RICS) and has a masters degree from UMIST (now University of Manchester) on building contract. He has extensive experience of the construction industry having worked both as a partner in private practice and as a director of a development/construction company. He became professor of construction procurement at the Polytechnic of Wales (now University of Glamorgan) in 1989 and later secretary general of JCT. He is currently a visiting professor at the University of Salford. Judging Panel JCT CONTRACTS DISCOVERY THE NEW EDUCATION MODULE FROM JCT IMPROVES THE UNDERSTANDING OF CONTRACTS FOR FUTURE PROFESSIONALS JULY 2012 JCTNEWS 6 SWEET & MAXWELL Management of performance is a crucial element in the success of a building project. For the purposes of this article, performance |s be|ng defned as hav|ng four elements namely quality, budget, programme and dispute management. Quality In relation to quality, the starting point is clause 2.1 of the Standard Building Contract which requires the Contractor to carry out the works in a proper and workmanlike manner and in compliance with the Contract Documents. The Contract Documents are the key p|ace for the qua||ty and spec|fcat|on of the works to be defned. Any |ater alterations to quality requirements are likely to trigger variations and the cost and time consequences of these. Subcontractors, particularly specialists, can be an important element in delivery of a project. Clause 3.7 provides that the Contractor shall not, without the Architects consent, subcontract any part of the works or the design. Where the Employer wishes to retain more control over the supply chain, the JCT Named Specialist Update (February 2012) allows the Employer to name individual specialists as domest|c subcontractors for |dent|fed parts of the work. A further important aspect of quality is the materials used. Clause 2.3 contains provisions linking the quality of materials back to the kinds and standards described in the Contract Documents. The Contractor can be obliged to provide reasonable proof that materials and goods are in compliance (clause 2.3.4). The contract allows for the Architects inspections of the works to include not just on site but also off site works, for example where off site fabrication is being carried out. Clause 3.1 contains provisions requiring the Architect to be given access for such inspections. The Employer also has the option of appointing an Employers Representative (clause 3.3) and a Clerk of Works (clause 3.4) whose duty is to act as an inspector on behalf of the Employer. Where there is a Contractors Designed Portion, the Design Submission Procedure within Schedule 1 applies. The Architect has an important role in commenting on any design documents submitted. The timescales for doing so are strict and need to be adhered to otherwise documents are deemed to have A status. A status means they are in accordance with the contract and the Contractor is to carry out the works in accordance with the documents. Budget In relation to budget, one key aspect in obtaining certainty is to ensure that the quality and quantity of work required is accurately described in the Contract Documents to give bidding contractors the opportunity to put forward accurate prices. Clause 4.1 makes clear that it is the quality and quantity of work set out in the Contract Bills and any CDP documents which is included in the Contract Sum. If these do not |n fact refect the Emp|oyer`s intentions or wishes then it is likely that variations will result which is where control can start to be lost in terms of managing the budget. As the work proceeds, the key management objective in monitoring spend is to ensure that interim payments are at the correct level. Clause 4.16 sets out details of how to calculate the gross valuation which includes work properly executed by the Contractor and payment for site materials as long as they are adequately protected against weather and are not on the works prematurely. Clearly some monitoring is required to ensure that work be|ng cert|fed has |n fact been properly executed and also that the provisions relating to site materials have been followed. This is particularly important in challenging economic times where there is a higher than normal insolvency risk. This risk increases if there are any overpayments or where materials are on s|te premature|y and not fxed to the works so that retention of title claims may be mounted by unpaid suppliers. var|at|ons are somet|mes |nev|tab|e but, again the Standard Building Contract provides mechanisms to create certainty as to their effect. Clause 5.3 allows the Architect to require the Contractor to prov|de a var|at|on Ouotat|on. Schedu|e 2 sets out details of what the quotation is to include: the adjustment to the contract sum including any loss and expense, any adjustment to the time required for completion, the cost of preparing the quote and additional resources. In other words |t seeks to fush out a|| |mpacts of the variation on the works. This allows the Architect and Employer to make an informed decision as to whether or not to proceed with the varied works. Where the Supplemental Provisions in Schedule 8 apply, paragraph 3 encourages the Contractor to propose changes to des|gns and spec|fcat|ons wh|ch may beneft the Emp|oyer e|ther in the form of a reduction in cost of the works or life cycle cost. Where the Employer wishes to proceed with any such proposals, the parties negotiate to agree a va|ue of fnanc|a| beneft and any adjustment to the contract Completion Date. Again the mechanism, if operated, allows certainty as to cost savings which may be achieved. A clear area to avoid in attempting to achieve cost certainty is the occurrence of Relevant Matters, where this is possible. The Relevant Matters listed in clause 4.24 do include matters within the control of the Emp|oyer/Arch|tect. var|at|ons are an obvious one. Others include instructions postponing work, opening up to inspect work (could it have been inspected prior to being hidden?), instructions to deal with discrepancies in information and any impediment, prevention or default by the Employer or those responsible to the Employer. These trigger loss and expense which, again, can lead to a loss of control in the cost of the project. Where necessary, the contract allows deduction mechanisms including pay less notices and liquidated damages in the event of delay. Again, key tools in management of cost. USING THE STANDARD BUILDING CONTRACT TO MANAGE PERFORMANCE SHONA FRAME, PARTNER MACROBERTS LLP 7 Programme Moving onto programme, the starting point is likely to be the decision on whether to have one Completion Date or whether Sectional Completion of the works is desirable. The Contract Particulars require an election to be made where there is to be Sectional Completion and the appropriate |nformat|on to be f||ed |n. Following on from that is the Contractors master programme. Clause 2.9.1.2 provides that the Contractor is to provide a master programme. The contract particulars allow the Employer to insist on this showing the critical paths through the project. This could be important information in considering in advance the impact of any variations to the works, particularly if these are made to critical activities. It should also allow for pre-planning of information supply. On that point, clause 2.11 requires the Architect to ensure that the information referred to in the Information Release Schedule (IRS) is released at the time stated in that schedule. Late information is a frequent complaint by Contractors and can clearly adversely affect progress. Use of the IRS along with the master programme should allow key pieces of information to be provided on time and to prevent delay occurring. As the works proceed, it may be that further |nformat|on |s |dent|fed as be|ng required and this is provided for within clause 2.12. This obliges the Architect to provide the Contractor with further drawings or details as necessary to allow the works to be completed in accordance with the contract and for this information to be provided at the time reasonably required by the Contractor with regard to progress of the works. Again, variations can sometimes be inevitable but the clause 5.3 provision for a var|at|on Ouotat|on as referred to above should prevent surprises relating to the time implications of any proposed variation. In addition to this, there is an option contained within Schedule 2 for an Acceleration Quotation to be requested if the Employer wishes to investigate the possibility of early completion. There are clear cost implications but in certain circumstances it may be an appropriate way to proceed. In general, the quotation procedure is a route to greater certainty. Where there are delays, an important feature of management of performance is to be aware of these so as to enable appropriate steps to be taken where possible. Clause 2.27 requires the Contractor to give notice as soon as it becomes reasonably apparent that progress of the works or any section is being delayed or is likely to be delayed. This notice is required whether or not the delaying event is a Relevant Event. The Contractor is then required to give particulars of the effects of the event on completion and to update the Architect with any material change in this estimate. Again this is an important management tool, not just to trigger entitlement to extension of time but to act as an early warning system and allow consideration to be given of omission of work, acceleration or other measures where completion on programme is critical. The Contractors role in this is not to be underestimated and clause 2.28.6 provides that the Contractor is to constantly use best endeavours to prevent delay, however caused. Further, the Contractor is to do all that may reasonably be required to the satisfaction of the Architect to proceed with the works. This may require a dialogue to agree actions. As with budget, a key consideration in attempting to keep to programme is to avoid, where possible, Relevant Events (as defned |n c|ause 2.29} from occurr|ng where this is within the control of the Employer and/or Architect. Dispute Management Some projects inevitably do end up with disputes arising. However a key part of performance is in how these disputes are managed and, if possible, prevented from escalating. The ground rules in terms of expectations of approach of the parties is the Supplemental Provisions in Schedule 8 which provide for parties to work together in a cooperative and collaborative manner. Where there is such collaborative working, dispute avoidance can be achieved. That is all very well in theory but sometimes is not suffc|ent. The Supplemental Provisions also contain an escalating dispute resolution procedure within paragraph 6 where, with a view to avoidance or early resolution of disputes or differences, parties are to notify each other of these promptly. This applies not just to items in dispute but also to items likely to give rise to a dispute. Thereafter, senior executives are to meet as soon as practicable to negotiate to resolve the matter. Where that does not achieve a resolution, a further step, in appropriate circumstances, would be the provision in clause 9.1 for parties to give serious consideration to any request to refer a matter to Mediation, a form of negotiated resolution where the control of the outcome is retained within the hands of the parties as opposed to being put in the hands of a third party. Where third party resolution is necessary, the contract of course contains provisions for Adjudication in clause 9.2 and then an option between Arbitration in clauses 9.3 9.5 and Court in clause 9.6. Parties are often reluctant to consider resolution of disputes at the stage of entering into contracts but it should be borne in mind that the default position in the Standard Building Contract is that disputes will be referred to Court. If parties wish Arbitration to be the method of dispute resolution then they require to opt in to this option at the time of entering into the contract. There are pros and cons to both Arbitration and Court but the key is to give this some thought and choose the one considered to be most appropriate to the case and which will provide the most effective forum for the disputes which are likely to arise from the spec|fc project. It is clear from the above that the standard form contains numerous provisions allowing management of the many aspects of performance at pre- contract stage, as the works proceed and beyond. It could be that proactive management early on in a project by implementing some of these measures could help prevent disputes arising at the latter stages. Shona Frame is a Partner at MacRoberts LLP. She has dual accreditation by the Law Society of Scotland as a Specialist in Construction Law and in Arbitration Law. She can be contacted on shona.frame@ macroberts.com JULY 2012 JCTNEWS 8 SWEET & MAXWELL No one needs to be reminded of the potentially enormous consequences of unforeseen ground conditions. Time, money and health and safety implications make this a serious issue which needs careful consideration. This article looks frst|y at the |ega| pos|t|on as to a||ocat|on of risk for ground conditions and secondly at JCTs approach. Starting Principles Most contracts expressly require the contractor to carry out and complete the works, or will have an implied term to that effect. Some contracts provide a get out such as under ICC 2011 where the contractor is obliged to complete the works save in so far as it is legally or physically impossible. But failing a similar clause the contractor is signing up to carrying out works, to his own design or the employers design depending on the contract, and he is under a duty to complete those works regardless of the d|ffcu|t|es |n do|ng so un|ess frustrated. What happens when unexpected ground conditions are encountered along the way? The starting point is that in the absence of contractual provisions the common law position is that the contractor bears the risk of unforeseen ground conditions i.e. the contractor will be responsible for the time and money consequences wh|ch fow from those ground conditions. Long established case |aw confrms that the ob||gat|on to complete includes anything which is indispensably necessary to complete the works e.g. dealing with unforeseen ground conditions. This will not, where the contract is silent, constitute a ground for extra payment, unless dealing with such ground conditions inevitably requires a change or variation to the works. What about where the employer provides ground investigation reports and site data as part of the tender process? Has the employer assumed the risk of accuracy of this information and is the contractor off the hook? The starting point as always is to look at the contract. This will determine if the relevant information is part of the contract. Unless the information is expressly stated to be part of the contract, it will not be. One example of this was a case where there were references to a site survey report in contract drawings and an item in the Bill of Quantities, but the report was not listed as a contract document itself. It was held the report was not incorporated into the contract [1] . If information is not part of the contract the contractor is effectively using it at its own risk, unless it can make out a case for some sort of misrepresentation, which genera||y speak|ng |s d|ffcu|t. If on the other hand the information in question is expressly included as part of the contract, this may amount to a warranty from the employer, entitling the contractor to rely on that information. One example is a case where a contractor used borehole data provided in a tender about the soil conditions on site, to design building foundations. Another type of ground material was later found to be present which necessitated additional excavation works and re-designing of the foundations. The court found there was an implied term or warranty that the ground conditions would be in accordance with what was shown or could be deduced from the borehole information. So the employer bore the cost of the design changes [2] . There are often spec|fc contract provisions as to how such site information offered by the employer will be treated. Clauses such as the contractor is deemed to have examined the site and |s sat|sfed as to the content and completeness of such information and has obtained all other relevant information which may affect the works and takes full responsibility for the accuracy of such information are common. This is often accompan|ed by a spec|fc statement that the employer is not giving any warranty or representat|on as to the suffc|ency GROUND CONDITIONS AND JCT CONTRACTS JANE FENDER-ALLISON, DUNDAS & WILSON R E U T E R S / A l y
S o n g 9 of the information it provides. In these circumstances close examination of the contract terms is essential in case there are some get outs, but typically the risk here lies with the contractor. JCTs Approach What is the approach in the JCT contracts? The Standard Building Contract Without Quantities 2011 does not deal expressly with ground conditions, so the common law position applies. The Design and Build Oontract 2011 does not have spec|fc ground conditions provisions either. However information contained in the Employers Requirements relative to ground conditions may amount to representations giving rise to implied terms or warranties as discussed earlier. Plus, if it becomes necessary to make any changes to ground condition information in the Employers Requirements, these are subject to the Change procedure (section 5) which values changes to the Employers Requirements which necessitate alteration of the design, quality or quantity of the works. Of course the contractor and the employer are at liberty to amend these forms; the employer might be content for the contractor to rely on some of its information or it might adopt the reasonably foreseeable and deemed knowledge approach used in the JCT Major Project Construction Contract 2011 (MP) and some other non-JCT forms. In MP, where the contractor encounters ground conditions or man- made obstructions which necessitate an amendment to the Employers Requirements/Contractors Proposals he shall notify the Employer. Where clause 14.2 is selected in the contract particulars as applying the amendments will be treated as a Change (which may give rise to time/money entitlement) to the extent that the conditions could not reasonably have been foreseen by an experienced and competent contractor at the Base Date (as |dent|fed |n the Oontract Particulars), having regard to any information that the contractor had or ought reasonably to have obtained. Points to bear in mind with this approach are; frst|y |t w||| a|ways be a matter of interpretation as to what reasonably foreseeable means. Court guidance will often turn on the particular facts of a case. Secondly, the use of the Base Date, or the date of tender, has been suggested as unrealistic given that in reality most contractors may not have had the opportunity to conduct in-depth surveys and investigations at this point. Contractors could end up pricing for the risk of unforeseen ground conditions much as they would under the unamended Standard Building Contract. Alternatively the JCT-Constructing Excellence Contract 2011 (CE), in line with its collaborative ethos, provides for a Risk Register and Risk Allocation Schedule (schedules A and B of part 5 of the Contract Particulars and section 5 CE). Where the Contract Particulars state that the Supplier is responsible for preparing the Risk Register, the Supplier has to carry out a risk assessment which is set out in the Risk Register. Even where not responsible, the Supplier has to provide all reasonable assistance in the preparation of the Risk Register. The Supplier may also be responsible for updating and amending the Risk Register, again where stated in the Contract Particulars. The Risk Allocation Schedule then sets out the agreed time and cost consequences of the risk items; both the amount provided for by the Supplier and the percentage allocation between Supplier and Purchaser over and above that. For example, in the case of unforeseen ground conditions the Supplier (as contractor) may include in its Target Cost Contract Sum for 50,000 and agree to be responsible for 4 weeks should they arise, and time and money consequences in excess of that may be split 50%/50% with the Purchaser (as employer). This offers an opportunity to deal with the risk of unforeseen ground conditions upfront. To do this the Risk Register and Risk Allocation Schedule should be completed very carefully. For example, will pollution or contamination be included? The more spec|fc the |dent|fed r|sk |s, the less likely there are to be arguments about whether that risk has arisen. If ground cond|t|ons are not |dent|fed/apport|oned |n the Risk Allocation Schedule they may still be Relief Events for which the Supplier is entitled to additional time/money. However at this point the Suppliers entitlement will fall back to the question of whether the risk was reasonably foreseeable and beyond the control of the Supplier. So there is an incentive for the Supplier to identify and allocate the risk of unforeseen ground conditions, where and to the extent that agreement can be reached with the Purchaser. The Standard Building Contracts With Quantities and With Approximate Quantities 2011 have a different approach. These contracts require the Bills of Quantities to be prepared in accordance with SMM 7 (clause 2.13). SMM 7 at section D provides standard rules as to measurement, defn|t|on and coverage of ground work items. Does this negate the need for spec|fc a||ocat|on of r|sk for ground conditions? Partly; insofar as the ground works are measured in accordance with the SMM an allocation of the risk has been made. However, using spec|fc contract c|auses as to who bears the risk for what, including unforeseen conditions and which data can be relied upon or taken at the contractors risk remains the clearest way to deal with these issues. Keating on Construction Contracts (9th Edition) suggests one solution of using reference conditions which the employer produces and against which the contractors prices are deemed to apply. The Bill of Quantities is then used to price adverse conditions beyond this. As Keating notes this would mean the Employer has an incentive to make the reference conditions as accurate as possible whilst the contractor is paid for what is actually encountered. [1] Cooperative Insurance Society Ltd v Henry Boot (Scotland) Ltd [2002] EWHC 1270. [2] Bacal Construction (Midlands) Ltd v Northampton Development Corporation [1976] 1 EGLR 127. JULY 2012 JCTNEWS 10 SWEET & MAXWELL Introduction Many contractors and others within the construction and infrastructure sectors have reviewed their compliance systems since the introduction of the Bribery Act. This article considers how contract wordings in construction contracts can help secure anti-corruption protections and highlights some common pitfalls. With the emphasis in the Government Guidance on taking a risk-based approach, how might organisations use boilerplate clauses effectively in their contracts with their supply chain and sub-contractors? And what level of protection is provided by such clauses? Where are the potential pitfalls? The new law The Bribery Act 2010 introduced four new corruption offences: paying bribes, receiving bribes, bribery of a Foreign Pub||c Offc|a|, and fa||ure by a commerc|a| organisation to prevent bribery. The law can cover corruption outside of the UK and private as well as public sector bribery. Sanctions for non-compliance include |mpr|sonment, un||m|ted fnes, confscat|on of assets and the possibility of being debarred from tendering for public sector contracts under EU procurement rules. The key development is the new corporate criminal liability for failure to prevent bribery. This is a major reason why many organisations have chosen to take another look at their anti-corruption contract wordings (a number of types of clause having been in common use previously, in reference to the old law). Under the new offence, a commercial organisation is now criminally liable where someone associated with the organisation (an associated person being anyone performing services for or on its behalf, such as a contracting party) bribes someone else, intending some form of business advantage for the company. The only defence for the organisation is to demonstrate it had adequate procedures to prevent bribery. Adequate procedures and the Government Guidance on contractual provisions The starting point to understand the meaning of Adequate procedures is the Government Guidance of March 2011, which sets out 6 principles for a company to consider: proportionate procedures, top level commitment, risk assessment, due diligence, communication (including training) and monitoring and review. In relation to anti-corruption contractual provisions, the Guidance includes the following remarks: The principal way in which commercial organisations may decide to approach bribery risks which arise as a result of the supply chain is by employing the types of anti-bribery procedures referred to elsewhere in this guidance (e.g. risk based due diligence and the use of anti-bribery terms and conditions) in the relationship with their contractual counterparty, and by requesting that counterparty adopt a similar approach with the next party in the c|a||. However, the Guidance does not go in to exhaustive details about the content of anti-bribery terms and conditions to consider in a supply chain relationship which is consistent with the mantra of the Gu|dance that |t |s not a set of fn|te rules and parties are encouraged to take a risk-based and proportionate approach. In any event, it is clear from the Guidance that contractual protections alone will not be suffc|ent to have adequate procedures under the Act (and similarly, where an organisation has simply introduced a new anti-bribery policy, it will almost certainly not have met the compliance bar with a paper policy alone). The Gu|dance does po|nt to w|der benefts of securing some level of contractual protection with immediate counter parties. As can be seen from the extracted passage above, where a contractor puts in place anti-corruption wording in an agreement and seeks equivalent measures for its sub-contractor to agree with others down the supply chain, the Guidance suggests this can help ring fence part of a contractors liabilities under the new corporate offence, so that it may not be held liable if bribes are paid by others further down the supply chain. Notwithstanding these words of comfort in the Guidance, caution should be exercised and it remains to be seen how the Courts will determine the liability for associated persons, several steps removed from a contractor, but whose corrupt acts may have been intended to g|ve an |nd|rect or d|rect beneft to a|| those in the supply chain. Where a principal contractor is aware of higher risks involving parties two or more steps removed from it contractually, it will be well-advised to consider additional anti-corruption measures based around those risks. Here it is important to keep in mind the broad defn|t|on g|ven |n the Act for the mean|ng of associated persons. Section 8(4) of the Act states: Whether or not [an associated person] is a person who performs services for or on behalf of [a commercial organisation] is to be determined by reference to all the relevant circumstances and not merely by reference to the nature of the relationship oe|wee| ||ese |wo oa|||esj The contractual relationship can never therefore be more than part of the picture. These principles aside, there is no comprehensive assistance in the Government Guidance about what types of contractual clauses may be suitable for a normal supply chain relationship. Some steer can be derived from a number of the example case studies at the end of the Guidance which include suggestions for anti-corruption contractual controls in higher risk relationships, such as joint ventures and the engagement of overseas agents. THE BRIBERY ACT AND CONTRACTUAL ANTI-CORRUPTION PROVISIONS NEIL MCINNES, SENIOR ASSOCIATE, BARRISTER - PINSENT MASONS LLP 11 A possible approach A number of organisations have chosen to adopt a tiered approach to their use of anti-corruption contractual protections. This can result in groupings of standard clauses, deployed according to different risk categories. In the most straightforward case, dependent on the scope of the contractors business in the UK and elsewhere, this might be possible to split into as few as two tiers. For example: 1. Standard terms for lower risk relationships (e.g. UK supply chain partners to whom the Bribery Act also applies and have their own adequate procedures in place, etc) 2. Enhanced terms for higher risk relationships (e.g. joint ventures, contracts involving agents, intermediaries, sponsors and consultants, all contracts involving public bodies/governments/state controlled agencies outside of the UK, etc) Th|s t|ered approach has the beneft of simplicity and proportionality and is risk- based. It must, however, be suitable for the contractors spread of business dealings and have add|t|ona| fex|b|||ty to cater for higher risk contracts where bespoke fne-tun|ng w||| often be necessary, notwithstanding the risk-based tiers. Some key questions for anti- corruption clauses Even adopting this risk-based approach, it is important to be aware of the overall pitfalls and limitations of anti-corruption contractual protections. As stated above, on their own they will not be a substitute for other adequate procedures. In addition, the drafting and range of clauses should be examined to understand whether their implementation is proportionate and achievable. If not, an organisation will be open to criticism that it did not live by the standards it set itself in the contract. Some organisations decide it is better to adopt a smaller number of anti- corruption contractual controls and enforce each of these effectively rather than having a wide suite of rights or protections that may never be exercised or properly reviewed. For example, where a contract provides for a party to have access to anothers books and records to conduct an anti-corruption audit, a regulator will be interested to learn if no audits have in fact taken place in the term of the contract. Turning to the scope of different types of clause, the checklist below provides a non- exhaustive list of issues to consider: How does your anti-corruption clause set the parameters of bribery? For example, does it take account of previous corruption laws, given acts prior to 1 July 2011 could give rise to a corruption investigation in future? Does it need to include reference to any other international anti-corruption legislation, such as the US Foreign Corrupt Practices Act? Are warranties necessary from contracting parties on the following: - That they have in place adequate procedures and/or spec|fc po||c|es and procedures designed to prevent bribery? - That they or their associated persons have not breached any relevant anti-corruption laws or been investigated or convicted for any bribery-related offence or currently being investigated by a regulator? - Relating to the identity and ownership and control of a counterparty (e.g. in respect of |nfuence or connect|ons to fore|gn pub||c offc|a|s}? - That accurate books and records are maintained? Are there rights to review the contract periodically during its lifespan, to consider any corruption concerns that have arisen? Are there termination rights for a breach of the anti-corruption clause and what are the triggers to exercise these? If a party would need to be convicted of a bribery offence before termination rights accrue for the other, this may be considered ineffective given the length of time before any corruption investigation or prosecution would normally be concluded. Are there obligations on parties to report bribery-related issues to their counterparties? Are these drafted in terms that comply with all relevant other laws, such as money laundering laws on tipping off? On a risk-based analysis, are enhanced protections required to allow a party to conduct an audit; oblige a party to undertake training; or cooperate with another party during an investigation? What obligations are imposed on a party to conduct anti-corruption due diligence on its sub-contractors, agents, and other intermediaries? Does the clause require compliance with a partys own anti-bribery policy or a policy containing similar or equivalent provisions? Are any indemnities contrary to public policy and unenforceable? For examp|e an |ndemn|ty for cr|m|na| fnes and penalties Conclusions There are a range of issues arising from deploying contractual anti-corruption protections. A useful starting point is to understand, through a risk assessment, whether the relationships require standard or more enhanced contractual provisions. This ensures a proportionate approach is taken throughout and unnecessarily burdensome obligations are not inserted into contracts that do not require these. Through design of a suitable tiered approach, contractors can also avoid the cost and inconvenience of bespoke provisions on all occasions. Neil McInnes is a Senior Associate, Barrister specialising in corporate criminal investigations at Pinsent Masons LLP. For recent developments on the Act, see www.thebriberyact.com, co-hosted by Barry Vitou, Partner, Pinsent Masons LLP. R E U T E R S / D a n i e l
M u n o z JCT CONTRACTS DIS COVERY: THE EDUCATION AND LEARNING MODULE FROM THE JOINT CONTRACTS TRIBUNAL SWEET & MAXWELL R E U T E R S / N a v e s h
C h i t r a k a r JCT Contracts Discovery |s an educat|on and |earn|ng modu|e des|gned spec|fca||y for those studying or teaching JCT Contracts and JCT contractual procedures. JCT Contracts Discovery: Explains the major elements of the JCT suite of contracts Goes through how JCT Contracts are set up and implemented Looks at the various roles of individuals including contractors, employers, sub- contractors and contract administrators within the contract process Discusses how JCT provisions deal with administrative matters, such as payment, control of the works, and control of time Visit www.jctcontracts.com to nd your local stockist and order today A NEW WAY TO UNDERSTAND JCT CONTRACTS FOR THE NEXT GENERATION OF CONSTRUCTION PROFESSIONALS ISBN: 9780414026735 PRICE: 30