These operating instructions contain fundamental directions on how to transport, assemble, operate and maintain the steam jet ejector (SJE) Paying attention to these instructions will help to avoid dangerous situations, to reduce repair costs and outage time and to increase the reliability and life expectancy of the SJE.
These operating instructions contain fundamental directions on how to transport, assemble, operate and maintain the steam jet ejector (SJE) Paying attention to these instructions will help to avoid dangerous situations, to reduce repair costs and outage time and to increase the reliability and life expectancy of the SJE.
These operating instructions contain fundamental directions on how to transport, assemble, operate and maintain the steam jet ejector (SJE) Paying attention to these instructions will help to avoid dangerous situations, to reduce repair costs and outage time and to increase the reliability and life expectancy of the SJE.
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 Hannover, 15.01.2014 STM-Kr These instructions concern the
steam jet ejector (SJE),
in this case used as a Steam Jet Vacuum Ejector for Extraction Process
Customer : EcoOils, Pasir Gudang Customer PO : Eco Sabah 026/2013 Krting Order Ref.-N. : 3/211/3/30680 Drawing N : 124021 450605 A (Item EXTF-0315)
LIST OF CONTENTS 1.0 Introduction 2.0 Safety, safety precautions 3.0 Transport, intermediate storage 4.0 Function, description 5.0 Operating data, noise emission values 6.0 Fitting position, dimensions, connections, assembly 7.0 Commissioning, operation, shut-down 8.0 Malfunctions and their sources 9.0 Procuring spare parts, parts subject to wear 10.0 Maintenance
ENCLOSURES
Technical Data Sheet resp. Table of Dimensions Characteristic curve(s) resp. Technical Specification as Operating Data Sheet
Page 2 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 1.0 Introduction
These operating instructions contain fundamental directions on how to transport, assemble, operate and maintain the steam jet ejector (SJE) in a safe, correct and economical manner.
Paying attention to these instructions will help to avoid dangerous situations, to reduce repair costs and outage time and to increase the reliability and life expectancy of the SJE.
2.0 Safety, safety precautions
2.1 Important instructions concerning safety which, when disregarded, could lead to the endangerment of persons, of the installed apparatus and its func- tioning, have been marked in these instructions with a .
It is most important that the fitter in charge resp. skilled workers/Owner/ Manager read these instructions through thoroughly before effecting transport, assembly, commissioning and maintenance and that these in- structions are observed at all times.
Not only are the instructions as stated under this item (Safety) to be observed but also those safety instructions given under other headings.
2.2 Qualification of personnel, training
The assembly, operation and maintenance of the SJE must be carried out solely by suitably qualified personnel.
Therefore the Owner/Manager must ascertain that the personnel designated to carry out jobs/activities in connection with this SJE have the required qual- ifications resp. have been suitably trained and that they fully understand the contents of these operating instructions.
The extent of responsibility, competence and supervision of personnel must be determined exactly by the Owner/ Manager.
2.3 These operating instructions must be always available at the SJE's service point.
Page 3 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 2.4 Possible dangers on non-observation of the safety measures
Non-observation of the safety measures can lead to the endangerment of persons as well as of the environment, of the SJE and of other apparatus connected to it. Non-observation of these safety measures can lead to the loss of all rights to claim indemnification.
In particular, Non-observation can cause the following dangerous situations: - breakdown of important functions of the steam jet ejector/the plant, - failure of prescribed methods for maintenance & care, - endangerment of persons, e.g. mechanical and chemical effects, - endangerment of the environment through leakage of noxious substances.
2.5 Working according to the safety rules
The safety measures in these operating instructions, national safety rules for the prevention of accidents as well as any internal rules concerning work, operating- and safety measures from the Owner/Manager's side, must be observed.
2.6 Safety measures for the Owner/Manager resp. Operator
If the SJE is to be subjected to substances for which its materials cannot be defined exactly, then a material durability test must be carried out at site before the SJE is put into operation.
This will prevent material damage at a later date and possible damages to the environment resp. injuries to persons as a result thereof.
When applicable, the SJE is to be provided with sound insulation at job-site for the prevention of damage to the hearing system - see Item 5 (Operating data) and the Data Sheet for Noise Emission Values.
Depending on the SJE's wall temperatures, the apparatus should be insulated at site against heat radiation and for contact protection. The above mentioned sound insulation serves also as such protection.
Page 4 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 2.7 Directions for safety precautions during maintenance and servicing
The Owner/Manager must take care that all maintenance and service jobs are carried out solely by authorised and qualified personnel. Furthermore, he must ascertain that the personnel concerned has acquired sufficient knowledge by studying the operating instructions very carefully.
On principle,
- in cases where the SJE has been subjected to aggressive substances - that it has been decontaminated/rinsed out and cleared for further activi- ties before dismantling and maintenance jobs take place!
Rules governing waste disposal and environmental protection must be observed at all times.
- dismantling and maintenance jobs are not to be carried out until the SJE - working under excess pressure and sometimes at high temperatures - has been,
- taken out of operation, - pressure in the system reduced, - and the SJE - where applicable - has cooled down, drained off and - see above - has been decontaminated/cleared for further activities,
thereby paying strict attention to the procedures as given under Items 7.3 (Shut-down) and 10.0 (Maintenance).
Observation of the above points will help to avoid injuries to persons, i.e. burns/scalds, with aggressive substances also acid burns, as well as damages to the apparatus/plant.
On completing such jobs, any safety protection devices in use must be reassembled immediately, checked through and set to operate.
Re-commissioning to take place according to Item 7.1 (Commissioning).
Page 5 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 2.8 Unauthorised modifications resp. manufacturing of spares
Modifications or alterations to the SJE are not allowed without our prior con- sent. Original spare parts are indispensable for a correct functioning of the apparatus and serve to guarantee safe operation. Use of other than original parts may cancel out a liability for consequential damages.
2.9 Correct use/Mechanical limiting values/ Unauthorised methods of operation
This SJE has been constructed especially for operation as described under Item 4.1 and for the operating data according to Item 5.1.
Safe operation can only be guaranteed by proper use (Item 4.1 (Function)), observation of the operating data - see Item 5.1 - as well as operation and maintenance by suitably qualified personnel - see Item 2.2 (Qualification of personnel). The safety precautions as given under Item 2.5 must be observed.
Correct use also entails observance of the operating instructions and carry- ing out maintenance according to Item 10.0.
On no account may the operating data as given under Item 5.1 be exceeded.
Mechanical limiting values
If the allowable working pressures are exceeded at the allowable working temperatures stated in the Technical Data Sheet resp. Table of Dimensions (enclosed herewith), the SJE could be damaged beyond repair and could al- so be the cause injuries to persons resp. material and/or environmental damages. The safety precautions as given under Item 2.5 must be ob- served.
The mechanical limiting values given here are not to be seen in context with the operating data as given under Item 5.1!
Incorrect handling and/or other use/application over and above the data as given under Item 2.9 (Safety precautions) and 4.1 (Function) are to be con- sidered as an inappropriate and undue method of operation. The manufacturer/supplier is not responsible for damages resulting from such handling.
Page 6 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 3.0 Transport, Intermediate Storage
Transporting the SJE to the point of installation resp. connection point must be effected with great care and with due consideration to the safety precau- tions given under Item 2.5.
Scope of supply - see packing list. Please check this list through when unpacking the goods.
All openings on the SJE should remain closed resp. are to be closed until assembly actually takes place as a protective measure to prevent dirt and other foreign objects entering the apparatus.
Intermediate storage: Only under cover (warehouse).
4.0 Function, Description
4.1 The SJE serves to convey gases and/or vapours in the respective process. They are compressed and then forwarded on to the next process stage.
4.2 Shut-off devices (shut-off valves, gate valves or ball-cocks), measuring instruments and pipelines are also indispensable for a correct functioning of the SJE.
4.3 A shut-off device must be installed in the motive steam line at job-site. Shut-off devices in the suction- and mixed-flow lines are unnecessary but their installation could be necessary to fulfil the Owner/Manager's require- ments.
Page 7 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 5.0 Operating Data, Noise Emission Values
5.1 The design point and the operating data have been given in the characteristic curve(s) resp. in the operating data sheet - see annex(es).
Note: All operating data pressures refer to the SJE's flange level.
5.2 Noise emission values are given in the enclosed data sheet for noise emission values. To prevent undue noise/hearing damage we recommend taking respective noise abatement measures in accordance with legal/corresponding rules & regulations at the site - see here also the information under Item 2.6 (Safety precautions, Insulation). If necessary, the personnel concerned should wear earplugs to protect their hearing.
6.1 There are no special instructions concerning the fitting position as the fitting position of such ejectors does not influence their functioning. However, take care that no condensate can collect in the head of the SJE when it is at standstill otherwise complications could occur when putting it back into operation at a later time.
6.2 Dimensions and connections - see Technical Data Sheet resp. Table of Dimensions.
Page 8 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 6.3 Before assembling the SJE, please ensure that the connecting pipelines have been cleaned thoroughly. Remove any rust protection applied previously to the flange sealing surfaces. See here and observe Item 10.4.3 (Maintenance)!
6.4 The approved rules of engineering are to be observed when fitting/ assembling the SJE - see here also Item 2.5 under the heading "Safety precautions". Qualified personnel is a prerequisite for assembling the SJE.
Especial care is to be taken
- that the correct flow directions acc. to the Technical Data Sheet resp. Table of Dimensions - marked by arrows - are observed,
- that the supply and discharge lines do not introduce any forces or moments,
- that clogging by welding globules, sealing residues or the like cannot occur.
Furthermore, pay attention that:
6.5.1 All gaskets are seated concentrically and do not narrow the flow cross- sections.
6.5.2 When installing the motive steam line please take care that the motive steam reaches the motive nozzle in a dry condition. Wet motive steam will cause premature wear in the motive nozzle and also in the diffuser of the SJE and this will interfere considerably with an efficient performance.
The motive steam line should be installed at least in the same nominal width as prescribed by the SJE.
If the motive steam is wet, then it has to be dried. We recommend the job- site installation of a droplet separator (steam strainer with drainage) in the motive steam line.
Page 9 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 Furthermore, a partial condensation of the steam should be prevented by the installation of short pipelines after the droplet separator (steam strain- er with drainage) - if this has been installed - and also by insulating these pipelines.
The withdrawal connection for motive steam must be situated at the top of the main steam line to prevent condensate from being carried over.
6.5.3 The suction- and mixed-flow lines should be installed in the same nominal width as the SJE - see also Technical Data Sheet resp. Table of Dimen- sions.
Too narrow a pipeline will lead to increased pressure losses.
6.6 The shut-off device for the motive steam can be situated at the most convenient point for handling, but not too far away from the SJE to assure that the specified minimum pressure can be adjusted just before inlet to the motive nozzle.
6.7 A pressure gauge to be provided at job-site is necessary to adjust the required minimum pressure for motive steam. This gauge must be installed between the shut-off device and the SJE. It is advisable to have this instru- ment calibrated from time to time.
6.8 The SJE can be subjected to an operational test before it is finally installed. This test can be carried out within the test scope for the whole unit. Proceed here according to Item 7.1 (Commissioning).
6.9 Retighten screws on previously assembled connections and again after first commissioning.
6.10 This SJE can be operated out of doors.
When the weather is cold and frosty or if the SJE is to be shut down over a longer period of time, please proceed according to Item 7.3.4 (Shut-down).
6.11 Parts made of C-Steel/GGG-40 have been provided with a shop coat of paint.
Additional protective measures are necessary at job-site if further corrosive influences are to be avoided.
Page 10 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 7.0 Commissioning, Operation, Shut-down only by suitably qualified personnel and in accordance with Items 2.2 and 2.5 (Safety precautions) as well as the following Items 7.1...7.3!
7.1 Commissioning
7.1.1 ATTENTION !
Before first commissioning it is important to ascertain that all connecting pipelines are in a clean condition, especially the motive steam line and above all, in the area between the droplet separator (steam strainer with drainage) and motive nozzle. Foreign objects (scale, welding globules and the like) can clog the nozzle.
Before commissioning takes place, check that the connections are leak-proof.
A further prerequisite is that the SJE may only be activated when it is in a properly operable condition together with resp. safety- & protection devices - as far as these have been installed.
7.1.2 At first, all shut-off devices in the supply- and discharge lines must remain closed.
7.1.3 If a shut-off device has been installed in the mixed flow line (at connection point DNG), then this device must be opened up first of all before the com- missioning starts.
If this particular shut-off device is not opened up first, then motive steam can flow back through suction connection DNS and can so cause damage to the product or to the system itself.
ATTENTION: The danger thereby is, that the mechanical limiting values - see Item 2.9 - could be exceeded thereby resulting in injuries to persons resp. damages to the environment.
7.1.4 Drain the motive steam line (at connection point DNT) thoroughly by means of the drainage device (e.g. droplet separator - steam strainer with drainage) until the white vapour trail disappears. In the case of saturated steam, leave the shut-off device open a little!
Page 11 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 7.1.5 Now, and only now, open up the shut-off device in the motive steam line.
Pay attention here that the motive steam pressure PTR as given under Item 5.1 (Operating Data) is available immediately at the entrance to the SJE.
ATTENTION: The allowable working pressure given together with the allowable working temperature in the Technical Data Sheet resp. Operating Data Sheet -see annex - must not be exceeded - see Item 2.9 under the heading "Safety precau- tions"!
Finally, open up the shut-off device in the suction line.
7.1.6 Adjust the shut-off device in the motive steam line accordingly, if this should be necessary.
7.1.7 All screwed connections must be re-tightened after first commissioning.
7.2 Operation
7.2.1 During operation pay attention to and supervise the operating data according to Item 5.1.
The allowable working pressure - given in the Technical Data Sheet resp. Table of Dimensions - see annex together with the allowable working temperature - may not be exceeded - see Item 2.9 under the heading "Safety precautions"!
7.2.2 If the SJE is not operating correctly, proceed immediately with shut-down according to the following Item 7.3 (Shut-down)!
7.3 Shut-down
ATTENTION !
The shut-down procedure as given below must be followed implicitly step by step.
If these instructions are not followed correctly, steam could flow back into the suction line and possibly cause damage.
Page 12 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 7.3.1 First of all, close the shut-off device (if installed) in the suction line.
7.3.2 Then close the shut-off devices for the motive steam.
7.3.3 On principle, any shut-off device in the discharge line is to be closed last of all.
7.3.4 At places open to the weather/subject to frost it is imperative to drain the SJE and the job-site installed supply- and discharge lines thoroughly (possi- ble condensate build-up!) - see Items 10.0...10.3 (Maintenance - Pressure reduction, Cooling down resp. also Decontamination/Rinsing).
For longer periods of shut-down we also recommend a draining of the apparatus as described above.
8.0 Malfunctions and their sources
ATTENTION !
For reasons of security, dismantling the SJE resp. the motive nozzle is to be carried out only
- in accordance with the instructions for safe working - Item 2.5 -,
- after shut-down according to Item 7.3 (Shut-down),
- after reduction of the excess pressure and after the SJE has cooled down resp. has been drained off. Please observe Item 2.7 of the safety precautions and the following paragraph of this Item 8.0.
Be especially careful if the SJE has been in contact with aggressive/noxious substances. Do not dismantle until the SJE has been decontaminated/rinsed off and released for further handling - see Items 10.1...10.4.2 (Maintenance).
Material damages could be the result if these instructions are not followed. Damages to the environment are also possible, as are injuries to persons.
Page 13 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 Loss of performance, even though Item 7.2 - observance of the operating data - has been followed
can have been caused by:
- Motive nozzle clogged
Remedial action: - Shut-down acc. to Item 7.3 (Shut-down). Then, with due consideration being given to the safety precautions mentioned at the beginning of this Item 8.0, carefully detach the screws and connecting flange/steam chest for the motive nozzle, remove the motive nozzle resp. the steam chest with welded on motive nozzle. Clean motive nozzle - see Items 10.4.1 and 10.4.3 (Maintenance). Reassemble according to Item 10.5 (Maintenance), re-commission according to Item 7.1 (Commissioning).
- Wear and Corrosion
Remedial action: - Shut-down acc. to Item 7.3 (Shut-down). Then, with due consideration being given to the safety precautions mentioned at the beginning of this Item 8.0, detach the flange connec- tions to the SJE carefully. Dismantle the SJE, clean it if necessary, and then inspect the narrowest cross-sectional parts of the motive nozzle and the mixing passage/diffuser. - If you find erosions and/or deformations, replace the motive nozzle or steam chest with welded motive nozzle respectively and/or mixing passage/diffuser or the complete SJE. Dismantling, cleaning, assembly, re-assembly according to Items 10.4.1...10.4.3 and 10.5 (Maintenance), re-commission according to Item 7.1 (Commissioning).
Page 14 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 - Motive steam pressure not high enough
Remedial action: - Increase the motive steam pressure, see Item 2.9 (use as authorised/mechanical limiting values/undue mode of operation), Item 5.1 (Operating data) and Item 6.7 (Manometer) as well as 7.1.5 (Commissioning - motive steam pressure PTR).
- Leakages
Remedial action: - Shut-down acc. to Item 7.3 (Shut-down). Retighten screwed connections uniformly. Re-commission the SJE in accordance with Item 7.1 (Commissioning).
- ATTENTION, the SJE is now under pressure again!
- If leakages can still be detected, shut-down again in accordance with Item 7.3 (Shut-down). Dismantle the SJE with due consideration being given to the safety precautions mentioned at the beginning of this Item 8.0. Loosen the flange connections to the SJE with care - see Item 10.4.2 (Maintenance) and carry out a hydraulic testing of the SJE. If leakages occur, dismantle the SJE in accordance with Item 10.4.2 (Maintenance). After cleaning according to Item 10.4.3 (Maintenance), reassemble the SJE with new gaskets and also with new parts, if necessary, in acc. with Item 10.5 (Maintenance). Carry out the hydraulic test again and - if satisfactory - reassemble the SJE according to Item 10.5 (Mainte- nance) and put back into operation in accordance with Item 7.1 (Com- missioning).
Page 15 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 9.0 Procuring spare parts, parts subject to wear
As the SJE has been designed and manufactured especially to your needs, any spare parts required will also have to be manufactured individually. This requires a certain amount of time.
Parts subject to wear are -
the motive nozzle or motive nozzle with welded steam chest resp. and the gaskets belonging to it. We recommend that you place an order for the above mentioned parts as spares in good time. When ordering spares it is most important to state the numbers punched into the motive nozzle and other parts of the SJE and the Item Nos. as given in the Technical Data Sheet resp. the Table of Dimensions.
10.0 Maintenance
Regular maintenance of the SJE serves to increase its working life and to ensure its proper functioning. The intervals between maintenance depend on the operating conditions. However, maintenance should take place at least once a year after shutting the SJE down in accordance with Item 7.3 (Shut-down) with due consideration being given to the safety precautions - see Item 2.5 - and espe- cially to the following Items 10.1 and 10.2.
Non-observance can lead to material damages, maybe also damages to the environment resp. injuries to persons! Maintenance of the SJE can also be carried out during the course of a sys- tem inspection.
10.1 Relieve the SJE of pressure by a careful and slow opening of the fittings provided for this action at job-site.
In the event that the SJE has been in contact with aggressive/noxious substances, the Owner/Manager is responsible for measures to ensure that the personnel does not come into contact with the liquid and can- not inhale vapours/gases. The rules and regulations concerning waste disposal and environmen- tal protection are to be observed at all times.
Page 16 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 10.2 In such cases where the SJE has been in contact with aggressive/noxious substances it is imperative to decontaminate/rinse it down and then release for handling before further jobs are undertaken.
10.3 Further jobs should not be carried out until the SJE has cooled down and is without pressure.
Any necessary drainage can be effected by opening the fittings provided for this action resp. by loosening the flange connections to let the condense wa- ter drain off.
The rules and regulations concerning waste disposal and environmental pro- tection are to be observed at all times.
10.4.1 Removing the motive nozzle
Detach motive steam line from connection DNT, detach nuts on steam chest, dismantle the steam chest and then remove the motive nozzle resp. the steam chest with welded motive nozzle. First of all, inspect the motive nozzle for fouling as well as for wear, then, by looking through the free opening in the SJE head, inspect the inner surfaces of the SJE for fouling resp. for wear and clean if required - see the following Item 10.4.3. If necessary, replace worn out part.
10.4.2 Removing/Dismantling the SJE
When required, remove the whole SJE (detach corresponding flange con- nections to the supply lines) and maybe also dismantle the apparatus, i.e., detach nuts, unscrew steam chest. Dismantle motive nozzle or steam chest with welded motive nozzle respectively, see Item 10.4.1. Then detach head from mixing passage/diffuser if they are screwed and not welded together. Then inspect the parts for fouling resp. for wear - see following Item 10.4.3. Replace worn out parts.
Page 17 of 17
BAL 110-11 / 102 E
GENERAL INSTRUCTIONS for Transport, Assembly, Operation and Maintenance of Steam Jet Ejectors (in short: SJE) 3/217/3/30680 Krting Hannover AG Krting Hannover AG Bereich S / Division S Postfach 91 13 63, D-30433 Hannover Telefon (0511) 2129-0 Telefax (0511) 2129-223 10.4.3 Depending on the circumstances cleaning can be effected by rinsing out with water, with a chemical agent or by mechanical means.
ATTENTION ! Pay attention to the instructions on how to use the cleansing agent and solvent and on how to prevent accidents. Furthermore, the rules and regulations concerning waste disposal and environmental protection are to be observed. The cleansing agent used during this treatment must not be able to attack the materials of the SJE (given in the Technical Data Sheet resp. Table of Dimensions) or corrode the surfaces. After treatment has finished, rinse out thoroughly with water. Here too, please observe the rules and regulations governing waste disposal and environmental protection.
10.5 Before re-assembly, clean the sealing surfaces - see preceding Item 10.4.3 (sealing surfaces should not be damaged) - and
when reassembling, use new gaskets, screw head (if not welded together with mixing passage/ diffuser) and mixing passage/diffuser together using a new gasket. Set motive nozzle into the head using a new gasket and put the steam chest on the head using a new gasket and bolt together with screws.
If the motive nozzle is welded with the steam chest, set the latter into the head using a new gasket and bolt together with screws.
If necessary, replace worn out parts. When doing so, observe Items 6.0 (Fit- ting position...Assembly) and 2.0 (Safety measures).
Mount the SJE using new gaskets for the flange connections.
Now we recommend checking over all SJE flange connections to see that they are leak-proof.
Immediately after completing maintenance jobs on the SJE, re-install any safety- resp. protective devices, check them through and reset for operation.
10.6 Re-commissioning according to Item 7.1 (Commissioning).