Wind Farm Work Breakdown Structure


ID Task Name Duration Start Finish 2009
3rd Quarter 4th Quarter 1st Q
Jun Jul Aug Sep Oct Nov Dec Jan
1 Initiation 1 day? Thu 7/10/08 Thu 7/10/08
2 Planning 413 days? Fri 7/11/08 Tue 2/9/10
3 Wind Resource Assessment and Site Selection 403 days? Fri 7/11/08 Tue 1/26/10
4 Preliminary Area Identification 1 day? Fri 7/11/08 Fri 7/11/08
5 Review Wind Resource Map 1 day? Fri 7/11/08 Fri 7/11/08
6 Identify Candidates 1 day? Fri 7/11/08 Fri 7/11/08
7 Initial Site Visits 11 days? Fri 7/11/08 Fri 7/25/08
8 Interconnection Assessment 10 days Fri 7/11/08 Thu 7/24/08
9 Lease or Buy 10 days Fri 7/11/08 Thu 7/24/08
10 Identify Regulatory Framework 10 days Fri 7/11/08 Thu 7/24/08 Lawyer
11 Identify Critical Issues Analysis 1 day? Fri 7/25/08 Fri 7/25/08
23 Telecommunications interference 1 day? Fri 7/11/08 Fri 7/11/08
24 Initial Economic Analysis 10 days Mon 7/28/08 Fri 8/8/08
25 Prioritization of Sites 1 day? Fri 7/11/08 Fri 7/11/08
26 Wind Assessment 403 days? Fri 7/11/08 Tue 1/26/10
27 Develop Assessment Plan 1 day? Fri 7/11/08 Fri 7/11/08
28 Acquire wind analyst resource 1 day? Fri 7/11/08 Fri 7/11/08
29 Selection of Tower locations 1 day? Mon 7/14/08 Mon 7/14/08
30 Validation (Meteorological Towers) 387 days? Tue 7/15/08 Wed 1/6/10
31 Permission if needed 10 days Tue 7/15/08 Mon 7/28/08
32 Permit if height restriction 10 days Tue 7/15/08 Mon 7/28/08
33 Acquire meteorological towers 10 days Tue 7/29/08 Mon 8/11/08
34 Install meteorological towers 3 days? Tue 8/12/08 Thu 8/14/08
35 Tower 1 day? Tue 8/12/08 Tue 8/12/08
36 Anemometers 1 day? Wed 8/13/08 Wed 8/13/08
37 Data Logger 1 day? Thu 8/14/08 Thu 8/14/08
38 Lights or power 1 day? Tue 8/12/08 Tue 8/12/08
39 Backup or redundant anemometer 1 day? Tue 8/12/08 Tue 8/12/08
40 Record data for year 365 days Thu 8/14/08 Wed 1/6/10
41 Obtain nearby airport data 10-20 years 1 day Wed 1/6/10 Wed 1/6/10
42 Determine if anomalies 4 days Thu 1/7/10 Tue 1/12/10
43 Wind roses 5 days Wed 1/6/10 Tue 1/12/10
44 Peak season, time of day, hours of power 5 days Wed 1/13/10 Tue 1/19/10

Page 1
1st Draft Solutions That Work Sun 8/17/08
Wind Farm Work Breakdown Structure
ID Task Name Duration Start Finish 2009
3rd Quarter 4th Quarter 1st Q
Jun Jul Aug Sep Oct Nov Dec Jan
45 Recommendation & prioritization 5 days Wed 1/20/10 Tue 1/26/10
46 Critical Issues Analysis/Regulatory Framework 91 days? Mon 8/11/08 Mon 12/15/08
47 Acquire biologist/permitting resource 30 days Mon 8/11/08 Fri 9/19/08
48 Develop constraints map 1 day? Mon 8/11/08 Mon 8/11/08
49 Include setbacks 1 day? Mon 8/11/08 Mon 8/11/08
50 Determine impacted species 30 days Tue 8/12/08 Mon 9/22/08
51 Plan mitigation, remediation 30 days Tue 9/23/08 Mon 11/3/08
52 Plan regulatory approvals 30 days Tue 11/4/08 Mon 12/15/08
53 Micrositing 54 days Thu 11/26/09 Tue 2/9/10
54 Acquire micrositing resource 30 days Thu 11/26/09 Wed 1/6/10
55 Potential tower locations 5 days Wed 1/27/10 Tue 2/2/10
56 Micrositing software? 5 days Wed 1/27/10 Tue 2/2/10
57 Site layout 5 days Wed 2/3/10 Tue 2/9/10
58 Economic Analysis, Site 5 days Wed 2/3/10 Tue 2/9/10
59 Execution & Control 728 days? Thu 7/10/08 Mon 4/25/11
60 Acquire Land Rights 365 days Mon 8/11/08 Fri 1/1/10
61 Transmission Capacity Analysis 375 days Mon 8/11/08 Fri 1/15/10
62 Environmental Impact Analysis, Avoidance & Mitigation 395 days Tue 12/16/08 Mon 6/21/10
63 Power Purchase Agreements 90 days Tue 12/16/08 Mon 4/20/09
64 Permitting / Regulatory approvals 508 days? Thu 7/10/08 Mon 6/21/10
65 Obtain environmental approvals 305 days Tue 4/21/09 Mon 6/21/10
66 ASTM ESA compliance 45 days Tue 4/21/09 Mon 6/22/09
67 Litigation & Appeals 1 day? Thu 7/10/08 Thu 7/10/08
68 Financing 204 days? Thu 7/10/08 Tue 4/21/09
75 Construction 728 days? Thu 7/10/08 Mon 4/25/11
127 Community Outreach 755 days Mon 7/28/08 Fri 6/17/11
128 Operation 65 days Tue 2/1/11 Mon 5/2/11
129 O&M Planning & Prep 30 days Tue 3/15/11 Mon 4/25/11
130 Staffing (1 per 10-20 towers) 60 days Tue 2/1/11 Mon 4/25/11
131 Commissioning 5 days Tue 4/26/11 Mon 5/2/11
132 Closing 1 day? Thu 7/10/08 Thu 7/10/08

Page 2
1st Draft Solutions That Work Sun 8/17/08
Wind Farm Work Breakdown Structure
2010 2011
arter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Page 3
1st Draft Solutions That Work Sun 8/17/08
Wind Farm Work Breakdown Structure
2010 2011
arter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter 1st Quarter 2nd Quarter
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

Developer