MANDATORY SPARES

(STATIC EQUIPMENT)
CCR REGENERATION PACKAGE
GGSRP, HMEL
SECTION: A-4.1
6922-502-16-46-MD-101
Page 1 of 3

Format No. EIL-1641-1924 Rev.1
Copyright EIL All rights reserved


SECTION: A-4: MANDATORY /RECOMENDED
SPARES

A-4.1: STATIC EQUIPMENT






CCR REGENERATION PACKAGE

PROJECT : GURU GOBIND SINGH REFINERY


OWNER : HPCL-MITTAL ENERGY LIMITED


PMC : ENGINEERS INDIA LTD.


JOB NO. : 6922









A 20.05.2008 ISSUED FOR BIDS TG VB AKM
Rev.
No
Date Purpose
Prepared
by
Checked
by
Approved
by
MANDATORY SPARES
(STATIC EQUIPMENT)
CCR REGENERATION PACKAGE
GGSRP, HMEL
SECTION: A-4.1
6922-502-16-46-MD-101
Page 2 of 3

Format No. EIL-1641-1924 Rev.1
Copyright EIL All rights reserved
(A) MANDATORY SPARE PARTS

1. PRESSURE VESSELS, REGENERATION TOWER, REACTOR

Sl.
No
Part Description Quantity Required
1 Bolting for each nozzle with blind/
companion flange and for each pad
nozzle
10% (min. 2 nos.) for each nozzle
2 Gaskets for each nozzle with blind/
companion flange and for each pad
nozzle
200 %
3 Bolting for internal flanges of each
nozzle
One set for each nozzle
4 Gasket for internal flanges of each
nozzle
200 %
5 Sight/light glasses assembly complete
with bolting and gasket
4 sets for each installed glass.
6. Bolts, nuts, clamps, spares for demister
of each size/ type
One set of each size / type



2. TUBULAR EXCHANGERS
SL.
NO
PART DESCRIPTION QTY
1 Gaskets for girth joints, each nozzle
with blind flange and interconnected
nozzles
400%
2 Bolting (stud & nuts) 20% Bolting (Min. 4 studs and 8 nuts per
joint)
3 Push Rods 100%
4 Lamiflex Sealing Strips 100%


3. ELECTRIC HEATER

SL.
NO
PART DESCRIPTION QTY
1 Gaskets for girth joints, each nozzle
with blind flange and interconnected
nozzles
400%
2 Bolting (stud & nuts) 20% Bolting (Min. 4 studs and 8 nuts per
joint)
3 Heating elements 10%(minimum 1) which shall be in-built
and electrically not connected.

4. FILTERS, COALESCERS

SL.
NO.
PART DESCRIPTION QTY
1 Filter Elements (Cartridges,
Coalescing, separating elements)
100% for non reusable type of elements.

2 Bolting (stud & nuts) One set of each size of each nozzle
3 Gaskets 200% of each installed gasket
MANDATORY SPARES
(STATIC EQUIPMENT)
CCR REGENERATION PACKAGE
GGSRP, HMEL
SECTION: A-4.1
6922-502-16-46-MD-101
Page 3 of 3

Format No. EIL-1641-1924 Rev.1
Copyright EIL All rights reserved


(B) COMMISSIONING SPARES :

To be recommended and supplied by vendor.

(C) TWO YEARS OPERATIONAL SPARES :

Any additional spares required over and above mandatory spares for 2 years operation
including spares for electrical, instrumentation, control etc. and any special tools and
tackles required for maintenance shall be quoted separately along with details.