NEQ.15238 Alpha Part #0540091 Power System Installation Checklist
Commissioning
Controller conguration:
CXC controller LCD verify/ set network IP parameters.
IP address: 10.10.10.201 (factory default)
Subnet mask:255.255.255.0
Logout.
Connect a laptop to the CXC controller with a network crossover cable.
Laptop IP Network settings (Start > Control Panel)
IP address: 10.10.10.202
Subnet mask:255.255.255.0
Turn off Pop-up Blocker.
10.10.10.201 in the web address bar
Login to the CXC controller:
Username: your company name and your initials
Password: 1234
Language selection: English
Set correct date and time (Controller > Date & Time).
Set Battery AH Capacity (Batteries > Congure Batteries).
Count number of battery strings.
Multiply the number of strings by the rated battery capacity.
Submit changes and Accept.
Logout.
8. Load Terminations
Multi-pole adapter plates in use Two-position and three-position breakers include a plate that links to-
gether the output connections of the breaker
GMT Fuses:
SIAD
LMU
Smoke Detector
Hydrogen Sensor
9. Alarm wiring
Installed Veried
K2 and K3
Un-assignable - no input leads connected
K4
Power System Minor
K5
Power System Major
K6
AC Mains Failure
K7
Distribution Fuse/Breaker alarm
K8
Battery on Discharge
System Installation continued