Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
4 days 14 days 14 days 7 weeks
**
11 weeks
*
Handover of
substation to SPPG
+
NA NA NA NA 10 weeks
*
Opening of account
with SPSL
4 days 14 days 14 days 14 days 11 weeks
Arrangements to
inspect customer's
installation (not
exceeding 45kVA) by
SPSL
NA 10 days NA NA NA
Application to EMA for
licence to use or
operate an electrical
installation
NA NA 10 days 10 days 10 days
Request for
energisation of service
connection
NA NA 14 days 14 days 14 days
* These are critical events. Failure to adhere to the schedule may result in delay in the turn-on of supply.
Implementation of connection work shall only be effected upon the payment of service
connection charge and execution of the Connection Agreement by the customer.
** For connection by underground cable, SPPG will have to seek road opening approval from the relevant
authorities before cable work can commence. The approval process usually takes about 3 weeks.
Depending on the length of cable to be installed, supply will normally be available 4 to 6 weeks from the
date customer's premises is ready to receive the service cable.
+ Energisation of service connection will normally take place within 10 weeks of handing over of
substation. This lead-time may vary from case to case, depending on the customers schedule.
31
4.9 NOTES TO BE READ IN CONJUNCTION WITH APPLICATION
PROCEDURE
4.9.1 Licensed Electrical Worker
4.9.1.1 There are three classes of LEW, namely Licensed Electrician, Licensed Electrical
technician and Licensed Electrical Engineer. Licensed electrical workers of
various class are licensed to design, install, repair, maintain, operate, inspect and
test an electrical or supply installation in accordance with the condition stated
below:
Electrical Workers Approved Load of Installation Voltage
Electrician Not exceeding 45kVA Not exceeding 1,000V
Electrical Technician Design: Not exceeding 150kVA
Install: Not exceeding 500kVA
Not exceeding 1,000V
Electrical Engineer No limit Subject to licence conditions
4.9.1.2 The customer should appoint an LEW appropriate to the capacity and voltage of
the proposed installation, and inform SPSL immediately of any change of LEW
during the course of the project.
4.9.2 Opening An Account
4.9.2.1 Before supply to an installation can be turned on, the customer must open an
account with SPSL. An application to open an account for electricity supply can
be made either personally, through the post or Internet. A sample of the
Application(s) for the Supply of Water, Electricity and /or Gas and GIRO forms to
be completed are shown in Appendix 6 and Appendix 7 respectively.
4.9.2.2 Application in person can be made at SPSL's Customer Services Centre, Upper
First Storey, 111 Somerset Road #01-10, Singapore Power Building; or at SPSL's
Application counter at Woodlands Civic Centre #02-06, 900 South Woodlands
Drive, Singapore 730900. Applications through the post should be addressed to:
Deputy Director (Customer Services)
SP Services Ltd
P O Box 341 Orchard Post Office
Singapore 912312
4.9.2.3 The following documents must be shown at the time of application in person:
4.9.2.3.1 Identity Card/Passport of owner/tenant/authorised signatory*
4.9.2.3.2 Copy of Business/ Company Registration Certificate*
4.9.2.3.3 Documentary proof of occupation of premises, e.g. rent receipt or sales letter from
HDB confirming the purchase of the premises
4.9.2.3.4 Bank account book to effect GIRO deduction from the account
32
*applicable for account in company's/organisation's name.
4.9.2.4 For applications submitted through the post, copies of the above-mentioned
documents must be enclosed.
4.9.2.5 An initial deposit is payable on opening an account. Customers may call the
Customer Enquiry Auto-Link (U-Link) at 1800-7380038 to enquire about the
opening and closing of accounts.
4.9.2.6 For domestic premises, the deposits are as follows:
Type of Premises Deposit
GIRO
Customers
Non-GIRO
Customers
HDB 1/ 2 rooms S$ 40 S$ 60
HDB 3/ 4/ 5 rooms S$ 70 S$ 100
HDB Executive/ HUDC/ Terrace S$ 100 S$ 150
Private Apts/ Semi-Detached/ Condo S$ 150 S$ 250
Bungalow/ Penthouse/ Townhouse S$ 250 S$ 400
4.9.2.7 The deposit for non-domestic premises varies according to the electricity load
required, the estimated water consumption, the floor area and type of operations.
For enquiry on the amount of deposit required, customers can call 1800-2222333.
4.9.3 Handover Of Completed Substation
4.9.3.1 The handover of substation to SPPG for installation of equipment is a key event,
which determines the earliest date when supply can be made available.
4.9.3.2 One week prior to the intended handover of the substation, the LEW must submit
a Request to Handover Substation form (Appendix 5) to Deputy Director
(Customer Projects - East / West / Distribution Projects), SPPG. Before this is
done, the LEW must ensure that the customer/developer has accepted the terms
and conditions of connection, including the payment of necessary charges.
4.9.3.3 It must be emphasised that SPPG will take over the substation only when it is
completed in accordance with plans and specifications approved by SPPG and
the relevant authority. It is particularly important that the access to the substation
must be clear and passable for transportation of heavy equipment.
33
4.9.3.4 Floor frames are needed for some types of switchgear. Prior to the final rendering
of the switchroom floor, the LEW is to notify the project engineer-in-charge to
make arrangements for the floor frame to be installed, if it is necessary.
4.9.3.5 Requirements on handover of a completed transmission substation are given in
General Requirements for EHT Substation (Appendix 17).
4.9.4 Installation Of Current Transformer Operated Meters
4.9.4.1 On the day the LEW arranges with SPSL for a date for energisation of the service
connection, he should also bring the letter of appointment for energisation of the
service connection to Meter Section to arrange for the installation of meters. On
the appointed day of meter installation, the LEW or his representative must be
present to provide a 230V 13A single-phase supply for testing of the meters.
4.9.5 Procedure For Application For Licence To Use Or Operate An Electrical
Installation
4.9.5.1 General
4.9.5.1.1 Under The Electricity Act, electrical installations in non-domestic premises,
residential buildings and condominiums with an approved load greater than 45kVA
are required to be licensed. In addition, certain premises classified as engaging in
dangerous trades, are also required to be licensed even though they may have
approved electrical loads not exceeding 45kVA.
4.9.5.1.2 Customer is required to appoint an appropriate class of licensed electrical worker
to take charge of his electrical installation and submit application for Electrical
Installation licence through his appointed licensed electrical worker via EMA
website at www.ema.gov.sg. The validity of the licence is for a period of 12
calendar months.
4.9.5.2 Conditions For The Issue Of The Licence
4.9.5.2.1 Conditions for the issue of the electrical installation licences are governed by
EMA.
4.9.5.2.2 The minimum grade of LEW required to take charge of the electrical or supply
installation is determined by the total approved load. The grades of Electrical
Workers and their authorisation conferred under the respective EMA licences are
shown in the table in paragraph 4.9.1.1.
34
4.9.6 Procedure For De-Energisation / Disconnection Of Service Cables
4.9.6.1 De-Energisation Of Service Cable For Maintenance Purpose
4.9.6.1.1 The LEW who needs to de-energise an existing service cable for the purpose of
maintenance or upgrading of the customers installation must submit the ADRE
form to SPPG 7 business days in advance (Appendix 19). For Contestable
Customers, an advance notice of 14 business days is required.
4.9.6.1.2 The SDRE form (Appendix 20) must be used to ensure that the service cable is
safely isolated after de-energisation and fit to be energised before re-energisation.
Both SPPGs officer in-charge and the LEW must duly complete and sign Part I
and Part II of the form after de-energisation and before re-energisation of the
service cable respectively. For Contestable Customers, the LEW must duly
complete and sign Part III of the SDRE form.
35
2. Customer's
Installation Requirements
5.1 REQUIREMENTS FOR HT AND LT CONNECTION (22kV AND BELOW)
5.1.1 Short-Time Withstand Current Ratings of Switchgear
5.1.1.1 For electrical installations taking electricity supply directly from SPPAs network,
the customers main supply incoming switchgear must comply with the following
short-time withstand current ratings:
5.1.1.1.1 For supply at 22kV
- 25kA for 3 sec
5.1.1.1.2 For supply at 6.6kV
- 20kA for 3 sec
5.1.1.1.3 For supply at low tension,
a) Single-Phase 230V
- 6kA for supply capacity up to 15kVA
- 9kA for supply capacity more than 15kVA and up to 23kVA
b) 3-Phase 400V
- 9kA for supply capacity up to 75kVA
- 25kA, 3 sec for supply capacity more than 75kVA and up to 180kVA
- 36kA, 3 sec for supply capacity more than 180kVA.
Note: The 3-second duration is not applicable to switchgear incorporating direct
acting tripping devices.
5.1.1.2 For electrical installations taking electricity supply from the landlords or
management corporations electrical installations, the LEW in-charge must ensure
that the customers main supply incoming switchgear is capable of withstanding
the prospective short-circuit current at the connection point.
5
36
5.1.2 Protection Requirements
5.1.2.1 Typical schemes and the protection requirements for customers HT and LT main
incoming switchgear taking electricity supplies from SPPAs system are shown in
Appendix 18. It must comply in general to conditions as set out in the
Transmission Code, Section 6.3 and Appendix F3.
5.1.2.2 For electrical installations taking electricity supply from the landlords or
management corporations electrical installations, advice on protection
requirements must be sought from the LEW responsible for the respective
licensed electrical installation.
5.1.2.3 Protection Requirement For 22kV Customer Connection
The main protection for the 22kV customer connection must be pilot wire
differential protection. The current transformers of ratio 500/5 must be of Class X
and the CT secondary star-point must be towards the protected line. The
standard overcurrent/earth fault setting for the incomer is shown in Appendix 18.
5.1.2.3.1 To effect fast fault clearence, the 22KV cable terminations and metering CTs/VTs
installed at the incomers must be included in the 'Protected Zone' of the cable's
Unit Protection, as shown in Appendix 18.
The LEW of the customer installation is responsible for:
5.1.2.3.2 proper specification, setting / commissioning of the protection system at the
customer incomers, and
5.1.2.3.3 ensuring that the 22kV circuits within the customer installation are equipped with
unit protection for fast fault clearance, inclusive of fault at cable terminations.
5.1.2.4 Protection Requirement For LT Supply Connection
The customers incoming circuit breaker shall be set according to the approved
load. For approved load exceeding 300A, external overcurrent relays of IDMTL or
DTL characteristics and earth fault protection (DTL) must be provided at the
incoming switchgear. The current transformer must be of Class 5P10, 15VA or
better. Details are shown in Appendix 18.
5.1.2.5 Every low tension electrical installation of supply capacity exceeding 75kVA must
be provided with short-circuit protection in the form of direct acting trip element at
the incoming switchgear as follows:
Approved Load Direct Acting Trip Setting
Above 1500A Up to 4500A
400A<Approved Load <1500A Up to 3200A
260A <Approved Load <400A Up to 2400A
200A <Approved Load <260A Up to 2000A
200A and below Up to 1200A
Alternatively, a backup HRC fuse may be used in place of direct acting trip.
37
5.2 REQUIREMENTS FOR EHT CONNECTION (230kV and 66kV)
5.2.1 Short-Time Withstand Current Ratings Of Switchgear
For electrical installations taking electricity supply directly from SPPAs network,
the customers main supply incoming switchgear must comply with the following
short-time withstand current ratings:
5.2.1.1 For 230kV Switchgear
- 63kA (1 sec)
5.2.1.2 For 66kV Switchgear
- 40kA (3 sec)
5.2.2 Protection Requirement For 66kV and 230kV Customer Connection
5.2.2.1 General
5.2.2.1.1 The protection system for the connections has to comply in general to the
conditions as set out in the Transmission Code.
5.2.2.1.2 All circuits connected to SPPAs transmission network, inclusive of busbars for
230kV and above, must be provided with unit protection for fast fault clearance.
5.2.2.1.3 Engineering details and protection settings will be discussed with the customer
during the project implementation.
5.2.2.1.4 The relays used for a unit protection scheme, and the characteristics of its
associated current transformers should be matched. For reason of obsolescence
or availability, the type of protection relays, signaling equipment and the protection
schemes is subject to review and confirmation during the consultation period.
5.2.2.1.5 Wherever applicable, protection signaling equipment is to be provided for tele-
protection function and for end-to-end transfer of intertrip and interlock signals.
5.2.2.1.6 Generally, the star-point of the current transformer secondary circuit must be
towards the protected object / zone.
5.2.2.1.7 Generally, the location of the current transformers for the circuit and that of the
installations busbar protection system for 230kV and above must be overlapped
across the circuit breaker to eliminate protection blind zone.
5.2.2.1.8 Current transformers supplied for unit protection must be rated in accordance with
IEC 60044 Part 1 & 6, BS 3938. They must be adequately dimensioned and of an
accuracy class meeting the specified relays requirement. The characteristic of
the current transformers installed at both ends of the connected circuit must be
closely matched with each other to ensure stability.
38
5.2.2.1.9 The LEW of the customer's installation is responsible for the proper specification,
setting/commissioning of the protection system at the customer 230KV or 66KV
incomers.
5.2.2.2 The proposed settings for the backup protection for the 66KV customer incomer
must generally be as follows:
PROPOSED RELAY SETTING FOR 66kV CUSTOMER INCOMER
Protection Relay General Setting
Over Current Protection (IDMTL) CT Ratio Setting
Feeder Circuit (1000/5) 150% 0.15
(800/5) 200% 0.15
Feeder Transformer Circuit
(for 75MVA transformer)
(1000/5) 100% 0.20 Hi-Set: 27A
(800/5) 125% 0.16 Hi-Set: 34A
Earth Fault Protection (IDMTL)
Feeder Circuit (1000/5) 10% 0.10
(800/5) 15% 0.10
Feeder Transformer Circuit
(for 75MVA transformer)
N/A
Notes:
- The coordinated setting for the backup protection is applicable to the standard
protection scheme proposed for a feeder or feeder-transformer type customer connection
and is applicable to radial feed connection only. (Refer to Appendix 18)
- The overcurrent and earth fault setting are subjected to periodic review by SPPG.
5.3 INFORMATION ON SPPA NETWORK EARTHING SYSTEM (230KV,
66kV and 22kV)
5.3.1 Where customer is connected directly to SPPAs network, customer shall note the
following earthing system at each voltage level.
5.3.1.1 230kV
Solidly earthed system.
5.3.1.2 66kV
Resistive earthed system with neutral ground resistor (NGR) of 19.5 ohms.
5.3.1.3 22kV
Resistive earthed system with neutral ground resistor (NGR) of 6.5 ohms.
5.3.2 Customer shall ensure that all equipment including CTs, VTs, and protection
systems connected to SPPA network meet the technical specification required for
the respective earthing system in accordance with the relevant standards.
39
2. Metering
Requirements
6.1 General
6.1.1 All metering requirements must comply with EMAs Metering Code. SPPG will
determine the location where the supply line terminates in the premises, based on
ease of accessibility to SPSL and SPPG personnel.
6.1.2 The developer or customer bears the cost of providing and maintaining the meter
boards, miniature circuit breakers (MCBs), isolators and wiring for installation of
meters. The meters are supplied and maintained by SPPA.
6.1.3 Meters can be mounted on any of the following types of meter boards:
6.1.3.1 Teak board or any hardwood board chemically treated against attacks by termites.
Plywood should not be used. The meter board must be at least 20mm thick and
rigidly fixed with a minimum of 4 fixing screws.
6.1.3.2 Metal panel with nylon inserts accurately positioned to accommodate the meter.
6.1.3.3 Glass reinforced polyester base fitted with nylon inserts accurately positioned to
accommodate the meter.
If item 6.1.3.2 or 6.1.3.3 is provided, SPPGs Meter Section has to be consulted on
the locations of the nylon inserts.
6.1.4 The LEW must ensure that all metering requirements are complied with, and
submit, at the planning stage, all relevant drawings on meter locations, meter
board size, meter rooms, meter compartments/riser ducts/ cupboard, etc to Meter
Section for approval. Sample units of each approved type of meter compartment /
riser duct / cupboard and meter board must be provided for final inspection and
approval by Meter Section before meters are installed.
6
40
6.1.5 If the doors of centralised meter rooms, meter gate posts, meter compartments/
riser ducts/ cupboards, etc are to be locked, they must be fitted with locksets which
can be opened with one of the following master keys:
6.1.5.4 Abloy master key code reference MK 911047
6.1.5.5 Chubb (Union) master key code reference G1HBG
6.1.5.6 Yale master key code reference MK48
The doors of meter rooms/compartments must be able to be opened from the
inside without the need to use a key or other devices/tools.
6.1.6 All access doors to meter rooms/compartments/riser ducts/cupboards, etc must
have a clear access opening of at least 600mm (width). The doors must be fitted
with doorknobs or handles.
6.1.7 Security access systems installed in any premises must not impede access by
SPSL and SPPG personnel.
6.2 LOCATION OF METER
6.2.1 General
6.2.1.1 The service board accommodating SPPA's service MCBs and meters must be
located near the termination of the service line. The meter/service position must
be easily accessible at all times to SPSL and SPPG personnel for maintenance
and reading of meters.
6.2.1.2 Meters must be installed in a safe location where they will not be damaged or be a
cause of danger to personnel (viz, in a clean and dry location, not exposed to
weather, mechanical damage, vibrations, extremes of temperature or dampness).
6.2.1.3 The height of the meter on the meter board must be between 1.0m and 1.8m
above ground level, and the depth of the compartment for installation of meters
must be between 200mm and 300mm.
It is advisable that the service board is housed in an approved box of non-
combustible high-impact material to give added protection to the metering
equipment and safety.
6.2.2 Grouping of Meters
Meters must be installed outside each tenant unit for ease of meter reading,
maintenance, etc. Where this is not possible for practical reasons, meters may be
grouped together in easily accessible centralised meter rooms or meter
compartments/riser ducts/cupboards in multi-metered premises (e.g., residential,
office, shopping or industrial high-rise building/complex).
41
6.2.3 Meters in Meter Compartments / Riser Ducts / Cupboards
6.2.3.1 Meters are to be grouped on the same floor as the tenant units.
6.2.3.2 There may be more than one group metering location on each floor.
6.2.3.3 There must be adequate lighting in the group meter location to facilitate meter
installation/maintenance and meter reading.
6.2.3.4 Meter boards in meter compartments/riser ducts/cupboards must be such that
meters can be mounted facing the doors.
6.2.3.5 All meter compartments/riser ducts/cupboards where meters are installed are to be
clearly and permanently labeled. Tenant unit numbers on permanent labels must
be fixed adjacent to their respective meters.
6.2.3.6 Meter compartments/riser ducts/cupboards housing the meters must have clear
glass windows provided on the doors, if these are locked, for ease of meter
reading. The window for each meter must not be less than 200mm (W) x 300mm
(H) x 6mm (thickness) and must be correctly positioned in front of where the meter
is to be installed. Plastic windows and UV resistant polycarbonates are not
acceptable. Full glass doors are not acceptable.
6.2.4 Meters in Centralised Meter Rooms
6.2.4.1 The height of the meter board or panel must be such that meters can be mounted
with the highest row not exceeding 1.8m above floor level and the lowest row not
less than 1m above floor level.
6.2.4.2 There must be standing space of at least 700mm in front of the meter panel.
However, if the meters are mounted on a free-standing panel, a clearance of
700mm all round the panel is required.
6.2.4.3 The meter board or panel must be rigidly and vertically mounted. The doors of the
panel must be hinged.
6.2.4.4 The meter room must not be used as a storeroom.
6.2.5 Meters Installed in Landed Properties
6.2.5.1 The meters and service cables must be installed in a weatherproof compartment
located at the gate pillar or perimeter wall. For supply capacity up to 100A 3
phase, the technical requirements for this compartment are as given in Appendix
24. For supply capacity greater than 100A 3-phase where a CT-operated meter
will be installed, the LEW has to submit the technical requirements to Meter
Section for approval.
42
6.2.5.2 If there is no gate pillar or fencing around the perimeter of the landed properties,
meters must be installed inside a weatherproof meter box/compartment and easily
accessible to SPSL and SPPG personnel. Meters must not be installed inside the
house.
6.3 METER/SERVICE BOARD SPECIFICATIONS (SINGLE-PHASE AND 3-
PHASE SERVICES, NOT EXCEEDING 100A PER PHASE)
The meter/service board for SPPA's service MCBs and meters must be as
specified in Section 6.1.3 and in accordance with the drawings in Appendices 25,
26 and 27.
6.4 WIRING, LAYOUT OF METERS, MCBs, ETC IN CENTRALISED METER
ROOMS, METER COMPARTMENTS/RISER DUCTS/CUPBOARDS
6.4.1 All wiring leading in and out of the group meter location must comply with SS CP5.
The landlord's wiring must be segregated from the tenant's wiring.
6.4.2 Meters are to be mounted together with their associated service MCBs / neutral
connectors such that each meter can be visually identified with its associated
service MCBs. Each meter position must be clearly labeled according to the
tenant unit number. There should be a space of 70mm between vertically
mounted meters.
6.4.3 Meters are to be mounted in neat vertical columns and/or horizontal rows.
6.4.4 Service MCBs shall be sealable. MCBs must be clearly labeled according to the
tenant units served. The labeling must also correspond to the labels used for the
meters.
6.4.5 All wiring on the meter boards from service MCBs / neutral connectors to the
meters and from the meters to the customer's main switches must be neatly run on
the surface - horizontally and/or vertically.
6.5 SUBMISSION OF LAYOUT PLANS
The layout of the meter rooms, meter compartments/riser ducts/cupboards
together with the meter board drawings and plans of the units served, must be
submitted at the planning stage by the LEW for approval by Meter Section.
6.6 METERS FOR 3-PHASE LOW TENSION CONNECTION
(EXCEEDING 100A PER PHASE)
6.6.1 Meters for connections exceeding 100A per phase are operated from metering
current transformers and are to be fixed on a pre-wired metering panel on the
customers main switchboard. However, where the length of the connecting leads
are not excessive, the pre-wired metering panel may, with the prior approval of
Meter Section, be wall-mounted away from the main switchboard or in a separate
meter room. The pre-wired metering panel with Meter Section approved type test
block, 6A (10kA) MCB, pilot lights and metering cables to the busbars and the
43
three metering current transformers, must be provided by the customer. Drawings
of the pre-wired meter panel can be obtained from Meter Section at St J ames
District Office, Telok Blangah Road.
6.6.2 Meter Panel Compartment Specifications
6.6.2.1 Meter panels must be of mild steel of at least 1.6mm thickness or other materials
subject to approval by Meter Section
6.6.2.2 The panels must be detachable and of a size given in Appendix 28.
6.6.2.3 The compartments must have a minimum depth of 100mm between cover and
base.
6.6.2.4 There must be openings with appropriate bushing for the meter wires.
6.6.2.5 The cover must have at least 3 hinges and be able to swing and open out at least
90
o
.
6.6.2.6 Facilities for sealing must be provided. Methods of sealing are illustrated in the
drawings in Appendix 29.
6.6.3 Meter Installation Requirements
6.6.3.1 The switchboard must be complete and securely mounted in its final position
before meters can be installed.
6.6.3.2 The top of the meter panel must not exceed 2.0m from the ground.
6.6.3.3 A 50mm x 50mm trunking of metal or other approved material between the
switchboard and the meter panel must be provided to house the meter cables if
the latter is installed away from the customers main switchboard.
6.6.3.4 A 6.0mm tap-hole plus screw/washer on each busbar must be provided to facilitate
connection of the voltage cables to the meter voltage coils.
6.6.3.5 If the meter panel is away from the customers main switchboard, sealable 30A
HRC fuse for each phase and a sealable 3-pole ganged MCB of 6A 10kA rating
must be provided on the front of the switchboard panel near the metering CT
enclosure for the protection of the meter voltage wiring. The MCB must be
appropriately labeled.
6.6.3.6 Mounting of metering current transformers must be as follows:
- Current transformers must be mounted on jumpers for easy installation.
- Bakelite clamps must be provided to secure the meter current transformers
in position.
- Adequate insulation between the metering current transformers and the
busbar must be provided.
44
- The metering current transformers and meter voltage tap off points must be
installed after the incoming connection main protection current
transformers.
6.6.3.7 Enclosure
A rigid enclosure of mild steel plate of thickness not less than 1.6mm must be
provided solely for housing the metering current transformers and voltage tap off
points. The enclosures must have facilities for sealing. A typical construction of
the enclosure is shown in Appendix 30.
6.7 HIGH TENSION / EXTRA-HIGH TENSION METERING
6.7.1 General Requirements
6.7.1.1 The customer is required to provide, install and maintain, at his own expense,
current transformers, voltage transformers, a pre-wired metering panel with test
blocks, MCBs, pilot lamps and accessories, at his receiving HT switchboard.
These must meet SPPAs requirements. Drawings of the pre-wired metering panel
can be obtained from Meter Section at St J ames District Office, Telok Blangah
Road.
6.7.1.2 All metering current and voltage transformers must be used solely for SPPA's
revenue metering equipment. No other apparatus of the customer is permitted to
be connected to such metering current and voltage transformers. However, a
voltmeter may be allowed to be connected via a 100 mA fuse (sealable) subject to
approval by Meter Section.
6.7.1.3 The customer must also provide a metering kiosk to be located close to where the
metering current and voltage transformers are installed, such that the route length
of the cables from the current and voltage transformers to the metering kiosk does
not exceed 20m. Where this cannot be complied with because of site constraints,
the LEW must consult Meter Section concerning the type and size of cables to be
provided and installed by the customer.
6.7.1.4 The requirements for the kiosk are given in Appendices 31 and 32. The access to
the metering kiosk must be from outside the HT switchroom and fitted with any one
of SPPA's approved master lock series as specified in Section 6.1.5.
6.7.1.5 The customer must provide an appropriate metering panel of a size given in
Appendix 33 and install a 50mm x 50mm trunking of metal or other approved
material between the customers HT switchboard and the metering panel together
with the required type and size of cables.
6.7.1.6 Facilities for sealing connections of all metering wire termination at the customer's
HT switchboard must be provided.
6.7.1.7 A schematic and wiring diagram of the customers switchboard must be supplied to
facilitate installation of the meters.
45
6.7.2 Specifications For Metering Current Transformers
6.7.2.1 The customer will provide two metering current transformers of 30VA burden for
66kV connection or 15VA burden for connection at 6.6kV or 22kV. These must be
of accuracy class 0.5 complying with SS 318 or IEC 60044-1.
6.7.2.2 The current transformers are to be installed on the red and blue phases at the
cable end for each of his receiving switchboard. The current transformer ratio will
be determined by SPPG based on the customers load requirement. For
connection at 230kV, the LEW will liaise with Meter Section on metering
requirements.
6.7.2.3 The rated short-time current rating must not be less than 63kA 1 second, 40kA 3
seconds, 25kA 3 seconds and 20kA 3 seconds for connection at 230kV, 66kV,
22kV and 6.6kV respectively.
6.7.3 Specifications for Voltage Transformers
6.7.3.1 For each of the customers receiving switchboard, one of the following voltage
transformers must be provided:
6.7.3.1.1 One unit 3-phase 66kV/110V, 22kV/110V or 6.6kV/110V voltage transformer of
100VA burden per phase, connected star-star with the yellow phase terminal of the
secondary winding earthed, or
6.7.3.1.2 Three units single phase,
66kV 110V or 22kV 110V or 6.6kV 110V
3 3 3 3 3 3
Voltage transformers of 100VA burden per phase, connected star-star with the
yellow phase terminal of the secondary winding earthed.
6.7.3.1.3 Voltage transformers must be of accuracy class 1.0 complying with BS3941 or IEC
60186.
6.7.3.1.4 The secondary wiring of the voltage transformer must terminate in a sealable MCB
incorporated in the switchgear panel. The MCB must be rated at 6A, 110V, 50Hz
with breaking capacity not less than 10kA and the terminals of the MCB must be
able to accept cables of cross section up to 6mm
2
.
6.7.3.1.5 The voltage transformers must be fused and adequate stock of spare high-voltage
fuses must be kept by the customer.
46
6.8 TESTING OF METERING CTs AND VTs
6.8.1 All metering current transformers and voltage transformers together with their
manufacturers' test certificates must be submitted for testing and approval by
Meter Section at least 2 weeks before connection is required. Voltage transformers
at 66kV and 230kV are exempted from testing and only the manufacturers test
certificates have to be submitted.
6.8.2 The metering VTs, after re-installation onto customers switchgear, have to be
tested and phase out, and a test report as per Appendix 34 have to be submitted
to Meter Section for approval before installation of meters.
6.9 METERING REQUIREMENTS
6.9.1 Low Tension Customer
6.9.1.1 Single Customer - More Than 75kVA
6.9.1.1.1 The customer will provide three metering current transformers (CTs) of 5VA
burden and accuracy class 0.5 complying with SS 318 or IEC 60044-1 and the
pre-wired metering panels on the customers intake switchboard. The pre-wired
metering panel must be fitted with SPPA approved type test block, MCB and pilot
lights and connected with metering cables to the CTs and busbars. The CTs
together with their manufacturers test certificates must be submitted for testing
and approval at least 2 weeks before connection is required.
6.9.1.1.2 A request for appointment to fix meters should be made only after the LEW has
arranged with SPSL for a date to energise the service connection.
6.9.1.1.3 Meter Section will arrange to install the meters upon production of the energisation
appointment letter issued by SPSL and requires at least 4 business days before
the energisation of service connection date.
6.9.1.2 Multi-Metered Buildings
6.9.1.2.1 Submission of floor plans of building showing the locations of metering kiosks,
meter room, meter compartments/riser ducts/cupboards.
6.9.1.2.2 Submission of dimensioned metering layout showing the plan, front and side
elevations of the meter boards/rooms/compartments/riser ducts/cupboards, etc.
6.9.1.2.3 Arrangements for sample units of each approved type of meter compartment/riser
duct/cupboard and meter board to be inspected and approved by Meter Section
before meters are installed.
6.9.1.3 Landed Housing Development
6.9.1.3.1 Submission of site plans of building showing the locations of meter compartments
at gate pillars.
47
6.9.1.3.2 Submission of dimensioned metering layout showing the plan, front and side
elevations of the meter compartments in the gate pillars.
6.9.1.3.3 Arrangement for sample units of each approved type of meter compartment and
meter board to be inspected and approved by Meter Section before meters are
installed.
6.9.2 High Tension / Extra-High Tension Customer
6.9.2.1 The revenue metering equipment will be installed at the customers end of the
service connection. The customer will provide a suitable metering kiosk at his
intake station, and metering CTs and VTs for each of his receiving switchboard.
The metering CTs ratio will be based on declared demand as shown in Section
6.9.2.4.
6.9.2.2 The customer will provide and maintain at its own cost, a fixed telephone line to
the metering kiosk to be used exclusively for the purpose of remote meter reading.
This telephone line must be terminated in a standard telephone socket at the
metering kiosk. Provision of this telephone line must be made before installation
of meters.
6.9.2.3 If the customer is unable to provide the fixed telephone line due to site constraint,
a GSM line can be considered subject to approval by Meter Section.
48
6.9.2.4 Based on the contracted capacity stated in the application form, the customer is
required to provide the correct metering CTs as follows:
Contracted Capacity
MW
CT Ratio
22kV Service Connection 0.0-0.8 50/25/5
0.81-1.7 100/50/5
1.71-2.5 150/75/5
2.51-3.2 200/100/5
3.21-5.0 300/150/5
5.01-6.6 400/200/5
6.61-10.0 500/300/5
66kV Service Connection 0.0-5.0 100/50/5
5.01-10.0 200/100/5
10.01-20.0 400/200/5
20.01-30.0 500/300/5
30.01-40.0 800/400/5
40.01-80.0 1000/500/5
6.10 CONTESTABLE CUSTOMERS
6.10.1 Eligibility
The eligibility of contestable customers is determined by EMA.
6.10.2 Additional Requirements For Contestable Customers
A contestable customer must provide and maintain at its own cost a fixed
telephone line to be used exclusively for the purpose of remote meter reading.
The LEW must liaise with Meter Section for the location and termination of this
telephone line.
49
Appendices
APPENDIX 1
APPLICATION FORM For official use only
FOR CONNECTION TO THE
TRANSMISSION SYSTEM
Application
Number :
Date Received :
To : SP Services Ltd
111 Somerset Road #06-05
Singapore Power Building
Singapore 238164
PART 1 APPLICANTS DETAILS
All connections with Distributed Generation (e.g. PV system) are required to submit this application.
I request you to provide/upgrade the load connection service to my premises as given in Part 2 by my Licensed Electrical Worker undertaking the project
Name of Company/Applicant * : ______________________________________________ ROC/NRIC No. : __________________
Name of Authorised Person & Designation * : ___________________________________________________________________
Forwarding Address : __________________________________________________ Postal Code : Singapore ______________
Tel : _________________ Fax : __________________ Mobile Phone : ___________________ Pager : __________________
Email : _________________________ Signature of Applicant : _______________________________ Date : _______________
PART 2 INSTALLATION DETAILS (To be completed by LEW)
Project Description : _______________________________________________________________________________________
Site Address : ________________________________________________________ Postal Code : Singapore ______________
Utility Account No. (existing) : _____________________________ Existing Approved Load : _____________________ kVA/kW *
Any previous Consultation? Yes / No* If Yes, please provide Consultation No. : _____________________
TYPE OF CONNECTION (Please tick the appropriate boxes)
New Connection Temporary Connection Replacement of switchboard (no load upgrading) [ same / different switchroom * ]
New Connection with Distributed Generation (Please specify):__________________ __________ __________________________
Existing Connection with Distributed Generation (Please specify): ___________________________________________________________
Upgrading the existing connection point Change of intake connection point (involving new switchroom) Re-energise existing connection
Others (Please specify) : ____________________________________________________________________________________________
TYPE OF DEVELOPMENT (Please tick the appropriate boxes)
Industrial Commercial Residential Renewable Energy
Others (Please specify) : __________________________________________________________________________________
Type of Business Activity (Brief Description) : _________________________________________ Voltage Dip Sensitive? Yes / No *
LOAD REQUIREMENT (One intake connection point per premises)
Total load requirement (to include existing load, if any)
30A/60A/100A* 30A/60A/100A* __________ kVA at 400V three-phase
230V single-phase 400V three-phase
22kV 66kV/230kV*
(min. 1,700kW for 2 HV services, min. 12,751kW for 4 HV services) (min. 25.5MW for 66kV, min. 85MW for 230kV)
SINGLE USER PREMISES (HIGH TENSION / EXTRA HIGH TENSION)
Total Contracted Capacity of ________________ kW at ____________________ kV via __________ service cable(s).
Initial Contracted Capacity of ______________ kW (shall not be less than of the Contracted Capacity) for _________ months
(not exceeding 12 months)
3/9/07
50
MULTI-TENANTED / MULTI-TENANTED MASTER-SUB PREMISES (HIGH TENSION / EXTRA HIGH TENSION)
Total Contracted Capacity of ________________ kW at ____________________ kV via __________ service cable(s).
Landlords Contracted Capacity (minimum 1,700kW) : ______________________ kW
Initial Landlords Contracted Capacity : ______________ kW (shall not be less than of the Landlords Contracted Capacity) for
_________ months (not exceeding 12 months)
Target date of Energisation : ________/_________/___________ Estimated ultimate load : ___________________ kVA/kW*
(Please refer to expected lead time in handbook. For service costing job, supply will normally be available 4 to 6 weeks from the date customer
switchboard/meterboard and cable entry pipes of your premises is ready to receive the service cable. For major work where substation is involved,
you shall handover the substation building 10 weeks before the target date of energisation.)
TYPE OF PREMISES (Please tick the appropriate box)
Single user premises Multi-tenanted premises Multi-tenanted Master-sub premises
Estimated Landlord Load __________ kVA/kW*
For multi-tenanted installation with the exception of HDB residential installation, the metering scheme shall be designed as Master/Sub-metering scheme.
TYPE OF METERING SCHEME
Please specify the metering scheme : Master / Normal*
Any change in metering scheme? Yes / No*. If yes, please specify _________________________________________________
O TO BE COMPLETED FOR INSTALLATION EXCEEDING 45kVA
Total Land Area : ___________________________ m
2
Gross Floor Area : ______________________________ m
2
PLANS AND DETAILS (Mandatory)
2 copies of Architects site and location plan
Substation Land Ownership: SLA / URA / HDB / J TC / Private / Others*, please specify: _____________________
2 copies of plan showing proposed customers intake connection point and the existing intake point (if applicable)
Details of the type, floor area & designed load of individual premises for multi-metered premises
1 copy of Fault Level Report (distributed generation and applicants with large motors only)
PART 3 LEW DETAILS
I confirm that the above information is correct and agree to advise SP Services should there be subsequent changes.
Name of Authorised LEW : ______________________________________ Licence Number:______________________________
Registered Forwarding Address : ______________________________________________________________________________
______________________________________________________________________ Postal Code : Singapore ______________
Tel : _________________ Fax : __________________ Mobile Phone : ___________________ Pager : __________________
Email : ___________________________________________________________________________________________________
Signature of Authorised LEW : _____________________________________________________ Date : _____________________
PART 4 QUALIFIED ELECTRICAL CONTRACTOR (QEC) DETAILS (if applicable)
Name of Authorised QEC : ______________________________________ Licence Number:______________________________
* Delete where not applicable
51
Appendix 2
CONSULTATION FORM For official use only
FOR CONNECTION TO THE
TRANSMISSION SYSTEM
Consultation
Number. :
Date Received :
To : SP PowerGrid Ltd
111 Somerset Road #08-05
Singapore Power Building
Singapore 238164
CONSULTATION DETAILS
Sub-metered consumers (tenants) are not eligible for this application. All tenants in multi-metered premises are required to
obtain supply from their landlord/MCST or HDB for HDB premises.
Reference to the consultation, I hereby enclose one copy of site & location plans including proposed customers intake connection point
Drawing No. ____________________________________________________________ for your advice on connection requirements.
SITE DETAILS
Connection Applicant/Developer* : _____________________________________________________________________________
Project Description : _____________________________________________________________________________
Site Location Lot & Mk No : _____________________________________________________________________________
Street Name : __________________________________________________________ Blk/Unit No :_______________________
LOAD REQUIREMENT (One intake connection point per premises)
New Connection Upgrading the existing service cable Temporary Connection
Change of intake connection point Other Services (Please specify):________________________________________
Type of Premises : Industrial/Commercial/Residential/Others*_________________________Gross Floor Area(m
2
): _____________
Type of Business Activity (for non-residential premise only) : _______________________________ Voltage Sensitive? Yes / No *
Existing Utility A/C No.(if any) : ________________________________
Existing Approved Load (kVA) : ________________________________ at 230V/400V/22kV/66kV/230kV*
Load Requirement (kVA) : ____________________________________ at 230V/400V/22kV/66kV/230kV*
Target date of Energisation :__________/___________/__________ Previous consultation No. (if any) : _________________
Additional information : ______________________________________________________________________________________
______________________________________________________________________________________
LEW DETAILS
I confirm that the above information is correct and agree to advise SP PowerGrid should there be subsequent changes.
Name of Authorised LEW : _____________________________________ Licence Number:_______________________________
Company Forwarding Address :________________________________________________________________________________
___________________________________________________________ Postal Code : Singapore __________________________
Tel : ______________________ Fax : __________________ Mobile Phone : _____________________ Pager : _______________
Email : ___________________________________________________________________________________________________
Signature of Authorised LEW ______________________________________________________ Date ______________________
* Delete where not applicable
52
Appendix 3
Form CS/3
Letter of Consent from the Landlord/Management Corporation
To: SP Services Ltd
111 Somerset Road #06-05
Singapore Power Building
Singapore 238164
ELECTRICITY SUPPLY TO :______________________________________________________________________
(Full Address of the Customer)
FOR :________________________________________________________________________________________
(Name of Customer)
TOTAL LOAD ALLOWED FOR: _______________________________ AT ___________________________ VOLTS
_____________________________________________________________________________________________
PART I
1. I have checked the loading of the electrical installation of the abovementioned building/complex and hereby
confirm that the abovementioned load requirement can be catered for from the rising/horizontal mains
system/main switchboard of the building/complex, and the total approved load to the entire building/complex will
not be exceeded.
2. I have no objection for the abovementioned load to be connected to the rising/horizontal mains system/main
switchboard of the building/complex.
3. The Electrical Installation Licence No. of the building/complex is ______________________.
4. The electrical installation of the building/complex from which this load is to be connected is
Unmetered (i.e. without Master Account)
Metered under Master Account No. ________________________.
5. I will check to ensure that the abovementioned installation is compatible with the electrical installation of the
building/complex.
_____________________________________ Date: ______________
Signature of Licensed Electrical Worker
Licence No: _____/___________ Tel No: __________________
Name: ______________________________________
Address: _____________________________________________________________________S (______________)
_____________________________________________________________________________________________
PART II
I hereby give consent for the abovementioned customer to tap electricity supply of a capacity indicated above from
the rising/horizontal mains system/main switchboard of the building/complex.
___________________________________ Date: ________________
Signature of authorised person
__________________________________________ ________________________
Name Designation
Official Stamp of the
landlord/developer/management corporation
53
Appendix 4
FORM CS/3H
Letter of Consent from Housing & Development Board
To: SP Services Ltd
111 Somerset Road #06-05
Singapore Power Building
Singapore 238164
ELECTRICITY SUPPLY TO :______________________________________________________________________
(Full Address of the Customer)
FOR : ________________________________________________________________________________________
(Name of Customer)
TOTAL LOAD ALLOWED FOR: ________________________________ AT _________________________ VOLTS
_____________________________________________________________________________________________
PART I
1. I have checked the loading of the electrical installation of the above-mentioned building/complex and hereby
confirm that the above-mentioned load requirement can be catered for from the rising/horizontal mains
system/main switchboard of the building/complex, and the total approved load to the entire building/complex will
not be exceeded.
2. I have no objection for the above-mentioned load to be connected to the rising/horizontal mains system/main
switchboard of the building/complex.
3. The Electrical Installation Licence No. of the building/complex is ___________________________.
4. The electrical installation of the building/complex from which this load is to be connected is
Unmetered (i.e. without Master Account)
Metered under Master Account No. _________________________________.
5. I will check to ensure that the above-mentioned installation is compatible with the electrical installation of the
building/complex.
________________________________ Date: _______________________
Signature of LEW
Licence No.: ______________________________________
Name: __________________________________________ Tel No.: _____________________
Address: _____________________________________________________________________________________
_____________________________________________________________________________________________
PART II
I hereby give consent for the above-mentioned customer to tap electricity supply of a capacity indicated above from
the rising/horizontal mains system/main switchboard of the building/complex.
________________________________ Date: _______________________
Signature of Authorised Person
For and on behalf of Housing & Development Board
________________________________ ____________________________
Name Designation
Official Stamp of the
Landlord/Developer/Management Corporation
54
Appendix 5
55
Request to Handover Substation
Date:
To: SP PowerGrid Ltd
111 Somerset Road #08-05
Singapore Power Building
Singapore 238164
Attn: Deputy Director
(Customer Projects East / West / Distribution Projects)
Dear Sir
PROJECT: ELECTRICITY SUPPLY TO ________________________________________________________________________
1. In connection with the electrification scheme (SPSL Appln No: ________________), I wish to advise that the proposed SPPA
substation has been completed in accordance with plans and specifications approved by your Company and the Competent
Authority.
2. I confirm that the structural Professional Engineer in-charge has certified that the substation structure is constructed according
to the approved plan to withstand the load specified by your Company.
3. I also certify that the electrical installation at the substation has been inspected and tested in accordance with the requirements
of your Company as follows:
a Earth value of electrode system is ______________ ohms.
b The continuity of each circuit protective conductor is satisfactory.
c All metal conduits have been bonded to earth.
d Polarity throughout the installation is correct.
e All single pole control devices are in live conductors only.
f The insulation resistance of the fixed wiring installation is ___________ Megaohm.
g All flexible cords, switches, fuses, plugs and socket outlets are in good serviceable condition.
h The installation includes ______________ Nos lighting points and _______________ Nos socket outlets.
4. I shall be obliged if you could send your representative for a joint site inspection on _____________________, and thereafter
to takeover the said substation.
Yours faithfully
_______________________________
Signature of Licensed Electrical Worker
Name: _______________________________________________________________________________________________
Address: _______________________________________________________________________________________________
Tel No: _______________________
NB: This form must be submitted one week prior to the date for joint site inspection, which shall normally take place
from 10 am to 12 noon.
Appendix 6
56
APPLICATION FOR INTERBANK GIRO
Please tick: New Application Change of Bank Account
Date: Name of SP Services Customer
To: Name of Bank: SP Services Account Number (1 account per form)
Branch
(a) I/We hereby instruct you to process SP Services instructions to debit my/our account.
(b) You are entitled to reject SP Services debit instructions if my/our account does not have sufficient funds and charge me/us a fee for this.
You may also at your discretion allow the debit even if this results in an overdraft on the account and impose charges accordingly.
(c) This authorisation will remain in force until termination by written notice sent to my/our address last known to you or upon receipt of
my/our revocation through SP Services.
My/Our Name(s) As in Bank Account:
My/Our Bank Account No: My/Our Contact (Tel/Pager/Handphone) No(s)
Bank Account Holder NRIC No/ P/P No:
To: SP Services Ltd
This application is hereby REJECTED (Please tick) for the following reason(s):
Signature / Thumbprint # differs from Financial institutions records Wrong account number
Signature / Thumbprint# incomplete / unclear# Amendment not countersigned by customer
Account operated by signature / thumbprint# Others:______________________________
___________________________________ ___________________________ _____________________________
Name of Approving Officer Authorised Signature Date
# Please delete where inapplicable
Co. Registration. : 199504470N
PART 1: FOR APPLICANTS COMPLETION
My/Our Signature(s)/Thumbprint(s)/Company Stamp
(as in banks records)
Please remember to sign in this box.
Please impress your thumbprint clearly if
your bank account is operated by
thumbprint.
PART 2: FOR SP SERVICESS COMPLETION
Bank Branch SP Servicess Account Number Utilities Account Number
Bank Branch Account Number To Be Debited
PART 3: FOR BANK/FINANCIAL INSTITUTIONS COMPLETION
Appendix 7
57
Appendix 8
FORM CS/5
APPLICATION FOR INSPECTION OF ELECTRICAL INSTALLATION
For official use
58
To: SP Services Ltd
111Somerset Road #06-05 APPLICATION NO:
Singapore Power Building
Singapore 238164
PART I
I/We,
#Mr/Mrs/Miss/Messrs____________________________________________________________________________________
(# Delete as appropriate). (name of applicant/company)
Utility Account No :
___________________________________________________________________________________________
request you to provide an electrical installation inspection and install kWh meter.
(Please tick if meter is required)
Details of my/our application are as follows:
(Please fill in the appropriate box below)
An application for electricity supply service has been submitted earlier and approved.
SP Services Application Reference No is: _______________________________________
OR
This is a new application with details as given in Part II by my/our Licensed Electrical Worker undertaking the project.
(Form CS/3 or CS/3H shall be attached for supply connection from landlords or HDBs electrical installation.)
My/Our particulars:
NRIC number/Company ROC number: ________________________________
Name of Authorised Person for Company:_________________________________________________________________
(if applicable)
Forwarding Address: _________________________________________________________________________________
________________________________________________________Postal Code: ______________
Tel:___________________ Fax : ___________________ Mobile phone: ___________________ Pager:_____________
Email: ____________________________
--------------------------------------------------- --------------------------------------------
Signature of Applicant Date
___________________________________________________________________________________________________________
PART II (INSTALLATION DETAILS - To be completed by Licensed Electrical Worker if there is no application submitted earlier)
Project Description: ________________________________________________________________________________________
Site Address: ___________________________________________________________________Postal Code: ________________
Type of Application (Please tick the appropriate boxes)
New Supply Temporary Supply Upgrading of Supply Downgrading of Supply
Extension Rewiring Replacement of switchboard/switchgear
Amalgamation Shifting of Meter
Conversion to Master/Sub Metering Scheme
Other Services (Please specify)
Appendix 8
Landlords installation HDBs installation Public Lighting Network
Supply SP PowerAssets (Form CS/3 is to be (HDB's endorsement (Form CS/3 PL is to be
Connection from: installation/mains submitted) is required) submitted)
Type of Development: Industrial Commercial Residential Others
Metering Scheme: *Master / Sub / Normal *(Delete as appropriate)
Type of Business (Brief Description): ___________________________________________________________________
Total supply capacity (including existing requirement,
if any)
30/40A# 230V 60A/80A/100A# 230V 30A/60A# 400V .............kVA
single-phase single-phase three-phase at 400V three-phase
(# Delete as appropriate)
PART III DETAILS OF PROPOSED INSTALLATION OR EXTENSION. For HDB residential unit, erasure/amendment to any of
the QTY figure below is NOT acceptable.)
QTY
QTY QTY QTY
5A socket outlets 20A SPN ISO Cooker Point Oven Point
13A socket outlets 20A TPN ISO Connection Unit Shaver Unit
15A socket outlets 30/32A SPN ISO Fan Point Urinal Sensor Point
10A SPN/DP ISO 30/32A TPN ISO Hair Dryer Point Washing Machine
10A TPN ISO 60A SPN/DP ISO Hand Dryer Point Water Heater Points
15/16A SPN ISO 60A TPN ISO Lamp points Other Equipment
15/16A TPN ISO Cooker hob point Neon Sign
( A completed Certificate of Compliance is required to be submitted if a new meter is required.)
Name of LEW : _____________________ LEW Licence No. : _____________
__________________________________
Signature of Licensed Electrical Worker Date : ______________________
Forwarding address (as registered with EMA): __________________________________ Fax No.: ____________________
_______________________________________________________________________ Contact No.: ___________________
Postal Code: ________________
__________________________________________________________________________________________________
PART IV Endorsement by HDB (applicable for HDB residentiaI premises)
1 I have checked the loading of the electrical installation of the abovementioned building/complex and hereby confirm that
the abovementioned load requirement can be catered for from the rising/horizontal mains system/main switchboard of the
building/complex, and the total approved load to the entire building/complex will not be exceeded.
2 I hereby give consent for the abovementioned customer to tap electricity supply of a capacity indicated above from the
rising/horizontal mains system/main switchboard of the building/complex.
_______________________________________
Name/designation/signature of authorised person Date: ___________________
for and on behalf of Housing & Development Board
59
Appendix 9
60
Types and Layout of Substation
The type of substation required will depend on the customer's load requirement. SPSL shall endeavour to provide the
requirement of the substation within 10 business days following the receipt of application form.
Typical layout plans and details for substations of the independent building type are given in Appendices 11 to 14.
As a guide, the types of substations applicable for the various load requirements are as follows: -
Load Requirement Primary
Distribution
Voltage
Type of
rooms
Drawings Applicable/Substation size
6.6kV Appendices 11 Up to 1,000 kVA at 400/230V
22kV Switchroom
Transformer
7.6M x 6.2M x 5.6M
4.0M x 4.5M x 3.6M
Up to 2,000 kVA at 400/230V 22kV Appendices 12
Up to 4,250 kW at 22kV 22kV Switchroom 6.9M x 6.2M x 5.6M
The functional requirements of the substation structure, however, must be complied with. For example, the minimum
clear height of the cable chamber and switchroom must be 1.5m and 3.1m respectively even if the substation is
integrated into a multi-storey building.
Subject to the layout and access being suitable, the customer may incorporate the substation as part of his main
building. The typical layout plans shown in this handbook depict only the functional requirements.
Appendix 10
61
Submission of Substation Site and Design Plans
Before construction of the substation, the LEW shall submit to SPPG, 2 sets of plans showing the location of the
proposed substation in relation to the rest of the development and detailed layout plans for the substation. One set of
plan will be endorsed and returned to the LEW.
All plans/drawings to be submitted must be on appropriate A1 or A2 size paper and endorsed by the LEW responsible
for the planning, design and supervision of the installation. To facilitate processing, SPSL's Application Reference
Number must be indicated in all submissions which shall be accompanied by a Checklist for Submission of
Substation Plans (Appendix 15).
In the case of re-submission of plans, all amendments (addition/deletion/revision) made must be highlighted in the
new set of drawings and listed out in covering letters.
All plans are to be drawn to scale and dimensions used shall be in metric units.
Substation Site Plans
These plans should show the location of the proposed substation(s) in relation to the surrounding area and should
include the following:
(i) The proposed substation(s)
(ii) The customer's switchroom(s)
(iii) The proposed SPPA's incoming cable and customer's service cable routes
(iv) The orientation of other buildings within the development site
(v) The proposed driveway to the substation entrance (to be shaded in red)
(vi) The existing and proposed drains; and
(vii) North-East Gridlines or 2 NE survey coordinates.
Substation Design/Layout Plans
It is mandatory that the drawings must include
1 The detailed requirements for the design of the substation are listed in Appendix 16. Unless explicit
waiver is granted, these requirements are to be incorporated in the architectural plans.
2 Plan, Front, Rear and Side Elevations of the substation and at least 2 cross-sections showing the
surrounding roads, cable chamber, switchroom beams and clear height, switchroom floor openings,
transformer plinths and other pertinent details.
3 Details of immediately adjoining upper floor, basement as well as adjacent space all around the
substation shall be depicted, if the substation is part of a larger building
It is the responsibility of the LEW in charge to ensure that all the requirements as endorsed on the drawings are
incorporated in the architectural and structural plans before construction work of the substation begins.
Appendix 11
6.6kV/LT
6.6KV/LT SUBSTATION
62
Appendix 11
63
6.6KV/LT SUBSTATION
Appendix 11
64
6.6KV/LT SUBSTATION
Appendix 11
6.6KV/LT SUBSTATION
65
Appendix 12
22kV/LT
22KV/LT SUBSTATION
66
Appendix 12
67
22KV/LT SUBSTATION
Appendix 12
22KV/LT SUBSTATION
68
Appendix 12
22KV/LT SUBSTATION
69
Appendix 12
22KV/LT SUBSTATION
70
Appendix 13
71
HEAVY ALUMINIUM LOUVRED DOOR
FOR ELECTRIC SUBSTATION
Appendix 13
72
HEAVY ALUMINIUM LOUVRED DOOR
FOR ELECTRIC SUBSTATION
Appendix 13
73
HEAVY ALUMINIUM NON-LOUVRED DOOR
FOR ELECTRIC SUBSTATION
CABLE CHAMBER EMERGENCY EXIT
ELEVATION
PLAN OF ALUMINIUM DOOR FOR
Appendix 13
74
HEAVY ALUMINIUM NON-LOUVRED DOOR
FOR ELECTRIC SUBSTATION
(2100 X 900 PANIC DOOR)
ELEVATION
PLAN OF ALUMINIUM DOOR FOR EMERGENCY EXIT
Appendix 13
75
HEAVY ALUMINIUM DOOR
FOR ELECTRIC SUBSTATION
Appendix 13
76
HEAVY ALUMINIUM DOOR
FOR ELECTRIC SUBSTATION
Appendix 14
77
GATE DETAILS
Appendix 14
78
GATE DETAILS
Appendix 15
79
SPPG
CHECKLIST FOR SUBSTATION BUILDING PLAN SUBMISSION
Proposal:
Name of Licensed Electrical Worker:
BP No (if any) :
Yes Not
Applicable
1) Drawings are in A1 or A2 series.
2) Plan, front, rear and side elevations are included.
3) Cross-sections in relation to roads and immediate surroundings are included.
4) Detailed layout scales of 1:50 for all plans and 1:100 for all sections and elevations.
5) Substation requirements stated in Handbook on How to Apply for Electricity Connection
including latest updating are complied with.
6) Plans are signed by the Licensed Electrical Worker.
7) Proper vehicular access to the substation from main road is coloured.
8) I have advised the structural PE that substation structure is to be designed to
withstand the loading specified in the Handbook and all structural requirements
have been reflected in this submission.
9) All trenches/floor openings are not affected by any beam.
10) Required clear height (from underside of any beam) of all equipment rooms
and cable chamber are complied with.
11) No column within substation
12) No wet area above substation
13) Location of Customer's Switchroom shown with proposed service cable route shown
14) I undertake to advise the architect and structural PE to ensure that all the requirements,
as endorsed, are incorporated into the architectural and structural plans prior to
substation construction
15) Previous drawings with SPPG's comments are attached (for resubmission case)
16) All additions/deletions/amendments are coloured
17) Any encumbrances?
.
Signature & Stamp of Licensed Electrical Worker License No Date
Note: Please tick in appropriate box for all items.
This checklist is to be submitted for every submission/re-submission.
Appendix 16
80
SPPG
SUBSTATION LAYOUT REQUIREMENTS TO BE
INCORPORATED IN THE ARCHITECTURAL PLANS
Item Requirement
Cable Entry Ducts Heavy duty 150mm dia. UPVC pipes in concrete jacket to be provided and terminated 300mm
after the roadside drain.
To be sealed with removable water-tight plugs at both ends of pipes.
To have piling, if necessary.
Cable Entry Ramp Cross Sectional views to be shown.
150mm wide removable hot-dipped galvanised mild steel gratings to be provided.
Walls and floors to be plastered and rendered waterproof.
Cable Trenches Sand filling to be carried out after cable installation.
Depth of 900mm (no beams shall be allowed within/across the trenches).
Openings to be covered by removable hot-dipped galvanised mild steel.
Switchgear Floor Grating of 300mm width which is able to support at least 100 kg.
To take a load of 1,600 kg per sq m. Floor beam is to be 200mm away from the HT floor
opening. All floor openings to be free of beam.
Switchroom Louvred heavy duty aluminium door to Appendix 13.
Size: 2.9M X 1.8M wide nett for 22KV switchroom 2.7M X 1.8M wide nett for 6.6KV switchroom,
Floor to have a 50mm thick cement rendering including a 20mm granolithic smooth finish of
cement, granite chips and sand in the ratio of 1:1:1 plus 9kg ironite or equivalent approved
hardener to each 45 kg of cement. For 22kV substations, final rendering of SPPA switchroom
floor to be done after installation of switchgear floor frame.
Height: No part from floor to ceiling beams to be less than 3.1M. No column allowed within the
switchroom.
Hot-dipped galvanised mild steel/stainless steel railing to be provided for stairs and loading
platform. (Removable type in front of door.)
Hasp and staple (140mm x 65mm x 6mm) and door hinges to be of brass or stainless steel.
Adequate natural lighting required. Provision of glass block in small modules.
Ventilation panels to be installed at high level
Transformer Room Noise level of 60 dB emitted from each transformer to be considered in the choice of
location of transformer yard.
Adequate natural cross air ventilation required. Provision of PC vent block or Aluminium
ventilation panels.
Each transformer plinth to be able to take a dead load of 6 tonnes.
Door: 2.7M x 2.7M nett for each transformer. Heavy duty aluminium louvered doors to
Appendix 13.
LT trench of 800mm min. width for every 2 transformers. Separate LT trench to be provided for
additional transformers.
Hasp and staple (140mm x 65mm x 6mm) and door hinges to be of brass or stainless steel.
Wall/Column finishes All concrete surfaces shall be properly prepared and 20mm cement plastering work carried out
such that there should be no cracks, blisters and other defects.
The emulsion painting system used for external walls shall be suitable for outdoor application.
There shall be a five (5) years warranty of the textured coating on all walls against all defects
arising from colourfastness, faulty workmanship and/or materials, etc.
Appendix 16
81
Item Requirement
Electrical Installation Schematic layout to be shown.
All wiring to be in surface conduits.
Circuits to be controlled by miniature circuit breakers and ELCB.
Isolators for battery chargers to tap supply by-passing ELCB.
Substation to be adequately lit. Light fittings are to be installed at 3M (suspension in type)
and 2.4M (wall-mounting type) from floor level.
Wire-mesh casing to be provided for light fittings installed in cable chamber.
To label circuits at DB (distribution board) corresponding to the respective switches, sockets
and isolators, etc.
Cable Chamber Trap door floor openings 760mm x 760mm leading to cable chamber to have
Basement (where (a) hinged aluminium chequered covers complete with wall catch.
required) (b) cat ladders with 6 non-skip steps. Details as shown on drawings.
Adequate natural ventilation required e.g. PC vent block/Aluminium vent panels.
- Height: 2.0m with no part less than 1.5m.
- To paint the front and back of all beam with 50mmH red luminous paint.
- Chamber floor to be suspended type capable of supporting 400 kg/m
2
(min).
Floor level: 150mm above the immediate external final road or driveway level and above
highest flood level recorded. Wall and floor to be waterproofed and adequate drainage to be
provided, where necessary.
Doors to be fitted with panic hardware and paint in red Push lever down to open on internal
side of door.
Metering Kiosks To be provided for SPPA (see Appendices 31 to 33) when customer is taking HT supply.
Woodwork, MetalWork, etc To be suitably painted and anti-termite treated for all woodwork.
Ceiling To be of smooth finishes and emulsion painted. All beam to be encased in RC concrete.
Roof To be of flat RC suitably waterproofed and laid to falls of 1:80 minimum.
Roof eaves with multiple 150mm wide long slot openings to be incorporated for rain water to
free-fall direct into apron drain.
Drainage Proper drainage around the substation to be provided with hinged hot-dipped
galvanised m.s. gratings.
Gate/Perimeter To be 1.8m high and designed to blend aesthetically with the overall development.
Fencing(where required) Hollow section anodised aluminium gates to Appendix 14.
A 600mm wide concrete apron to surround the fence externally.
Access Road To withstand heavy vehicles with laden load of 10 tonnes for all 22kV & 6.6KV substations.
Width of driveway to be 4000mm (min) and surface to be properly paved.
No car parking lots are to be drawn in such a way as to obstruct vehicular access to
substation.
NOTE: (a) Appointed project LEW is to liaise closely with Architect and Structural Engineer to obtain all their
respective requirements for incorporation into final layout plans submitted for SPPGs endorsement.
(b) All dimensions and figures are to be checked by the Architect/structural engineer/appointed project LEW prior to
substation construction.
(c) If the Management Committee (MC) were to subsequently replace the security personnel with other means e.g.
electronic security systems, etc; SPPG shall be consulted on the free access arrangement to the substation.
(d) LEW/M&E consultants are to ensure that the proposed substation is constructed to SPPG approved plans.
Appendix 17
82
GENERAL REQUIREMENT FOR EHT SUBSTATION
(66KV and 230KV ONLY)
1. Where an application for supply of electricity necessitates the provision of a substation, the site shall be provided and
substation constructed by the applicant consumer at his own cost. The Guidelines/Requirements for EHT Substation
Buildings will be made available in SPPGs service connection proposal to the applicant.
2. The applicant shall grant SPPG, its officers and agents an irrevocable licence at all times to have full and unrestricted
use of the substation and have free access thereto.
3. SPPA may utilize the substation and site in such manner as it deems fit. Subject to the applicants requirement being
fully provided for, SPPA shall be at liberty to use the substation for the purpose of supplying other customers or for the
improvement of the transmission network (e.g. upgrading, modification to substation structure, alteration and addition
works, etc.)
4. The substation site within the substation perimeter fence shall be intended solely for the substation development.
5. The substation structure may be an independent building or form part of a larger building. It shall be located at the 1
st
storey level and must be readily accessible from the public road. Proper vehicular access to the substation shall be
provided for transportation of substation equipment by normal means, i.e. truck and trailer. The gradient of the access
road to the EHT substation site (66kV and above) shall not be more than 1:20.
6. There shall be no danger from flooding and fire hazards.
7. The substation site shall be free from all encumbrances (existing and future proposed services).
8. Suitable and proper cable access shall be provided on at least two sides of the substation site for all cables entering
and leaving the proposed site. If there is any roadside drain fronting/surrounding the substation site, the applicant shall
be required to install cable ducts under-crossing the drain. If the depth of the drain is more than 2.0 meters from the
proposed substation ground level, the cable ducts shall be installed to over-cross the drains with approval from the
relevant authorities.
10. The applicant consumer shall consider the effect of noise disturbance to neighbouring development in its selection of
the substation site.
11. The site of the substation shall be approved by SPPG and the relevant authorities. The applicant shall ensure that all
necessary approval for the substation site be obtained from the relevant authorities.
12. The applicant shall consult SPPG on the substation site before commencement of detail design for the substation
building.
The applicant shall submit the necessary architectural and M&E design drawings, incorporating the necessary
requirements in the above-mentioned guidelines/requirements, for SPPGs review and clearances. The applicant shall
also obtain the necessary clearances from the relevant authorities.
Appendix 18
83
PROTECTION REQUIREMENTS FOR CUSTOMERS
22KV MAIN INCOMING SWITCHGEAR
INCOMING SUPPLY FROM
SPPA SUB-STATION
CUSTOMERS 22kV MAIN INCOMING SWITCHBOARD
O/C - Overcurrent relay type IDMTL with 3/10 characteristics.
Plug Setting =100%, Time Multiplier=0.1.
E/F - Earth fault relay type IDMTL with 3/10 characteristics.
Plug Setting =20%, Time Multiplier=0.1.
PW - Pilot wire protection relay Solkor R/ RF, HOR 4, MHOR.
A - Ammeter
CB - Circuit breaker
To circuit breaker trip circuit
500/5
CLASS 5P20 15VA
OR BETTER
M
REVENUE METERS
A
O
C
O
C
E/F
PW
CB
PILOT WIRES TO
SPPAS SWITCHGEAR
500/5
CLASS X
R B Y
METERING CTs/PTs
TO SPPGS
REQUIREMENTS
O
C
CABLE TERMINATIONS
Notes:
1. Pilot wire protection CTs shall comply with the following requirements:
a. Rated knee point voltage at maximum secondary turns not less than 80V.
b. Exciting current at the rated knee point voltage not more than 150mA.
c. Resistance of the secondary winding, corrected to 75
o
C not more than 0.15 ohm.
2. No other auxiliary device shall be connected to the pilot wire protection CTs. Pilot wire protection CT star-point shall
be towards protected line.
3. Where there is more than one incoming service, a bus-section breaker shall be provided and be electrically and
mechanically interlocked against parallel operation of the incoming services.
4. All 22kV circuits in the customer installation shall be equipped with unit-protection for fast fault clearance, inclusive
of fault at cable terminations.
Appendix 18
84
PROTECTION REQUIREMENTS FOR CUSTOMERS
LT MAIN INCOMING SWITCHGEAR
N
O
C
O
C
O
C
KWH
REVENUE METER
METERING CTs
E/F
Y
CB
X
B R
INCOMING SUPPLY
CLASS 5P10 15VA
OR BETTER
CUSTOMERS LT INCOMING SWITCHBOARD
O/C - Overcurrent relay type IDMTL with 3/10 characteristics or DTL relay. For DTL relay, the setting shall be 100%
of approved load with a time lag of not more than 0.5 sec. For IDMTL relay, the plug setting shall be 100% of
approved load with a time multiplier of 0.1 (or 0.2 for approved load more than 1.5kA and up to 2.2kA and with
source from SPPAs 22kV substation).
E/F - Earth fault relay operating at primary fault current of 20% of approved load subject to a maximum of 120 Amp
with time lag of not more than 0.5 second.
Note: LEW is reminded that under CP5, the overall ohmic resistance of earthing system should not exceed one
ohm. The maximum earth fault current setting shall be equal to 50V divided by the earth resistance value.
CT - Current transformer Class 5P10, 15VA or better.
CB - Circuit breaker with adequate breaking capacity and circuit breaker using shunt trip shall be provided with
series trip (Direct acting trip) device that operates with no time delay under short-circuit condition, or with HRC
fuses in series.
To circuit breaker trip circuit.
Note:
Where there is more than one incoming service, a 4-pole bus-section breaker shall be provided and be mechanically
interlocked against parallel operation of the incoming services.
Appendix 18
85
TYPE 1: CUSTOMER 66KV FEEDER CONNECTION
(WITHOUT EMBEDDED GENERATION PLANT)
Type 1a : Supply from SPPA 66kV Source Station
Numerical Relay System (OFC) (see note iii)
Feeder Main 1 Current Differential 1
Feeder Main 2 Current Differential 2
Inter-tripping Current Differential 1
Remote End Interlock (on ES & DS) Mechanical
Electromechanical Relay System
(Metallic pilot wire) (see note iii)
Feeder Main 1 Solkor - R
f
Feeder Main 2 Translay S
Inter-tripping Solkor-R
f
Remote End Interlock (on ES & DS) Mechanical
Type 1b : Supply from SPPA 66kV
Non-Source Station
Numerical Relay System (OFC) (see note iii)
Feeder Main 1 Current Differential
Inter-tripping Current Differential
Remote End Interlock (on ES & DS) Mechanical
Electromechanical Relay System
(Metallic pilot wire) (see note iii)
Feeder Main 1 Solkor - R
f
Inter-tripping Solkor-R
f
Remote End Interlock (on ES & DS) Mechanical
SPPA
66kV S/S
Feeder Main 1
(plus Main 2 if
Source S/S)
87L
Interface
points
SPPAs
Scope
Customers
Scope
Pilot/OFC
Marshalling
Box
87L
Notes:
Customer
66kV S/S
i) All electromechanical feeder protection relays are to be
equipped with supervision and guard relays.
ii) Engineering and Protection details including
interlocking and intertripping shall be discussed on
application.
iii) For reason of obsolescence or availability, the type of
Relays, signalling equipment and protection schemes
shall subject to review and confirmation during the
consultation period.
iv) Intertrip and interlock schemes, where applicable, shall
be implemented via the numerical current differential
system or the dedicated signalling equipment if
supplied.
v) Customer to supply and install pilot marshalling board
of approved design to accommodate the optic fibre
cables and other auxiliary cables.
vi) Customer shall be responsible for all termination works
at their equipment.
Appendix 18
86
TYPE 2: CUSTOMER 66KV FEEDER CONNECTION
(WITH EMBEDDED GENERATION PLANT)
Feeder Main 1
(plus Main 2 if
Source S/S)
Customer
66kV S/S
SPPA
66kV S/S
Customers
Scope
SPPAs
Scope
Interface
points
87L
87L
Pilot/OFC
Marshalling
Box
Signalling
equipment
For inter-tripping
and remote
electrical interlock
Signalling
equipment
Type 2a : Supply from SPPA 66kV Source Station
Numerical Relay System (OFC) (see note iii)
Feeder Main 1 Current Differential 1
Feeder Main 2 Current Differential 2
Inter-tripping Signalling equipment
Remote End Interlock
(on ES, DS & CB)
Mechanical & Electrical
(via signalling equipment)
Switching sequencing Signalling equipment
Electromechanical Relay System
(Metallic pilot wire) (see note iii)
Feeder Main 1 Solkor - R
f
Feeder Main 2 Translay S
Inter-tripping Signalling equipment
Remote End Interlock
(on ES, DS & CB)
Mechanical & Electrical
(via signalling equipment)
Switching sequencing Signalling equipment
Type 2b : Supply from SPPA 66kV
Non-Source Station
Numerical Relay System (OFC) (see note iii)
Feeder Main 1 Current Differential
Inter-tripping Signalling equipment
Remote End Interlock
(on ES, DS & CB)
Mechanical & Electrical
(via signalling equipment)
Switching sequencing Signalling equipment
Electromechanical Relay System
(Metallic pilot wire) (see note iii)
Feeder Main 1 Solkor - R
f
Inter-tripping Signalling equipment
Remote End Interlock
(on ES, DS & CB)
Mechanical & Electrical
(via signalling equipment)
Switching sequencing Signalling equipment
Notes:
v) Customer shall be responsible for all
termination works at their equipment.
i) All electromechanical feeder protection relays are to be
equipped with supervision and guard relays.
ii) Engineering and Protection details including interlocking
and intertripping shall be discussed on application.
iii) For reason of obsolescence or availability, the type of
Relays, signalling equipment and protection schemes shall
subject to review and confirmation during the
consultation period.
iv) Customer to supply and install pilot marshalling board of
approved design to accommodate the optic fibre cables
and other auxiliary cables.
Appendix 18
87
TYPE 3: CUSTOMER 66KV FEEDER
TRANSFORMER CONNECTION
Type 3a : Supply from SPPA 66kV Source Station
Numerical Relay System (OFC) (see note iii)
Feeder Main 1 Current Differential 1
Feeder Main 2 Current Differential 2
Inter-tripping Current Differential 1
Remote End Interlock
(on ES & DS & neutral)
Mechanical
Electromechanical Relay System
(Metallic pilot wire) (see note iii)
Feeder Main 1 Solkor - R
f
Feeder Main 2 Translay S
Inter-tripping Signalling equipment
Remote End Interlock
(on ES & DS & neutral)
Mechanical
Type 3b : Supply from SPPA 66kV
Non-Source Station
Numerical Relay System (OFC) (see note iii)
Feeder Main 1 Current Differential
Inter-tripping Current Differential
Remote End Interlock
(on ES & DS & neutral)
Mechanical
Electromechanical Relay System
(Metallic pilot wire) (see note iii)
Feeder Main 1 Solkor - R
f
Inter-tripping Signalling equipment
Remote End Interlock
(on ES & DS & neutral)
Mechanical
Include REF,
TF Diff, OC/EF
& other local
protection
system
Customer
22kV S/S
Customers
Scope
SPPAs
Scope
87L
Feeder Main 1
(plus Main 2 if
Source S/S)
87L
Pilot/OFC
Marshalling
Box
Interface
points
87T
SPPA
66kV S/S
Notes:
i) All electromechanical feeder protection relays are to be
equipped with supervision and guard relays.
ii) Engineering and Protection details including
interlocking and intertripping shall be discussed on
application.
iii) For reason of obsolescence or availability, the type of
Relays, signalling equipment and protection schemes
shall subject to review and confirmation during the
consultation period.
iv) Intertrip and interlock schemes, where applicable, shall
be implemented via the numerical current differential
system or the dedicated signalling equipment if
supplied.
vi) Customer shall be responsible for all termination
works at their equipment.
v) Customer to supply and install pilot marshalling board
of approved design to accommodate the optic fibre
cables and other auxiliary cables.
Appendix 18
88
TYPE 4: CUSTOMER 230KV
FEEDER CONNECTION
Supply from SPPA 230kV Source Station
Numerical Relay System (OFC) (see note ii)
Feeder Main 1 : Current Differential
Feeder Main 2 : Current Differential with
Distance Protection
Teleprotection Signalling equipment
Inter-tripping Signalling equipment
Remote End Interlock
(on ES, DS & CB):
Mechanical & Electrical
(via signalling equipment)
Switching sequencing: via signalling equipment
Notes:
Customer
230kV S/S
SPPA
230kV S/S
Customers
Scope
SPPAs
Scope
Interface
points
87L
87L
Pilot/OFC
Marshalling
Box
Main 1 and
Main 2
Signalling
equipment
For teleprotection
inter-tripping and
remote electrical
interlock
Signalling
equipment
i) Engineering and Protection details including interlocking
and intertripping shall be discussed on application.
ii) For reason of obsolescence or availability, the type of
relays, signalling equipment and protection schemes shall
subject to review and confirmation during the consultation
period.
iii) Customer to supply and install pilot marshalling board of
approved design to accommodate the optic fibre cables
and other auxiliary cables.
iv) Customer shall be responsible for all termination works
at their equipment.
Appendix 18
89
TYPE 5: CUSTOMER 230KV
FEEDER TRANSFORMER CONNECTION
Supply from SPPA 230kV Source Station
Numerical Relay System (OFC) (see note ii)
Feeder Main 1 Current Differential
Feeder Main 2 Current Differential with
Distance Protection
Teleprotection signalling equipment
Inter-tripping signalling equipment
Remote End Interlock
(on ES, DS & CB)
Mechanical & Electrical
(via signalling equipment)
Switching sequencing signalling equipment
Notes:
i) Engineering and Protection details including interlocking
and intertripping shall be discussed on application.
ii) For reason of obsolescence or availability, the type of
relays, signalling equipment and protection schemes
shall subject to review and confirmation during the
consultation period.
iii) Customer to supply and install pilot marshalling board of
approved design to accommodate the optic fibre cables and
other auxiliary cables.
iv) Customer shall be responsible for all termination works at
their equipment.
Customers
Scope
Include T/F
Diff, REF,
OC/EF &
other local
protection
system
SPPAs
Scope
87L
87L
Customer
230kV S/S
Pilot/OFC
Marshalling
Box
Interface
points
Main 1 and
Main 2
87T
Signalling
equipment
For teleprotection
inter-tripping and
remote electrical
interlock
Signalling
equipment
SPPA
230kV S/S
APPLICATION FOR DE-ENERGISATION / RE-ENERGISATION (ADRE)
Licensed
Installation No
Service No Voltage
Name of Installation:
Address of Installation:
Requested De-energisation Requested Re-energisation
Date Time *am/pm Date Time *am/pm
Contestable Customer:
*Yes / No
#Name of Customer: #MSS A/C No: #Name of Retailer:
To: *Deputy Director (EHV Network)
*Deputy Director (Regional Network *West / Central / East / North / South)
*Deputy Director (Customer Projects *East / West)
*Deputy Director (Distribution Projects)
(1) I, the undersigned LEW for the above installation, wish to apply for a *de-energisation / re
energisation at the time stated above. My work, after the de-energisation, will involve the
following:
*1 Routine Servicing
2 (Please Specify)
(2) * I / or ________________________________________ (Name / Licence No of appointee
approved by Regulation Division of EMA) will attend to the *de-energisation / re-energisation
PERSONALLY.
(3) I understand that: -
(a) No work is to be carried out on the service cable until both SP PowerGrid officer and
myself have signed the SDRE (Statement for De-energisation and Re-energisation) after
we have safely isolated the service cable at both ends.
(b) I am required to be on time on the approved date of de-energisation or re-energisation,
failing which the SP PowerGrid officer may cancel any appointment made.
Signature: ______________________________ Telephone / HP No.: __________________
Name: _________________________________
Date: _______________ Licence No: _________________ * Grade: Engineer
Technician
Electrician
Notes: (a) All requested date and time are subject to SP PowerGrids approval.
(b) For non-contestable customers, this form should reach SP PowerGrid 7 business days before the
requested date.
(c) For contestable customers, this form should reach SP PowerGrid 14 business days before the
requested date.
(d) For urgent work on Sundays / Public Holidays and after office hours, LEW is required to co-
ordinate with SP PowerGrid personally.
(e) * Delete whichever not applicable.
(f) #To be filled in for contestable customer.
Section Fax No Tel No
EHVN 62909124 62909121
RNW 66609390 66609301
RNC 62799590 62799501
RNE 62409203 62409218
RNN 67653745 63146172
RNS 62909110 62909101
CPE 62409225 62409257
CPW 62799532 62799559
DP 62909140 62909139
Appendix 19
90
SP POWERGRID LTD A No. 00001
Appendix 20
STATEMENT FOR DE-ENERGISATION AND RE.ENERGISATION (SDRE)
Part I & II concern the de-energisation and re-energisation of the service cable specified below. Each statement is valid only
when it is signed by both the LEW of the installation and the SP POWERGRID officer-in-charge of the de-energisation or re-
energisation.
Name Of Installation: __________________________________________________________________________________
Service Cable No.: *1 / 2 / 3 / 4
Isolated From (Substation Name, OG Box Etc): _____________________________________________________________
This de-energisation is *due to tripping/requested by SP PowerGrid / requested by LEW.
* - please delete whichever is not applicable
___________________________________________________________________________________________________
PART I: DE-ENERGISATION STATEMENT (TO BE SIGNED AFTER DE-ENERGISATION)
(This statement is required only when work is to be done on the service cable by either the LEW or the SP PowerGrid
officer, or both)
Date: ________________________________ Time: ____________________________
DECLARATION BY LEW: I, the undersigned LEW, hereby declare that the above service feeder has been turned off and
safely isolated from the customers intake switchboard.
Signature: ___________________ Name: _____________________ Licence No.: __________________________
DECLARATION BY SP POWERGRID OFFICER I, the undersigned SP POWERGRID officer, hereby declare that the
above service cable has been de-energised and safely isolated from the SP PowerAssets network.
Signature: ___________________ Name: _____________________ Section: _____________________________
As agent for and behalf of SP PowerAssets Ltd
___________________________________________________________________________________________________
PART II: RE-ENERGISATION STATEMENT (TO BE SIGNED BEFORE RE-ENERGISATION)
DATE: ____________________________________ TIME: _____________________________
DECLARATION BY LEW: I, the undersigned LEW, hereby declare that the consumer's switchgear, to which the above
mentioned service feeder is connected, is cleared of all earthing leads, labour and tools, and that the switchgear is fit for re-
energisation from SP POWERASSETS end with effect from the time specified above. I undertake to ensure that no work by
any person will be carried out on the service feeder at the consumer's end until a new shutdown statement is signed by both
parties.
Signature: ___________________ Name: _______________________ Licence No: ______________________________
ACKNOWLEDGEMENT BY SP POWERGRID OFFICER:
Signature: ___________________ Name: _______________________ Section: _________________________________
As agent for and behalf of SP PowerAssets Ltd
___________________________________________________________________________________________________
PART III: DECLARATION BY LEW ON THE TIME OF TURN-OFF AND TURN-ON OF INCOMING
SUPPLY AT CUSTOMERSS INTAKE SWITCHBOARD (for Contestable Customer only)
To: SP SERVICES LTD (Fax no: 63092509, Tel no: 63092543)
Name of Customer: ___________________________________________ MSS A/C No: _______________________
Address of Installation: ________________________________________________________________________________
DECLARATION BY LEW: I, the undersigned LEW, hereby declare that I had turned-off and turned-on the incoming supply at
customers intake switchboard at the following date / time:
Date of Turn-Off: ___________________________ Time of Turn-Off: __________________________________
Date of Turn-On: ___________________________ Time of Turn-On: __________________________________
Signature: ____________________ Name: _________________________ Licence No. ______________________
91
Appendix 21
92
CERTIFICATE OF READINESS
FOR THE ENERGIZATION OF SERVICE CONNECTION
Name of Customer Installation:
Address:
Customer Installation Licence No/Expiry Date:
Connection Voltage:
Approved Load:
Name of Connection Cable(s):
Owned by Connection Applicant (Yes / No)
MSS Account No:
Name of Retailer:
Certification By LEW
I, ______________________(name) the undersigned LEW, hereby certify that the service connection*, the equipment
and works at the above installation (Licence No: ______________) is now ready and fit for energisation with effect
from the date and time specified below.
Date:
Time:
I certify that:
a. protection details are as follows:
CT Ratio: /1A or 5A*
Short-Time Withstand Current Ratings of Main Supply incoming Switchgear kA for 1 sec or 3 sec
Main 1 Type:
Main 2 Type*: Direct Acting Tripping Setting :___________
O/C Type: Setting:
E/F Type: Setting:
b. the switching equipment/transformer/service connection* and all associated apparatus related to the service
connection have been tested and checked by me and they have passed the pre-commissioning checks and
tests in compliance with the Market Rules, Transmission Code, Handbook on How to Apply for Electricity
Connection, Connection Agreement, all other applicable standards, and the associated protection systems
have all been proven effective
c. The main protection schemes for the service connection have been commissioned by load simulation method
on date: _______________**.
d. *for multi-metered installation with the exception of HDB residential installation, the metering scheme has
been designed as master/sub-metering scheme.
* Delete where applicable
** To indicate NA where protection scheme is not applicable
Appendix 21
93
e. all necessary meters have been installed.
f. the safety coordination requirements of the Transmission Code have been fully complied with.
g. all workmen have been withdrawn and warned that it is no longer safe to continue to work on the equipment
without a Permit-to-work (PTW), and that all tools, scaffolding, ladders, construction materials including any
temporary local earthing connections have been removed from the equipment, and all protective screens or
guards, if any, have been securely fixed and the appropriate warning signs displayed and that all keys, if any,
necessary for the isolation and operation of the equipment have been handed to me.
h. all circuit earth on equipment to be energized are removed.
i. equipment to be energized in this request (the diagram must clearly indicate the portion of the
equipment to be energized. If space is insufficient, please provide diagram as attachment) is shown below:
Name & Signature of LEW requesting for
energisation of supply line
Licence No. Date
Appendix 22.1
FORM CS/6
REQUEST FROM CONTESTABLE CUSTOMER FOR INSTALLATION OF ELECTRICITY KWH METER
For Official Use
Serial No. : ________________________ CMS Installation no. : _____________________
PART I : Customer Details To be completed by LEW
To Meter Section, SP PowerGrid Ltd through SP Services Ltd
Name of Customer(Mr/Mdm) /Company(Messrs): __________________________________________
NRIC/Company ROC: ____________ Telephone No. : ____________ Pager/Handphone No. : _________
Existing MSS Account no (if any) : ___________________ Master Account No.(if any) : ______________
Application no.: ____________________ Type Of Business: ___________________________
Site Address as given by IRAS :___________________________________________________________
(You are required to enclose a copy of the IRAS letter.)
Telephone No(s)/point(s) : _______________________________________________________________
(For contestable customer, you are required to install telephone point(s) adjacent to the meter panel and provide the telephone no. before applying for
the installation of the meters)
Supply Capacity :___________KVA/KW at ___________ Volts
[Form CS/3 or CS/3H(if supply is from landlord) and COC shall be submitted together with this form]
Metering Scheme: ________________ Turn on date : ______________________
Source of supply : SP PowerAssets Landlord
Type of connection : New Connection Upgrading Downgrading
I hereby confirm that the electrical wirings at the meter installation have been checked and certified correct.
Name of LEW : ___________________ LEW License no. : ______________
Telephone no. : _____________ Handphone no. : _____________ Facsimile no. : ____________
Signature : __________________________________ Date : _______________________
*Note: For new supply, customer may apply for contestability status & MSS account no. after meters have been installed. LEW shall apply for license
under this MSS account no. to operate electrical installation before proceeding to Installation Section to book for turn on appointment date.
__________________________________________________________________________________________________________________
PART II To be completed by SP Services Ltd
To Meter Section, SP PowerGrid Ltd Application is in order. Please arrange to install the revenue meters.
Name : _____________________ Signature: _____________________ Date : _______________
__________________________________________________________________________________________
PART III To be completed by Meter Section SP PowerGrid Ltd
To Supply Application, SP Services Ltd Meters had been installed on _______________. Details in CMS.
Name : _____________________ Signature: ________________________ Date : _____________________
________________________________________________________________________________________________________________
PART IV (For official use)
To Meter Data Management Branch, SP Services Ltd Facsimile no.:6737 2472
Date : _____________________ Data Entered by: ________________________ Signature : _______________
(Full Name)
________________________________________________________________________________________________________________
.PART V (For official use)
To Client Relation Branch (MSSL Section), SP Services Ltd
Create MSS Account no. : ______________________ Consumer has been notified MSS account no.
Date : ______________ Account Opened by: ________________________ Signature : _______________
(Full Name)
94
04/07/05
Appendix 22.2
Form CS/7
REQUEST FOR INSTALLATION OF ELECTRICITY KWH METER (FOR LOAD EXCEEDING 45KVA)
For Official Use
Serial No. :______________________________ CMS Installation No. : ____________________
PART I Customer Details To be completed by LEW
To Meter Section, SP PowerGrid Ltd through SP Services Ltd
Name of Customer(Mr/Mdm) /Company(Messrs): _________________________________________________
NRIC/Company ROC:________________ Name of Contact Person for Company: _______________________
Telephone No. : ____________________ Pager/Handphone No. : ____________________
Site Address for Installation of Meter: ___________________________________________________________
Detail location of supply intake point: ___________________________________________________________
A/c no.:
: _________________________ Master A/c no.: ___________________________
Source of supply : SP PowerAssets Landlord HDB
Type of connection : New Connection Upgrading Downgrading Others : ____________
Supply Capacity :___________kVA/kW at ___________ Volts
Type of Business: ______________________
(Form CS/3 or CS3/H and COC shall be submitted together with this form)
Details of Landlord/MCST
Name of Landlord/MCST: _______________________________ Landlords Account no. : ___________________
Forwarding Address : _______________________________________________________Postal Code ________
Name of LEW in charge of landlords electrical installation : ____________________________________________
Contact no of Landlords LEW : _____________________________
____________________________________________________________________________________________
I hereby confirm that the electrical wirings at the meter installation have been checked and certified correct.
Name of LEW : ___________________ LEW Licence no. : ___________
Forwarding Address (as registered with EMA) : ____________________________________Postal Code_________
Telephone no. : _____________ Handphone no. : ______________ Facsimile no. : ______________
Signature : __________________________________ Date : ____________________
____________________________________________________________________________________________
PART II - To be completed by SP Services Ltd
To Meter Section, SP PowerGrid Ltd -- Application is in order. Please arrange to install the revenue meters.
Name : Signature : Date :
PART III -To be completed by Meter Section SP PowerGrid Ltd
To Supply Application, SP Services Ltd - Meters had been installed on ____________. Details in CMS.
Name : Signature : Date :
_____________________________________________________________________________________________________________________________________________________________________________________
PART IV (For official use)
Check and perform Master-sub Tagging
Sent to CRO for account move in on ____________
Move in/ Turn-On Date is on __________________
95
01/07/05
Appendix 23
96
APPLICATION FOR APPOINTMENT FOR
ENERGISATION OF SERVICE CONNECTION BY FAX
FACSIMILE TRANSMITTAL SHEET
Total No. of Pages (including this page): [ ]
To: Deputy Director, Installation Branch From [Name of LEW]:
Company: SP Services Ltd Company:
Fax No.: 62777044 Fax No.:
Date: Office Telephone No.:
Application No.: Pager/Handphone No.:
MSSL A/C No.: Approved Load:
I would like to make an appointment for energisation of service connection to __________________________________________
_______________________________________________________________________________________________________.
(site address)
The following documents are faxed together with this application.
Documents Tick if applicable
1) Opening of Account with SP Services Ltd
2) Opening of Account with Electricity Retailer (for contestable consumer)
3) Confirmation of meters already fixed (for contestable consumer)
4) Electrical Installation Licence issued by EMA
5) Certificate of Compliance (original to be submitted to SPPGs project officer)
6) Letter from IRAS confirming official address
I will submit the Certificate of Readiness on site, failing which service connection shall not be energised and SPPG & SPPA shall
not be liable for any loss arising therefrom.
I understand that the date of appointment is subject to confirmation by SP Services Ltd and the appointment date shall not be
earlier than 4 business days from this fax date. The preferred appointment dates are as follows:
1
st
choice: Date: Time: Morning / Afternoon*
2
nd
choice: Date: Time: Morning / Afternoon*
3
rd
choice: Date: Time: Morning / Afternoon*
( *delete whichever not applicable )
Name & Signature of LEW Licence No.
FOR OFFICIAL USE
The appointment for energisation of service connection is fixed on __________________________ at ____________________.
(date) (time)
Please liaise with Meter Section of SPPG for the fixing of revenue meter before the energisation.
For clarification, please contact ______________ at Telephone No.: 627770 __________.
Appendix 24
97
TECHNICAL REQUIREMENTS FOR SERVICE CABLE
AND METER COMPARTMENT FOR LANDED HOUSES
1 The service cable termination and meter compartment shall be located at the front-gate pillar/perimeter wall
such that it is accessible to SPSL's and SPPG's officer without the need to enter the customer's premises.
2 It shall be constructed of concrete, brick or high impact fibre glass and shall be completely weatherproof.
Provision shall be made to prevent any stagnation of water within the compartment.
3 The main dimensions of the compartment are shown in the layout drawing (see Appendix 25). The depth of
the compartment shall be between 250 mm and 300 mm.
4 A meter board of 20 mm thick and constructed of teak wood or any hardwood chemically treated against
termite attack shall be provided. Plywood board is not acceptable. A minimum space of 450 mm (W) x
800 mm (H) shall be allowed for the termination of the service cable and the installation of service MCBs and
meters. Customer's MCBs or connectors shall be mounted on a separate board in a separate compartment.
5 A hinged door with a clear glass viewing window shall be provided. The viewing window with a 200 mm (W) x
300 mm (H) x 6 mm (thickness) glass cover shall be positioned to be directly in front of the meter location. To
avoid high humidity and condensation within the compartment, sufficient ventilation shall be provided. The
access door shall not have less than 450 mm clear access opening.
6 The door shall be constructed of stainless steel, anodised aluminium or high impact type fibre glass reinforced
material. Where a metal door is provided, a means of earthing shall be provided.
7 One 100mm diameter UPVC lead-in pipe shall be provided for SPPA service cable. The pipe shall be laid up
to 100 mm from the floor slab of the electric meter compartment and shall undercross any drain in front of the
compartment.
8 There shall be adequate standing space in front of the compartment to facilitate meter reading, installation
and maintenance work. Where there exists a drain in front of the compartment, a suitable concrete platform or
hinged galvanised steel grating shall be provided.
9 The compartment shall be exclusively used for service cable and electricity meter. No water meter, gas meter
or other facilities shall be placed within the same compartment.
10 Please obtain clearance from URA's Development Control Division if the meter-box structure exceeds their
stipulated dimensions.
Appendix 24
98
STANDARD METER COMPARTMENTS AT GATE PILLAR
Appendix 25
99
STANDARD METER BOARD
STANDARD SIZE FOR SINGLE-PHASE METER BOARD
Appendix 26
Fig A
MCB / cut-out
Max 100 Amps
Neutral
Single
Phase
Meter
230 mm
2
8
0
m
m
L
(
L
=
3
0
0
m
m
f
o
r
3
5
s
q
m
m
c
a
b
l
e
)
4
0
m
m
L
i
v
e
N
e
u
t
r
a
l
N
e
u
t
r
a
l
L
o
a
d
PG
Electrical
Service
Box
L
i
v
e
N
e
u
t
r
a
l
N
e
u
t
r
a
l
L
o
a
d
230 mm
4
0
m
m
L
(
L
=
3
0
0
m
m
f
o
r
3
5
s
q
m
m
c
a
b
l
e
)
2
8
0
m
m
Single
Phase
Meter
Fig C
Single
Phase
Meter
230 mm
L
(
L
=
3
0
0
m
m
f
o
r
3
5
s
q
m
m
c
a
b
l
e
)
4
0
m
m
MCB / cut-out
Max 100 Amps
Neutral
Fig B
2
8
0
m
m
L
i
v
e
N
e
u
t
r
a
l
N
e
u
t
r
a
l
L
o
a
d
1. Minimum space for single-phase meter position (enclosed within broken lines):
(i) 230mm (W) x 280 mm (H) for 25 sq. mm cable and below.
(ii) 230mm (W) x 300 mm (H) for 35 sq. mm cable.
2. A customers earthing terminal shall be provided on the meter board for termination of the
earthing lead and earth continuity conductor.
3. Not more than one wire should be connected to each terminal of the meter terminal block.
4. All wires on the meter board from MCB/Cut-Out to the meter and meter to main switch
should preferably be run on the surface.
5. The size of cables to be used for connection to meters should not exceed 35 sq. mm.
6. The length of wire L protruding from the meter board to the meter terminal shall be at least
200 mm.
7. For meters grouped in a centralised meter room etc, an additional minimum spacing of
70mm is necessary between each row of meters for ease of installation/change.
8. The meter cables should be colour-coded red for live and black for Neutral.
9. Some typical layouts are shown in figures A, B and C.
Note : Drawing not to scale. All dimensions in mm.
100
Appendix 27
STANDARD SIZE FOR THREE-PHASE METER BOARD
Overhead Type
MCB / cut-out
Max 100 Amps
Neutral
Whole
Current
Poly
Phase
Meter
450 mm
4
5
0
m
m
4
0
m
m
M
a
i
n
L
o
a
d
M
a
i
n
L
o
a
d
M
a
i
n
L
o
a
d
N
e
u
t
r
a
l
L
o
a
d
L
Type-written on
cable sleeve
(
L
=
3
0
0
m
m
f
o
r
3
5
s
q
m
m
c
a
b
l
e
)
MCB / cut-out
Max 100 Amps
Neutral
Whole
Current
Poly
Phase
Meter
450 mm
4
5
0
m
m
4
0
m
m
M
a
i
n
L
o
a
d
M
a
i
n
L
o
a
d
M
a
i
n
L
o
a
d
N
e
u
t
r
a
l
L
o
a
d
L
UnderGround Type
Type-
written
on cable
sleeve
(
L
=
3
0
0
m
m
f
o
r
3
5
s
q
m
m
c
a
b
l
e
)
1. Minimum space for three-phase meter position 450 mm (W) x 450 mm (H) (enclosed within
broken lines).
2. A customers earthing shall be provided on the meter board for termination of the earthing
lead and earth continuity conductor.
3. Not more than one wire should be connected to each terminal of the meter terminal block.
4. All wires from the meter board from MCB/Cut-Out to meter and meter to main switch should
preferably be run on the surface.
5. The size of cables to be used for connection to meters should not exceed 35 sq. mm.
6. The length of wire L protruding from the meter board to the meter terminal shall be at least
200 mm.
7. The meter cables should be colour-type respective to their phases or be shrouded with
coloured sleeving.
Note : Drawing not to scale. All dimensions in mm.
101
Appendix 28
102
CT METER PANEL FOR LOW TENSION SUPPLY
Appendix 29
103
METHODS OF SEALING METERING PANELS
Appendix 30
104
ENCLOSURE FOR LOW TENSION METERING CURRENT TRANSFORMERS
Appendix 31
105
HT METERING KIOSK REQUIREMENTS
(FOR 1 OR 2 FEEDERS)
Meter Panel
Note: Drawing not to scale. All dimension in mm
Side Elevation of Metering Kiosk for 1 or 2 feeder panel
The following are required:
a) Metering kiosk : 650mm by 1700mm by minimum height 2400mm of solid brick as shown.
b) Floor opening 50mm by 50mm as shown.
c) Staircase and 1000mm landing where required.
d) Steel or heavy duty aluminium door of 1200mm wide by 2100mm height to be fitted with one of the SPPA
approved master series locksets as given in section 6.1.5.
e) One 13A switched socket outlet, one 40W lighting points and one fixed telephone c/w telephone socket
outlet.
f) If landing is above ground level, safety railings must be provided.
Appendix 32
HT METERING KIOSK REQUIREMENTS
(FOR 3 OR 4 FEEDERS)
2100 mm high
heavy duty aluminium door
Note : Drawing not be scale. All dimension in mm
STAIRS
1000 mm
100 mm x 60 mm floor opening
BASEMENT
40W fluorescent lamp
100 mm thick
610 mm
r.c. floor
Side Elevation of Metering Kiosk for 3 or 4 feeder panel
The following are required :
a) Metering kiosk : 810mm by 2650mm by minimum height 2400mm of solid brick as
shown
b) Floor opening 100mm by 60mm as shown.
c) Staircase and 1000mm landing where required.
d) Heavy duty aluminium door of 800mm width by 2100mm height to be fitted with one
of the the SPPA approved master series locksets as given in section 6.1.5.
e) One 13A switched socket outlet, two 40W lighting points and one fixed telephone line
c/w telephone socket outlet.
f) If landing is above ground level, safety railing must be provided.
106
Appendix 32
107
HT METERING KIOSK REQUIREMENTS
(FOR 3 OR 4 FEEDERS)
40Wfluorescentlamp
a=40Wfluorescentlamps
b=13Aswitchedsocketoutlet
c=5Aswitchforfluorescentlamps
Appendix 33
108
HT METERING PANEL REQUIREMENT
(FOR 1 OR 2 FEEDERS)
Appendix 34
109
METERING VTS
Voltage Ratio, Sequence & Phase Angle Tests Report
Customer : ____ A/C No. :
Project Address : A/C No. :
PT No. : Voltage Ratio :
For Feeder No. :
I, , EMA Licensed No. had carried out the above test
and results are given below.
I hereby certified that the VTs are correctly connected up for tariff metering.
Stamp & Signature of LEW
Date :
Secondary Phase Angle
Primary ( V)
Across
Sequence Across Volt
Frequency
Lead Lag
RY RE
YR
YB YE
RY
BR BE
YB YE
BY
BR BE
YB
RY RE
BR BE
RB
RY RE
BR
YB YE
Appendix 35
110
BASIS FOR THE SERVICE CONNECTION CHARGE
1 Service Connection Charges for Low Tension (LT) Connection
All LT consumers are required to pay a one-time upfront service connection charge. These charges which vary for
different load requirements are categorised depending on the provision of a substation.
For larger consumers with substations, their supply intake point is usually adjacent to the substation, which requires a
service cable of approximately 15m in most instances. Therefore, the standard connection charge is computed based
on a cost of service cable length of 15m. Consumers shall pay the additional cost for service cable exceeding 15m. In
addition, consumers shall also pay for those dedicated assets, such as switchgear and transformers, which are
serving them and do not benefit others.
For individual small consumers without substations, the cost of LT service cable for the same capacity may vary
widely depending on their locations with respect to the nearest LT mains. These consumers are not the sole
beneficiaries of the extension of the LT network. To achieve a greater degree of equity in terms of cost for these
general consumers, a standard cost approach is adopted based on similar requirements. The average global cost
based on capacity is determined from past statistics. As such, this category of consumers which comprises mainly the
individual landed residential owners, applying for the same applied load would pay the same standard connection
charge regardless of the location of their premises from the existing LT network.
Standard charges are only applicable to consumers who are connected to the shared network. The rates, which are
approved by EMA, are available in the Transmission Services Rate Schedule. Standard charges are not applicable to
consumers where the network created is unlikely to be shared by others. Some of these include supply to HDB
premises, premises involving installation of bigger capacity cable in order to overcome the excessive voltage drop,
temporary work sites, public installations and offshore island premises. These consumers would have to pay for the
full connection network cost, based on user-pay principle, as they are the main beneficiaries.
2 Service Connection Charges for HT and EHT Connection
Customers receiving HT and EHT connection shall pay the cost of the service connections to their intake equipment
including cables, associated equipment and facilities to effect the connection of customers equipment to SPPAs
substation/network. The service connection shall cater for single contingency.
Customers requesting for additional level of contingency above single contingency are required to pay for the full cost
of such provision.
3 Dedicated Network/Substation
The customer shall pay the full cost for all associated equipment and facilities under a dedicated network/substation
scheme which the network capacity is intended to serve to its development exclusively.
Substation comprises land, building, electrical equipment and associated cables. Substations which serve a
development or premises have to be provided and paid for by the developer or customer. As the capacity of electrical
equipment is lumpy, the substations may have excess capacity. The developer or customer will carry the cost of this
excess capacity which cannot be avoided. As these substations are required to serve the development or customer
loads, they are dedicated substations.
To reduce cost, a developer or customer can choose to let SPPA bear the cost of the electrical equipment and
associated cables. In return, SPPA must therefore be allowed to sell off the excess capacity. Even after the excess
capacity is sold off, SPPA remains committed to return the capacity to the customer if his demand grows later. At
present, most substations provided by developer or customer are non-dedicated substations.
Appendix 36
111
STANDARD SERVICE CONNECTION CABLES
The type of service connection cables for terminating into a customers intake point for the applied load connected
at the LT and 22kV level and the typical connection schemes are illustrated as follows:
Voltage Level Applied Load (kVA) Size of Cables Type of cables
Up to 15 35mm
2
2Core Cu/XLPE/SWA/PVC
16 45 35mm
2
4Core Cu/XLPE/SWA/PVC
46 75 35mm
2
4Core Cu/XLPE/SWA/PVC
76 140 120mm
2
4Core Al/XLPE/SWA/PVC
141 180 185mm
2
4Core Al/XLPE/SWA/PVC
181 230 300mm
2
4Core Al/XLPE/SWA/PVC
231 280 300mm
2
4Core Cu/XLPE/SWA/PVC
281 460 2x300mm
2
4Core Al/XLPE/SWA/PVC
461 560 2x300mm
2
4Core Cu/XLPE/SWA/PVC
561 1000 7x500mm
2
1Core Cu/XLPE/PVC
1001 1500
*
7x1000mm
2
1Core Cu/XLPE/PVC
1001 2000
^
2 sets of 7x500mm
2
1Core Cu/XLPE/PVC
LT
2001 3000
^
3 sets of 7x500mm
2
1Core Cu/XLPE/PVC
Up to 12750kW
^
2x300mm
2
3Core Cu/XLPE/DSTA/PVC
12751 25500kW
^
4x300mm
2
3Core Cu/XLPE/DSTA/PVC
25501 38250kW
^
6x300mm
2
3Core Cu/XLPE/DSTA/PVC
22kV
+
Pilot cables 1.5 mm
2
5 pair Cu/PE/DSTA/PVC
For installations where the customers supply, install and maintain the service cables, to ensure that these cables
comply with SPPA's specifications, the customers shall seek approval from Distribution Engineering Section prior to
procurement.
* applies to upgrading of applied load.
+ The 22kV scheme is designed to cater for the outage of a single service connection circuit. The customer is
required to reduce or maintain his load to within the rated capacity of the remaining service connection circuit(s)
in the event of a busbar failure or outage for maintenance.
^ There must be an electrical and mechanical interlocking bus coupler between each set of cables terminating
into the customers switchboard as shown below, and to ensure that there is no possibility of paralleling SPPA
source:
Bus Coupler
HT Customers
SwitchBoard
12751- 25500kW
7x500mm
2
1Core 7x500mm
2
1Core
LT Customers
SwitchBoard
1001- 2000kVA
Bus Coupler
LT Customers
SwitchBoard
2001- 3000kVA
7x500mm
2
1Core 7x500mm
2
1Core 7x500mm
2
1Core
Bus Coupler Bus Coupler
300mm
2
3Core 300mm
2
3Core
HT Customers
SwitchBoard
Up to 12750kW
Bus Coupler
300mm
2
3Core 300mm
2
3Core 300mm
2
3Core
Normally Open
HT Customers
SwitchBoard
25501- 38250kW
(subject to SPPG
approval)
300mm
2
3Core 300mm
2
3Core 300mm
2
3Core 300mm
2
3Core 300mm
2
3Core 300mm
2
3Core
Bus Coupler
Normally Open
Normally Open
Normally Open Normally Open
Normally Open
300mm
2
3Core
Appendix 37
CERTIFICATE OF COMPLIANCE
Particulars of Electrical Installation
Name of Consumer: ________________________________________________
Address of Installation: ______________________________________________
_________________________________________________________________
Electrical Installation Licence No. _________ MSS Account No. _____________
Approved load & Supply Voltage: _______________ kW ____________ Volts
Generator(s) Installed: Operated in parallel with SP PowerAssets network.
No. of generator: ________ Rating: _________ kVA
Standby generator.
No. of generator: ________ Rating: _________ kVA
Not applicable
Electrical Installation Design Certification
I certify that the design of the above-mentioned electrical installation complies with the
requirements of the Electricity (Electrical Installations) Regulations 2002 and the relevant
Singapore Standard Code of Practice. With the certification of compliance by the LEW
responsible for the installation work as shown below, I hereby request for the energisation of
the supply line to the said electrical installation on _________________ (date).
__________ _________
Name & Signature of LEW responsible Licence No. Date
for design of electrical installation*
Electrical Installation Inspection Certification
I have supervised the work of the above-mentioned electrical installation and hereby certify
that the electrical installation complies with the requirements of the Electricity (Electrical
Installations) Regulations 2002 and the relevant Singapore Standard Code of Practice. I
further certify that the technical requirements as stipulated by the person responsible for
turning on the switchgear which controls the supply of electricity to the said electrical
installation have been complied with.
__________ _________
Name & Signature of LEW responsible Licence No. Date
for electrical installation work*
* The same LEW may perform both design and installation work for the electrical installation.
Copy to:
Market Support Services Licensee
REF: E(EI)Reg5(2)
112
Appendix 38
113
STATEMENT OF TURN-ON OF ELECTRICITY
ELECTRICITY SUPPLY TO _____________________________________________________________
(Name of Applicant)
AT__________________________________________________________________________________
(Address of Installation)
ELECTRICAL INSTALLATION LICENCE NO : ______________________________________________
APPLICATION NUMBER : ______________________________________________________________
I agree that the above-mentioned electrical installation is suitable for connection to the electrical system.
I certify that the supply line to the installation has been energised on
_______________________at ______________________.
(date) (time)
____________________________________ _____________ ____________
Name & Signature of SP PowerGrid officer NRIC No. Date
SP PowerGrid Ltd
As agent for and on behalf of SP PowerAssets Ltd
I acknowledge that the supply line has been energised on the date and time as indicated above.
_______________________________________ ________________ ____________
Name & Signature of LEW requesting for Licence No. Date
energisation of supply line
I acknowledge that the supply line has been energised on the date and time as indicated above and
confirm that I will be responsible for the operation of this electrical installation hereafter.
_______________________________________ ________________ ____________
Name & Signature of LEW responsible for the Licence No. Date
operation of the electrical installation*
I acknowledge that the supply line has been energised on the date and time as indicated above.
______________________________________ ________________ _____________
Name & Signature of Applicant NRIC / Passport No. Date
or his representative
*Not Applicable for an electrical installation that is exempted from licensing
Original Copy - SP PowerGrid Ltd
Pink Copy - LEW (Requesting)
Yellow Copy - LEW (Operation)
Green Copy - Applicant
Blue Copy - MSSL
White (last) Copy - File REF: E(EI) REG 5(4)
Appendix 39
114
REQUIREMENTS FOR DISTRIBUTED GENERATION FACILITY
The customer applying for distributed generation facility is required to obtain SPPAs approval and shall comply with
the technical, safety & operational and commercial & legal requirements as follows:
A) Technical Requirements
1 real and reactive power/voltage output and voltage and frequency response times must be within agreed limits
2 not contribute to the voltage unbalance, voltage fluctuation and harmonic content specified for the transmission
network
3 ensure that there is no interference to SPPAs Equipment or any other directly or indirectly connected consumers
4 ensure adequate partitioning of the exempt generation facility equipment from SPPAs equipment
5 where required by SPPA, install harmonic filtering circuit at the incoming switchboard of the service connection in
compliance with the harmonics standard
6 LEW is required to submit fault level reports to SPPGs Distribution Planning Section. The distributed generation
system shall limit their fault level contribution to the grid to a level acceptable to SPPG.
B) Safety & Operational Requirements
1 provide an interlocking and inter-tripping facility for the service connection that meets SPPAs requirement
2 fit exempt generation facility with reverse power relays to prevent export of power to the transmission system.
However, this requirement will not apply in the event that EMA / EMC had given approval for the export of power
to the transmission system
3 not operate the exempt generation facility in islanding mode i.e., the embedded generator must isolate itself from
the distribution network when there is a fault/tripping on the latter or the customers installation (non-islanding
protection)
4 provide a synchronizing facility at the incoming switchboard of its service connection and ensure that any output is
always synchronized with the distribution network
C) Commercial & Legal Requirement
The customer with an exempt generation facility shall
1 pay standby use of system charges or any other charges approved by the EMA
2 indemnify SPPA
i) for all losses and liabilities arising from any loss of synchronisation caused by any tripping or re-closing of any
breakers in the transmission system and the exempt generation facility connected in parallel to the
transmission system ; and
ii) against losses to third parties caused by impedance, disruption degradation interference or failure of
transmission services to third parties caused by the system or works carried out on the transmission system
3 certify to SPPG that the exempt generation facility meet all conditions of the relevant legislation, regulation
(including installation, fire and safety, noise and environment);
4 conduct regular site tests and to notify the SPPG of the results
5 allow SPPG to conduct inspection of, disconnect and enforce conditions in respect of the service connection if the
exempt generation facility fails to meet any of the above requirements
6 resolve, at its own expense all third party complaints concerning the exempt generation facility (e.g.complaints
due to noise, or aesthetic reasons); and
7 use the service connection to operate in parallel with its exempt generation facility at its own risk
Appendix 39.1
TERMS AND CONDITIONS FOR CAPPED CAPACITY SCHEME (CCS)
1 The Consumer shall at its own expense, install and maintain, in accordance with such
requirements that Transmission Licensee may from time to time stipulate:
1.1 at the Consumers incoming switchboard (or at such other point that
Transmission Licensee may specify), a Load Limiting Device (LLD), which will
automatically disconnect the Service Connection from the Transmission
System in the event (Event) that the Consumers intake from the
Transmission System exceeds one hundred twenty percent (120%) of the
Contracted Capacity (CC) continuously for more than ten (10) seconds.
1.2 at the HT metering kiosk (or at such other point that Transmission Licensee
may specify), a Load Monitoring Device (LMD) including all control cables for
the LMD as well as metering accessories and telephone line(s) for
Transmission Licensee to monitor the Consumers intake from the
Transmission System.
2 Upon installation, all title, rights and interest in the LMD shall vest immediately in
Transmission Licensee. However, the Consumer shall ensure that:
2.1 The LMD shall at all times be set and adjusted to the satisfaction of
Transmission Licensee;
2.2 No modification, reset or adjustment to the LMD is carried out without first
obtaining Transmission Licensees approval;
2.3 The testing, commissioning and subsequent annual testing of the LMD as well
as any modification, reset or adjustment to the LMD approved by the
Transmission Licensee is to be carried out by a Licensed Electrical Worker and
in the presence of a representative from Transmission Licensee;
2.4 The LMD is re-tested and re-commissioned as and when required at the
discretion of Transmission Licensee;
2.5 All test results are submitted to Transmission Licensee at such address as
notified by Transmission Licensee within two (2) weeks of the testing;
2.6 The telephone line(s) set up for Transmission Licensees remote data
downloading from LMD shall be operational at all times;
2.7 Transmission Licensee officers are granted unrestricted access to substation
premises for on-site inspection and retrieval of data from the LMD; and
2.8 The LMD is covered under a valid maintenance contract providing for relevant
technical support and replacement parts to keep the LMD in good operational
condition at all times.
3 The Transmission Licensee shall witness the testing of LMD at its own expense. All
other expenses in connection with the testing of the LMD shall be borne by the
Consumer.
i
4 The conversion to CCS shall be effective upon the following (the CCS Effective
Date):
4.1 the Consumers compliance with Item 1 above; and
4.2 the successful commissioning of the LLD and LMD.
5 In the event that the LLD fails to cap the power demand (kW) drawn from the network
in the circumstances as described in Item 1.1, the Uncontracted Standby Capacity
Charge (USCC) shall apply and be payable.
6 USCC is a monthly charge payable in any month for the Uncontracted Standby
Capacity utilised. The Uncontracted Standby Capacity is the peak power demand in
kW drawn from the network exceeding 120% of CC, recorded from the time the power
drawn exceeds 120% of CC to the time the power drawn falls below 120% of CC. This
peak power demand is recorded by the LMD at single second intervals.
7 The rate of USCC shall be the prevailing rate stated in the Transmission Service Rate
Schedule. SPPA reserves the right to review the USCC rate applicable to the
Consumer from time to time, such review to be subject to EMAs approval. The
current rate for USCC is 5 times CC Charge for demand drawn exceeding 120% of
CC.
8 For each Event, as defined in Item 1.1 above, the Consumer is required to submit,
within two weeks of the occurrence of the Event, a report to the Transmission Licensee
on the causes of the occurrence. The report shall also include the Consumers follow-
up actions to prevent similar Events from occurring.
9 The Consumer shall ensure that multiple sources of Transmission System are not
connected in parallel at any time, and that any switching between circuits is
undertaken on black changeover or break before make basis.
10 Transmission Licensee reserves the right to withdraw the CCS from the Consumer if
the Consumer fails to comply with the terms and conditions applicable to the scheme,
and to offer only the Summation Scheme (as outlined in Clause 12.14(a) of the CCA)
to such Consumer.
11 In the event of a change in scheme for whatever reason, the Service Connection may
be disconnected temporarily to facilitate the installation of energy meters and other
equipment for the purposes of the implementation of the Summation Scheme.
ii
Appendix 39.2
TERMS AND CONDITIONS FOR EXTENDED CAPPED CAPACITY SCHEME (ECCS)
1 The Consumer shall at its own expense, install and maintain, in accordance with such
requirements that Transmission Licensee may from time to time stipulate:
1.1 at the Consumers incoming switchboard (or at such other point that
Transmission Licensee may specify), a Load Limiting Device (LLD), which will
automatically disconnect the Service Connection from the Transmission
System on the happening of any one of the following events (Event):
(a) when the Consumers intake from the Transmission System exceeds
one hundred twenty percent (120%) of the Contracted Capacity (CC)
continuously for more than one hundred (100) seconds; or
(b) when the Consumers intake exceeds two hundred percent (200%) of
the CC continuously for more than ten (10) seconds.
1.2 at the HT metering kiosk (or at such other point that Transmission Licensee
may specify), a Load Monitoring Device (LMD) including all control cables for
the LMD as well as metering accessories and telephone line(s) for
Transmission Licensee to monitor the Consumers intake from the
Transmission System.
2 Upon installation, all title, rights and interest in the LMD shall vest immediately in
Transmission Licensee. However, the Consumer shall ensure that:
2.1 The LMD shall at all times be set and adjusted to the satisfaction of
Transmission Licensee;
2.2 No modification, reset or adjustment to the LMD is carried out without first
obtaining Transmission Licensees approval;
2.3 The testing, commissioning and subsequent annual testing of the LMD as well
as any modification, reset or adjustment to the LMD approved by the
Transmission Licensee is to be carried out by a Licensed Electrical Worker and
in the presence of a representative from Transmission Licensee;
2.4 The LMD is re-tested and re-commissioned as and when required at the
discretion of Transmission Licensee;
2.5 All test results are submitted to Transmission Licensee at such address as
notified by Transmission Licensee within two (2) weeks of the testing;
2.6 The telephone line(s) set up for Transmission Licensees remote data
downloading from LMD shall be operational at all times;
2.7 Transmission Licensee officers are granted unrestricted access to substation
premises for on-site inspection and retrieval of data from the LMD; and
2.8 The LMD is covered under a valid maintenance contract providing for relevant
technical support and replacement parts to keep the LMD in good operational
condition at all times.
3 The Transmission Licensee shall witness the testing of LMD at its own expense. All
iii
other expenses in connection with the testing of the LMD shall be borne by the
Consumer.
4 The conversion to ECCS shall be effective upon the following (the ECCS Effective
Date):
4.1 the Consumers compliance with Item 1 above; and
4.2 the successful commissioning of the LLD and LMD.
5 In the event that the LLD fails to cap the power demand (kW) drawn from the network
in the circumstances as described in Item 1.1, the Uncontracted Standby Capacity
Charge (USCC) shall apply and be payable. The USCC is a monthly charge payable
in any month for the Uncontracted Standby Capacity utilised.
6 For the purposes of this ECCS, the term Uncontracted Standby Capacity shall mean
the capacity by which the demand in kW drawn from the network:
6.1 exceeds 120% up to a level of 200% of the CC at the metered intake supply
point for a duration of more than 100 seconds continuously; or
6.2 exceeds 200% of the CC at the metered intake supply point for a duration of
more than 10 seconds continuously,
in both cases, arising from a failure by the Consumer to cap the demand in kW drawn
from the Transmission System. The definition of Uncontracted Standby Capacity as
stated in the CCA is hereby superceded.
7 The rate of USCC shall be the prevailing rate stated in the Transmission Service Rate
Schedule. SPPA reserves the right to review the USCC rate applicable to the
Consumer from time to time, such review to be subject to EMAs approval. The
current rate for USCC is:
7.1 5 times CC Charge for demand drawn exceeding 120% up to 200% of CC; and
7.2 12 times CC Charge for demand exceeding 200% of CC.
8 For each Event, as defined in Item 1.1 above, the Consumer is required to submit,
within two weeks of the occurrence of the Event, a report to the Transmission Licensee
on the causes of the occurrence. The report shall also include the Consumers follow-
up actions to prevent similar Events from occurring.
9 The Consumer shall ensure that multiple sources of Transmission System are not
connected in parallel at any time, and that any switching between circuits is
undertaken on black changeover or break before make basis.
10 Transmission Licensee reserves the right to withdraw the ECCS from the Consumer if
the Consumer fails to comply with the terms and conditions applicable to the scheme,
and to offer only the Summation Scheme (as outlined in Clause 12.14(a) of the CCA)
to such Consumer.
11 The Consumer acknowledges and accepts that in the event of a change in scheme for
whatever reason, the Service Connection may be disconnected temporarily to facilitate
the installation of energy meters and other equipment for the purposes of the
implementation of the Summation Scheme.
iv
Appendix 40
115
LIST OF STANDARDS
IEC Standards
IEC 60044-1 (1996-12) Ed. 1.0 Instrument transformers - Part 1 : Current transformers
IEC 60044-1-am1 (2000-07) Ed. 1.0 Amendment 1
IEC 60044-2 (2000-11) Consol. Ed. 1.1 (incl. am1) Instrument transformers - Part 2 : Inductive
voltage transformers
IEC 60044-6 (1992-03) Ed. 1.0 Instrument transformers - Part 6 : Requirements for protective
current transformers for transient performance
IEC 60060-1 (1989-11) Ed. 2.0 High-voltage test techniques - Part 1 : General definitions and
test requirements
IEC 60060-2 (1994-11) Ed. 2.0 High-voltage test techniques - Part 2 : Measuring systems
IEC 60060-2-am1 (1996-03) Ed. 2.0 Amendment No.2 to IEC 60-2
IEC 60076-1 (2000-04) Consol. Ed. 2.1 (incl. am1) Power transformers - Part 1 : General
IEC 60076-2 (1993-04) Ed. 2.0 Power transformers - Part 2 : Temperature rise
IEC 60076-3 (2000-03) Ed. 2.0 Power transformers - Part 3 : Insulation levels, dielectric tests
and external clearances in air
IEC 60076-5 (2000-07) Ed. 2.0 Power transformers - Part 5 : Ability to withstand short circuit
IEC 60076-8 (1997-11) Ed. 1.0 Power transformers - Part 8 : Application guide
IEC 60076-10 (2001-05) Ed. 1.0 Power transformers - Part 10 : Determination of sound levels
IEC 60099-4 (2001-12) Consol. Ed. 1.2 (incl. am1 + am2) Surge arresters - Part 4 : Metal-oxide
surge arresters without gaps for a.c. systems
IEC 60137 (1995-12) Ed. 4.0 Insulating bushings for alternating voltages above 1000V
IEC 60141-1 (1993-09) Ed. 3.0 Tests on oil-filled and gas-pressure cables and their accessories
Part 1 : Oil-filled, paper or polypropylene paper laminate insulated, metal-
sheathed cables and accessories for alternating voltages up to and including
500kV
IEC 60141-1-am1 (1995-02) Ed. 3.0 Amendment No.1
IEC 60141-1-am2 (1998-08) Ed. 3.0 Amendment No.2
IEC 60228 (1978-01) Ed. 2.0 Conductors of insulated cables
IEC 60228-am1 (1993-01) Ed. 2.0 Amendment No.1
IEC 60230 (1966-01) Ed. 1.0 Impulse tests on cables and their accessories
IEC 60255-3 (1989-06) Ed. 2.0 Electrical relays Part 3: Single input energizing quantity
measuring relays with dependent or independent time
IEC 60255-5 (2000-12) Ed. 2.0 Electrical relays Part 5: Insulation coordination for measuring
relays and protection equipment Requirements and tests
IEC 60255-6 (1988-12) Ed. 2.0 Electrical relays Part 6: Measuring relays and protection
equipment
IEC 60255-8 (1990-10) Ed. 2.0 Electrical relays Part 8: Thermal electrical relays
IEC 60255-12 (1980-01) Ed. 1.0 Electrical relays Part 12: Directional relays and power relays
with two input energizing quantities
IEC 60255-13 (1980-01) Ed. 1.0 Electrical relays Part 13: Biased (percentage) differential
relays
IEC 60255-14 (1981-01) Ed. 1.0 Electrical relays Part 14: Endurance tests for electrical relay
contacts Preferred values for contact loads
IEC 60255-16 (1982-01) Ed. 1.0 Electrical relays Part 16: Impedance measuring relays
IEC 60255-19 (1983-01) Ed. 1.0 Electrical relays Part 19: Sectional specification:
Electromechanical all-or-nothing relays of assessed quality
IEC 60255-23 (1994-10) Ed. 1.0 Electrical relays Part 23: Contact performance
IEC 60255-24 (2001-05) Ed. 1.0 Electrical relays Part 24: Common format for transient data
exchange (COMTRADE) for power systems
IEC 60273 (1990-03) Ed. 3.0 Characteristics of indoor and outdoor post insulators for
systems with nominal voltages greater than 1000V
Appendix 40
116
LIST OF STANDARDS
IEC Standards continued
IEC 60186 Voltage Transformers
IEC 60287-1-1 (2001-11) Consol. Ed. 1.2 (incl. am1 + am2) Electric cables - Calculation of the
current rating Part 1-1: Current rating equations (100% load factor) and
calculation of losses General
IEC 60287-1-2 (1993-12) Ed. 1.0 Electric cables - Calculation of the current rating Part 1:
Current rating equations (100% load factor) and calculations of losses Section 2:
Sheath eddy current loss factors for two circuits in flat formation
IEC 60287-2-1 (2001-11) Consol. Ed. 1.0 (incl. am1) Electric cables - Calculation of the current
rating Part 2-1: Thermal resistance Calculation of the thermal resistance
IEC 60287-2-2 (1995-05) Ed. 1.0 Electric cables - Calculation of the current rating Part 2:
Thermal resistance Section 2: A method for calculating reduction factors for
groups of cables in free air, protected from solar radiation
IEC 60287-3-1 (1999-05) Consol. Ed. 1.1 (incl. am1) Electric cables - Calculation of the current
rating Part 3-1: Sections on operating conditions Reference operating
conditions and selection of cable type
IEC 60287-3-2 (1995-07) Ed. 1.0 Electric cables - Calculation of the current rating Part 3:
Sections on operating conditions Section 2: Economic optimization of power
cable size
IEC 60287-3-2-am1 (1996-10) Ed. 1.0 Amendment No.1 to IEC 287-3-2
IEC 60289 (1988-05) Ed. 2.0 Reactors
IEC 60298 (1990-12) Ed. 3.0 A.C. metal-enclosed switchgear and controlgear for rated
voltages above 1kV and up to and including 52kV
IEC 60332-1 (1993-04) Ed. 3.0 Tests on electric cables under fire conditions - Part 1 : Test on a
single vertical insulated wire or cable
IEC 60354 (1991-10) Ed. 2.0 Loading guide for oil-immersed power transformers
IEC 60376 (1971-01) Ed. 1.0 Specification and acceptance of new sulphur hexafluoride
IEC 60502-1 (1998-11) Consol. Ed. 1.1 (incl. am1) Power cables with extruded insulation and
their accessories for rated voltages from 1kV(Um = 1,2kV) up to 30kV (Um =
36kV) - Part 1 : Cables for rated voltages of 1kV (Um = 1,2kV) and 3kV (Um =
3,6kV)
IEC 60517 (1990-10) Ed. 3.0 Gas-insulated metal-enclosed switchgear for rated voltages of
72.5kV and above
IEC 60517-am1 (1994-11) Ed. 3.0 Amendment No.1
IEC 60521 (1988-03) Ed. 2.0 Class 0.5, 1 and 2 alternating-current watthour meters
IEC 60529 (2001-02) Consol. Ed. 2.1 (incl. am1) Degrees of protection provided by
enclosures (IP Code)
IEC 60651 (2001-10) Consol. Ed. 1.2 (incl. am1 + am2) Sound level meters
IEC 60660 (1999-10) Ed. 2.0 Insulators Tests on indoor post insulators of organic material
for systems with nominal voltages greater than 1000V up to but not including
300kV
IEC 60687 (1992-06) Ed. 2.0 Alternating current static watt-hour meters for active energy
(classes 0,2 S and 0,5 S)
IEC 60694 (2001-05) Consol. Ed. 2.1 (incl. am1) Common specifications for high-voltage
switchgear and controlgear standards
IEC 60722 (1982-01) Ed. 1.0 Guide to the lightning impulse and switching impulse testing of
power transformers and reactors
IEC 60811-1-1 (2001-07) Consol. Ed. 2.1 (incl. am1) Common test methods for insulating and
sheathing materials of electric cables and optical cables - Part 1-1 : Methods for
general application Measurement of thickness and overall dimensions - Tests for
determining the mechanical properties
IEC 60840 (1999-02) Ed. 2.0 Power cables with extruded insulation and their accessories for
rated voltages above 30kV (Um = 36kV) up to 150kV (Um = 170kV) - Test
methods and requirements
Appendix 40
117
LIST OF STANDARDS
IEC Standards
IEC 60859 (1999-07) Ed. 2.0 Cable connections for gas-insulated metal-enclosed switchgear
for rated voltages of 72.5kV and above - Fluid-filled and extruded insulation cables
- Fluid-filled and dry type cable-terminations
IEC 60885-1 (1987-03) Ed. 1.0 Electrical test methods for electric cables. Part 1: Electrical tests
for cables, cords and wires for voltages up to and including 450-750V
IEC 60885-2 (1987-03) Ed. 1.0 Electrical test methods for electric cables. Part 2: Partial
discharge tests
IEC 60885-3 (1988-07) Ed. 1.0 Electrical test methods for electric cables. Part 3: Tests methods
for partial discharge measurements on lengths of extruded power cables
IEC 60947-1 (2001-12) Consol. Ed. 3.2 (incl. am1 + am2) Low-voltage switchgear and
controlgear - Part 1 : General rules
IEC 60947-7-1 (1999-08) Consol. Ed. 1.1 (incl. am1) Low-voltage switchgear and controlgear
Part 7 : Ancillary equipment - Section 1 : Terminal blocks for copper conductors
IEC 61000-4-2 (2001-04) Consol. Ed. 1.2 (incl. am1 + am2) Electromagnetic compatibility (EMC) -
Part 4-2 : Testing and measurement techniques Electrostatic discharge
immunity test
IEC 61036 (2000-09) Consol. Ed. 2.1 (incl. am1) Alternating current static watt-hour meters
for active energy (classes 1 and 2)
IEC 62098 (2000-11) Ed. 1.0 Evaluation methods for microprocessor based instruments
IEC 62271-100 (2001-05) Ed. 1.0 High-voltage switchgear and controlgear - Part 100 : High-
voltage alternating-current circuit-breakers
IEC 62271-102 (2001-12) Ed. 1.0 High-voltage switchgear and controlgear - Part 102 : High-
voltage alternating-current disconnectors and earthing switches
IEC 60068 (1988-06) Environmental testing. Part 1: General and guidance
IEC 60068-1-am1 (1992-04) Amendment No. 1
IEC 60068-2-3 (1969-01) Environmental testing - Part 2: Tests. Tests Ca: Damp heat, steady
state.
IEC 60068-2-11 (1981-01) Environmental testing - Part 2: Tests. Tests Ka: Salt Mist.
IEC 60068-2-11 (1999-12) Corrigendum 1.
IEC 60068-2-30 (1980-01) Environmental testing - Part 2: Tests. Tests Db and guidance: Damp
heat, cyclic (12 + 12-hour cycle)
IEC 60068-2-30-am1 (1985-08) Amendment No. 1
IEC 60068-2-67 (1995-12) Environmental testing Part 2: Tests Test Cy: Damp heat, steady
state, accelerated test primarily intended for components.
IEC 60068-3-4 (2001-08) Environmental testing Part 3-4: Supporting documentation and
guidance Damp heat tests
IEC 60068-4 (1987-09) Environmental testing. Part 4: Information for specification writers
Test Summaries
IEC 60068-4-am1 (1992-02) Amendment No. 1
IEC 60068-4-am2 (1994-03) Amendment No. 2
IEC 61000-1-1 (1992-05) Electromagnetic compatibility (EMC) Part 1: General Section 1:
Application and interpretation of fundamental definitions and terms.
IEC 61000-1-2 (2001-06) Electromagnetic compatibility (EMC) Part 1-2: General Methodology
for the achievement of the functional safety of electrical and electronic equipment
with regard to electromagnetic phenomena.
IEC 62067 (2001-10) Power cables with extruded insulation and their accessories for rated
voltages above 150kV (Um = 170kV) up to 500kV (Um = 550kV) Test methods
and requirements
Appendix 40
118
LIST OF STANDARDS
British Standards
BS EN 60051-1 (1999)
[IEC 60051-1(1997)]
Direct acting indicating analogue electrical measuring instruments and their
accessories. Definitions and general requirements common for all parts.
BS 89-2 (1990)
[IEC 60051-2 (1984)]
Direct acting indicating analogue electrical measuring instruments and their
accessories. Specification for special requirements for ammeters and
voltmeters
BS 89-3 (1990)
[IEC 60051-3 (1984)]
Direct acting indicating analogue electrical measuring instruments and their
accessories. Specification for special requirements for wattmeters and
varmeters.
BS 89-4 (1990)
[IEC 60051-4 (1984)]
Direct acting indicating analogue electrical measuring instruments and their
accessories. Specification for special requirements for frequency meters.
BS 89-5 (1990)
[IEC 60051-5 (1985)]
Direct acting indicating analogue electrical measuring instruments and their
accessories. Specification for special requirements for phase meters, power
factor meters and synchroscopes.
BS 89-9 (1990)
[IEC 60051-9 (1988)]
Direct acting indicating analogue electrical measuring instruments and their
accessories. Recommended test methods.
BS 148 (1998) Specification for unused and reclaimed mineral insulating oils for transformers
and switchgear.
BS 159 (1992) Specification for high-voltage busbars and busbar connections.
BS EN 60076-1
(1997)
Power transformers. General
BS 171-5 (1978)
[IEC 60076-5 (1976)]
Power transformers. Specification for ability to withstand short circuit.
BS EN 60060-2
(1995)
High-voltage testing techniques. Measuring systems
BS 3938 (1973) Specification for current transformers
BS 3941 (1975) Specification for voltage transformers
BS EN 60214 (1998) On-load tap changers
BS 5207(1975) Specification for sulphur hexafluoride for electrical equipment
BS 5209 (1975) Code of practice for the testing of sulphur hexafluoride taken from electrical
equipment
BS 5311(1996) High-voltage alternating-current circuit-breakers
BS EN 60947-4-1 (1992) Specification for low-voltage switchgear and controlgear. Contactors and motor-
starters. Electromechanical contactors and motor-starters
BS 5685-1(1979) Electricity meters. Specification for class 0.5, 1 and 2 single-phase and
polyphase, single rate and multi-rate watt-hour meters.
BS 5685-2 (1986) Electricity meters. Specification for single-phase coin operated prepayment flat
rate and two-part tariff watt-hour meters of class 2 and fixed charge collectors of
class 2.
BS 5685-3 (1986) Electricity meters. Specification for meters having class 1 electro-mechanical
maximum demand indicators.
BS 5685-4 (1986) Electricity meters. Specification for class 3 var-hour meters.
BS 5685-5 (1987) Electricity meters. Specification for input and output switching or logic
arrangements for multi-rate registers for electricity meters.
BS 5685-8 (1991) Electricity meters. Specification for impulse operated multiple registers for use
with induction electricity meters.
BS 5730 (2001) Monitoring and maintenance guide for mineral insulating oils in electrical
equipment.
BS 5992-1(1980)
[IEC 60255-0-20 (1974)]
Electrical relays. Specification for contact performance of electrical relays
BS 6231(1998) Specification for PVC-insulated cables for switchgear and controlgear wiring.
BS EN 60044-2 (1999)
[IEC 60044-2 (1997)]
Instrument transformers. Inductive voltage transformers
Appendix 40
119
LIST OF STANDARDS
Singapore Standards
SS 318 (1987) Current transformers for measurement and protection
SS 404 (1997) Power transformers Part 1: General
SS 404 (1997) Power transformers Part 2: Temperature rise
SS 404 (2001) Power transformers Part 3: Insulation levels and dielectric tests and external
clearances in air
SS 404 (2001) Power transformers Part 5: Ability to withstand short circuit
SS 404 (2000) Power transformers Part 8: Application guide
SS 443 (1998) Part 1: Power cables with extruded insulation and their accessories for rated
voltages from 1kV (Um = 1.2kV) up to 30kV (Um = 36kV) Cables for rated
voltages of 1kV (Um = 1.2kV) and 3kV (Um = 3.6kV)
SS ISO 9000 (2000) Quality management systems Fundamentals and vocabulary
SS ISO 9001 (2000) Quality management systems Requirements
SS ISO 9004 (2000) Quality management systems Guidelines for performance improvements
CP 5 (1998) Code of practice for electrical installations
CP 10 (1993) Code of practice for the installation and servicing of electrical fire alarm systems
CP 16 (1991) Code of practice for earthing
CP 19 (2000) Code of practice for the installation and maintenance of emergency lighting and
power supply systems in buildings
CP 31 (1996) Code of practice for installation, operation, maintenance, performance and
constructional requirements of mains failure standby generating systems
CP 33 (1996) Code of practice for lightning protection
Other Standards
IEEE C37.09
ANSI C37.09 (1999)
Test procedure for A.C high-voltage circuit breakers rated on a symmetrical
current basis
IEEE 32 (1972)
Neutral grounding devices, req term and test procedures
ISO 7-2 (2000) Pipe threads where pressure-tight joints are made on the threads Part 2:
Verification by means of limit gauges
AEIC CS2 (1997) Impregnated paper and laminated paper polypropylyne insulated cable high-
pressure-pipe type
AEIC CS4 (1993) Impregnated-paper-insulated-low and medium pressure self-contained liquid
filled cable
ASTM B187 (2000) Standard specification for copper bar, bus-bar, rod and shapes
ASTM B3 (2001) Standard specification for soft or annealed copper wire
Appendix 41
FORM CS/12
To: SP Services Ltd Fax No: 6823 8289
APPLICATION FOR ELECTRICAL INSTALLATION INSPECTION (UP TO 45KVA)
I/We hereby request an appointment to inspect the electrical installation at the premises with
SP Services Account No :
(Please tick or fill in the appropriate boxes)
An application for electricity supply service has been submitted earlier and approved.
SP Services Application Reference No is:
OR
This is a new application. Form CS/5, together with Certificate of Compliance (COC), is
enclosed. (Please note that CS/3 form is required for supply connection from Landlords
Electrical Installation).
Type of Single- Three No new meter
Meter Required: phase phase required
Removal of old meter(s) : Yes No
*Preferred Dates : 1 ___________ Morning Afternoon
(in order of
preference) 2 ___________ Morning Afternoon
3 ___________ Morning Afternoon
Remarks: ___________________________________________________________________
(*Your preferred dates shall be from the third working day onwards. If you do not give us your
preferred date(s), we shall provide you with the earliest available appointment date & time. )
Signature :
Licensed Electrical Worker :
Telephone/ Handphone No : FAX NO :
Pager No :
_________________________________________________________________________________
Please note the following:
1. For applications received before 3pm, it will be processed on the same day. For applications
received after 3pm, it will be processed on the following business day.
2. The granting of an appointment on the preferred date is at SP Services discretion and
subject to availability.
3. It is important that you provide us with your contact number and fax number.
4. All applications are to be accompanied by Certificate of Compliance (COC).
09/06/2005
120
Appendix 42
APPLICATION FOR CONTESTABILITY STATUS
Existing Electricity
Account No :
(if applicable) Name of Consumer
(company):
(the Consumer)
Official Premises
Address where
supply is required:
(the Premises)
Mailing Address:
(if different from
the Premises) Fax No:
Contact Person: Contact Tel: E-mail:
1.
2.
3.
4.
5.
6.
SIGNATURE:
DESIGNATION:
NAME:
COMPANY STAMP:
DATE:
I wish to apply to be a contestable consumer with respect to the premises stated above (the Premises)
In accordance with the Electricity (Contestable Consumers) Regulations 2003 or such further amendments thereto, I
confirm that the Premises is a non-residential premises.
The phone number of the phone line connected to my meters for the purpose of remote meter reading is _____________.
I agree that my application for contestability is subject to my compliance with paragraph 3 above and that SP Services
shall not be liable for any inconvenience, loss, expense and damage that may be incurred or suffered as a result of a
delay or postponement of my compliance or non-compliance of paragraph 3 provided always that such delay,
postponement or non-compliance is not caused by SP Services or is within its reasonable control.
If my application as a contestable consumer is approved, I agree to open an account with you for Market Support
Services and to pay a Security Deposit for an amount declared and in the form approved by you within the time period
stipulated by you.
I agree to be bound by the Conditions of Service (a copy which will be given to me), which shall take effect when I open
an account with you for Market Support Services after being classified as a contestable consumer.
* Requested Date of contestability:
* Note : (a) You shall be classified as a contestable consumer from such date as may be notified by SP Services Ltd and approved by the Authority.
(b) This form should reach SP Services Ltd at least 12 business days before the Requested Date of contestability
Company
Registration No:
SP Services Ltd
111 Somerset Road #06-05 Singapore Power Building Singapore 238164
Tel : 1800- 2338000 Website: www.mssl.com.sg Email: aboutmssl@singaporepower.com.sg Fax: 6820 6800
Updated 15 April 2005
121
Appendix 43
APPLICATION TO OPEN A MARKET SUPPORT SERVICES ACCOUNT
(For Official Use)
MSSL A/C No.
Name of Consumer
(company):
(the Consumer)
Company
Registration No:
Official Premises
Address where
supply is required :
(the Premises)
Fax No:
Contact Person: Contact Tel: E-mail:
Tick where appropriate
I confirm that I am a contestable consumer and have been notified by Energy Market Authority/SP Services through the
Contestability Notice dated ______________. (Please attach the Contestability Notice).
I confirm that I intend to move-in/take-over a contestable premises currently taking high tension supply.
Contract Capacity : _________________
Contract Expiry date : _________________
I agree that my move-in/take-over of the premises is subject to the corresponding move-out of the existing consumer of
the premises and I agree that SP Services shall not be liable for any inconvenience, loss, expense and damage that may
be incurred or suffered as a result of a delay, postponement or cancellation of such move-out by the existing consumer,
provided always that such delay, postponement or cancellation is not caused by SP Services or is within its reasonable
control.
I agree to pay a Security Deposit for an amount declared and in the form approved by you within the time period stipulated by
you or before the supply at the premises has been turned on, whichever is earlier.
I wish to apply to open an account for Market Support Services (MSS) for the above premises (the Premises).
I agree to be bound by the Conditions of Service (a copy of which has been given to me) which shall take effect when this
application is approved.
I will make arrangement to turn on the supply of electricity to the electrical installation of my premises on ________ (date),
and I will send a confirmation to notify you of any changes.
I agree that I will be billed from 00:00hrs on the date of move in/take over and up to 23:59hrs on the date I move out of the
Premises.
SIGNATURE:
1.
2.
3.
5.
4.
6.
DESIGNATION:
COMPANY STAMP:
DATE:
Mailing Address:
(if different from
the Premises)
Please specify Retailer Name : Billing Option: * Split / Consolidated (delete appropriately)
* Requested Date of Account Activation:
(must be at least 12 business days from date of application)
NAME:
I intend to purchase my electricity supply from :
An Electricity Retailer
Indirectly from the wholesale electricity market through SP Services Ltd
Directly from the wholesale electricity market
SP Services Ltd
111 Somerset Road #06-05 Singapore Power Building Singapore 238164
Tel : 1800- 2338000 Website: www.mssl.com.sg Email: aboutmssl@singaporepower.com.sg Fax: 6820 6800
Updated 15 April 2005
122
Appendix 44
COMPLETION CERTIFICATE FOR MODIFICATION
OF SMALL ELECTRICAL INSTALLATION
To: SP Services Ltd
111 Somerset Rd #06-05
Singapore Power Building
Singapore 238164
MODIFICATION TO ELECTRICAL INSTALLATION AT ____________________________
__________________________________________________________________________________________
(Address of installation)
MSSL Account No. : ____________________________________________________________
in the name of : ______________________________________________________________
I, ______________________________ certify that the modification to the above-mentioned
electrical installation has been inspected and tested by me in accordance with Singapore Standard
CP5: Code of Practice for Electrical Installations, and that to the best of my knowledge and belief the
modification summarized below complies with the said Singapore Standard CP5 and the relevant
Regulations.
Description Quantity
Lighting points
13 Amp socket outlets
15 Amp socket outlets
Heater
Isolator
Others (please specify)
The said modification has been connected to the supply of electricity on ____________. The existing
supply line is adequate for the after diversity maximum demand of the above-mentioned electrical
installation.
2. I append below the result of my inspection and test:
Incoming supply : SP PowerAssets Network / Third party electrical installation
MCB / Cutout size : Amp
Revenue meter no :
RCCB rating : Amp/30mA sensitivity
Phase to Phase insulation : Mohm
Phase to Earth insulation : Mohm
Neutral to Earth insulation : Mohm
RCCB test satisfactory : Yes/No
Polarity check satisfactory : Yes/No
Earth fault loop impedance : ohm
Date of inspection/test : _________________
________________________________________ ____________ ____________
Name & signature of Licensed Electrical Worker Licence No. Date
cc Consumer
REF:
E(EI)Reg7(1)
201003
123
Appendix 45
FORM E CERTIFICATE OF FITNESS OF RESIDENTIAL UNIT
Application No. ____________________
To: Deputy Director, Installation Branch
SP Services Ltd
111 Somerset Road #06-01
Singapore Power Building
Singapore 238164
PROJECT:
AT APARTMENT BLOCK No. STREET NAME:
DATE OF TEST: POSTAL DISTRICT:
Type/Total No. of Units / ( units) / ( units)
MCB Rating
MCB Type
(Before & after Revenue Meter)
Service Cable Size
RCCB Rating / Sensitivity
Cooker / Oven Point
Water Heater Point
15A Socket Outlet
13A Socket Outlet
Fan Point
Lamp Point
20A isolator SPN
20A isolator TPN
30A isolator SPN
30A isolator TPN
Others
Unit Nos.
I hereby declare that I have supervised the
installation, inspected and tested the electrical
installation of the residential units(s) in accordance
with the relevant Regulations and Code of Practice.
________________________________________
Signature/Name/Licence No. of LEW responsible
for electrical installation work*
I hereby certify that the electrical installation of the
residential unit(s) has been designed in accordance with
the relevant Regulations and Code of Practice.
_____________________________________________
Signature/Name/Licence No. of LEW responsible
for design of electrical installation*
O
t
h
e
r
s
D
e
t
a
i
l
s
o
f
E
l
e
c
t
r
i
c
a
l
I
n
s
t
a
l
l
a
t
i
o
n
*The same LEW may perform both design and installation work for the electrical installation.
124