ZORLU ENERJI PAKISTAN

56.4 MW
WIND POWER PLANT
September 2013
ZORLU ENERGY
GROUP
ZORLU INDUSTRIAL PAKISTAN
Engineering,Design, Construction
Services for Power Plants
ZORLU ENERJ I PAKISTAN
56.4 MW WPP under
construction
Up to 300 MW Expansion

ZORLU O&M PAKISTAN
Operation and Maintenance
Services for Power Plants
ZORLU ENERGY IN PAKISTAN
WF ZORLU
ZORLU PAKISTAN WPP PROJECT LOCATION
HISTORY OF ZORLU ENERGY WIND POWER PROJECT
2007
First Wind Mast of 85 m height in Pakistan
Approvals from Authorities and arrangements for Phase I (6 MW) and Phase II (43.5 MW)
2008
Construction works starts (Phase I 6 MW) 5 Vensys 1.2 MW
2009
Despite the economical crisis, Zorlu Energy completed Phase-I with %100 Equity.
6 MW Phase I starts to generate electricity.
2010
New financing opportunities are arisen.
2011
Vestas V90 1.8 MW for Phase II and the total capacity increased to 56.4 MW.
All approval are renewed. Financial arrangements are done.
2012
Energy Purchase Agreement and Implementation Agreement signed with Goverrnment of Pakistan.
EPC and O&M agreements are signed. The construction is started. Financial Close is done.
2013
25
th
July 2013, COD Achieved (3 months before Required COD)
HISTORY PHASE I CONSTRUCTION
2007
2009
2008
HISTORY PHASE I INAGURATION (19th April 2009)
HISTORY PHASE II CONSTRUCTION
2013
HISTORY 2008 - 2013
2008 2013
PROJECT MILESTONES
2013
Civil Works Jan 12 Dec `12
Turbines Deliveries Apr12 July`12
Mechanical Works Jul 12 Nov`12
Electrical Works Sep 12 Dec`12
Pre-commissionning Jan 13 May`13
Energisation of the Complex May`13
Hot-commissionning and Run Tests May 2013 July 2013
COD 25.07.2013 25.07.2013
PAKISTAN WIND POWER PROJECT DETAILS
Project: Pioneer in Wind Sector (Zorlu Enerji)
Location: Jhimphir, District Thatta
Installed Capacity: 56.4 MW
Expected Generation: 159.010 GWh
Number of Turbines: 5*Vensys 62 1.2 MW (Phase I)
28*VestasV90 1.8 MW (Phase II)
Project Area: 1,148 acres
Project Cost*: 143.7 M $
Debt/Equity: 70:30
Loan Amount: 100.2 M $
Foreign Lenders : IFC / ADB / ETDB
Local Lender : HBL
COD Achieved: July13
Required COD Date: November 2013
DEVELOPMENT STAGE




ALTERNATIVE ENERGY DEVELOPMENT BOARD (AEDB)
Letter of Intent (LOI) 01 Month
Allocation of Land 3 Months
Feasibility Study
Wind Assessment
Soil Investigation
Environmental Study
Selection of Technology

6 Months
National Electric Power Regulatory Authority (NEPRA)
1. Tariff Determination 03 Months
CENTRAL POWER PURCHASING AGENCY (CPPA)
EPA Negotiations 6 Months
IA Agreement 01 Month
Financial Closure 01 Month
Issues


Lengthy Procedure

Lack of Wind
Knowledge

Communication









Execution

1. Local Issues
2. Security Issues
3. Transport & Logistics Problems
4. Land Issues


Protest at ZEPL Site
2008 2013
BLADE DAMAGE
ILLEGAL SETTLEMENTS
OPERATION PHASE





EPA COMPLIANCE:
BILLING

FUTURE DEVELOPMENTS
LAND ACQUISATION
SLOW TRANSMISSION
INFRASTRUCTURE
BAD ROAD INFRASTRUCTURE
SECURITY ISSUES