HAND OVER REPORT
Mr.REGO & Mr.YUVARAJ ,
PRADEEP
THIRD LINE WORK-SHOP JL-1100694
1-Chilled water pipe line work & flushing & first camical completed.
2-Stanllone control wiring completed to operate the system
3- RF shielding area work balance
4-Power will get on 13/14th March 2011
DESCRIPTION
1
Mr.PRADEEP
BIN OMAIR RESIDENCE JL-1100608
1- Commission report & O/M manual to be submit DIPU
Mr.PRADEEP, SAQIB
SIYABI SOHAR JL-1100421
1-Commissioning Completed.
2-Material require for maintenance quantity attached
Mr.PRADEEP, SAQIB
KHALIFA AL RASHID JL-1100719
1-Copper Pipe & Insulation ordered to start the work.
Mr.SANTOSH PATIL
RCA SOHAR JL-1100745
1-Commissioning Completed.
2-Final inspection for hand-over the system on 14th March 2011
3- O/M manual will submit on 26th March 2011
4
5
8
Complains
Mr. Sam is handling
ENTERTAINMENT CENTER JL-1100604
1- Copper Pipe & Insulation completed
2- Package Unit Cable wiring balance being of main contractor not
yet provided isolator
Mr.DIPU & Mr.PRADEEP 7
6
OMAN FOOD STUFF RUSYAL JL-1100775
1- 4 Nos Package unit commissioned & other activity is going on