No. Item of Work Spec.

Section Preparatory Inspection Intermediate Inspections Completion Inspection


4. Cast-In-Place Structures


VDOT
Contract Special Provisions
& Section
302
Design-Builders QA Manager to schedule
and conduct preparatory inspection meeting
(hold point) to review work prior to
beginning construction activity on feature
of Work.
Verify formwork and rebar conforms to the
plans and specifications and is free of
debris.
Frequency - Weekly
Monitor curing based on the current and
forecasted weather conditions. Control
cylinders cast should be cured in the same
manner as the in-place concrete.
Verify design documents that relate to the
work to be performed have been approved.
Verify that two (2) Certified Concrete Field
QC Inspectors are present during
placement and that proper testing methods
are being implemented.
Frequency - Weekly
Physical field inspection performed with
final payment
Verify the Quality Assurance (QAM IA &
VST) and Quality Control (QC)
requirements as specified in the Design-
Builders QA/QC Plan
Verify that the proper frequency of testing
and material samplings is performed by the
QAM and QC personnel.
QC- fresh concrete properties each load.
QAM IA fresh concrete 10
th
load
QAM VST fresh concrete 50
th
load

Review items of work and the frequency
of OIA and OVST Inspections
Test results on the TL-28 Coding Form
Concrete Batch Report at the frequency
previously approved.
OIA fresh concrete 1 per 10 QAM VST.
OVST fresh concrete anytime before
500
th
load

Verify by observation or review of QAMs
records, that each foundation has been
probed or tested in another manner and
accepted by the QA Manager
On an OVST tests for consistency (slump)
and air entrainment; take cylinders at a
ratio of one (1) OVST for each two (2)
QAM VST.

Verify hydraulic cement mix design has
been approved for applications. Review
any special design requirements.
Provide written notice of non-compliant
materials to the Design-Builders QA
Manager.
Frequency As required


No. Item of Work Spec. Section Preparatory Inspection Intermediate Inspections Completion Inspection
4. Cast-In-Place Structures
(Continued)
Review concrete strength requirements
prior to the placement of superimposed
concrete or backfill
Perform OIA testing at a rate of one (1)
every ten (10) QAM VST tests for
consistency (slump), air entrainment, unit
weight, temperature and at a rate of one (1)
for every two (2) QAM VST for strength
(3 cylinders) and permeability.

ALTERNATE PROJECT DELIVERY OFFICE
5/2006
FORM IPD-CL040
Page 1of 1


CAST-IN-PLACE STRUCTURES INSPECTION FORM


REPORT NO.: DATE OF WORK:
PROJECT NO.: CONTRACTOR:
LOCATION:
PLAN PAGE: INSPECTOR:



ITEM
INSPECTOR
(INITIAL)
DATE REMARKS


PREPARATORY

APPROVED MATERIALS SOURCE
APPROVED MIX DESIGN
QA/QC PLAN APPROVED & TESTING
REQUIREMENTS ESTABLISHED

INTERMEDIATE

STRENGTH REQUIREMENTS IAW
PLANS & SPECS FOR PRECEDING
WORK

PROPER SUBSURFACE & BEDDING
IAW PLANS & SPECS

PROPER FORMWORK &
REINFORCING STEEL IAW PLANS &
SPECS

AREA FREE OF DEBRIS, WATER, &
MUD

2 INSPECTORS PRESENT DURING
ENTIRE PLACEMENT OF CONCRETE

PROPER TESTING METHODS
PERFORMED & RECORDED

PROPER PROTECTION & CURING
METHODS IAW PLANS & SPECS

CONTROL CYLINDERS CURED IN
SAME MANNER AS IN-PLACE
CONCRETE

VERIFY 28-DAY STRENGTH TESTS
RESULTS IAW PLANS & SPECS

PERFORM INDEPENDENT
VERIFICATION/ASSURANCE TESTING
AS REQUIRED

COMPLETION

VERIFY TESTING DOCUMENTATION
FOR COMPLETION AND ACCURACY

FINAL FIELD INSPECTION
PERFORMED

REMARKS:
ALTERNATE PROJECT DELIVERY OFFICE
5/2006
FORM IPD-CL040
Page 1of 1