SCOPE OF WORK

The Scope of Project is as below:-


(a) Construction of the Project Highway on the Site set forth in Schedule A and a
s specified in Schedule-B together with provision of Project Facilities as speci
fied in
Schedule-C, and in conformity with the Specifications and Standards set forth in
Schedule-D;
(b) Operation and Maintenance of the Project Highway is in accordance with the p
rovisions of the Agreement;
(c) Performance and fulfillment of all other obligations of the Concessionaire i
n accordance with the provisions of this Agreement and matters incidental theret
o or necessary for the performance of any or all of the obligations of the Conce
ssionaire under this Agreement.
i. Construction of Four Lane Project Highway including Two Bypasses and Construc
tion of Two Lane Project Highways including Two Bypasses, as described in Conces
sion Agreement
ii. Operation and Maintenance of the Project Highway in accordance with the prov
isions of Agreement
iii. Performance and fulfillment of all other obligations of the Concessionaire
in accordance with the provisions of Agreement.
PROJECT MILESTONE
PROJECT MILESTONE
During construction period, the concessionaire shall comply with the requirement
s set forth in schedule G for each of the project mile stone and the scheduled f
our / two laning date with in 15 (fifteen) days of the date of each project mile
stone, the concessionaire shall notify to the Authority of such compliance along
with necessary particulars.
PROJECT COMPLETION SEDULE AND MILESTONE
Sr.no Milestones Period of appointment date Completion date Descript
ion Remarks
1 Milestone - I 200th day
19-April-2014 Concessionaire shall have
commenced construction
of Project Highway and
expended not less than 10
% of the total capital cost set forth in the Financial Package. Achieved
2 Milestone-II 410th day
15-Nov-2014 Concessionaire shall have
commenced construction
of all bridges and
expended not less than 35
% of the total capital cost
set forth in the Financial
Package.
3 Milestone -III 620th day
13-June-2015 Concessionaire shall have
commenced construction
of all Project Facilities and
expended not less than 70
% of the total capital cost
set forth in the Financial
Package.
4 Scheduled
Completion Date 730th day
01-Oct-2015 Concessionaire shall have
completed the Four-Lane
Project Highway in accordance with this Agreement.
PRE
CONSTRUCTION ACTIVITIES
PRE-CONSTRUCTION ACTIVITIES
STATUS OF LAND ACQUISION
Consequent to availability of land, the handing over has been completed between
authority and concessionaire as per following details, Appointed date has been d
eclares as 01st Oct. 2013 and work commenced at site as per approved programme a
nd drawings.
HANDING AND TAKING OVER