RETAINING WALL

DEFINITIONS

Topsoil Stripping :



Unsuitable Material :


Cut and Fill :


Clearing and Grubbing :


Excavation :

Concreting :

Formwork :

Lean concrete :

Weepholes :
Material on original ground usually comprising shrubs,
vegetation, roots, humus with depth as nominated in
construction drawings or specifications.

Generally soft peat, slurry and muddy material. May be of
organic composition. This material has no structural value.

These are major earthworks operations. Cut refers to the
removal of excess material to reach formation level.

Removal and excavation operation of natural material trees,
roots etc. for disposal from that area.

Excavation of soils

The use of designed concrete grade.

Mould being use to form proper shape

Grade 15 concrete

75mm PVC Pipes use to drain.























METHOD STATEMENT FOR RETAINING WALL
- 2 -

ACTIVITY

Stage 1 : Survey Works

1.1 Carry out survey earthworks to identify proper position/level of R.C wall.


Stage 2 : Excavation

2.1 Excavation to the level required.
2.2 Protect slope from falling.

Stage 3 : Lean Concrete

3.1 Lay 50mm thick lean concrete.

Stage 4 : Placement of formwork

4.1 Placement of formwork for footing.

Stage 5 : Placement of reinforcement

4.2 Placement of reinforcement in the formwork and tied up properly.
4.3 Install weepholes at specified locations

Stage 6 : Concreting works

4.4 Pour concrete to footing.
4.5 Vibrating concrete in footing

Stage 7 : Backfilling and compact earth

4.6 Backfill and spread the soil using selected backfill
4.7 Compact the soil in layers of 0.3m thick


Stage 8 : Placement of formwork for wall

4.8 Placement of formwork for the wall.

Stage 9 : Placement of reinforcement

4.9 Placement of reinforcement in the formwork and tied up properly.
4.10 Install weepholes at specified locations

Stage 10 : Concreting works

4.11 Pour concrete to wall.
4.12 Vibrating concrete in wall
METHOD STATEMENT FOR RETAINING WALL
- 3 -

Stage 11 : Strike the formworks
4.13 Strike the formwork.

Stage 12 : Backfiling and compact earth

4.14 Backfill and spread the soil using selected backfill
4.15 Compact the soil in layers of 0.3m thick

Stage 13 : Site clearance

4.16 Clear the site from all construction debris