Ian Nuttall Helge Urdal Generation Dynamic Performance Operations and Trading Background on Generator Controls Compliance process overview Project Timeline Post-Event Analysis examples Compliance process to accommodate Power Parks Main Topics Conventional Power Stations Synchronous Machines - Voltage Control Field Voltage, EFD Excitation System b c a b c Automatic Voltage Regulator a The Purpose of the AVR is to Control the Machine Terminal Voltage - This is achieved by adjusting the setting of the Excitation System which ultimately adjusts the field voltage seen by the machine In the UK it is common practice to use the AVR to fix the terminal voltage of the machine and adjust the HV Grid Voltage by tapping the Generator Transformer Generator Transformer with Tap Synchronous Machine To Grid (400 kV) Signals to Measure Terminal Voltage, Vt Conventional Power Stations Synchronous Machines - Frequency Control Grid (400 kV) Power Signal Frequency Signal Governor Control System Controlled Torque Power Turbine Frequency Control is achieved by the governor control system. The Governor will sense variations in system frequency and adjust the power output accordingly. The Governor will initiate changes to the turbine not the Machine. Power Output from Machine Single Line Representation Fuel & Air or Steam Synchronous Machine Overview of Compliance Process Technical appraisal of critical control systems and Analytical / Modelling work Compliance Testing Life-time compliance / Event Investigation / System monitoring Main Aims: Purpose of Compliance Ensure compliance with Regulatory and Commercial documents (CUSC, Grid Code, BCA, MSA) Avoid connection of plant with inherent design or commissioning defects Excitation failures can lead to: - Pole slipping or Generator instability Governor control defects can lead to - Generators responding erratically with frequency - Risk of generator trips at times of system stress Typical Project Timeline 3 Months 18 to 24 Months 6 to 12 Months Application & Offer Tender & Construction Commissioning & Approval Preliminary Studies Functional Spec. Offer Data Analysis, Model Simulation, Operational Notification Process On-site Testing Model Verification Model to Database Duration Project Milestones NGC Activities Lifetime Ongoing
Compliance System Incident Analysis Stage 1 2 3 4 Timeline Stage 1 Application and Offer Development of New Technology Liase with manufacturers on their plant compliance issues Understand changes in technology Ensure compliance process evolves to meet changes within the industry Discuss with developers the compliance issues related to any unusual proposals Application and Offer Timeline Stage 2 Tender and Construction Technical Appraisal of Generating Plant Operational Notification Process Discuss compliance issues with project developers Ensure any problems are identified and addressed early Tender and Construction Appraisal of Excitation Control Systems Excitation Control System Specification to meet the Grid Code and Bilateral Agreement Ceiling voltage Exciter type (static or brushless) With or without Power System Stabiliser (PSS) Manufacturers PSS tuning study results Appraisal of Governor Control Systems Governor System / Module Load Controller details Droop settings Target frequency setting facility Module frequency operating range 47 to 52Hz Governor deadband Load rejection / island mode operation Compliance with CC6.3.3 / BC3.7.2 Timeline Stage 3 Commissioning and Approval Compliance Testing Commissioning and Approval Compliance Testing Why do we need to test? To confirm that what is expected from the design is put in place .... and the right place! Are the systems working correctly ? Verify the stability and performance of the control systems Check the model supplied accurately represents the plant as connected Typical Excitation System Tests Open circuit and full load step responses Step test with and without power system stabiliser if applicable On load power spectrum analysis for PSS applications Under and Over-excitation limiter functionality Typical Governor System Tests On load frequency injections at a number of loading points to determine; Control System robustness Governor deadband and droop CC6.3.3 functionality Plant frequency response capability data to populate a MSA frequency response matrix Load rejection tests to determine the capability to regulate frequency in a power island Timeline Stage 4 Ongoing Compliance When do we get involved ? Event based analysis of performance Requests to changes in machines response capability Changes to key performance affecting components Ongoing Compliance Event Analysis Investigate events of non-compliance or unusual plant behaviour Check responsive plant against contract for frequency events outside operational limits For significant frequency deviations conduct a review against CC6.3.3 / BC3.7.2 requirements Good Response Performance 80% 85% 90% 95% 100% 105% 0 5 10 15 20 25 30 TIME (mins) G E N S E T
O U T P U T
( %
o f
R e g
C a p ) 49.8 49.9 50 50.1 50.2 50.3 F R E Q U E N C Y
( H z ) CAPPED COMMITTED LEVEL (MW) MEL FREQUENCY Event Analysis example (Response) Good Response Performance 80% 85% 90% 95% 100% 105% 0 5 10 15 20 25 30 TIME (mins) G E N S E T
O U T P U T
( %
o f
R e g
C a p ) 49.8 49.9 50 50.1 50.2 50.3 F R E Q U E N C Y
( H z ) CAPPED COMMITTED LEVEL (MW) EXPECTED RESPONSE (MW) MEL FREQUENCY Good Response Performance 80% 85% 90% 95% 100% 105% 0 5 10 15 20 25 30 TIME (mins) G E N S E T
O U T P U T
( %
o f
R e g
C a p ) 49.8 49.9 50 50.1 50.2 50.3 F R E Q U E N C Y
( H z ) GENSET OUTPUT CAPPED COMMITTED LEVEL (MW) EXPECTED RESPONSE (MW) MEL FREQUENCY Event Analysis example (Response) Poor Response Perfomance 80% 85% 90% 95% 100% 105% 0 5 10 15 20 25 30 TIME (mins) G E N S E T
O U T P U T
( %
o f
R e g
C a p ) 49.8 49.9 50 50.1 50.2 50.3 F R E Q U E N C Y
( H z ) GENSET OUTPUT CAPPED COMMITTED LEVEL (MW) EXPECTED RESPONSE (MW) MEL FREQUENCY Event Analysis example (Oscillations) Example of unexpected oscillations 40% 45% 50% 55% 60% 65% 70% 0 5 10 15 20 25 30 TIME (mins) G E N S E T
P O W E R
( %
R e g
C a p ) 49.8 49.9 50 50.1 50.2 50.3 50.4 F R E Q U E N C Y
( H z ) GENSET OUTPUT CAPPED COMMITTED LEVEL (MW) SEL FREQUENCY Summary Our compliance process and the team aims are to: work with Generators to achieve an understood compliance position adopt a pragmatic approach to confirming compliance witness compliance tests to confirm the expected performance investigate events which could indicate failure of plant to maintain compliance Maintaining compliance throughout the plant lifetime is vital to transmission system integrity A new Era World of Wind - What difference does it make? Compliance of Power Park Modules Key Issues Compliance task - different requirements & project characteristics Process reviewed Guidance Notes for Power Park Developers Help available to get started - site specific documentation Your feedback on process awaited Compliance task Different requirements - New issue of Grid Code Different project characteristics Thermal Power station - few large synchronous plant Power Parks - many asynchronous generators Different types of asynchronous generators Extensive use of power electronics New Grid Code - 1 June 2005 web address < www.nationalgridinfo.co.uk/grid_code/index.html > Requirements based on Point of Connection - variations size & location New topic - Fault Ride Through Projects characteristics Size range extended from 5 MW to 1000MW+ Volume of projects - 10 fold increase. Compliance Process review Fresh look at process starting with objectives. For: System Operator / Transmission Owner Generator / Developer Contractor / manufacturer Compliance moved from Generator Terminals to Point of Connection Generic Review of Type information Strong emphasis on self certification Minimise expensive site activity Less predictable source of power Consideration of part move to remote access to live data during testing Guidance Notes for Power Park Developers Guidance notes on how to demonstrate compliance - now issued web address < www.nationalgridinfo.co.uk/grid_code/mn_associated.html > Intended to provide Project Managers with clarity Practical methodology to save resources for 3 interest groups by maximising reuse of compliance material providing a clear path to Operational Notification Uniform compliance review by standardised summary & compliance sheets Help available to get you started project specific compliance sheets - removes N/A requirements Compliance .... and at sea On land . Any questions about Compliance for Generators - Contact us We will both be around through lunch In NGT House in Warwick By telephone to the team phone on (01926) 654601