BOS IV&V Monthly Status Report

Deliverable 5.4.2.4
Reporting Period:
September 1 October 31, 2013

www.pcgtechnologyconsulting.com
BOS Monthly Status Report
Topics
Project Summary
IV&V Activities Summary
IV&V Risks Summary
Planned Activities for Next Reporting Period
BOS IV&V Monthly Status Report 2
IV&V Project Summary
BOS IV&V Monthly Status Report

3
This section provides the consolidated status of IV&V and Quality Assurance activities in the table
below:
Project Area* Risk
Status
IV&V Observations
Project Planning and
Administration
IV&Vs ability to assess vendor project planning and administration activities has been
constrained by the lack of visibility into these activities. While IV&V, Xerox and the SSHIX
staff attended bi-weekly Steering Committee meetings, many of these formal status meetings
were significantly abbreviated during this reporting period in order for Xerox to address
critical project concerns. IV&Vs access to project documentation has been minimal and
participation in ad hoc meetings limited.
Although Xerox presented an updated project schedule during this reporting period, most
critical milestones were not met and project delays occurred.
Requirements Specification /
Validation & Requirements
Specification Document
Significant failures occurred during integration testing which indicated a lack of coordination
between BOS and HCR-EE requirements definition, resulting in additional coding, testing,
and frequent builds.
In August, Xerox agreed to provide system extracts and update system documentation to
provide additional requirements traceability information to IV&V, which has yet to occur. As a
result, IV&V could not trace the BOS requirements to any of the testing results as of the date
of this report.
Data Retention Recovery
Protection and Management Plan
No change: IV&V Data Retention Recovery Protection and Management Plan review
completed; no risks identified at this time.
Hosting Plan No change: Hosting Plan review completed; no risks identified at this time.
* Project areas assessed depend on the deliverables that are available for review per the DD&I project schedule.
M
NA
NA
M
IV&V Project Summary (Continued)
BOS IV&V Monthly Status Report

4
Project Area Status IV&V Comments
Project Management Plan
(PMP)
IV&V has identified multiple risks (see IV&V Assessment workbook) in this area, which the State has
chosen to accept. IV&V continues to keep these risks open, however, to track the overall affect to the
project.
Risk Management IV&V continues to experience limited insight into formal risk management practices performed on behalf
of the project and believes that the project is not implementing best practices in relation to identifying,
tracking and mitigating project risks.
Implementation IV&V participated in BOS implementation meetings 3-times per week leading up to implementation,
which provided IV&V additional insight into the project.
As 10/1/13 approached, concerns arose over the projects ability to go live on time. As a result, the NV
Governors Office stepped in to monitor the project. In one of the meetings, alternatives were presented
to delay implementation, which was rejected by the Governors Office. The BOS went live on 10/1/13
with (known) missing functionality, undefined business processes and incomplete testing, (including
CMS Blueprint testing). After implementation many critical defects were identified that required multiple
production builds. In the coming days / weeks IV&V believes that the project needs to prioritize defects
to be fixed, outstanding functionality to be implemented, and develop a schedule for doing so.
M
NA
H

IV&V Project Summary (Continued)
BOS IV&V Monthly Status Report

5
Project Area Status IV&V Comments
Test Management
User Acceptance Testing
Xerox completed wave testing as required by CMS and IV&V submitted the States Attestation Letter in
accordance with CMS regulations. BOS did not fully complete end-to-end testing by 10/1/2013 and
therefore IV&V was unable to fully assess if testing was successful during this reporting period.
The project did not complete Blueprint testing by 10/1/31 (with CMS approval), which has yet to be
scheduled as of the date of this report.
As IV&V had limited insight into the BOS User Acceptance Testing (UAT) process, IV&Vs assessment
in this area is based on the results of wave testing and defect reporting.
Interfaces Delayed design and development of interfaces created delays in testing and coordinated mapping of
data. Since implementation, the project continues to identify data errors in the interfaces which could
not be identified before implementation due to the delays in interface development.
Release Management While IV&V completed its assessment of Xeroxs Release Management Plan several months ago,
release management is not scheduled to start until the BOS is in full production.
Defect Management BOS & HCR-EE are co-managing defects identified during testing. Teams do not share a defect
repository but are executing a process to ensure defects are recorded in each tool to ensure
coordination of identified defects.
Status has been updated to high due to the fact that a number of high magnitude critical defects
continue to occur.
Configuration Management No change: Configuration Management Plan released.
NA
NA
H
M
H

IV&V Project Summary (Continued)
Project Area Status IV&V Comments
Change Management No change: Change Management assessment completed.
Performance and Scalability
Plan
IV&Vs system assessment of Performance and Scalability has been delayed to allow project resources
to focus on development of the BOS.
Security Management Single sign-on (SSO) functionally is still in development. The BOS has escalated this problem for
resolution. Lack of SSO negatively affecting testers ability to successfully complete testing. Should
SSO functionality not be feasible, workarounds will be required.
IV&V reviewed 3
rd
party vendor security assessment to determine if vendor fulfilled contractual
obligations. No issues identified. IV&V is monitoring security related artifacts and has offered
assistance, if needed.
Detailed System Design Xeroxs second version of the SDD did not address significant issues/concerns that were raised in the
initial reviews of the draft documentation. IV&V rejected this version of the SDD and recommended that
the State do the same. IV&Vs assessment cannot be completed with the limited information provided
in this document. The SDD does not follow standard guidelines for acceptable design documentation. If
a well-documented and more complete version of the SDD is not delivered, the State will be unable to
determine if the BOS was built as designed.
NA
NA
L
M

IV&V Project Summary (Continued)
BOS IV&V Monthly Status Report

7
Project Area Status IV&V Comments
Contingency Planning: The State should define contingency workarounds/processes and stakeholder communications based
on limited functionality available for 10/1/2013 implementation date. Work efforts should be coordinated
with HCR-EE to ensure all issues are resolved before implementation.
Status has been updated to medium. The BOS was implemented with multiple workarounds (i.e. paper
applications) due to missing functionality. The State has not provided updated contingency plans to
IV&V for review.
Risk Assessment Rating Legend

Not Applicable Low Medium High Completed L M H NA C
M

IV&V Activities Summary (Continued)
BOS IV&V Monthly Status Report

8
IV&V activities completed in the current reporting
period:
Participated in Exchange Steering Committee Meetings
Attended conference calls and webinars with CMS/CCIIO as appropriate
Participated in test planning including UAT, BluePrint, and joint HCR-EE / BOS testing
meetings
Testing ongoing and attestation letters submitted as required by CMS
Monitoring UAT testing progress
Attended daily defect meetings
Attended daily BOS programmer status meetings
Attended UAT progress meetings
Attended Governors Aide status meeting
Attended defect prioritization planning meetings






BOS IV&V Monthly Status Report

9
Contractors Project Management
e-pm.51122 Scope Management
e-pm.51235 Schedule (Time) Management
e-pm.51237 Contingency Planning
e-pm.52054 Implementation Communication Logistics
e-pm.52067 Business Continuity Plan Lacks Business Operations
Representation
e-pm.52068 Command Center Model/Communications Difficulties
e.pm.52069 Implementation Activities/Objectives
e.pm.52070 Exchange Business Readiness
Testing
e-te.52073 UAT Defect Management
Security
b-se.52061 System Security Plan and Safeguards Procedure Report








IV&V Risks
A recap of the risks listed in the Monthly IV&V Assessment Workbook is provided
below:
BOS IV&V Monthly Status Report

10
IV&V Assessment Metrics
The IV&V assessment metrics provide a summary of the risks and findings reported
in the IV&V Assessment Workbook.
Base Risk Metrics:
Total Open
22
Total Closed
1
Total Accepted
0
Total Updated
8
Total Closed (30-day)
0
Total Open (30-day)
0
Note: 30-day period since last status
update
Total Open
71%
Total Closed
3%
Total
Accepted
0%
Total
Updated
26%
Total Closed
(30-day)
0%
Total Open
(30-day)
0%
Risks
BOS IV&V Monthly Status Report

11
IV&V Assessment Metrics
The IV&V assessment metrics provide a summary of the risks and findings reported
in the IV&V Assessment Workbook.
Project Management
11
Requirements
0
Quality
0
Operating Environment
0
Design & Development
0
Testing
8
Data Management
0
Security
1
Open Risks by Section:
0
2
4
6
8
10
12
N
o
.

o
f

R
i
s
k
s

Risk Sections
Open Risks by Section
BOS IV&V Monthly Status Report

12
IV&V Assessment Metrics
The IV&V assessment metrics provide a summary of the risks and findings reported
in the IV&V Assessment Workbook.
Total Open
79
Total Closed
240
Total Accepted
0
Total Updated
0
Total Closed (30-day)
0
Total Open (30-day)
1
Base Findings Metrics:
Note: 30-day period since last status update
Total Open
25%
Total Closed
75%
Total Accepted
0%
Total Updated
0%
Total Closed
(30-day)
0%
Total Open
(30-day)
0%
Findings
IV&V Planned Activities







BOS IV&V Monthly Status Report

13
The following activities are planned for the next reporting period:
Continue participation in Exchange Steering Committee Meetings
Continue onsite presence when required
Participate in BOS daily status meeting
Initiate IV&V system assessments
Continue IV&V testing validations
Continue with Xerox deliverable reviews
Monitor defect resolution and Fast Follow development



BOS IV&V Monthly Status Report

14
Public Consulting Group Technology Consulting
2150 River Plaza Drive, Suite 380 Sacramento, CA 95833
(916) 565-8090 www.publicconsultinggroup.com