CONSUMER CONNECTION

CHARGES CALCULATIONS
-In conjunction with tariff restructuring-

13
th
September 2011
NEW CCC




Consumer Connection Charge = A + B + C + D
where:

A = Project Cost (Material + Petty Contract + Labour + Transportation)
B = Development Charge (20% of A)
C = Processing Fee (RM 100)
D = Zoning Charge (if applicable for greenfield areas where electricity
infrastructure is not yet available or improvement to existing system is carried out
by SESB at its own cost first )

2

CURRENT CCC -BACKGROUND

Presently consumers are charged full contribution or full project
cost for electricity supply connections due to the low tariff rates
which resulted in the inability to recover the project cost through
tariff.
RETURN ON CAPITAL INVESTMENT FORMULA:

Rate of Return :-

a) If EAR APC = + ANP and > 1/3 Project Cost,
then Consumer only pay Development Charge.

b) If EAR APC = + ANP and < 1/3 Project Cost,
then Consumer to pay Total Project Cost and Development Charge
minus 3 times of EAR.

c) If EAR APC = - ANP (loss),
then Consumer to pay Total Project Cost and Development Charge.


Note:

Project Cost is based on AKM.
EAR: Estimated Annual Revenue (based on new tariff)
APC: Annual Production Cost (a.k.a Cost Per Unit)
ANP: Annual Nett Profit



CURRENT CCC -BACKGROUND

The financial position of SESB is expected to improve with the
forthcoming tariff restructuring and therefore the Consumer
Connection Charges (CCC) has been approved for implementation
in January 2012 by KeTHHA.

Consumer Connection Charges (CCC):
Consistent with the State Governments efforts to spur economic
development and taking into consideration the concern on the high
up-front capital investment cost borne by new consumers, it is
proposed that consumer connection charges to qualified category
of consumers be reduced up to 50% of the project cost; against the
current practice of 100%.

The qualified category of consumers shall be determined based on
location and distance of new consumers from the nearest SESB
source of supply.

(Note : Rural residential consumers not qualified under this category shall be treated
under existing Government Rural Electrification (BELB) programme where 100% of the
project cost is borne by the Government.)

4

NEW CCC -PROPOSAL



Consumer Connection Charge = A(0.5) + B + C + D + E

where:

A = Project Cost (Material + Petty Contract + Labour + Transportation)
B = Special Features (if any)
C= Development Charge (10% of A)
D = Processing Fee (RM 100)
E = Zoning Charge (if applicable for greenfield areas where electricity
infrastructure is not yet available or improvement to existing system is carried out
by SESB at its own cost first )

5

NEW CCC -PROPOSAL

Consumers to be charged 50% of project cost for electricity
supply connections.
A. Project Costing Estimate
AKM (Anggaran Kerja Modal)
CAPITAL COST OF INSTALLATION RM
A. Project Cost 326,168.82
Calculation for Project Cost:
Substation 232,362.47
HV UG 35,824.92
HV OH (Bare & ABC) 40,423.24
LV UG 15,648.52
LV OH (Bare & ABC) 1,133.15
Service Line (V.Main & Cutout) 776.52
B. Special Features (50% of cost if any) 25,000.00
C. Others 32,716.88
Calculation for Others:
10% Development Charges
32,616.88
Processing Fee (Revision of AKM)
100.00
ZONE CHARGE (if any)
-
D. 50% of A 163,084.41
E. SESB Capex (D-B) 150,584.41
F. Consumer Connection Charges (B+C+D) 208,301.29
G. GRAND TOTAL WBS Element (E+F) 358,885.71
PROJEK MEMERLUKAN TAPAK PENCAWANG

Bagi projek di mana tapak/tanah diperlukan bagi pembinaan pencawang
(PMU/PPU/SSU/PE), pemohon/pemaju adalah dikehendaki menyediakan
tapak/tanah serta bangunan pencawang menurut polisi dalam ESAH.





A. Project Costing Estimate
AKM (Anggaran Kerja Modal)
Land/Building Size Requirements For Sub-station
Substation Category Type

Land Size
Building Design

Transmission Main Intake /
Pencawang Masuk Utama
(PMU)
-132/33/11kV

Gas Insulated Switchgear (GIS)
Without outdoor switchyard
1.5 acre
Customized design subject to
SESB approval

Conventional
3 acre
Customized design subject to
SESB approval
Main Distribution Substation
(PPU)
- 33/11kV

Indoor type

45m x 45m
(150' x 150')
Customized design subject to
SESB approval
Outdoor switchyard
Main Switching Substation
(SSU)
- 33kV & 11kV
Conventional 12m x 12m
Customized design subject to
SESB approval (with
inclusion of meter room)
Distribution Substation (PE)
- 11/0.400kV
(a) Single chamber

16.5m x 13.5m
(55' x 45')
According to SESB design
(b) Double chamber
20m x 13.5m
(65.5'x 45')
According to SESB design
(a) Compact Substation Subject to SESB approval For special case application
(a) Outdoor
10' x 10'
15 x 15
20' x 20'
Limited to those located in
the rural areas. Substation
size proportional to
transformer capacity.



Land/Building Size Requirements For Sub-station
Area Title Type
Urban
Land Indoor
Strata Indoor/compartmental
Town Centre
Land Indoor
Strata Indoor/Compartmental
Rural Land Outdoor
Industrial Land
Indoor up to 1000kVA
Custom >1000kVA
B. Special Features

Caj Skema Bekalan Ciri Khas (Special Features)

Prinsip adalah untuk sistem lazim yang berpandukan kepada Electricity Supply Application
Handbook (ESAH) dan Distribution Planning Guideline 2009 SESB.

Jenis skema pepasangan yang tidak mengikuti skema bekalan lazim SESB adalah seperti berikut:-

i) Kabel serbis bawah tanah untuk pengguna 1 fasa atau skema kabel bawah tanah menyeluruh
(full underground scheme).

ii) Kerja-kerja Horizontal Directional Boring (HDD) yang perlu dilakukan untuk merentang kabel
bawah tanah sepanjang jalan atau merentas jalan pada laluan dua hala atau kurang.

iii) Kerja mengesan pepasangan utiliti sediada dalam tanah (Utility Mapping) yang mungkin
dikenakan oleh pihak berkuasa tempatan sebelum permit rentangan kabel projek diberikan.

iv) Kerja menurap penuh jalan (Mill & Pave) melebihi had kerja korekan dan tampalan yang
dilakukan setelah kerja penanaman kabel selesai. Memenuhi sepenuhnya spesifikasi
penurapan jalan oleh Jabatan Kerja Raya atau Pihak Berkuasa Tempatan.

v) Penggunaan pencawang padat (Compact Substation) untuk projek bekalan.


Scenario 1:
Scenario 2:
Scenario 3:
Standard feature: Single phase OHL
(1) Special feature: Single phase UGC 4C
(2) Standard feature: Three phase UGC 4C
A - Special feature: Single phase UGC 4C
B - Standard feature: Single phase OHL
P.E.
P.E.
FP
HOUSING DEV.
B. Special Features
Low Voltage Cable
Underground scheme for single phase customer


B: Special Features : calculation


Pengiraan caj ciri khas untuk perkara (i) dan (v) di atas;

Caj Skema Ciri Khas = Anggaran Kos Ciri Khas Anggaran Kos Ciri Lazim

Bagi permohonan yang memerlukan ciri-ciri khas di atas, SESB hanya membiayai
kos berdasarkan prinsip-prinsip sistem lazim saja manakala pemohon dikehendaki
membayar kos selebihnya.

Pengiraan caj ciri khas untuk perkara (ii), (iii) dan (iv) di atas;

Caj Skema Ciri Khas = 100% Anggaran Kos Ciri Khas




C: Project Costing Estimate - Others
i. Caj Pembangunan adalah caj untuk membiayai sebahagian Upstream cost,
iaitu penyediaan prasarana Penghantaran (Voltan Tinggi) & Penjanaan
(Transmission Lines & Power Generation).

Formula Caj Pembangunan (Development Charge) adalah seperti berikut:-

1) Pengguna Kategori 1: 10% daripada Kos Projek bagi komponen
downstream projek, iaitu tahap voltan 33kV dan ke
bawah.
2) Pengguna Kategori 2: 10% daripada Kos Projek
3) Pengguna Kategori 3: Tidak dikenakan

ii. Yuran Pemprosesan

Yuran untuk memproses permohonan bekalan elektrik dan ditetapkan pada
RM100 untuk setiap permohonan. Juga dikenakan setiap kali terdapat
perubahan pada AKM disebabkan kerana perubahan cadangan teknikal
dari pihak pengguna atau kerana kelewatan pengguna membayar caj
sambungan pengguna sehingga menyebabkan Anggaran Kerja Modal baru
perlu dibangkitkan.




C: Project Costing Estimate - Others
iii. Caj Pengezonan (Zoning Charge)

Caj yang dikenakan apabila projek baru terlibat dengan projek peningkatan
sistem (umpamanya penyuap baru atau penambahan beban alatubah)
yang telah / akan dibiayai oleh SESB bagi kawasan tersebut dan dicaj
berdasarkan RM/kVA berdasarkan Kehendak Maksima dipohon dan
designed loading capacity talian/pencawang tersebut.






b) Zoning Charge
Zoning Charge: Terms
Maximum Demand subjected to Zoning Charge :

1) For Medium Voltage Cable: Applicable to consumer with MD >=300kW
(Note: 70% supply application in this range)
- Installations include RMU and Transformer (i.e tapping to Medium Voltage line)
- Indicates Affordability (no victimization)

2) For Transformer ITC: Applicable to consumer with MD > 50kVA
- For easy record tracking & avoid contradiction to new CCC

3) Propose exception to:
- Rumah Ibadah, Rumah Kos Rendah (with letter from Housing Ministry ) & Sekolah.
(note: refer Kategori Pengguna with 10% discount on tariff restructuring)

4) File will be closed when either 100% cost recovered or after 7 years (from system
improvement project completion)

b) Zoning Charge
1) ITC Increase Transformer Capacity




(RM) cost SI
Capacity Tx
applied MD
Charge Zone
Example: ITC cost = RM100k
New MD = 100kVA



loading) (100% 20k 100k
500
100

ITC to
Zoning Charge Transformer ITC

2) Transformer under contingency


Example : Construction Cost = RM 2mil
New MD = 10MVA
Zoning Charge Transformer Contigency
(RM) cost SI
Capacity Tx
applied MD
Charge Zone
33kV

11kV
loading) (100% RM0.666mil 2mil
2x30(0.5)
10

3) Cable Capacity
Cable Size (mmp) MVA CCC (Amps)
300 6.7 400
240 5.5 340
- Cable rating to be standardize throughout (Sabah & Labuan F.T)
Scenarios:
1) Existing System Overload System Improvement Future including New Load
2) Existing System Normal System Improvement done in the past
Ideal feeder loading
Overloading feeder
with MSVT needed
Note: Standard Current CT ~ 300/5A
Zoning Charge System Improvement (cable)
Example : System Improvement Cost= RM 500k
New MD = 2MVA

loading) (100% RM182k 500k


5.5
2

CATEGORY 1
CATEGORY 2
CATEGORY 3
Capital works involving construction of 33kV system & above
Capital works involving construction of 11kV system

New service Connections involving Low Voltage connections
(below 1 kV only)
NEW CCC PROPOSAL Category 1
CCC will be considered on individual basis, and calculated principle of cost recovery over 3
years period
Definition:
Consumer Connection Charges (CCC) are the charges for electricity supply
applications and are divided into the following categories :-
MAXIMUM DEMAND
15MVA 30MVA 5MVA 15MVA > 30MVA
System can
sustain without
PMU
System cannot
sustain without
PMU
a-PPU b-SSU
ZC ROR
PMU &
PPU
ZC ROR
a-SESB
need PPU
Bulk
11kV
ZC ROR ZC ROR
b-SESB do
not need
PPU
Bulk
33kV
SESB need
PMU
SESB do
not need
PMU
[1S] [1B] [BU] [SWI] [POIC] [SFI~40MW]
Bulk 33kV : 10MVA < x < 15MVA
Bulk 11kV : 10MVA (limit to maximum 2 x 500mmp1C Al. Feeders)
Definitions: a) standard scheme = mirror +LILO
b) single customer = 1 compound/land title & 1 owner
Note:-
single customer
multiple customer
CASE STUDY ROR Category 1
1 Borneo 33kV Bulk Customer
Category No. Of Customers kW/house kWh/house/month RM/house/month RM Total/year
Domestic: 1 2.66 478.39 127.74 1532.88
1008 2681.28 - - 1,545,143.04


MD (kW)
Energy
Consumption
kWh/month
Energy
Consumption
RM/month
MD Charges
RM(kW)/month
RM (Total)
/month RM Total/year
Overall
Tariff
13198 8,116,770
Commercial :

11,464
Hotel Best Western
CM1
- 114,490 32,057.20 - 32,057.20 384,686.40
Tune Budget Hotel
CM1
- 52,658 14,744.24 - 14,744.24 176,930.88
Mercure Hotel Tower (12storey)
CM2
624 302,296 84,642.88 11,544.00 96,186.88 1,154,242.56
Novotel Hotel Tower (12 storey)
CM2
1,177 588,991 164,917.48 21,774.50 186,691.98 2,240,303.76
TNB Chiller
CM2
2,419 1,138,634 318,817.52 44,751.50 363,569.02 4,362,828.24
Other (Submeter metered by 1B)
CM2
8,841 5,437,481 1,522,494.68 163,566.50 1,686,061.18 20,232,734.16


Total

28,662,019.70
Keterangan RM
Kos Projek 5,000,000.00
1/3 Kos Projek 1,670,000.00
10% Dev Charges 500,000.00
Jumlah Kos Projek 5,500,000.00
Keterangan RM
Anggaran Hasil (AH) 30,207,162.74
Kos Pengeluaran Tahunan (KP) 30,739,831.34
Hasil Bersih (HB) (532,668.60)
*HB (Kerugian) Pengguna dikehendaki membayar kos
keseluruhan projek serta caj pembangunan
1 Borneo 33kV Bulk Customer
CASE STUDY ROR Category 1
Maximum Demand : 6,594kW
: 7.76MVA
Carrying Capacity for 2cct x 630mm2 1C
UGC XLPE Alu at 50% : 2 x 30 x 0.5 MVA
: 30MVA
Total Project Cost : RM12,678,980.00
Zoning Charge : 7.76
30.00 x RM12,678,980.00
= 25.86% x RM12,678,980.00
= RM3,278,635.06
1) Zoning Breakdown for Substation & UGC & Fibre
Optic Cable
2) Processing Fee
3) 11kV UGC Service Cable
4) 11kV 20% Dev Charges
Consumer Contribution Charges (CCC)
RM3,278,635.06
RM100.00
RM19,340.00
RM3,868.00
RM3,301,943.06
CASE STUDY ZC Category 1
1 Sulaman PPU Sharing Concept bulk 11kV
M M
PPU 1Sulaman
(SESB)
Consumer
2x30MVA
spare spare
PMU
Full Project Cost
(SESB Cost)
Project Need Cost
(Zoning to
Customer)
Consumer portion
(100% full cost)
Permohonan Baru dan Penambahan Beban

Caj Minima Bulanan Projek (Project Minimum Monthly Charge) dan Bayaran
Gantirugi Beres (Liquidated Damages) adalah dikenakan bagi permohonan Kategori
1.

Project Minimum Monthly Charge (PMMC)

Bayaran ini dikenakan ke atas pengguna demi untuk memastikan modal yang
dilaburkan SESB memberi pulangan minimum yang diperlukan. Ia berdasarkan
kepada 3.15% daripada Kos Bersih Modal projek bekalan. Ia dikenakan untuk
tempoh 3 tahun pertama bekalan sekiranya bil bulanan kurang daripada PMMC
tersebut.

PMMC = 0.0315 x (KP CB)

Di mana KP = Kos Projek,
CB = Caj Bersih = Caj Sambungan Pengguna Caj Pembangunan
Yuran Zoning Charge (jika ada)
(KP CB) = Kos Bersih Modal projek
NEW CCC PROPOSAL Category 1
Project Minimum Monthly Charge
(PMMC)
PMMC = 0.0315 x (KP-CB)

Where: KP is the capital cost of the project
CB is the connection charge paid by the developer or consumer,
less Development Charge, Processing Fee, Zoning Charge paid
(KP-CB) is the Net Capital Cost of the project
PMMC = 0.0315 x (KP-CB) + A

Where: KP is the capital cost of the project
CB is the connection charge paid by the developer or consumer,
less Development Charge, Processing Fee, Zoning Charge paid
(KP-CB) is the Net Capital Cost of the project
A is the 6 months average of the customer bill.
Permohonan Baru

Gantirugi Beres (Liquidated Damages)

Gantirugi Beres adalah terpakai bagi pengguna yang gagal atau tidak
dapat mengambil bekalan untuk 3 tahun selepas menandatangani kontrak
bekalan.

Asas pengiraan kuantum Gantirugi Beres adalah seperti berikut:

Bagi setiap bulan yang kurang dari tempoh 3 tahun, pengguna
dikehendaki membayar 1/36 dari Kos Bersih Projek, tertakluk kepada had
maksima iaitu separuh dari Kos Bersih Projek.

Pada amnya, Gantirugi Beres = 1/72 x Kos Bersih Projek (36 n)
= (36 n) x (KP CB)
72
NEW CCC PROPOSAL Category 1
LD = (36-n) x (KP-CB)
72
Di mana:
KP = Kos Projek
CB = Caj Bersih = Caj Sambungan
Pengguna dibayar - Caj Pembangunan
dibayar Yuran Zoning Charge
n = bilangan bulan selepas bekalan
diberi
Gantirugi Beres (Liquidated Damages)
CADANGAN PENGENAAN CCC
CAJ SAMBUNGAN PENGGUNA - KATEGORI 1
CATEGORY 1
CATEGORY 2
CATEGORY 3
Capital works involving construction of 33kV system & above
Capital works involving construction of 11kV system

New service Connections involving Low Voltage connections
(below 1 kV only)
Definition:
Consumer Connection Charges (CCC) are the charges for electricity supply
applications and are divided into the following categories :-
CCC will be reduced 50% based on standard design project cost. Special features will be at
consumers cost.
NEW CCC PROPOSAL Category 2



1) Loop In Loop Out (LILO) Scheme is standard scheme and is compulsory
for the following important customers such as:
Airport, Hospital, VVIP, Istana, Mahkamah, Majlis Daerah, etc.

a) Pole mounted transformer connection scheme is exempted from
LILO provided the distance from the existing/main line is < 250m or
1 cable drum length.

b) Other factors to consider for the usage for the LILO scheme is the
number of customer affected during outage (SAIDI mins)







NEW CCC PROPOSAL Category 2
CATEGORY 2
Capital works involving construction of 11kV system
CATEGORY 2
Capital works involving construction of 11kV system
NEW CCC PROPOSAL Category 2
The connection charge of 50% for the category 2 consumer is applicable only for
request not more than than 6 kilometre(KM) away from the nearest available
supply (that could meet the demand). The term available means the nearest
supply that will meet the requested load.

Should the distance exceed 6 kilometre, then the consumer will need to pay full
cost of the additional length.


SESB
Customer
OR
m
m
SESB
Customer
scheme
2. 11kV Bulk Customer must have SESB SSU 11kV then to Customer
breaker (mirror image concept)
NEW CCC PROPOSAL Category 2
CATEGORY 1
CATEGORY 2
CATEGORY 3
Capital works involving construction of 33kV system & above
Capital works involving construction of 11kV system

New service Connections involving Low Voltage connections
(below 1 kV only) *
*Single phase consumers requiring only service line to existing pole will be connected free of charge.
CCC for other consumers will be reduced 50% based on standard design project cost.

(Applicants who qualify for BELB, i.e. long distance from existing lines and estimated project cost is greater than
RM50,000 would be excluded).

NEW CCC PROPOSAL Category 3
Definition:
Consumer Connection Charges (CCC) are the charges for electricity supply
applications and are divided into the following categories :-
Scenario Project
Cost
(RM)
Technically
Viable
CCC Calculation Method
1 >50k Yes 50% of RM50k & 100% of remaining
eg. House 1.5kW (domestic)
Petronas Pipe Gas Control Valve 1.5kW (commercial)
2 <50k Yes 50% project cost
3 >50k No Option 1: Upgrade to Category 2 (50% project cost)
Option 2: Unable to supply to consumer (offer non-grid)
4 <50k No Option 1: Zoning +50%
Option 2: 50% all the way eg. Telco tower project
a) Table of scenarios for category 3:
CCC Category 3 Calculation Basis
Note: Technically Viable means available supply could meet the demand without
compromising the system stability with ease of system operation and maintenance






Calculation:
50% project cost up to RM50k = Rm25k
100% project cost the remaining onwards = RM88k-RM50k=RM38k
Total ccc = RM25k + RM38k = RM63k

Scenario 1:

CCC Category 3 Calculation Basis


Standard feature: Single phase OHL (free) +
50% of 500m




Scenario 2:
CCC Category 3 Calculation Basis
Option 1: Upgrade to Category 2
Scenario 3:
CCC Category 3 Calculation Basis
Option 1: Zoning + 50%
Example 1: System MV experience Low Voltage & Need Booster
Zoning charge on Booster + 50% project cost
Option 2: 50% all the way
Example 2: System LV experience Low Voltage eg. Telco tower project
Scenario 4:
CCC Category 3 Calculation Basis
Bayaran permulaan berjumlah RM30,000.00 atau 50% daripada
keseluruhan bil, yang mana lebih tinggi dan bakinya diberi maksima empat
(4) bayaran ansuran
Selepas bayaran pendahuluan atau ansuran pertama, setiap ansuran
berikutnya hendaklah dikenakan kadar faedah sebanyak 1% ke atas jumlah
bayaran ansuran berkenaan (ke atas jumlah keseluruhan yang belum
dibayar).
Contoh 1:

Jumlah Caj Sumbangan Modal = RM160,000.00
Bayaran pendahuluan (ansuran 1) = RM80,000.00
Bayaran ansuran 2 {RM20,000.00 + 1%(RM80,000.00)} = RM20,800.00
Bayaran ansuran 3 {RM20,000.00 + 1%(RM60,000.00)} = RM20,600.00
Bayaran ansuran 4 {RM20,000.00 + 1%(RM40,000.00)} = RM20,400.00
Bayaran ansuran 5 {RM20,000.00 + 1%(RM20,000.00)} = RM20,200.00


CCC Installments

Sekiranya ada kelewatan hingga melangkaui bulan berikutnya, tambahan kadar
faedah 1% akan dikenakan ke atas jumlah bayaran ansuran berkenaan (ke atas
jumlah keseluruhan yang belum dibayar).

Kerja-kerja di tapak akan dimulakan selepas pembayaran ansuran yang pertama

Projek bekalan tidak akan dimulatugas selagi keseluruhan caj sambungan
pengguna tidak dibayar.

CCC Installments

Caj Sambungan Pelbagai

i) Bagi permohonan yang tidak melibatkan penambahan beban; umpamanya
penukaran paras voltan, penukaran tarif antara pengguna komersil/industri,
penukaran kepada cogenerator dan sebagainya, caj penuh akan dikenakan.

Nota : Caj Pembangunan tidak dikenakan bagi permohonan tersebut

ii) Bagi permohonan yang tidak melibatkan penambahan beban, umpamanya
pemindahan talian/kabel serbis atau unjang dan sebagainya (tidak disebabkan
usang/rosak), caj penuh akan dikenakan.

CCC - Miscellaneous


TEMPOH SAH BAGI CAJ SUMBANGAN MODAL

Setiap Caj Sumbangan Modal yang dikeluarkan hanya sah untuk tempoh empat (4)
bulan dari tarikh ianya dikeluarkan.

Jika pemohon hendak membuat pembayaran selepas tempoh tersebut, caj yang baru
akan dikeluarkan menurut harga terbaru bahan-bahan.

Yuran pemprosesan RM 100 akan dikenakan untuk setiap ulangkaji dan dimasukkan di
dalam Caj Sambungan Pengguna yang baru.

CCC Validity Period

CAJ SUMBANGAN MODAL BAGI KERJA YANG DILAKUKAN SENDIRI OLEH PEMAJU (TURNKEY PROJECT)
Pihak pemaju adalah dibenarkan untuk melaksanakan sendiri kerja-kerja pembahagian HV/LV di dalam
kawasan yang dimajukan mereka.

i. Bagi projek di mana pihak pemohon/pemaju diberi kelulusan untuk perlaksanaan secara konsep
turnkey, pemohon/pemaju akan dibayar balik amaun Kos Projek yang dibiayai oleh mereka,
berdasarkan prinsip pengiraan Caj Sambungan Pengguna seperti di atas.

Nota : Kos Projek akan berdasarkan AKM (Anggaran Kerja Modal) SESB dengan kadar
harga SESB atau harga barangan pemohon/pemaju, di mana yang lebih murah.

ii. Pihak pemohon/pemaju juga dikenakan Caj Pembangunan (B), Yuran Pemprosesan (C) dan
Zoning Charge (D) (sekiranya ada).

iii. Proses permohonan dan perlaksanaan projek secara Turnkey adalah merujuk kepada pekeliling
sediada.


CCC - Turnkey
CAJ SUMBANGAN MODAL BAGI KERJA YANG DILAKUKAN SENDIRI OLEH PEMAJU (TURNKEY PROJECT)





CCC Turnkey Calculation
CAPITAL COST OF INSTALLATION RM
A. Project Cost 326,168.82
Calculation for Project Cost:
Substation 232,362.47
HV UG 35,824.92
HV OH (Bare & ABC) 40,423.24
LV UG 15,648.52
LV OH (Bare & ABC) 1,133.15
Service Line (V.Main & Cutout) 776.52
B. Special Features (50% of cost if any) 25,000.00
C. Others 32,716.88
Calculation for Others:
10% Development Charges
32,616.88
Processing Fee (Revision of AKM)
100.00
ZONE CHARGE (if any)
-
D. 50% of A 163,084.41
F. Consumer Connection Charges
(B+C+D)
208,301.29
i. Turnkey Cost Borne by
Developer for substation works
= RM 250k

ii. 50% Developer Substation Cost
= RM 250k/2
= RM 125k

iii. 50% Cost Sharing
= RM 232,363.47/2
= RM 116,181

Hence; payment to Developer
= RM116,181
in accordance to SESB project cost
whichever cheaper


ESAH Addendum

Penambahan dan perubahan syarat serta kriteria para 3.4Supply
Project Lead Time dan para 4.1 Maximum Demand Levels and Supply
Schemes bagi memperjelaskan skim keperluan beban daripada
pengguna dan cara penyambungan bekalan kepada pengguna serta
anggaran tempoh perlaksanaan projek bekalan.

Kelulusan daripada mesyuarat MTCC ke-56 yang bersidang pada 20hb
September 2010 adalah dirujuk.


ESAH Addendum
Requirement Supply Project Construction Lead Time
(from CCC payment date)
132 kV and above 4 years
33 kV 2 years
11 kV 8 months
Requirement Supply Project Typical Lead Time
132 kV and above 3 years 5 years
33 kV 1 year - 3 years
11 kV 1 year
ESAH Addendum
Maximum Demand Levels and Supply Schemes

The table below indicates the typical schemes for various demand levels of individual consumers. In the
case of maximum demand (M.D) ranges of 5MVA to 10MVA, the supply voltage options of either 11 kV or
33kV will ultimately be determined by the predominant supply voltage where the prospective consumer is to
be connected. Consumer with M.D of 700kVA and above have to take supply at 11 kV.
M.D. ranges of individual
consumer
Supply
Voltage
Typical Supply Scheme
Up to 23kVA 230V* Overhead services from mains
23kVA to 70kVA 400V*
Three phase overhead or underground
cable service from existing mains
70kVA to 700kVA 400V*
Direct cable service from Substation
Feeder Pillar
700kVA
#
to 5000kVA 11kV
Directly fed through SESB 11kV
switching station
5000kVA to 15000kVA 33kV
Directly fed through SESB 33kV
switching station
Above 15000kVA 132kV
Directly fed through SESB 132kV
switching station respectively
CCC Proposal
Actions needed:-

1) Award M&E Consultant within the required lead time:-
-12 months for 11kV supply
- 36 months for 33kV supply
- 60 months for 132kV supply & above

2) Submit Complete Electricity Supply Application to SESB by February of every for
SESB budget purposes for supply in September onwards


Thank You