100%(1)Il 100% ha trovato utile questo documento (1 voto)
80 visualizzazioni92 pagine
This dissertation provides comprehensive details of productivity improvement through One-piece Flow implementation in MTM cutting department, silver spark apparel limited, Doddaballapur. One piece flow is a technique used to manufacture components in a cellular environment. The goals of one piece flow are: to make one part at a time correctly all the time, to achieve this without lengthy queue times.
This dissertation provides comprehensive details of productivity improvement through One-piece Flow implementation in MTM cutting department, silver spark apparel limited, Doddaballapur. One piece flow is a technique used to manufacture components in a cellular environment. The goals of one piece flow are: to make one part at a time correctly all the time, to achieve this without lengthy queue times.
This dissertation provides comprehensive details of productivity improvement through One-piece Flow implementation in MTM cutting department, silver spark apparel limited, Doddaballapur. One piece flow is a technique used to manufacture components in a cellular environment. The goals of one piece flow are: to make one part at a time correctly all the time, to achieve this without lengthy queue times.
A dissertation submitted in partial Fulfillment Of the requirement for the award of Degree in
Bachelor of Fashion Technology (Apparel Production)
Submitted By MD JAWED AKHTAR
Under the Guidance of MR. T.V.S.N. Murthy
Department of Fashion Technology National Institute of Fashion Technology, Hyderabad May, 2014 i
ABSTRACT
The Made to Measure is a nascent business in India and catching the eyes of customers rapidly. The company needed to increase its capacity in response to the increased demand.The company has increased the number of MTM shops from 71 to 82 and has been planning further to open more MTM outlets. In response to the increase in demand the company needs to increase its production capacity also. But Cutting Department is the bottleneck point. Hence, there is a need to increase the capacity of this section. This dissertation provides comprehensive details of productivity improvement through NVA elimination and one-piece flow implementation in MTM cutting department, Silver Spark Apparel Limited, Doddaballapur. One-piece flow (also commonly referred to as continuous flow manufacturing) is a technique used to manufacture components in a cellular environment. The goals of one piece flow are: to make one part at a time correctly all the time, to achieve this without unplanned interruptions, to achieve this without lengthy queue times. In this work existing layout was studied followed by method study and time study and then new layout and improved working methods were proposed to enhance the capacity of the department. In the process several non-value added activities were also eliminated. As in one piece flow sequential movement of piece is necessary without wastage of transportation, a conveyor system has been introduced which works like a pull system leading to increased productivity and reduced lead time.
Key Words: Lean Manufacturing, One-piece Flow, Process Improvement, Standard Work in Progress (SWIP).
ii
CERTIFICATE This is to certify that this Project Report titled PRODUCTI VI TY I MPROVEMENT I N MTM CUTTI NG SECTI ON USI NG LEAN CONCEPTS is based on my, MD J AWED AKHTAR, original research work, conducted under the guidance of MR. T.V.S.N. Murthy towards partial fulfillment of the requirement for award of the Bachelors Degree in Fashion Technology (Apparel Production), of the National Institute of Fashion Technology, Hyderabad. No part of this work has been copied from any other source. Material, wherever borrowed has been duly acknowledged.
Signature of Author
Signature of Guide
iii
ACKNOWLEDGEMENT I would like to express my eternal gratitude to my mentor, Mr. Varun Mishra, for his support and encouragement throughout my graduation project. His mentorship was paramount in providing a well-rounded experience consistent with my long-term career goals. I extend my gratitude to him for finding time for listening to little problems and roadblocks that unavoidably cropped up in course of project implementation. My thanks also go to Mr. Nitesh Srivastava, MTM Assistant Manager, for giving an opportunity to work in his department and for his support and guidance throughout the project. I am also thankful to Mr. Lingappa, Cutting Supervisor, who provided first-hand information and coordinated in the implementation. It will be grave injustice if I dont mention the name of Mr. Pokhraj, Maintenance Head, who converted my ideas into reality. I would like to thank my college mentor, Mr. T.V.S.N. Murthy, Assistant Professor, DFT, NIFT, Hyderabad, for his valuable guidance, feedback and encouragement that he provided throughout my project. His editorial skill helped a lot in the preparation of this dissertation. His support and encouragement was in the end what made this dissertation possible. I would like to thank the Department of Fashion Technology, NIFT, Hyderabad, especially faculty members for their input, valuable discussion and accessibility. It was their continuous guidance which helped me complete my project. Finally and most importantly, the friendship of Miss Juhi Kumari, Miss Shweta Yadav and Mr. Sanjeeb Kumar Naik is much appreciated and has led to many interesting and good spirited discussion relating to the project. Their critical analysis of the various ideas led to many successful implementations. iv
Table of Contents ABSTARCT.............i CERTIFICATE.......ii ACKNOWLEDGEMENT....iii GLOSSARY..x Chapter 1 INTRODUCTION .................................................................................................... 2 1.1 Project Objectives ...................................................................................................... 2 1.2 Problems Definition ................................................................................................... 2 1.3 Project Scope and Constraints .................................................................................... 3 1.4 Key Project Benefits................................................................................................... 3 1.5 Made To Measure An Introduction ......................................................................... 3 Chapter 2 LITERATURE REVIEW ......................................................................................... 8 2.1 Lean Manufacturing ................................................................................................... 8 2.1.1 What is Lean? ..................................................................................................... 8 2.1.2 Wastes in Lean Manufacturing ........................................................................... 9 2.1.3 Lean Approach .................................................................................................. 11 2.2 One-Piece Flow ........................................................................................................ 12 2.2.1 Introduction ....................................................................................................... 12 2.2.2 Why is using One-Piece Flow important in production? .................................. 12 2.3 Lead Time ................................................................................................................ 14 2.1 Method Study ........................................................................................................... 16 2.2 Time Study ............................................................................................................... 17 2.3 Standard Work In Progress (SWIP) ......................................................................... 18 v
Chapter 3 METHODOLOGY ................................................................................................. 20 Chapter 4 EXISTING SYSTEM ............................................................................................. 22 4.1 Process Flow of MTM Department .......................................................................... 22 4.2 Process Flow in Cutting Department ....................................................................... 22 4.3 SOP for Cutting Department .................................................................................... 24 Chapter 5 DATA COLLECTION AND ANALYSIS ............................................................ 29 6.1 Cycle Time for Various Operations in Cutting Department .................................... 29 6.2 Existing Capacity Calculation .................................................................................. 31 6.3 Existing capacity summary ...................................................................................... 35 Chapter 6 IMPLEMENTED SYSTEM .................................................................................. 37 6.1 Caveat to One-Piece Flow System ........................................................................... 37 6.2 Conveyor System ..................................................................................................... 39 6.3 Non-Value Added (NVA) Activities Elimination .................................................... 46 6.3.1 Laying ............................................................................................................... 46 6.3.2 Block Cutting .................................................................................................... 49 6.3.3 Fusing Cutting ................................................................................................... 52 6.3.4 Ready Cutting ................................................................................................... 55 6.4 Sequential Movement (FIFO) .................................................................................. 59 6.4.1 A Track Sheet Holder at Pattern Cutting Machine ........................................... 60 6.4.2 Fabric Holding Stand in Store........................................................................... 60 6.5 Emergency Order Handling Flag System................................................................. 64 6.4 New Capacity Calculation ........................................................................................ 66 6.5 New capacity summary ............................................................................................ 69 Chapter 7 PROJECT COST .................................................................................................... 71 vi
8.1 Project Costing ......................................................................................................... 71 Chapter 8 RESULTS AND SAVINGS................................................................................... 74 Chapter 9 LIMITATIONS AND SCOPE OF FURTHER STUDY ....................................... 77 Chapter 10 CONCLUSION .................................................................................................... 79 APPENDICES AND ANNEXTURES81 vii
List of Figures Figure 1.1 MTM Flow Diagram .............................................................................................. 5 Figure 2.1 Batch and queue flow vs One-piece flow .............................................................. 12 Figure 3.1: Methodology Diagram ......................................................................................... 20 Figure 4.1: Process Flow of MTM Department ...................................................................... 22 Figure 4.2: Process flow diagram of cutting department ........................................................ 22 Figure 4.3: Existing layout of cutting department .................................................................. 23 Figure 4.4: Cutting Department .............................................................................................. 23 Figure 6.1: Implemented Process Flow with Conveyor ......................................................... 39 Figure 6.2: Conveyor System ................................................................................................. 40 Figure 6.3: Conveyor Basket .................................................................................................. 41 Figure 6.4: MS square Pipe ..................................................................................................... 42 Figure 6.5: Bush ...................................................................................................................... 43 Figure 6.6: J-Hook .................................................................................................................. 43 Figure 6.7: GI Pipe .................................................................................................................. 44 Figure 6.8: Wheel.................................................................................................................... 44 Figure 6.9: Lining Cutting Process ......................................................................................... 47 Figure 6.10: Lining Stand ....................................................................................................... 47 Figure 6.11: Tucking for Checks and stripes matching using hand needle ............................ 48 viii
Figure 6.12: Tucking for Checks and stripes matching using Tag Gun ................................. 49 Figure 6.13: Previous Cutting Process .................................................................................... 50 Figure 6.14: Implemented Process .......................................................................................... 51 Figure 6.15: Previous Fusing Cutting Flow Diagram ............................................................. 52 Figure 6.16: Previous Fusing Cutting Flow ............................................................................ 52 Figure 6.17: New Fusing Cutting Flow Diagram ................................................................... 53 Figure 6.18: New Fusing Cutting Flow .................................................................................. 53 Figure 6.19: Pattern Stand....................................................................................................... 55 Figure 6.20: Ready Cutting ..................................................................................................... 56 Figure 6.21: Rotary Knife for Ready Cutting ......................................................................... 56 Figure 6.22: Pattern Movement Along With Trolley.............................................................. 57 Figure 6.23: Color Coding and a Color Coded Track sheet ................................................... 59 Figure 6.24: FIFO Stand at Pattern Cutter .............................................................................. 60 Figure 6.25: Cut Fabric for laying .......................................................................................... 61 Figure 6.26: Piled up fabrics falling and mixing .................................................................... 62 Figure 6.27: Stand for cut fabric in the store .......................................................................... 62 Figure 6.28: Emergency Order Handling System (Previous) ................................................. 64 Figure 6.29 Emergency Order Handling System (Implemented) ........................................... 65
ix
List of Tables Table 2.1 One Piece Flow vs. Batch Flow System (Michal Marton) ..................................... 13 Table 2.2: Method Study Steps (Kanawaty, 1992) ................................................................. 16 Table 5.1: Cycle Time for Jacket ............................................................................................ 29 Table 5.2: Cycle Time for Trouser ......................................................................................... 30 Table 5.3: Existing Capacity Summary .................................................................................. 35 Table 6.1 New Capacity Summary ......................................................................................... 69
x
GLOSSARY MTM: Made to measure (MTM) typically refers to the clothing that is sewn from a standard size base pattern. The base pattern is altered according to the measurement & fit required by the particular customer. TRACK SHEET: The specification sheet which various informations like measurement details, fabrics details, barcode for tracking, and color coding for day- wise movement. ORDER: An order refers to the customer booking for a particular garment or garments. Generally an order has 1-5 suits 0r 1-10 trousers or a combination of both. The order doesnt contain large quantities like in mass production. BLOCK CUTTING: The cutting done according to marker planning having 2 cm extra allowances for shrinkage consideration after fusing and stripes and check matching. READY CUTTING: The block cut parts are re-cut using paper pattern matching stripes and checks within a margin of error of 1 mm.
1
CHAPTER 1 INTRODUCTION 2
CHAPTER 1 INTRODUCTION 1.1 Project Objectives Primary Objective: Productivity Improvement and Lead time reduction in MTM cutting department by one piece flow implementation using Conveyor System Secondary Objectives: To increase productivity of MTM cutting department To maintain continuous and streamlined flow of materials Eliminate NVA Reduce lead time Improve order tracking 1.2 Problems Definition Decreased productivity due to excessive NVA Increased lead time due to extra WIP Missing and mixing of parts Difficulty in order tracking No co-ordination between CAD and cutting department No systematic movement of emergency orders
3
1.3 Project Scope and Constraints The scope of this project includes analyzing the existing process, particularly identifying the non-value added activities and thereby elimination of such activities. It also includes maintaining a continuous flow and a standard work in progress (SWIP) which will require sequential flow of materials. Deliverables of the project includes improved productivity with increased visibility and better order tracking. The scope doesnt include the process re-engineering. Rather, its a continuous improvement. The constraint of the project is limited working area. 1.4 Key Project Benefits Considerable increase in productivity Streamlined flow of materials Reduced throughput time Improved order tracking Work Place visualization
1.5 Made To Measure An Introduction Raymond Group Company provides a mass customization to customers of suits and trousers. Made to measure typically refers to the clothing that is sewn from a standard size base pattern. The base pattern is altered according to the measurement & fit required by the particular customer. The concept behind made-to-measure is to provide the customer a tailored fit garment with high quality like readymade garments, with the fabric, trims, style & design according to the need of the customer. Since the made to measure garment is manufactured by following the traditional method of measurement and industrial method of manufacturing with much attention to minute detailing, its quality is like and even better than the ready to wear garments. 4
The steps followed by made-to-measure can be summarized as:- Taking measurements of the customer. Getting the closest tryon garment and trying that on the garment. Pinning the trial garment according to the need and fit of the customer Taking the pictures to help the pattern master to understand the fit requirement and to work on intuition. Selection of the fabric, style by the customer Conveying all the collected data to the manufacturing unit Selecting the base size and doing the alteration according to the need of the customer Developing the customized garment
Made to measure differs from ready to wear garments The garment is made according to the measurement of the customer, so it gives a proper fit. MTM garments are made in industrial way with advanced technology and thus minimize human errors. MTM gives the customer the advantage of choosing the fabric, style and trims. MTM allows the customer to customize the garment from start to finish. The final garment produced is of high quality.
5
Working Process Flow Of Made To Measure Garment
Figure 1.1 MTM Flow Diagram Receive order from customer at the Retail Store Style and Fabric selection by the customer Measurement of the chest& waist to decide the try on Size and Drop Customer tries the Try on of the Drop & Size Taking measurements and filling the same in the Shop Order Form Checking the fitting problems and pinning the Try Ons at the places where alteration needs to be done Taking photographs of the Fit & Pinning done for Alterations Sending the measurement, Style details, photographs and Shop Order Form to the Manufacturing Unit CAD Department receives the Details Cutting, Stitching, Sewing processes is done Product Finishing & Checking Delivery to the Customer 6
Terminology Frequently Used In Made To Measure (MTM Department) Try ons- try ons are the jacket/ trouser/ waist coat which is of different sizes and styles. It is the set from which a customer uses for the trial purpose. It is always kept in the retail store/ shop floor for the trial basis. For men, the try on set is of 5 different drops (0, 2, 4, 6, and 8) from sizes. Jacket/ trouser size- the sizes correspond to the half of the chest measurement (for jacket) and half of the waist measurement (for trouser). As an example if the chest is of 100 cm the size of the jacket is 50. And if the waist is 80cm the size of the trouser is 40. Drop- it is defined as difference as the difference between half of chest measurement and half of waist measurement. .
CHAPTER 2 LITERATURE REVIEW 2.1 Lean Manufacturing 2.1.1 What is Lean? Lean Manufacturing can be defined as "A systematic approach to identifying and eliminating waste through continuous improvement by moving the product at the demand of the customer." Taiichi Ohno once said that Lean Manufacturing is all about looking at the time line from the moment the customer gives us an order to the point when we collect the cash. And we are reducing that time line by removing the non value added wastes (Ohno, 1988). Lean always focuses on identifying and eliminating waste and fully utilizing the activities that add value to the final product. From the customer point of view, value is equivalent to anything he is willing to pay for the product or service he receives. Formally value adding activities can be defined as: activities that transform materials and information into products and services the customer wants. On the other hand non-value adding activities can be defined as: activities that consume resources, but do not directly contribute to product or service. This non-value adding activities are the waste in Lean Manufacturing. Waste can be generated due to poor layout (distance), long setup times, incapable processes, poor maintenance practices, poor work methods, lack of training, large batches, ineffective production planning/scheduling, lack of workplace organization etc. By eliminating wastes in the overall process, through continuous improvements the products lead time can be reduced remarkably. By reducing lead time organization can obtain operational benefits (enhancement of productivity, reduction in work-in-process inventory, improvement in quality, reduction of space utilization and better work place organization) as well as administrative benefits (reduction in order processing errors, streamlining of 9
customer service functions so that customers are no longer placed on hold, reduction of paperwork in office areas, reduction of labor turnover) 2.1.2 Wastes in Lean Manufacturing The waste can be categorized into seven types which are commonly referred to as the Seven wastes. Taiichi Ohno suggests that these account for up to 95% of all costs in non Lean Manufacturing environments. These wastes are: Overproduction Producing more than the customer demands. There are two types of overproduction (Shingo, 1989): 1. Quantitative making more products than needed. 2. Early making products before needed. Overproduction is highly costly to a manufacturing plant because it obstructs the smooth flow of materials and degrades the quality and productivity. Overproduction manufacturing is referred to as Just in Case whereas Lean Manufacturing is referred to as Just in Time (McBride, 2003).The corresponding Lean principle is to manufacture based upon a pull system, or producing products just as customers order them. Anything produced beyond customer order ties up valuable labor and material resources that might otherwise be used to respond to customer demand. Ohno considered the fundamental waste to be overproduction, since it leads to other wastes such as overstaffing, storage, and transportation costs because of excess inventory. Waiting Whenever goods are not being moving or being processed, the waste, waiting occurs. Typically more than 99% of a products life cycle time in traditional mass production is spent in idling. This includes waiting for material, labor, information, equipment etc. Lean requires that all resources are provided on a just-in- time (JIT) basis not too soon, not too late by linking processes together so that one feeds directly into the next and can dramatically reduce waiting. 10
Transportation or conveyance Moving product between processes does not add value to the product. Excessive movements and handlings can cause damages and can lead to reduction in quality. Materials should be delivered to its point of use. Lean requires the material be shipped directly from the vendor to the location in the assembly line where it will be used. This is called Point-Of-Use-Storage (POUS). Over processing or incorrect processing Taking unneeded steps to process the parts. Some of the more common examples of this are reworking, inspecting, rechecking etc. This is due to poor layout, poor tools and poor product design, causing unnecessary motion and producing defects. Excess Inventory Any type of inventory (raw material or in process or finish goods) does not add value to the product and it should be eliminated or reduced. Excess inventory uses valuable floor space and hides problems related to process incapability. Excess inventory results in longer lead times, obsolescence, damaged goods, transportation and storage costs, and delay. Defects Defects can be either production defects or service errors. Having a defect results a tremendous cost to organizations. In most of the organizations the total cost of defects is often a significant percentage of total manufacturing cost. Repairing of rework, replacement production and inspection means wasteful handling time, and effort. Excess Motion Any motion that employee has to perform which does not add value the product is an unnecessary or excess motion. Unnecessary motion is caused by poor workflow, poor layout, poor housekeeping, and inconsistent or undocumented work methods.
11
2.1.3 Lean Approach Lean organizations are highly customer focused, providing the highest quality, lowest cost products in the shortest lead time possible. According to the book Lean Thinking by James P. Womack and Daniel Jones, the Lean approach can be summarized in five principles (Womack and Jones, 2003): Specify what creates value from the customers perspective - Value should be specified from the customer point of view not by the perspective of individual firms, functions and departments. If the customer does not pay for an activity, it is a non- value adding activity and should be eliminated. Identify all the steps along the process chain This means identifying the value stream. It can be used to identify activities where value is added to the product and those do not. Make those processes flow The value added product must flow continuously from the start to finish without interruptions, detours, backflows, waiting, scrap and stoppages. Make only what is pulled by the customer The customer should pull the product from the source as needed rather than process pushing the products onto the customer. Strive for perfection After implementing above steps the team should be continuously remove wastes as they are uncovered and pursue perfection through continuous improvement. Lean uses practically proven tools and techniques to systematically implement these Lean principles. If these are correctly applied, it will bring improvements to quality, cost and delivery of the final product. Those tools help in implementing, monitoring, and evaluating Lean efforts and its results. On the other hand if these were used without proper understanding, it can spoil Lean efforts in ones organization.
12
2.2 One-Piece Flow 2.2.1 Introduction One-piece flow (also commonly referred to as continuous flow manufacturing) is a technique used to manufacture components in a cellular environment. The cell is an area where everything that is needed to process the part is within easy reach, and no part is allowed to go to the next operation until the previous operation has been completed. The goals of one piece flow are: to make one part at a time correctly all the time, to achieve this without unplanned interruptions, and to achieve this without lengthy queue times. One-piece flow describes the sequence of product or of transactional activities through a process one unit at a time. In contrast, batch processing creates a large number of products or works on a large number of transactions at one time sending them together as a group through each operational step. In one-piece flow, focus is on the product or on the transactional process, rather than on the waiting, transporting, and storage. One-piece flow methods need short changeover times and are conducive to a pull system. 2.2.2 Why is using One-Piece Flow important in production? The following illustration shows the impact of batch size reduction when comparing batch and one-piece flow.
Figure 2.1 Batch and queue flow vsOne-piece flow 13
The difference between the two systems is conspicuous through the depicted diagram (Figure.1 and Figure.2).First; one-piece flow system saved 18 minutes for the same batch of 10 pieces. This shows dramatic improvement in production capacity. Second, first piece was in processed only 3minutes. Unlike batch system, one piece flow allows operator to check a part immediately in each process (A, B and C). If there is any quality issues it will be detected too late and many parts will be damaged.. Impacts One Piece Flow Batch System Operations Staff Work as a team in a system. Respond immediately to errors picked up by downstream colleagues. High morale. Work to own teams service level. Tend not to proactively collaborate with other teams. Do not see impact of their errors. Staff Productivity Superior- each part of the system pulls work to them and avoids backlogs being created. High visibility of staffs too busy or idle. Hostage to build up of backlog when demand or supply factors change. Large value of non-value added work. Leadership time and effort Team takes ownership of work and sticks to agreed rules of working. Any issues affecting system performance are immediately obvious Constant supervision of 1005 of staff. Distracted by dealing with escalations, hidden in the backlog. Customers Cycle time is very quick and predictable. Errors picked up early and adjustments made. Cycle time is too long or too variable. Errors are slow to fix. Business Partners Respond Immediately to rework caused up by sales and feedback provided. Major cause of rework.
Table 2.1 One Piece Flow vs. Batch Flow System(Michal Marton) 14
2.3 Lead Time In todays unpredictable economic environment, retailers and consumer product companies (brands) may be challenged to deliver trend-right products in the right quantities to the right locations. This challenge is often exacerbated by long lead times. Performance goal may vary from one cell or factory to the next. For some, quality is the foremost measure of performance. For others, delivery speed and customer response dominates. For others, labor efficiency is foremost. Where equipment is expensive and capital scarce, equipment utilization is the main focus.For this company faster delivery with superior quality of the products is the main goal. Silver et al. (Silver, 1998)defined, lead time as the time that elapses between the placement of an order and the receipt of the order into inventory, lead time may influence customer service and impact inventory costs. As the Japanese example of just-in-time-production has shown, consequently reducing lead times may increase productivity and improve the competitive position of the company. The Japanese experience of using Just-In-Time (JIT) production shows that there are advantages and benefits associated with their efforts to control lead time. Japanese manufacturers are known for their strong and lasting partnership with their suppliers. This helps reduce lead time and is one of the sources of success of their JIT philosophy. Before 1980, customers tolerated long lead times which enabled producers to minimize product cost by using economical batch sizes. Later, when customers began to demand shorter lead times, they were able to get them from competitors. This is when the problem arose and companies started to look for changes to be more competitive. In an attempt to reduce lead time, businesses and organizations found that in reality 90% of the existing activities are non-essential and could be eliminated. As soon as manufacturers focused on processes, they found waste associated with changeovers, quality defects, process control, factory layout, and machine down time. So they tried to find ways to reduce or eliminate waste. Harrington (Harrington, 1996)proposes by eliminating the non-value adding activities from the processes and streamlining the information flow significant optimization results can be realized. In the 1960s and 70s, manufacturers competed on the basis of cost efficiency. In 15
the 1980s, quality was the rage and Zero Defects and Six Sigma came into vogue. Cost and quality are still crucial to world-class operations, but today, the focus is squarely on speed. Nearly all manufacturers today are under pressure from customers to cut lead times. And rapid-response manufacturing pays big dividends.
16
2.1 Method Study Method study is the systematic recording and critical examination of ways of doing things in order to make improvements. (Kanawaty, 1992). The basic approach to method study consists of the following eight steps: 1 SELECT the work to be studied and define its boundaries. 2 RECORD the relevant facts about the job by direct observation and collect such additional data as may be needed from appropriate sources. 3 EXAMINE the way the job is being performed and challenge its purpose, place, sequence and method of performance. 4DEVELOP The most practical, economic and effective method, drawing on the contributions of those concerned. 5 EVALUATE Different alternatives to developing a new improved method comparing the cost-effectiveness of the selected new method with the current method of performance. 6 DEFINE the new method, as a result, in a clear manner and present it to those concerned, i.e. management, supervisors and workers. 7 INSTALL the new method as a standard practice and train the persons involved in applying it. 8 MAINTAIN the new method and introduce control procedures to prevent a drifting back to the previous method of work.
Table 2.2: Method Study Steps(Kanawaty, 1992)
17
2.2 Time Study Work measurement is the application of techniques designed to establish the time for a qualified worker to carry out a task at a defined rate of working (Kanawaty, 1992). Method study is the principal technique for reducing the work involved, primarily by eliminating unnecessary movement on the part of material or operatives and by substituting good methods for poor ones. Work measurement is concerned with investigating, reducing and subsequently eliminating ineffective time, that is time during which no effective work is being performed, whatever the cause. Work measurement, as the name suggests, provides management with a means of measuring the time taken in the performance of an operation or series of operations in such a way that ineffective time is shown up and can be separated from effective time. Work measurement has another role to play. Not only can it reveal the existence of ineffective time; it can also be used to set standard times for carrying out the work, so that, if any ineffective time does creep in later, it will immediately be shown up as an excess over the standard time and will thus be brought to the attention of management. Time study is a work measurement technique for recording the times of performing a certain specific job or its elements carried out under specified conditions, and for analyzing the data so as to obtain the time necessary for an operator to carry it out at a defined rate of performance (Kanawaty, 1992).
18
2.3 Standard Work In Progress (SWIP) SWIP is the minimum necessary in process inventory (work in process or WIP) to maintain Standard Work; No more, no less. SWIP or Standardized Work in Progress is the minimum necessary process inventory to maintain one-piece flow. Need to Control WIP: Two major cost areas can be reduced if WIP is controlled. 1. Investment in inventory: Inventory is the money invested in raw materials. If the inventory is not moved through the plant quickly then it affects cash flow directly. 2. Ability to reduce the production cycle By having low inventory between operations, garments usually have less waiting time and go through the production cycle in less time. Large inventory levels between the operations keep the goods waiting longer to be processed. This increases the overall through put time. Low through put time permits better co-ordination between sales and production. Low cycle times give manufacturers the ability to handle multiple styles. Clients/buyers are looking for the factories that can meet production schedules, that can handle multiple styles, and that can handle low inventories which will reduce their investment. The factories that work with low WIP only will be able to sustain in the present market. 19
CHAPTER 3 METHODOLOGY
20
CHAPTER 3 METHODOLOGY The steps followed in the research project are given below: Step 1: Theoretical construction of the thesis Step 2: Preparation of questionnaires and database sheet based on primary observation Step 3: Data collection and analysis Step 4: Problem findings and suggest improvement scope. Step 5: System Implementation Step 6: System Testing and thereby further improvements
CHAPTER 4 EXISTINGSYSTEM 4.1 Process Flow of MTM Department
Figure 4.1: Process Flow of MTM Department 4.2 Process Flow in Cutting Department
Figure 4.2: Process flow diagram of cutting department Order Received in CAD Order Verification Pattern Alteration Fabric Store Track Sheet Generation Marker Planning Block Cutting Ready Cutting Sewing Dispatch Finishing Fabric receiving from store Lining cutting Fabric Laying Fusing Fusing Cutting Block Cutting By Machine Ready Cutting Checking Loading 23
Figure 4.3: Existing layout of cutting department
Figure 4.4: Cutting Department 24
4.3 SOP for Cutting Department Activity Purpose/Objective Procedure Performed By Person Responsible Reports/ Documentatio ns Fabric Cutting in store To issue for cutting Check Track sheet for fabric Code and Consumption Before cutting cross-check swatch with fabric code Place the fabric with track sheet on the table in serial order Tick in the order tracking list against the serial number Store Boy(01) Team Leader(Mrs. Putthama) Order Tracking Checklist Lining Cutting For Feeding into cutting m/c Look the lining code in Track sheet and match shade from lining swatch board. Bring the roll on the table and Cut as per indicated quantity. Place the roll back in the rack Operator(01) Team Leader(Mrs. Putthama) - Laying For Feeding into cutting m/c Check for lining marker- half width or full width. Lay Shell and lining Place fusing block on shell for JKT & Suit. Tick in the order tracking list against the serial number Operators(02) Team Leader(Mrs. Putthama) Order Tracking Checklist 25
Block Cutting Cutting lay into panels Look for selvedge alignment Match marker plan with track sheet Cut Data feeding to be done without stopping m/c while cutting is in process. Tick in the order tracking list against the serial number
Operators(02) Team Leader(Mr. Kemp Raj) Order Tracking Checklist Marking To identify right and wrong side Mark using pencil on wrong sides Place the cut panels in basket- small parts on one side & big parts on other side. Keep the TRS part in yellow basket and JKT & W.C. in blue basket and pass to next station. Helpers(02) Team Leader(Mr. Kemp Raj) Order Tracking Checklist Fusing Cutting Front and Lapel To cut exactly according to front and lapel size Take the rolls out from the table and cut a block Place the front and lapel shell fabrics to use as a pattern and cut Re-cut 1 cm all around to eliminate seam allowances on front and lapel Operator(01) Team Leader(Mr. Kemp Raj) - Fusing M/C (Jacket) To provide stiffness/good drape Place all the fusing parts appropriately and pass through the machine. Tick in the order tracking list against the serial number Operator(01) Team Leader(Mr. Kemp Raj) Order Tracking Checklist Place the fused panels in basket- small parts Helper(01) Team Order Tracking 26
on one side & big parts on other side. Leader(Mr. Kemp Raj) Checklist Fusing M/C (Trouser) To provide stiffness Place all the fusing parts appropriately and pass through the machine. Tick in the order tracking list against the serial number
Team Leader(Mr. Kemp Raj) Order Tracking Checklist Ready Cutting(JKT) Checks matching and shrinkage ----- Look for the order no and serial no. Pick up the pattern from the stand after carefully matching the order no & serial no. Cut using pattern Put back all the parts in the basket. Tick in the order tracking list against the serial number Operator(02) Team Leader(Mr. Kemp Raj) Order Tracking Checklist Ready Cutting(TRS) Checks matching and shrinkage ----- Look for the order no and serial no. Pick up the pattern for checked and striped fabric from the stand after carefully matching the order no & serial no. Cut using pattern Bundle all the parts and pass to next station. Tick in the order tracking list against the serial number Operator(01) Team Leader(Mr. Kemp Raj) Order Tracking Checklist Tagging & Pocketing To identify parts and attach trims Attach the pocketing material Cut the labels and tag to the parts. Paste swatch to the order tracking list. Pass for checking Helper(01) Team Leader(Mr. Kemp Raj) Order Tracking Checklist With Swatch 27
Checking(TRS) Checking for quality Check number of parts Measurement check against the track sheet Check Notch Marks Look for other fabric defects, if any Update in V-stitch Operator(01) Cutting Executive Order Tracking Checklist Checking(JKT) Checking for quality Check number of parts(for avoiding any miss) Measurement check against the track sheet Check Notch Marks Look for other fabric defects, if any Update in V-stitch Update defects, if any Operator(01) Cutting Executive Order Tracking Checklist And quality Report
28
CHAPTER 5 DATA COLLECTION AND ANALYSIS
29
CHAPTER 5 DATA COLLECTION AND ANALYSIS 6.1 Cycle Time for Various Operations in Cutting Department Operations No of Operato rs Operator Rating Cycle Time (Sec) VA (Sec) NVA (Sec) Basic Time(Cycle time*Rating) (Sec) SAM= 1.15*Basic Time(15% Allowance) (Min) Lining Cutting(2P 1 ) 1 100% 166 77.8 88.2 166 3.18 Laying(2P) 2 100% 356.17 281.01 75.16 356.17 6.83 Block Cutting m/c 1(2P) 1 90% 701.67 557 144 631.50 12.10 Block Cutting m/c 2(2P) 1 100% 706.88 580.02 126.86 706.88 13.55 Fusing Cutting 1 75% 399.5 176.56 222.94 299.63 5.74 Fusing 1 90% 245 245 0 220.5 4.23 R C(Solid) 4 75% 1114 294.89 795.29 835.5 16.02 R C (Checks) 75% 1368 307.2 1060.8 1026 19.67 R C(Stripes) 75% 1154.2 230.2 924 865.65 16.59 Checking 1 90% 494.8 494.8 0 445.32 8.54 Table 5.1: Cycle Time for Jacket
1 The reading is for 2-piece suit till bundling because the operations at these work stations cant be separated. 30
2 ,* - Already Counted In Jacket Cycle Time; Same operator for both jacket and trouser 31
6.2 Existing Capacity Calculation Lining Cutting Man Hour= 8 SAM for 2-piece suit = 3.18 min SAM for trouser = 0.28 min Let the ratio of suit to trouser be 1:2 (From output report Appendix III) So, average time = (1*3.18 + 2*0.28)/ (1+2) = 1.25 min So, Capacity = 480 /1.25 = 384 i.e. 128suits and256 trousers Laying Man Hour= 8 x 2= 16hr. SAM for 2-piece suit = 6.83 min SAM for trouser = 2.55 min Let the ratio of suit to trouser be 1:2 (From output report Appendix III) So, average time = (1*6.83 + 2*2.55)/ (1+2) = 3.98 min So, Capacity = (480*2) /3.98 = 241 i.e. 80 suits and 161 trousers Block Cutting Machine 1 Machine Hours = 8 * 0.85 = 6.8 hour (At 85% efficiency) SAM for 2-piece suit = 12.10 min SAM for trouser = 4.91 min 32
Let the ratio of suit to trouser be 1:1 3 (From output report Appendix III) So, average time = (1*12.10 +1 *4.91)/ (1+1) = 8.5 min So, Capacity = 408 /8.5 = 48 i.e. 24 suits and 24 trousers Machine 2 Machine Hours = 8 * 0.95 = 7.6 hour (At 95% efficiency) SAM for 2-piece suit = 13.55 min SAM for trouser = 4.87 min Let the ratio of suit to trouser be 1:1 (From output report Appendix 3) So, average time = (1*13.55 +1 *4.87)/ (1+1) = 9.21 min So, Capacity = 456 /9.21 = 50 i.e. 25 suits and 25 trousers Hence, Total capacity of block cutting should have been = 49 suits and 49 trousers orders. But due to excessive NVA and unplanned trims cutting, there is momentum breakdown and consequently the efficiency is 80%. Hence actual capacity = 39 Suits and 40 trousers orders. Fusing Cutting (Jacket) Man Hour= 8 hrs. SAM= 5.74 min So, Capacity = 480 /5.74 =83 jackets Fusing Machine (Jacket) Machine Hours = 8 hour (At100% efficiency) SAM = 4.23 min
3 Ratio considered as 1:1 because even if trouser has multiple quantities, it is cut in a single marker. 33
Man Hours = 8 * 4 = 32 hrs. SAM for JacketRC (solid) = 16.02 min SAM for JacketRC (stripe) = 16.59 min SAM for Jacket RC (checks) = 19.67 min Let the ratio of solid, stripe and checks be5:3:2 (50%:30%:20%) (From output reportAppendix III) So, average time = (5*16.02 +3 *16.59 + 2*19.67)/ (5+3+2) = 16.92 min So, Capacity = (480*4) /16.92 = 113 i.e. 57 solid, 34 stripe and 22 checked But due to excessive NVA, there is momentum breakdown and consequently the efficiency is 50%. And therefore actual output = 57 i.e. 29 solid, 17 stripe and 11 checked.
Ready Cutting (trousers)
Man Hours = 8 hrs. SAM for JacketRC (solid) =2.51min SAM for JacketRC (stripe) = 6.55 min SAM for Jacket RC (checks) = 9.77 min 34
Let the ratio of solid, stripe and checks be5:4:1 (50%:40%:10%) (From output report Appendix 3) So, average time = (5*2.51 +4 *6.55 + 1*9.77)/ (5+4+1) = 4.85 min So, Capacity = 480 /4.58 = 105i.e. 53 solid, 42 stripe and 10 checked
35
Checking (Jackets)
Man Hours = 8 SAM =8.54 min So, Capacity = 480 /8.54 = 56
Checking (Trousers)
Man Hours = 8 SAM forTrouserChecking (solid& stripe) =2.23 min SAM for Jacket Checking (checks) = 4.27 min Let the ratio of solid& stripe, and checks be9:1 (90%:10%) (From output report Appendix III) So, average time = (9*2.23 + 1*4.27)/ (9+1) = 2.434 min So, Capacity = 480 /2.434 =197 i.e. 177 solid and stripe, and 20 checked 6.3 Existing capacity summary Operations No Of Operators Jackets Trousers Lining 1 128 256 + 128 Laying 2 80 161 + 80 Block Cutting 2 39 40 + 39 Fusing Cutting 1 83 Fusing M/C 2 113 180 Ready Cutting 5 57(29,17,11) 105(53,42,10) Checking 2 56 197(177,20)
Table 5.3: Existing Capacity Summary
36
CHAPTER 6 IMPLEMENTED SYSTEM
37
CHAPTER 6 IMPLEMENTED SYSTEM After careful study and analysis, it was been found that there were considerable non-value added activities at almost each work stations. Further throughput time for the cutting department was also high which led to increase in lead-time. In order to eliminate theses NVA and reduce the lead time, various changes like process change, layout modification and one piece flow implementationwere done. They have been explained in detailed in the successive sections. 6.1 Caveat to One-Piece Flow System The one-piece flow is implementation must be preceded by a caveat on the factors which often leads to its failure. These factors (Miller, 2007) along with the solutions have been listed below: a. Unreliable equipment that may break down, causing downstream processes to run out of parts: This particular problem is encountered on block cutting machines. The machine downtime due to machine break down is very high (14%; source: Appendix II). These machines require preventive maintenance preceded by a complete overhauling. The breakdown report for one month has been complied and sent to top management for consideration. b. People will resist this change: Believing in the system is essential for its success. People will have to be motivated. This is what a leader does. The benefits of the system should be effectively conveyed to the operators so that their heart and mind is for the system. Workers were shown motivational video on continuous flow to convey the benefits. The result was surprising- they were very receptive of the change. 38
c. People are not cross trained to do more than one or two limited tasks: For one piece flow its essential that operators are cross trained for countering the problem arising from the absenteeism of a particular operator or operators. Limiting people's potential to learn and develop to their fullest never benefits a company. Training the people for cross jobs and taking "boring" out of work by giving people variety boost their morale. This is what we did here to tackle the problems arising out of absenteeism. Workers were cross trained on all the critical work stations especially cutters and ready cutting. d. There is too much distance between processes to move one at a time: This particular problem is one of the major cause of one the seven wastes of the lean manufacturing i.e. transportation. In cutting section bundles have to be carried to successive stations manually. In order to eliminate this conveyor system has been suggested which is explained in next section 6.2. e. Process cycle times are unstable or variable, creating imbalance between workers. The first step was to examine the process cycle times through direct process observation, breaking the work into smaller work elements and segregating VA & NVA. The detailed steps of NVA elimination has been explained in section 6.3. Since, in MTM style varies and also the quantity in an order varies. Sometimes re- cutting is also done. The chronic variation is still above the 5% to 10% range. It's unpredictable variation. To counter this problem, a standard WIP as buffer needs to be defined. If we maintain a SWIP the successive stations will not be affected due to shortage and we will also be able to avoid excess WIP. Thats why a SWIP of 5 orders per work station is being maintained. f. Occasional work like Trims cutting that interrupts the process: Through the data analysis, it has been found that cutter machine is the bottleneck. Unplanned cutting of trims aggravates the problem. Further, one piece flow will not work as successive will run out of piece. The solution for this is to plan the cutting of each and every trim and cut them in overtime or on Sunday. The planning should be done in a manner that inventory lasts at least for a fortnight. Such a plan has been shown in appendix 4. 39
6.2 Conveyor System There is too much distance between processes to move one at a time in the department. This particular problem is one of the major cause of one the seven wastes of the lean manufacturing i.e. transportation. In cutting section bundles have to be carried to successive stations manually. In order to eliminate manual transportation and minimize material handling a flexible conveyor system has been implemented.
Figure 6.1: Implemented Process Flow with Conveyor
28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 Checking RC JKT RC TRS Tagging Pocketing Checking Pattern Pattern Band Knife Fusing M/C F u s i n g
M / C Trims Laying Fusing Cutting Block Cutting Block Cutting Bundling Bundling Laying Laying L i n i n g
S t a n d G A T E S t a i r Loading Loadin Fabric From Store P a t t e r n D u s t
B i n L i n i n g
S t a n d RC TRS RC JKT Unit: One Tile = 2' x 2' 13" 15" 13" 8" 40
Technically the system consists of overhead conveyors having two lines- one for the trousers and one for the jackets. The parts are carried in a basket as shown in figure 10.Though the system is not automated but it has been crafted judiciously using wheels for free and smooth movement. A simple push carries the basket to next work station.
Figure 6.2: Conveyor System 41
Figure 6.3: Conveyor Basket This system transports all the pieces of the product through the manufacturing process. The basket carries all pieces of one entire garment through different steps of production. Operations are performed at individual work stations. The end result is a cost-efficient product, processed from pieces to completion. A conveyor system is often the lifeline to a companys ability to effectively move its product in a timely fashion.
42
Components of the conveyer system a) MS square Pipe Structural Support
Figure 6.4: MS square Pipe The mild steel square pipe has been used as a structural support. The vertical pipe dimension is 2 x 2 whereas the horizontal pipes used are of dimensions 1.5 x 1.5.
43
b) Bush and J Hook
Figure 6.5: Bush
Figure 6.6: J-Hook In order to suspend the GI rod (conveyor pipe), bush and J-hooks have been used so that the system remains flexible and can be expanded anytime. 44
c) GI Pipe
Figure 6.7: GI Pipe This is the conveyor pipe on which baskets move. d) Wheel
Figure 6.8: Wheel The baskets move on wheels which have bearings inside them so that the flow is very smooth. 45
Number of Baskets Calculation As discussed in section 6.1, the SWIP for jacket considered is 5 per work station. There are 4 work stations for jackets that the conveyor covers viz. cutting, fusing, ready cutting and checking. Hence, number baskets for jacket = 4* 5 = 20 The SWIP for trouser is 10. There are 3 work stations for jackets that the conveyor covers viz. cutting, fusing, waist and ready cutting. Hence, number baskets for jacket = 3* 10 = 30 Hence, total number of baskets required is 50.
46
6.3 Non-Value Added (NVA) Activities Elimination In order to maintain one-piece flow system NVA elimination is must so that the pitch time is balanced. The successive sections describe the various non-value added activities elimination technique which has been implemented. 6.3.1 Laying a) Lining stand near work stations For cutting body lining, sleeve lining and knee lining a separate worker was required because the rolls of different shades were in the store and cutting them took almost 3 minutes. To minimize this transportation wastage a lining stand was made and placed near the laying table. The different steps involved were as follow:
Place back thge roll Cut the specified length Go to Fabric store, pick the roll and bring on the table. Look for reference number in the tracksheet 47
Figure 6.9: Lining Cutting Process
Figure 6.10: Lining Stand 48
Result:The time taken for cutting a body lining came down to just 30 second from 130 second (Appendix 1sheet 1). Further, there is no need for an extra worker especially for this job. Hence, there is not only time saving but manpower saving also. b) Tacking Gun for checked and striped fabric In order to match checks and stripe during laying hand needle is used to tuck the fabrics in place. This is a time consuming process. So, a tag gun has been introduced to do the tucking.
Figure 6.11: Tucking for Checks and stripes matching using hand needle
49
Figure 6.12: Tucking for Checks and stripes matching using Tag Gun Result: The hand stitching took 2-3 minutes depending on fineness of stripes and checks whereas the tag gun takes approximately one minute. 6.3.2 Block Cutting During the data collection it was found that block cutting is the bottleneck point (See Table 6). The study revealed the following causes for the problem: External Factor Lack of Co-ordination between CAD and Cutting Department- There was lack of synchronization between marker planning and cutting as there was no sequencing of orders. Most often laying was done and fed to cutter machine but there was no marker file. This problem was solved by one piece flow implementation which works on FIFO (First in first out) principle. Internal Factors Machine o Improper preventive maintenance: The machine breakdown rate is very high resulting in high machine downtime. (Appendix II). So, a complete 50
overhauling was done. Though this reduced the breakdown but its still not satisfactory. So, breakdown report for a month has been sent to the top management for machine replacement consideration. Process o No Continuous feeding: Through the time study using element breakdown it was found that activities like unrolling of lay,order sheet searching, feeding and aligning took considerable time and they dont add any value.
Figure 6.13: Previous Cutting Process Unrolling of folded lay Track sheet search Feeding Aligning 51
Figure 6.14: Implemented Process So, in order to eliminate the non-value added activities, continuous feeding is being done. A stand was fixed to the laying table and the paper roll was mounted on it using a pipe. Now, the machine automatically draws the fabric lay in. Result:
Not only this continuous feeding also led to reduction in laying time because paper rolling and unrolling is no longer required. Current Capacity Suits- 40 (orders) Trousers- 53 orders or 76 pieces Improved Capacity Suits- 60 (orders) Trousers- 76 orders or 109 piece
52
6.3.3 Fusing Cutting For small parts fusing there is no need for size-wise cutting but larger parts like front and lapels require cutting exactly to the shell fabric. Hence, fusing is cut manually. The process flow is as follow:
Figure 6.15: Previous Fusing Cutting Flow Diagram
Figure 6.16: Previous Fusing Cutting Flow Roll Pick up Bloack Cutting and putting the roll back Fusing Cutting using the shell fabric as a pattern Re-cutting to remove the seam allowances 53
The manual handling took too much time. To minimize the time, marker planning was done in such a manner so that the front position is fixed in all the markers. Now block cutting was done in two sizes for front and lapel (Annexure IV). While laying the block is placed at the fixed place and is cut on the machine along with the fabric. Now, re-cutting is done to remove seam allowance that too without using shell as pattern which took time.
Figure 6.17: New Fusing Cutting Flow Diagram
Figure 6.18: New Fusing Cutting Flow Place the fusing block on fabric lay Cut along with the shell on block cutter machine Re-cut to remove seam allowances 54
Result:
55
6.3.4 Ready Cutting In ready cutting the shell fabric is re-cut by rotary knife using paper patterns made for that order (see figure 6.20 and 6.21). Though this work station is not a bottleneck point but the number of operators used is more than the required because non-value added time is highest at this work station. Patterns requisition from CAD and matching them as per orders tookabout 30 min time for 25 orders i.e. 1.5 man hours. Sometimes order reached at the ready cutting table but pattern was not ready because there was no sequencing or rather they were not synchronized.
Figure 6.19: Pattern Stand 56
Figure 6.20: Ready Cutting
Figure 6.21: Rotary Knife for Ready Cutting 57
If the flow is maintained and CAD and cutting are synchronized, this waste of time of skilled labor can be avoided. In order to do this concept of FIFO has been implemented which will be explained in next section 6.4 in detail. After synchronization a system has been developed to move the patterns in which the pattern passes along with the track sheet and the cut parts. This eliminates not only the pattern searching time but also minimizes movement as the operators used to go to pattern stand.
Figure 6.22: Pattern Movement Along With Trolley
58
Result:SAM for Jacket (Solid) = (795.29 * 0.75*1.15)/60 = 11.43 SAM for Jacket (Stripe) = (924 *0.75* 1.15)/60 = 13.28 SAM for Jacket (Checks) = (1060 * 0.75*1.15)/60 = 15.24 (Appendix 1 sheet10) Let the ratio of solid, stripe and checks be5:4:1 (50%:30%:20%) (Appendix- From output report) So, average time = (5*11.43 +3 *13.28 + 2*15.24)/ (5+3+2) = 12.75 min So, Capacity = (480*4) /12.75 = 150i.e. 75 solid, 45 stripe and 30 checked Hence, the number of operators required is only two instead of 4.
59
6.4 Sequential Movement (FIFO) Earlier the concept of FIFO was followed on Day-wise basis. There is a color coding for each day of the week and the orders move in that order. But in order to make the system successful, each order has to be moved as per FIFO i.e. FIFO within the day-wise color coding.
Figure 6.23: Color Coding and a Color Coded Track sheet Now, a SWIP of 5 has already been defined but the whole system will collapse if the pattern for ready cutting is not made available at the time of ready cutting. The baskets will create a jam. So, in order to have FIFO within the day following implementations were done: 60
6.4.1 A Track Sheet Holder at Pattern Cutting Machine
Figure 6.24: FIFO Stand at Pattern Cutter 6.4.2 Fabric Holding Stand in Store The store boy used to cut each order and pile up one after another. When they were loaded for laying all the fabrics were mixed and no order was followed except for day-wise. Many a time it happened that the order which came first moved too late and the order which came later moved first. Now, the pattern is ready for the order which came first but not for the order which came last. So, the pattern is ready for the order which did not reach at the ready cutting table and pattern is not available for the order which is already there at ready cutting table. 61
Figure 6.25: Cut Fabric for laying 62
Figure 6.26: Piled up fabrics falling and mixing
Figure 6.27: Stand for cut fabric in the store 63
To solve this problem, a separate trolley (See Figure 27) was made having three sections divided by removable plywood. Having tree sections distributes the weight of the fabrics. How does it work? The store boy picks the track sheet from the stand in an order and cuts the fabric and place in the lowest section. The stand at this point is empty and plywood boards are outside. He cuts and put one after another till first section is full. Now he puts the plywood back. Next, het put the cut fabric in the second section and so on. Once the Trolley is full, laying operator takes it to the laying table and draws the fabric from bottom. Though the total cut fabrics are around 25-30 in the trolley but there is weight of only about 10 fabrics on the lowest fabric. Hence, it can be easily drawn out. Meanwhile, the store boy fills other trolley and once the trolley at laying is empty its brought back and next filled trolley goes back.
64
6.5 Emergency Order Handling Flag System As per current procedure, for urgent order the word urgent is hand written on the track sheet. The worker sees it and passes forward after processing. The main problem with this was that its not clearly visible and was mixed along with other orders. The supervisor or cutting executive had to search and give them manually to the workers and they had to track constantly to see it thats passing or not.
Figure 6.28: Emergency Order Handling System (Previous) 65
Many times workers dont see and is mixed with other orders. For this a red flag is attached to the basket containing urgent order.
Figure 6.29 Emergency Order Handling System (Implemented) Result:This will increase visibility not only for workers but also for executives and thus smooth flow of emergency order will be maintained.
66
6.4 New Capacity Calculation Lining Cutting and laying Man Hour= 8 x 2 = 16 hours SAM for 2-piece suit = 1.5+5.59 min = 7.09 min SAM for trouser = 0.33+ 1.99= 2.32 min Let the ratio of suit to trouser be 1:2 (From output report Appendix III) So, average time = (1 x 7.09 + 2 x 2.32)/ (1+2) = 3.91 min So, Capacity = (480 x 2)/3.91 = 245 i.e. 82 suits and 163 trousers Block Cutting Machine 1 SMV for 2-piece suit = 501sec SAM for 2-piece suit = 575.50 sec = 9.61 min SMV for Trouser = 179.82 sec SAM for Trouser = 206.79 sec = 3.45 min If the machine is repaired, we can take efficiency to be 95%. Machine hours= 8*0.95 = 7.6 hours Let the ratio be 1:1 Average time = (9.61 + 3.45)/2 = 6.53 So, Capacity = (7.6 * 60)/6.53 = 70 i.e. 35 suits and 35 trousers orders.
67
Machine 2 SMV for 2-piece suit = 580.02 sec SAM for 2-piece suit = 667.023 sec = 11.12 min SMV for Trouser = 189.36 sec SAM for Trouser = 217.76 sec = 3.63 min If the machine is repaired, we can take efficiency to be 95%. Machine hours= 8*0.95 = 7.6 hours Let the ratio be 1:1 Average time = (11.12 + 3.63)/2 = 7.38 So, Capacity = (7.6 * 60)/7.38 = 62 i.e. 31 suits and 31 trousers orders. Out of 456*2 = 912 min, 15 % 0f 912 min i.e. 136.8 min has been given as PFD allowance. Now, the co-worker is trained at least 5% i.e. 45 min can be used. This implies that 3 more suits and 3 more trousers can be cut. Hence, total capacities = (35+31+3) 69 suits and 69 trouser orders (or 69+1.45*69=169).
Fusing Cutting and Fusing Machine (Jacket) Machine Hours = 8 hour (At100% efficiency) SAM = 4.23 + 1.33 = 5.56 min Capacity = 480/5.6= 86 jackets
SAM for Jacket (Solid) = (795.29 * 0.75*1.15)/60 = 11.43 SAM for Jacket (Stripe) = (924 *0.75* 1.15)/60 = 13.28 SAM for Jacket (Checks) = (1060 * 0.75*1.15)/60 = 15.24 (Appendix 1 sheet10) Let the ratio of solid, stripe and checks be5:4:1 (50%:30%:20%) (Appendix- From output report) So, average time = (5*11.43 + 3 *13.28 + 2*15.24)/ (5+3+2) = 12.75 min So, Capacity = (480*4) /12.75 = 150 i.e. 75 solid, 45 stripe and 30 checked Hence, the number of operators required is only two instead of 4. So, Capacity = (480*2) /12.75 = 75 i.e. 37 solid, 23 stripe and 15 checked
Ready Cutting (trousers)
Man Hours = 8 hrs. SAM for Jacket RC (solid) =2.51min SAM for Jacket RC (stripe) = 6.55 min SAM for Jacket RC (checks) = 9.77 min 69
Let the ratio of solid, stripe and checks be5:4:1 (50%:40%:10%) (From output report Appendix 3) So, average time = (5*2.51 +4 *6.55 + 1*9.77)/ (5+4+1) = 4.85 min So, Capacity = 480 /4.58 = 105i.e. 53 solid, 42 stripe and 10 checked Checking (Jackets)
Man Hours = 8 SAM =8.54 min So, Capacity = 480 /8.54 = 56
Checking (Trousers)
Man Hours = 8 SAM for Trouser Checking (solid& stripe) =2.23 min SAM for Jacket Checking (checks) = 4.27 min Let the ratio of solid& stripe, and checks be9:1 (90%:10%) (From output report Appendix III) So, average time = (9*2.23 + 1*4.27)/ (9+1) = 2.434 min So, Capacity = 480 /2.434 =197 i.e. 177 solid and stripe, and 20 checked 6.5 New capacity summary Operations No Of Operators Jackets Trousers Lining Cutting and Laying 2 82 163 + 82 Block Cutting 2 69 69 + 69 Fusing Cutting and Fusing M/C 1 86 320 Ready Cutting 3 75(37,23,15) 105(53,42,10) Checking 2 56 197(177,20)
Table 6.1 New Capacity Summary 70
CHAPTER 7 PROJECT COST
71
CHAPTER 7 PROJECT COST 8.1 Project Costing Tools a) Fabric Stand = Rs. 1200 x 1 = Rs. 2000 b) Lining Stand = Rs. 5000 x 1 = Rs. 5000 c) Tag Gun = Rs. 1300 x 2 = Rs. 2600 Total = Rs. 9,600 Conveyor Assembly a) 2 x 2 Square Pipe = Rs. 900 x 3 = Rs. 2,700 b) 1.5 x 1.5 Square Pipe = Rs. 800 x 15 = Rs. 12,000 c) Bush = Rs. 100 x 44 = Rs. 4,400 (Though the original cost of bush was Rs. 300 each but they were in scrap, so scrap value considered @ Rs.55 per kg) d) J hook = Rs. 900 x 7 = Rs. 6,300 e) GI Pipe(diameter ) = Rs. 900 x 12 = Rs. 10,800 f) Wheel(Handle) = Rs 150 x 50 = Rs. 7,500 g) Chain = Rs. 100 x 50 = Rs. 5,000 h) Others(Bolt, welding materials) = Rs. 5,000 i) Baskets =Rs. 150 x 25 = Rs. 3,750 Total = Rs. 57,450 Hence, total project cost = Rs. 67,050 72
The labor cost has been not included in the cost analysis because everything was developed in-house as there is a team of 45 staff in maintenance department. They are paid each month regardless of work. Since, the company is paying them regardless work they do, hence their labor cost has not been reflected in the cost sheet.
73
CHAPTER 8 RESULTS AND SAVINGS
74
CHAPTER 8 RESULTS AND SAVINGS
a) The overall capacity of the cutting department increased by 76% for suits i.e. from 39 to 69 and 72 % for trousers i.e. from 40 orders to 69 orders (Quantity can vary as an order may contain 1-10 trousers). The result was that overtime is no longer required.
No. of operators used in Over Time per day = 5 Average wage per hour = Rs. 55 Average number of hours Over Time Done = 4 hours Hence, Wage paid per day = Rs. 5 x 55 x 4 = Rs. 1100 Wage paid per month = Rs. 1100 x 30 = Rs. 33,000 (30 days has been considered because overtime was done on Sunday also) Wage paid per annum = Rs. 33,000 x 12 = Rs. 3,96,000
Hence, there will be a total saving of Rs. 3,96,000 per annum on account of avoiding overtime.
b) Four labors were shifted to other department where there was requirement. Hence, the cost incurred in cutting has been reduced on account of decreased number of labors. Labor Saved = 4 Hence, saving from operators = Rs. 5200 x 4 = Rs. 20,800 per month = Rs. 20,800 x 12 = Rs. 2,49,600 per annum Hence, a total of Rs. 2,49,600 will be saved per annum. 75
c) Reduced throughput time: As there was no sequencing and the orders which came first did not necessarily move first. So, for some orders throughput time was 12- 16 hours depending on the delay and mix up. But now the throughput time is reduced to 2-2.5 hours depending on style. Hence, the order received can be loaded in the line same day can be delivered next day by the evening reducing lead time to just 2 days from the current lead time of 4 days. d) Better workplace visualization: The status of work can be seen from anywhere in the department. If there is any hold up, the baskets will pile up and can be enquired. e) An efficient emergency order handling system:Now the emergency order is handled very efficiently and there is no need to constantly guide the worker to move emergency order. Its very systematic. The executives can also have a glance while passing and can question if there is no movement of the emergency order. f) Increased efficiency: Workers are now forced to work to supply materials to succeeding stations. Hence, the overall efficiency has increased.
76
CHAPTER 9 LIMITATIONS AND SCOPE FOR FURTHER STUDY
77
CHAPTER 9 LIMITATIONS AND SCOPE OF FURTHER STUDY Since, each order is unique in style in MTM, the data gathered for observed time, the ratio of suits to trouser quantity for capacity calculation may not be accurate; its only approximate value. One can never predict the number of orders received and their style variations in this department. So, every data presented is approximate, though care has been taken to take in account each variation. Since, the demand for increased capacity was something which needed to addressed urgently, hence, continuous improvement has been made and no drastic change was done as it requires huge capital, months of planning and culture change. But in future projects can be taken to eliminate the ready cutting. Also, the basket being used now is a bit bulky as existing unused baskets have been used for the time being because of lack of budget. But there can be alternatives to this basket. Not only this, methods can be devised to avoid manual pushing of baskets to the succeeding work stations.
78
CHAPETR 10 CONCLUSION 79
CHAPTER 10 CONCLUSION The project has achieved its intended objectives of increasing the capacity and decreasing throughput time of cutting department.The overall capacity of the cutting department increased by 76% for suits i.e. from 39 to 69 and 72 % for trousers i.e. from 40 orders to 69 orders (Quantity can vary as an order may contain 1-10 trousers). The result was that overtime is no longer required saving Rs. 3,96,000per annum. Four labors were shifted to second shift where there was requirement. Hence, the cost incurred in cutting has been reduced byRs. 2,49,600 per annum on account of decreased number of labors. Hence, a whopping sum of Rs. 6,45,600 will be saved per annum. Further, the throughput time has been reduced to 2-2.5 hours depending on style from 12-14 hours. Hence, the order received can be loaded in the line same day can be delivered next day by the evening reducing lead time to just 2 days from the current lead time of 4 days. There is increased work place visibility of work place. The status of work can be seen from anywhere in the department. If there is any hold up, the baskets will pile up and can be enquired. Now, the company has an efficient emergency order handling system and there is no need to constantly guide the worker to move emergency order. Its very systematic. The executives can also have a glance while passing and can question if there is no movement of the emergency order. .
80
BIBLIOGRAPHY Books Bicheno, J. (2004). New Lean Toolbox : Towards Fast Flexible Flow. Picsie Books. Harrington, H. (1996). The complete benchmarking implementation guide: total benchmarking management. New York: McGraw-Hill. Kanawaty, G. (1992). INTRODUCTION TO WORK STUDY. geneva: Publications of the International Labour Office. Michal Marton, I. P. (n.d.). One Piece Flow - Another View on Production Flow In The Next Continuous Process Improvement . Miller, J. (2007, April 21). Retrieved from gemba panta rei: http://www.gembapantarei.com/2007/04/ten_reasons_why_one_piece_flow.html Silver, E. P. (1998). Inventory Management and Production Planning and Scheduling. New York: Wiley. Websites http://www.fibre2fashion.com/industry-article/6/591/the-long-and-short-of-garmenting- leadtime1.asp http://apparel.edgl.com/case-studies/Optimize-Lead-Times,-Maximize-Profits74689 http://www.onlineclothingstudy.com/2011/02/garment-cm-cost-estimation-using-sam- or.html http://www.onlineclothingstudy.com/2014/02/how-to-calculate-cost-of-manufacturing.html http://www.onlineclothingstudy.com/2011/08/how-to-stop-missing-of-garments-in.html