Sei sulla pagina 1di 109

Document Title: Final Report

ENERGY MANAGEMENT ASSESSMENT / AUDIT FOR PSC


CORRIDOR (SUBAN-GRISSIK-RAWA)

COPI Doc No.:

Originator: COPI
COPI Group Owner: UO – Engineering – Onshore Sumatra
Area: General
Location: General
System: General System
Document Type: Final Report
Discipline / Sub discipline:
Old COPI Document No.: -

1 IFR 14 Dec 07 Issued for Review


2 IFR 14 Jan 08 Issued for Review

Rev Status Issue Date Reason for Issue Prepared Checked


Approvals

Printed initials in the approval boxes confirm that the document has been signed.
The originals are held within Document Management.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 2 of 109

Revision Sheet PT.E M I (Persero)


ConocoPhillips Indonesia Inc. Ltd

REVISION DATE DESCRIPTION OF CHANGE

1 14 Dec 07 Issued for Review


2 14 Jan 08 Issued for Review
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 3 of 109

CONTENTS
I. INTRODUCTION
II. METHODOLOGY
2.1 METHODOLOGY OF ENERGY ASSESSMENT

2.2 METHODOLOGY OF CALCULATION


2.2.1 CALCULATION OF EQUIPMENT
2.2.2 CALCULATION OF SYSTEM

III. ENERGY ASSESSMENT AT SUBAN GAS PLANT


3.1. GENERAL PLANT OPERATION AND PERFORMANCE
3.3.1. GENERAL PLANT OPERATION OF SUBAN GAS PLANT
3.3.2. GENERAL PLANT PERFORMANCE OF SUBAN GAS PLANT

3.2. PERFORMANCE EVALUATION EACH SYSTEM


3.2.1. SEPARATION & COOLER SYSTEM
3.2.2. AMINE SYSTEM
3.2.3. CONDENSATE STABILIZING SYSTEM
3.2.4. DEW POINT CONTROL AND REFRIGERATION SYSTEM
3.2.5. GAS COMPRESSION SYSTEM
3.2.6. GAS TURBINE GENERATOR
3.2.7. AIR COMPRESSOR
3.2.8. ELECTRICAL MAP SUBAN GAS PLANT

3.3. FINDINGS AND RECOMMENDATIONS

IV. ENERGY ASSESSMENT AT GRISSIK CENTRAL GAS PLANT


4.1. GENERAL PLANT OPERATION AND PERFORMANCE

4.1.1. GENERAL PLANT OPERATION OF GRISSIK GAS PLANT


4.1.2. GENERAL PLANT PERFORMANCE OF GRISSIK GAS PLANT

4.2. PERFORMANCE EVALUATION EACH SYSTEM


4.2.1. GAS PRETREATMENT AND MEMBRANE SYSTEM
4.2.2. AMINE SYSTEM
4.2.3. REFRIGERATION SYSTEM
4.2.4. CONDENSATE STABILIZING SYSTEM
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 4 of 109

4.2.5. DEHYDRATION SYSTEM


4.2.6. WASTE HEAT BOILER
4.2.7. GAS TURBINE GENERATOR
4.2.8. AIR COMPRESSOR
4.2.9. ELECTRICAL MAP CENTRAL GRISSIK GAS PLANT

4.3. FINDINGS AND RECOMMENDATIONS

V. ENERGY ASSESSMENT AT RAWA OIL PLANT


5.1. GENERAL PLANT OPERATION AND PERFORMANCE

5.2. PERFORMANCE EVALUATION

5.2.1. GENERAL PERFORMANCE


5.2.2. PERFORMANCE EVALUATION OF MAIN EQUIPMENT

5.3. FINDINGS AND RECOMMENDATIONS

VI. PERFORMANCE MONITORING INDICATOR


6.1. EQUIPMENTS
6.1.1. Fired Heater
6.1.2. Waste Heat Boiler
6.1.3. Gas Turbine Generator
6.1.4. Residue Gas Compressor
6.1.5. Air Compressor
6.1.6. Propane compressor
6.1.7. Pumps
6.1.8. Air Cooler
6.1.9. Heat Exchanger

6.2. SYSTEM
6.2.1. Gas Pretreatment
6.2.2. Membrane System
6.2.3. Amine System
 Amine Contactor
 Amine Regenerator
6.2.4. Dehydration System
6.2.5. Dew Point Control System
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 5 of 109

 Gas Chiller
 Low Temperature Separator
6.2.6. Condensate Stabilizer
6.2.7. Depropanizer

APPENDICES
1. SCHEDULE OF ENERGY ASSESSMENT/AUDIT

2. MEASUREMENT DATA

3. LABORATORY ANALYSIS

4. LIST OF DATA HAS BEEN COLLECTED

5. SPREAD SHEET OF EFFICIENCY AND ENERGY CONSUMPTION


EQUIPMENTS

 SUBAN GAS PLANT

 GRISSIK CENTRAL GAS PLANT

 RAWA OIL PLANT

6. SPREAD SHEET OF PERFORMANCE MONITORING INDICATOR

 EQUIPMENTS

 SYSTEMS

7. SIMULATION RESULT OF SUBAN GAS PLANT

8. SIMULATION RESULT OF GRISSIK CENTRAL GAS PLANT


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 6 of 109

I. INTRODUCTION

As a part of energy management program, in the year of 2007 the Indonesia Business
Unit of ConocoPhillips committed to develop plan regarding various efforts to conserve
sources and to reutilize waste, energy utilization and to reduce emission reduction for
each operating asset. Since 2004, emission level forecasts were generated as part of
environmental performance report that shall be further followed up in actual action
plans. This assessment is intended to guide the company in identifying energy-related
business opportunities and appropriate methods and developing the strategic
framework for realizing them. By performing this assessment / audit, it could also find
emission reduction opportunities in onshore operating asset.

The aim of this assessment is to identify where and how much energy is used in a
facility and for determining energy saving and emission reduction opportunities in
onshore operating asset.

The objectives of this assessment / audit are as followed;

1. Provide clear direction or appropriate method as to potential inherent in a


strategic approach to energy planning and management.

2. Define specific facilities that consume high energy and generate high emission.

3. To observe and evaluate the present situation of those plants in regards with
energy consumption, process efficiency or performance and emission reduction
opportunities.

4. Provide options based on a set of criteria (measures) and select the most
promising options for implementation.

5. Provide recommendations and action plans in order to reduce energy


consumption, increase plant efficiency and reduce emission rate in onshore
operating assets by implementing energy diversification, energy efficiency and
optimization and possibility to reuse energy waste.

The Scope of this assessment / audit are as followed;,

1 Preliminary Energy Audit / Assessment which includes : Review and prepare


additional information, Identification and inventory energy consumption and
production data; Analyze data to determine which equipment will get high priority
to be assessed and; prepare action plan to perform energy management audit /
assessment

2 Performing Energy Audit / Assessment which includes : Identifies area of high


energy usage and where energy waste occurs; Develop priorities for reducing
energy waste and emission; Provides a criteria of measures which improvements
could be implemented and; Generate spreadsheet for energy consumption per
equipment
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 7 of 109

3 Establish Calculation Performance Monitoring Indicators per equipment and


system

4 Provide Recommendation for Improvements a part of COPI energy management


program

To achieve the targets and to establish interactive cooperation of involved personnel


without disturbing surveyed objects routine activities, the procedure of the Energy
Assessment / Audit at Suban Gas Plant, Grisik Central Gas Plant and Rawa Oil Plant
are as follows:
Preparation of the plant survey,
Field inspection and data collection,
Data verification (of the data collected)
Discussion
Data analysis and evaluation
Preliminary report,
Discussion
Field verification
Interim Report/Draft Final Report
Presentation,
Final Report.

The preparation of the plant survey has been held on 10 – 21 September 2007. The
activity are includes define the boundaries, define data to be collected, define
instruments / meter related to the data to be collected and prepare checklist for
interview.

The Field inspection and data collection has been held on 24 September – 5 October
2007. The activity are includes collection of technical data of main energy-consuming
equipment, operation data, historical data, interview data, and direct measurement
with portable equipment. Principally, the data collected should be enogh to calculate
material and heat balance in each equipment.

During data collecting period at Suban Gas Plant, Grissik Central Gas Plant and Rawa
Oil Plant, not all the data requirement for analysis has been collected. Some of the
data are completed from COPI Office Jakarta and the other data are completed during
2nd field inspection. Direct measurement are done for all fired heater at Suban Gas
Plant and Waste Heat Boiler at Grissik Central Gas Plant.

In order to crosscheck the data gathered are accurate and reliable before carrying out
analyses, it is need to do the data verification. The data verification, has been held on
8 - 10 October 2007 and the discussion regarding the result of data verification has
been held on 23 October 2007.

Data analysis and evaluation has been held on 22 October – 23 November 2007. The
activity of the analysis are includes preparation of calculation methodology, spread
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 8 of 109

sheet of equipment, develop heat and material balance, performance evaluation,


identification/quantification of heat loss and calculation of energy conservation
opportunities. The result of data analysis and evaluation are reported in the
Preliminary Report on 26 November 2007 and discussion regarding this report has
been held on 29 – 30 November 2007.

2nd field survey has been held on 3 – 7 December 2007 at Suban and Grissik. The
activity during 2nd field survey are includes :
Measurement of flue gas composition and temperature of Heater and
Waste Heat Boiler.
Electrical data records for rotating equipments.
Presentation of draft final report has been held on 18-19 December 2007
The Schedule of Energy Assessment, data has been collected and measured,
laboratory analysis are summarized in the appendices no.1 – no. 4.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 9 of 109

II. METHODOLOGY

2.1. METHODOLOGY OF ENERGY ASSESSMENT/AUDIT


Obviously, the Methodology of Energy Assessment / Audit at Suban Gas Plant, Grisik
Gas Plant and Rawa Oil Plant will involve :
 Collect and Analyze Energy-Usage Data
 Review, identify and inventory energy consumption data
 Identify the main energy consumption system and equipments
 Performance evaluation and identify the main energy consumption
equipment.
 Quantity energy waste and emission.
 Recommendation.

The information regarding plant operation has been collected during data collection
period from 24 September to 5 October 2007.

The data will be used in the analysis are include;


 Daily Log Sheets
 Computer logged data (for Suban and Grissik)
 Laboratory analysis
 Direct measurement during plant survey
 Design data

After all the data has been collected, It is need to develop mass balance of each unit
in order to verify the accuracy of flow meter reading. If there are discrepancy between
mass inlet and outlet, ones of the mass flow should be adjusted, and than the data
that has been verified will be used as data basis for development of heat and mass
balance each equipment and system.

By using Spreadsheet and Process Simulation, a plant model will be created to


calculate performance aspect of the equipments and compare with design or available
references.

The plant model spreadsheet is constructed based on material and energy balance
each equipment, energy efficiency and losses. Process Simulation used to develop
material and energy balance for overall process gas plant.

Especially on the fired heater and waste heat boiler the spreadsheet is constructed
based on the calculation of energy efficiency, losses and emission level of each
equipment. Based on the data that has been collected, performance of each
equipment, efficiency level, energy waste and emission reduction potential of
equipment will be calculated and quantified.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 10 of 109

Based on the energy and emission reduction potential level of each equipment and
refer to technical and financial criteria, recommendation for improvement measure will
be identified.

All of the results of the evaluation / analysis will be discuss, present and reported to
ConocoPhillips.

The reporting of energy assessment / audit wil include preliminary report, interim/draft
final report and final report.
The preliminary report which covers : energy audit methodology, all data
collected, all formula for calculations and preliminary findings.
The interim/draft final report which covers : energy audit methodology, all
data collected, energy performance analysis result, quantity of all energy
waste and emission, energy waste and emission reduction opportunities
and performance monitoring system.
The final report which contains of: executive summary, evaluation result
during audit / assessment, spreadsheet of energy consumption,
spreadsheet of performance monitoring indicators and detail
recommendation report.

2.2. METHODOLOGY OF CALCULATION


The methodology of calculation are developed in two model which includes the
calculation of equipment and the calculation of process system.

 The Calculation of Equipment are includes :


Fired Heater; Waste Heat Boiler; Gas Turbine Generator; Residual
Compressor; Air Compressor; Propane Compressor; Pumps; Air Cooler; Heat
Exchanger .

 The Calculation of Process system are includes :


Separation system; Amine System; Dehydration System; Condensate Stabilizer
System, Depropanizer System and Refrigeration System

All of the calculation are explained regarding the efficiency and performance of each
equipment and process system.

2.2.1. CALCULATION OF EQUIPMENTS

2.2.1.a. Fired Heater


The biggest energy consumption in the operation of gas plant is fired heater, so
the evaluation of fired heater especially the efficiency and performance are very
important in this assessment.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 11 of 109

%O2, T stack

Conv. Flue Gas


Rad.
Ta(ambient air temp)

AIR

FUEL FIRED HEATER Proc Fluid

Proc Fluid T out

Fluid Flow
T in

Efficiency of Fired Heater can be calculated in two ways ie. :

 Direct Method
 Heat Loss Method *
* Refer to Enercon Handbook

a. Direct Method :

The step of calculation are as follows,


Calculate heat duty of fired heater, k cal/hr
Calculate LHV of fuel gas (refer to lab test), kcal/hr

heat duty of fired heater


Efficiency = X 100%
LHV of fuel gas

b. Heat Loss Method

Fired Heater Efficiency are calculated based on the heat loss of :


 dry flue gas
 H2O from combustion of H2
 H2O moisture from fuel gas
 H2O moisture from air
 radiation and convection (refer to design)
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 12 of 109

The step of calculation of heat loss method in the fired heater are as follows,
a. Measure Ta, Tstack and % O2 in flue gas
b. Calculate combustion air for stoichiometry condition
c. Calculate excess air at % O2 as measure
d. Calculate flue gas flow, kg/h
(flue gas flow = fuel + comb air stoch + excess air)
e. Calculate flue gas loss, kcal/hr
(flue gas loss = flue gas flow x Cp x (Tst – Ta))

LHV of Flue Gas – flue gas loss – Rad & Conv Loss**
Efficiency = X 100%
LHV of Fuel Gas
** Refer to design condition

The efficiency calculated from heat loss method can be used to check the accuracy of
fuel gas flow meter recorded at each fired heater. The step of calculation are as follows
:
 calculate heat duty of fired heater based on the different enthalpy of BFW
(steam) inlet and outlet.
 calculate the heat release of fired heater based on the calculated efficiency
(ie. the heat duty divided by efficiency).
 heat release from the calculation can be used to check the accuracy of fuel
gas flow meter recorded at each fired heater

2.2.1.b. Waste Heat Boiler (WHB)


The calculation methodology of WHB is similar with fired heater, the small different is
in the calculation of steam flow which is calculated based on BFW flow rate minus
blow down flow rate.

Efficiency of Waste Heat Boiler also can be calculated in two ways ie. :
 Direct Method
 Heat Loss Method *
* Refer to Enercon Handbook

a. Direct Method

(Hst – HBFW) x ST.Flow


Efficiency = X 100%
L.H.V. (Fuel Gas + Pem Gas + Acid Gas)
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 13 of 109

% O2 , Tstack
Ta (ambient air temp)
Conv. Flue Gas
Rad.

AIR

Fuel Gas

Steam
Acid Gas
WASTE HEAT
BOILER Flow, P, Tsteam
Permeat Gas

Water

Blow Down

b. Heat Loss Method

The step of calculation are as follows,


a. Measure Ta, T stack and % O2 in flue gas
b. Calculate combustion air of acid gas, permeate gas and fuel gas for
stochiometry condition
c. Calculate excess air at actual condition
d. Calculate dry flue gas flow at actual conditions, kg/hr
e. Calculate total loss, kcal/hr

Total loss = dry flue gas loss + blow down loss + rad & conv. loss

Dry flue gas = flue gas flow x Cp x (Tst – Ta)


Blow down loss = % blow down *x ST. Flow x ( H Saturate – HBFW)
*Assume % blow down (± 2%)

** Refer to design condition

LHV (Total) – Total loss


Efficiency = X 100%
LHV (Total)
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 14 of 109

2.2.1.c. Gas Turbine Generator

Conv Flue Gas


Rad.

AIR

FUEL GTG BH
P G ELECTR
IC

kWh x 860.1 x 3.968


Efficiency = X 100%
LHV Fuel Gas x Flow F.G (Btu/h)

LHV Fuel Gas x Flow Fuel Gas


Performance =
kWh

Efficiency of Gas Turbine also can be calculated by using heat loss method, which
include heat loss of :
 dry flue gas
 H2O from combustion of H2
 H2O moisture from fuel gas
 H2O moisture from air
 radiation and convection (refer to design)

2.2.1.d. Residual Gas Compressor

Mechanical work derived from


Fuel gas input pressure

compressor

Energy loss
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 15 of 109

Mechanical work
Efficiency =
Heat from fuel gas input

ZRT n Pd n-1
Mechanical Work *= Qx x x (( ) n - 1 ) / (33,000 x 0.77)
MW n –1 Ps

Q = Gas Flow, lb / mnt


R = Gas Constant
MW = Molecular weight
T = inlet Temperature, oR
Z = Compressibility Factor
n = Polytropic Factor
Pd = Discharge Pressure
Ps = Suction Pressure
* Refer to Pipeline Handbook

Efficiency of Gas Turbine also can be calculated by using heat loss methode, which
include heat loss of :
 dry flue gas
 H2O from combustion of H2
 H2O moisture from fuel gas
 H2O moisture from air
 radiation and convection (refer to design)

2.2.1.e. Air compressor

Electric power Mechanical work derived from


input pressure

Energy loss

Mechanical work
Efficiency =
Electric power input

1.4 Ps Q Pd 0.4 O x 10.000


Mechanical Work * = x x(( )1.4 - 1) x
0.4 6120 Ps 0.8 x 0.95
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 16 of 109

Ps = Inlet Press Kgf/ cm2


Q = Air Flow m3 / mnt
R = Press ratio P2 / P1
O = Factor ( 1.0 – 1.5 )

* Refer to Energy Conservation Handbook – ECC Japan

2.2.1.f. Propane compressor

Electric power Mechanical work derived from


input pressure

Energy loss

Mechanical work
Efficiency =
Heat from fuel gas input

ZRT n Pd n-1
Mechanical Work * = Q x x x (( ) n - 1 ) / (33,000 x 0.77)
MW n–1 Ps

Q = Gas Flow, lb / mnt


R = Gas Constant
MW = Molecular weight
T = inlet Temperature, oR
Z = Compressibility Factor
n = Polytropic Factor
Pd = Discharge Pressure
Ps = Suction Pressure

* Refer to Pipeline Handbook


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 17 of 109

2.2.1.g. Gas Chiller

From Gas to Gas HE


To Propane
Gas Compressor
H2
T1

Gas Chiller

H1
To
To Propane
From Propane
Low Temperatur Acumulator
Separator

Cooling Load* = (GF x Cp g (To – Ti)) + (CF x Cpc (To – Ti)) + (f x CF x Latent Heat)

Cooling Load
COP Actual* =
compressor motor power (actual)

Cp g = Specific Heat gas at P & T operation


GF = Gas Flow
CF = Condensate Flow
Cp c = Specific Heat condensate
f = fraction of condensate

* Refer to ASHRAE Handbook (fundamentals)

2.2.1.h. Pumps
Energy loss

Electric power input


Mechanical work (capacity, total head)

Obtained from curves into data sheet

Mechanical work
Efficiency =
Electric power input
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 18 of 109

Mechanical Work (Pw) *:


Pw (hp) = fv.(Sg x Ht) / 3960

Sg = Specific grafity
Ht = Total Head (feet)
Fv = Correction factor related to
viscousity

Ht (psia) = Dp – Sp

Sp = Suction pressure (psia)


Dp = Discharge pressure (psia)

Ht (feet) = 2.31 x Ht (psia)

* Refer to Pump Handbook - Karrasik, Krutzsch

2.2.1.i. Air cooler

Energy
T in h loss T out l

m, p
Electric power
input

T in l T out h

Efficiency = Cooling Load


Electric power input

Cooling Load = Q

Q = m (H)
Where
m : Flow rate
H : Enthalpy different

Fouling Factor Performance are calculated based on the value of Overall heat
transfer coefficient (Uo):
Uo = Q / (A Tlm)
Q : actual heat load (Q act)
A : Heat transfer Area
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 19 of 109

Tlm : Log Mean Temperature Different

2.2.1.j. Heat Exchanger


Evaluation of heat exchanger are include the performance of heat transfer
coefficient compare to design condition. If the heat transfer coefficient are lower it
is could be caused by fouling or there are change in quality or quantity in the
process side.

VAP. OUT VAP. OUT

VENT
STEAM IN

LIQ. OUT VAP. IN VAP. IN CONDENSATE


OUT

a. Performance Calculation:

Performance = [Heat load based on actual data calculation]


[Heat load based on basic design calculation]

= Q act / Q design

b. Fouling Factor Performance are calculated based on the value of Overall heat
transfer coefficient (Uo):
Uo = Q / (A Tlm)
Q : actual heat load (Q act)
A : Heat transfer Area
Tlm : Log Mean Temperature Different
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 20 of 109

2.2.2. CALCULATION OF SYSTEMS

2.2.2.a. Separation System


a. TSA UNIT

FEED GAS

ADSORBTION
COLUMN

TREATED
GAS

Adsorption Rate = (mole C6+ Feed - mole C6+ Treated) (lbmole/lbmole)


Mole C6+ Feed
TSA Regeneration Rate = BTU (BTU/lbmole)
(mole C6+ Feed - mole C6+ Treated)

b. Membrane Unit

PROCESS GAS

MEMBRANE
FEED GAS

PERMEATE GAS

Membrane separation rate = mole CO2 in Permeate Gas (lbmole/ lbmole)


Mole CO2 in Feed Gas
HC Slipped rate = mole HC in Permeate Gas (lbmole/ lb mole)
Mole HC in Feed Gas
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 21 of 109

2.2.2.b. Amine System


a. Amine Contactor
TREATED
GAS

LEAN
AMINE

FEED GAS AMINE


CONTACTOR

RICH
AMINE

Absorbtion Rate = ``mole-CO2 absorbed (lbmole/lbmole) and (lb/lb)


Mole pure lean amine
Mole Weight of pure Lean Amine are dynamic should be calculated

b. Amine Regenerator

ACID GAS

RICH
AMINE

STEAM

AMINE
REGENERATOR
CONDENSATE

LEAN
AMINE

Amine Regeneration Rate = BTU(steam) (BTU/lbmole -CO2)


CO2 removed
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 22 of 109

2.2.2.c. Dehydration System

GAS

TREATED DEHYDRATION GLYCOL


MAKE-UP
GAS PACKAGE
FUEL GAS
CONSUMPTION
GLYCOL
MOISTURE
CYCLE
OUT
WATER VAPOR
OUT

Absorbtion Rate = lbs-H2O absorbed (lbmole/GPM) and (Lb-H2O/Lb-Glycol)


GPM Pure Lean Glycol

Glycol Regeneration Rate = BTU (Fuel Gas) (BTU/lb –H2O)


Moisture removed

2.2.2.d. Condensate Stabilizer

LP FUEL GAS

FEED
LIQUID LIGHT HC

STEAM

CONDENSATE
STABILIZATION
STEAM
CONDENSATE
CONDENSATE
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 23 of 109

Yield of Stabilization = BBL Treated Condensate (bbl/ bbl)


BBL Raw Condensate

Quantity total of condensate refer to percentage of feed inlet

Stabilizer Performance = BTU(steam) (BTU/ bbl)


BBL Treated Condensate flow

2.2.2.e. Depropanizer

PROPANE
PRODUCT

FEED
LIQUID

DEPROPANIZER

CONDENSATE
PRODUCT

Yield of Stabilization = mole Propane product (lbmole/ lbmole)


Mole Feed HC

Deprop. Performance = kWh(Electric) (kWh/ lbmol)


Lbmole Propane product
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 24 of 109

III. ENERGY ASSESSMENT AT SUBAN GAS


PLANT

3.1. GENERAL PLANT OPERATION AND PERFORMANCE


3.1.1. GENERAL PLANT OPERATION OF SUBAN GAS PLANT

Gas from well head is delivered to CGP with flow line about 1 km length to the
separation unit, HP Production Separator. Because gas produced from HP Production
Separator still contain CO2, H2S and H2O in high concentration, it has to be treated
by CO2/H2S Removal Package and Dehydration Unit to meet the gas delivery
condition requirements.

A selective Amine based on MDEA solvent shall be provided for removal of CO2 &
H2S in feed gas from Gas Scrubber, to meet the sales gas specification. The
system shall also include the regeneration of the MDEA solvent used to absorb
H2S.

Acid Gas Removal Unit is installed with capacity 700 MMSCFD (total 4 trains) Sour
Gas and should be removed CO2 / H2S until meet sales gas specification (3%).
Acid gas released from Acid Gas Removal unit should be routed to The treated gas
scrubber Unit with enough pressure approximately 1400 psig to ensure Acid Gas
have enough pressure for next processes.

A Ethylene Glycol based gas dehydration unit shall be provided to dehydrate gas
from amine unit to achieve the sales gas specification (5-7 Lb/SCF). EG Dehydration
Unit is with capacity 700 MMSCFD (Total 4 trains).

The treated gas will be compressed by GTC (Gas To Compressor) with capacity 235
MMSCFD (There are 4 GTC, each of GTC has 235 MMSCFD Capacity) to increase
sales gas pressure until 1280 psig. The other part of treated gas is delivered to Fuel
Gas Filter as Fuel Gas for Gas Turbine Generator (GTG),Gas Turbine Compressor or
as fuel gas for the CPP gas engine equipment.

The Condensate from Horizontal Separator is routed to Stabilizer Feed Drum for
further separation process from carry over gas. To meet the Condensate Delivery
Condition, the condensate produced is stabilized with Condensate Stabilization Units,
with capacity are 44,349 Lb/hr for train 1 & 82,211 Lb/hr for train 2, and then stored in
the Condensate Storage Tank with capacity is 30,000 BBL. The condensate pumps
will be used to dispatch the condensate to Condensate Truck Loading.

Water collect from separation unit is automatically drained to a common header and
then to be processed in the produced water treatment system.

Blow down system is used for over pressure protection or for reducing the CGP
pressure either in emergency (ESD) or at the operator’s discretion in a shutdown and
blocked condition. The blow down system shall be capable of relieving the entire CPP
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 25 of 109

equipments from the highest possible shut-in pressure down to half times in 15
minutes. The blow down system is arranged with automatic blow down valves which
is fitted at the downstream of the separation units and at the discharge of CNG
Compressor to blow down through the HP Flare vent line.
Localized venting of gas to atmosphere is also provided for piping and vessels via
manual vents and pressure relieving devices, i.e. relief valves.

Fire water will be supplied from the fire water make up pump to a Fire Water Pond.
Fire water is distributed to the fire water main ring by three fire water pumps (two
pumps act as main pumps, and one as jockey) in a duty standby arrangement. Foam
tank and foam pump are provided to protect the condensate storage tank. The CGP
shall be fully equipped with fire and gas detection system.

All electric instruments shall be hard-wired to CGP Control Room and communicated
to Programmable Logic Control (PLC) and Human Machine Interface (HMI) to monitor
and control the process.

The simple process flow of Suban field is shown with block diagram in figure 2.1

Gas to Flare
7

Acid Gas

T 1 T 2 T 3 T 5 T Sales Gas
6

Suban Gas Well Gas Seperation Unit Amine System TEG Dehydration Unit Residual Compressor

T Condensate
8 10

Condensate Stabilizer

11 Liquid water

Figure 3.1. Simple Block Diagram

Gas from Inlet Separator still contains CO2 and H2O in high concentration. The gas
shall be treated in purification unit before the gas is delivered to Grissik Central Gas
Processing plant by Pipe line system.

3.1.2. GENERAL PLANT PERFORMANCE OF SUBAN GAS PLANT

The Energy source of Suban Gas Plant actually are fuel gas from Scrubber which is
consumed by GTG, GTC and Fired Heater (thermal oxidizer, amine re-boiler heater
and heat medium heater).

Based on 29 September 2007, the fuel gas consumption for each equipment are
shown in table below;
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 26 of 109

Table 3-1 : Fuel gas consumption

Fuel Gas to Flare


248-FQI-2131B D 0.200 MMSCFD
248-FQI-2231B D 1.000 MMSCFD
TOTAL C 1.200 MMSCFD
Fuel Gas to Heater
Thermal Oxidixer
225-H-102 D 0.314 MMSCFD
225-H-202 D 0.161 MMSCFD
0.475 MMSCFD
Amine Reb Heater
225-H-111 D 0.620 MMSCFD
225-H-211 D 0.563 MMSCFD
1.183 MMSCFD
Heat Medium Heater
257-H-101A D 0.121 MMSCFD
257-H-101B D 0.016 MMSCFD
257-H-201A D 0.152 MMSCFD
257-H-201B D 0.138 MMSCFD
C 0.428 MMSCFD
Fuel gas to GTG
247-GT-101A -
247-GT-101B -
247-GT-201A C 0.900 MMSCFD
247-GT-201B C 0.900 MMSCFD
247-GT-201C C 0.900 MMSCFD
D 2.700 MMSCFD
Fuel gas to GTC
242-KT-101 D 0.590 MMSCFD
242-KT-201 D - MMSCFD
242-KT-301 D 0.730 MMSCFD
242-KT-401 D 0.700 MMSCFD
C 1.430 MMSCFD
TOTAL - 2
C 6.22 MMSCFD
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 27 of 109

TOTAL
C 7.42 MMSCFD

Note : D = Data ; C = Calculated

The total fuel consumption at 29 September 2007 (including fuel gas to flare) is
7.42 MMSCFD. There are two type of fuel gas used in Suban Gas Plant ie. : LP
Fuel gas and HP Fuel gas. LP Fuel gas is used to fired heater and HP Fuel gas is
used to GTG and GTC. The heating value (HHV) of LP Fuel gas is around 1,574
Btu/SCF and HP Fuel Gas is around 1,130 Btu/SCF.

Based on the heat balance calculation of Fired Heater, GTG and GTC, the energy
picture on 29 September 2007 which are includes Heat Release, Heat Absorb,
Heat Loss and CO2 emission are as follows :

Table 3-2 : The energy picture of Suban Gas Plant

HEAT HEAT STACK TEMP, CO2


RELEASE, ABSORB, LOSS, Deg F Emission,
Btu/hr Btu/hr Btu/hr lb/hr

FLARE
248-FQI-2131B 13,200,110 0 11,898,856 1,472 1,849
248-FQI-2231B 66,000,552 0 59,494,279 1,472 9,243
HEATER
Thermal Oxidizer
225-H-102 38,486,293 0 35,495,414 932 81,738
225-H-202 10,602,175 0 8,303,983 2,012 1,488
Amine Reboiler H-M
Heater
225-H-111 40,771,370 32,203,736 9,055,361 405 5,730
225-H-211 37,035,660 29,160,613 8,988,198 361 5,204
Heat Medium Heater
257-H-101A 8,017,576 5,448,456 2,338,395 486 1,123
257-H-101B 0 0 0 0 0
257-H-201A 10,004,765 7,479,528 2,322,751 543 1,405
257-H-201B 9,088,243 6,758,329 2,473,720 500 1,275
GTG
247-GT-101A 0 0 0 0 0
247-GT-101B 0 0 0 0 0
247-GT-201A 42,371,386 7,714,245 33,163,974 916 5,611
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 28 of 109

247-GT-201B 42,371,386 7,721,419 29,310,275 921 5,611


247-GT-201C 42,371,386 7,702,911 29,397,944 925 5,611
GTC
242-K-101 28,157,031 4,816,837 21,555,786 1,213 1,668
242-K-201 0 0 0 0 0
242-K-301 34,800,050 7,277,193 22,755,271 1,261 2,064
242-K-401 33,379,354 6,924,878 21,806,787 1,237 1,979

TOTAL 456,657,336 123,208,143 298,360,993 689 131,598

Plant Performance :

The production rate at 29 September 2007 is 94,023 BOE which include 517
MMSCFD of sales gas (note : 1 SCF = 6000 BOE) and 7,823 barrel of condensate, and
total heat released including flare gas is 456,657,336 Btu/hr. The performance of
Suban Gas Plant as shown in table below :

Table 3-3 : Suban Gas Plant performance

PRODUCTION RATE
Sales Gas = 517.20 MMSCFD
= 86,200.00 BOE

Condensate = 7,823.00 BOE

Total Prod => 94,023.00 BOE

ENERGY CONSUME
Excluding Flare 377,456,674.27
Including Flare 456,657,336.12 Btu/hr

ENERGY INTENSITY
Excluding Flare 4,014.51 Btu/BOE
Including Flare 4,856.87 Btu/BOE

It shown that the energy consumption to produce one BOE (= Energy Intensity) at
Suban Gas Plant is 4,014.51 Btu/BOE (Excluding Flare) or 4,856 Btu/BOE (including
flare) . (Note : No design data to compare the Actual Energy Intensity).
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 29 of 109

This condition can not compare with another gas plant, because every plant have its
own characteristic. The important thing is how to reduce energy consumption based
on its own characteristic.

3.2 PERFORMANCE EVALUATION EACH SYSTEM

3.2.1 SEPARATION & COOLER SYSTEM

A. DESCRIPTION

Gas from manifold enters the Inlet Separator which will separate gas from the bulk
liquid. The separator are designed for gas flow 160 MMSCFD (for train 1,2) and 214
MMSCFD (for train 3,4), whereas liquid flow are designed about 1973 gallon/min ( for
train 1,2) and 2640 gallon/min (for train 3,4) . Production Separator will be normally
operated at pressure 1188 psig and temperature 240 °F.

The Inlet Separator is a three phase separator to provide primary gas-condensate-


water separation. This is to ensure that no significant carry-over/under of the
respective phases.

B. PERFORMANCE
Main equipment of Separation and cooler system are include : Inlet Cooler 215-E-
101A/B, 215-E-201A/B, 215-E-401A/B and 215-E-301A/B. The performance of
main equipment are as follows.

Table 3-4 : Performance of Inlet Cooler

215-E-101 215-E-201 215-E-301 215-E-401 DESIGN

INLET GAS COOLER


Temp inlet, F 220.00 218.00 220.00 220.00 240.00
Temp outlet, F 110.00 110.00 110.00 110.00 115.00
Flowrate, lb/hr 323,297 323,297 486,956 486,956 476,174
AIR COOLANT
Temp inlet, F 93.20 93.20 93.20 93.20 95.00
Temp outlet, F 113.00 113.00 114.00 114.00 131.60
Delta T LMTD 45.96 45.96 46.54 46.54 52.30

HEAT DUTY, MMBtu/hr 28.37 28.37 43.04 43.04 50.01


HEAT TRANSFER RATE, 4.46 4.46 3.08 3.08 5.09
BTU/HR.FT2.F
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 30 of 109

ELECTRIC 13.13 13.13 13.13 13.13 16.41


CONSUMPTION, KW
ACTUAL FAN OPERATED 4.00 4.00 4.00 4.00 4.00
CALCULATE FAN 3.04 3.04 3.44 3.44 4.00
OPERATED

The above table shows that the actual heat duty of each inlet cooler are less than
design. It means that the actual cooling rate needs less energy than design. The heat
duty on Train #1 and #2 are operated at 60% of design.

The heat transfer rates of exchangers are closed to the design. Based on actual
condition, the performance of cooler is still in good condition.

Losses at inlet cooler are described from cooler outlet temperature. If the outlet
temperature higher than the design outlet temperature, it means the cooling rate is not
good. At this case, the exchangers are still in good condition.

3.2.2 AMINE SYSTEM

A. DESCRIPTION

The feed gas from Inlet Separator contains CO2 5.42% by mole and small of H2S
content. A typical feed condition is 114 oF and 1163 psia; The products specifications
is designed for the CO2 content is 3.4 % by mole respectively. The acid gas removal
package uses activated methyl-di ethanolamine (MDEA) to remove the acid gases
(H2S & CO2) by means of counter-current mass transfer in an Amine Contactor unit.

The gas from the inlet separator will be fed to the Acid Gas Removal Package. As the
inlet gas is a saturated gas stream, there is a possibility of hydrocarbon and water
condensation prior to inlet of the amine contactor. To minimise liquid carry-over to the
system, a Horizontal filter unit is provided. The horizontal filter unit will have level
control drain-off valves, both on the upstream and downstream of the filter element,
whereby the liquid is sent to the flare system for disposal.

The liquid free gas from the Horizontal filter is then fed to the Amine Contactor,
whereby the gas is in contact with lean aqueous MDEA solution (amine). The
enhanced solubility of the acid gas in lean amine would soluble the acid gas
component, thus stripping it of H2S and CO2.

The rich amine from the contactors flows to the rich amine flash drums. The rich
amine flows under level/flow control through the lean/rich amine exchangers where it
is heated to about 206 oF by heat exchange with the hot lean amine from the two
regenerators. The rich amine feeds the regenerator above the stripping section which
contains stainless steel structured packing. CO2 and H2S are stripped from the rich
solution by heat produced in the regenerator re-boilers.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 31 of 109

B. PERFORMANCE

Main equipment of Amine System are includes :

Amine Heat Medium Heater (225-H-111; 225-H-211); Amine Reg. Reboiler


(225-E-102 A/B, 225-E-202 A/B); Treated Gas Cooler (225-E-105, 225-E -205, 225-E
-305, 225-E -405), Amine Charge Pump (225-P-102A/B/C), Amine Booster Pump
(225-P-101A/B/C) and Amine Heat Medium Circ. Pump (225-P-111A/B/C, 211A/B/C).

The performance of main equipment of Amine System are as follows.

Amine Heat Medium Heater :

Table 3-5 : Performance of Amine Heat Medium Heater

225-H-111 225-H-211 DESIGN


FUEL,
Flow, MMSCFD 0.62 0.56 1.13
FLUE GAS
T out, F 404.60 361.40 412.00
O2, % 6.50 9.20 3.00
Excess Air, % 41.00 83.15 15.27
HOT WATER
lb/hr 2,285,233 2,004,973 2,910,000
T in, F 257 257 285
T out, F 270 270 305
P in, Psi 280 280 285
P out, Psi 270 270 274
PERFORMANCE
Heat absorption (LHV), 31.81 28.70 57.98
MMBtu/hr
Heat absorption (HHV), 32.20 28.94 58.12
MMBtu/hr
Efficiency (LHV), % 85.80 84.87 89.11
Efficiency (HHV), % 78.95 78.06 81.18
CO2 EMISSION
CO2 Emission from fuel 5,730 5,203 10,609
gas, lb/hr

The heat duty of Amine H-M Heater was only 55 % and 50 % load compare to design
condition.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 32 of 109

The efficiency by using heat loss method are calculated based on the flue gas
composition and temperature measurement by using portable analyzer and
thermometer. No meter of temperature and O2 analyzer in flue gas line.

The flue gas temperature at actual condition is lower than design condition but the
excess air is too high and the operating load is too low. The efficiency at actual
condition is around 85 % compare to design condition which is 89 %. This efficiency
is low compare to design condition, it is caused by higher excess air and lower
operating load.

Amine Regenerator Reboiler:

Table 3-6 : Performance of Amine Regenerator Reboiler

225-E-102A/B 225-E-202A/B DESIGN

HEAT MEDIUM SIDE (TUBE)


Pressure, psig 280.00 8.70 235.00
Temp. inlet (F) 275.00 278 305.00
Temp. outlet (F) 250.00 250 285.00
Flowrate Heat Medium, Lb/hr 1,025,912 894,957 1,412,550
AMINE SIDE (SHELL)
Temp. inlet Regenerator, F 212.00 205 249.1
Temp. outlet Regenerator, F 220.00 240 254.3
Delta T LMTD 45.98 41.40 42.88

HEAT DUTY, Btu/hr 26,313,323 25,711,215 29,084,405


HEAT TRANSFER RATE SERVICE, 85 93 101
2
BTU/HR.FT .degF

The above table shows that the heat duty operated closed to the design. The
difference between actual heat duty and design only 10%. The operated temperature
higher than design value.

The performance of heat exchanger can be evaluated from the value of overall heat
transfer rate (U). The U at actual condition is 85 BTU/(Hr/Ft2.F) and 93 BTU/(Hr/Ft2.F)
compare to design value which is 101 BTU/(Hr/Ft2.F..
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 33 of 109

Treated Gas Cooler :

Table 3-7 : Performance of Treated Gas Cooler

225-E-105 225-E-205 DESIGN


WATER+ACID GAS
Pressure,psig 1206 1202 1162
Temp inlet, F 147.90 152.00 139.80
Temp outlet, F 120.70 125.70 120.00
Flowrateof Acid gas, MMSCFD 138.92 119.56 151.80
AIR COOLANT
Temp inlet, F 92.00 92.00 95.00
Temp outlet, F 110.00 112.00 118.40
Delta T LMTD 33.09 36.76 26.50

HEAT DUTY, Btu/hr 4,622,698 3,873,942 4,300,000


ELECTRIC CONSUMPTION, KW 56.79 55.61 59.68
ACTUAL FAN OPERATED 2 2 2
CALCULATE FAN OPERATED 2.1 1.8 2.0
HEAT TRANSFER RATE, 3.9 3.0 5.2
BTU/HR.FT2.F

225-E-305 225-E-405 DESIGN


WATER+ACID GAS
Pressure,psig 1206 OFF 1162
Temp inlet, F 147.90 OFF 139.80
Temp outlet, F 126.50 OFF 120.00
Flowrateof Acid gas, MMSCFD 204.82 OFF 203.40
AIR COOLANT
Temp inlet, F 92.00 OFF 95.00
Temp outlet, F 110.00 OFF 118.40
Delta T LMTD 33.09 OFF 26.5/23

HEAT DUTY, Btu/hr 5,346,317 OFF 5,810,000


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 34 of 109

ELECTRIC CONSUMPTION, KW 59.15 OFF 59.68


ACTUAL FAN OPERATED 2 OFF 2
CALCULATE FAN OPERATED 1.9 OFF 2.0
HEAT TRANSFER RATE, 4.5 OFF 5.4
BTU/HR.FT2.F

The above table shows that the actual heat duty closed to the design. The difference
between actual and design only +/- 10%. Electric power consumption for motor fan
drivers also close to design with deviance not more than 7%. The fan running at actual
condition also same as design, each exchanger have 2 (two) fans running. This
indicates that the process is in good condition. Temperatures of gas outlet from these
exchangers all meet the specification process condition, 120.7 and 125.7 deg F for
train#1 and #2, and 126 deg F for train#3 refer to the design is 120 and 203.4 deg F
respectively.

The performance of heat exchanger can be evaluated from the value of overall heat
transfer rate (U). The U at operating condition give value of 3.9 and 3.0
BTU/(Hr/Ft2.F) for train#1 and train#2 and 4.5 BTU/(Hr/Ft2.F) for train#3. The design
value is 5.2 and 5.4 BTU/(Hr/Ft2.F).

Regenerator Reflux Condenser :

Table 3-8 : Performance of Regenerator Reflux Condenser

225-E-101 225-E-201 DESIGN


WATER+ACID GAS
Pressure,psig 11.9 12 26.9
Temp inlet, F 194.40 226.4 205.00
Temp outlet, F 135.60 120.5 120.00
Flowrateof Acid gas, MMSCFD 5.50 7.3 8.76
AIR COOLANT
Temp inlet, F 92.00 92 92.00
Temp outlet, F 140.00 145 144.00
Delta T LMTD 48.80 50.41 48.60

HEAT DUTY, Btu/hr 9,259,749 13,234,590 16,824,662


ELECTRIC CONSUMPTION, KW 17.67 40.04 44.00
ACTUAL FAN OPERATED 2 4 4
CALCULATE FAN OPERATED 2.2 3.1 4.0
HEAT TRANSFER RATE, 1.9 2.7 3.0
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 35 of 109

BTU/HR.FT2.F

The above table shows that regenerator reflux condenser is operated at 55% load for
225-E-101 and 78% load for 225-E-201 compare to design condition. This caused by
the flow rate of acid gas are 62% and 83% compare to design condition.

Actual fan operated for the cooler 225-E-101 is 2 fans running, but the calculated fan
should be operated is 3 fans (2.2). This causes the temperature of the outlet of cooler
is higher than the design. Design value state the temperature is 120 deg F, but this
cooler operated at 135 deg F. The outlet temperature of cooler 225-E-201 is meet to
the design value.

The U (overall heat transfer rate) at actual condition is 1.9 and 2.7 BTU/(Hr/Ft2.F) for
225-E-101 and 225-E-201 compare to design is 3.0 BTU/(Hr/Ft2.F).

Lean Amine Cooler :

Table 3-9 : Performance of Lean Amine Cooler

225-E-103 225-E-203 DESIGN


LEAN AMINE SIDE
Pressure, psig 135.00 135.00 129.43
Temp inlet, F 180.00 180 182.90
Temp outlet, F 130.00 130 125.00
AIR COOLANT SIDE
Temp inlet, F 94.00 94 95.00
Temp outlet, F 135.00 134 137.20
Delta T LMTD 40.33 40.80 37.30

HEAT DUTY, Btu/hr 16,784,037 16,254,308 31,537,959

ELECTRIC
35.35 35.35 76.00
CONSUMPTION, KW

ACTUAL FAN OPERATED 2.00 2.00 4.00

CALCULATE FAN
2.1 2.1 4.0
OPERATED

HEAT TRANSFER RATE,


1.6 1.5 1.8
BTU/(HR.Ft2.degF)
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 36 of 109

The above table shows that the actual heat duty of 225-E-103 and 225-E-203 are
rated at 50% compare to the design. This caused by the flow rate of lean amine only
about 50% - 60% from design capacity.
The flow rate of lean amine affects to the power required of fan cooler driver.
The actual operated fans for 225-E-103 and 225-E-203 are 2 fans compare to 4 fans
for design. This condition affects the performance of cooler, especially with heat
transfer rate.
The value of U (overall heat transfer rate) at actual condition is 1.6 BTU/(Hr/Ft2.F) for
225-E-103 and 1.5 for 225-E-203 compare to design 1.8 BTU/(Hr/Ft2.. This difference
indicated that the performance of coolers are still have good performance.

Rich-Lean Amine Exchanger :

Table 3-10 : Performance of Rich-Lean Amine Exchanger

225-E-104A-B 225-E-204A-B DESIGN

RICH AMINE SIDE


Pressure, psig 90.00 100.00 100.00
Temp inlet, F 105.00 105.00 138.20
Temp outlet, F 190.00 210.00 210.20
Flowrate of Rich Amine, USGPM 458.20 483.40 1,138.90
LEAN AMINE SIDE
Temp inlet, F 250.00 250.00 253.20
Temp outlet, F 210.00 210.00 182.30
Delta T LMTD 80.41 67.35 43.55

HEAT DUTY, Btu/hr 16,403,302 20,960,808 39,616,136


HEAT TRANSFER RATE, N/A N/A N/A
BTU/(Hr/Ft2.F)

The flow rate of fluid in Rich-lean amine exchanger is about 40% from design
capacity. This will affect the heat load for these exchangers at 40% for 225-E-103 and
50% for 225-E-203.

LMTD between hot fluid and cold fluid are higher than the design specification. This
case will affect the heat transfer rate for these exchangers. The temperature inlet of
Rich amine is lower compare to the design value. This is indicate the amine contacting
process in the field running on lower temperature than the design specification.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 37 of 109

Lean Amine Charge Pump :

Table 3-11 : Performance of Lean Amine Charge Pump

DESCRIPTION UNIT 225-P-102A 225-P-102B 225-P-102C Design


value value value value
specific gravity 1.05 1.05 OFF 1.00
Temperature F 137.00 137.00 OFF 125.00
suction pressure psia 111.00 111.00 OFF N/A
discharge pressure psia 1550.00 1550.00 OFF N/A
flow GPM 265.00 265.00 OFF 1165.00
Total head ft 3180.05 3180.05 OFF 2550.00
Electric motor power HP 575.00 575.00 OFF 1000.00
Mechanical work HP 227.34 227.34 OFF 766.69

Efficiency % 39.54 39.54 OFF 76.67

Two Amine Charge pumps were running at 265 GPM each, and had efficiency of
39.54%. This efficiency is quite low compare with 76.67% efficiency at design
condition. This is due to very low flow rate they handled. The 76.67% efficiency can
be achieved at 1165 GPM.

The sum of fluid flow rate for each pump (530 GPM) is still far below the design flow
rate for one pump. Higher efficiency could be achieved should the fluid flowing is
handled by one pump only.

Amine Reboiler H/M Circulation Pump :

Table 3-12 : Performance of Amine Reboiler H/M Circulation Pump

DESCRIPTION UNIT 225-P- 225-P- 225-P- 225-P- Design


111A 111B 211A 211B
specific gravity 1.00 1.00 1.00 1.00 1.00
Temperature F 137.00 137.00 137.00 137.00 285.00
suction pressure psia 205.70 205.70 205.70 205.70 N/A
discharge pressure psia 294.70 294.70 294.70 294.70 N/A
flow GPM 2211.00 2186.00 1911.00 1911.00 3044.00
Total head ft 205.59 205.59 205.59 205.59 180.00
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 38 of 109

Electric motor HP 168.00 168.00 152.00 152.00 190.00


power
Mechanical work HP 117.31 115.99 101.40 101.40 141.41
KW 87.52 86.53 75.64 75.64 105.49
Efficiency % 69.83 69.04 66.71 66.71 74.43

Two of the three pumps were working to feed Amine re-boiler medium heater, so four
pumps worked to serve two Amine re-boiler medium heater. Each circ.-pump (P-111
A/B) worked at 2211 and 2186 GPM, with 69% efficiency and P-211 A/B worked at
1911 GPM, with 66% efficiency. All pumps are operated close to design efficiency.

Lean Amine Booster Pump :

Table 3-13 : Performance of Lean Amine Booster Pump

DESCRIPTION UNIT 225-P-101A 225-P-101B Design


specific gravity 1.05 1.05 1.00
Temperature F 137.00 137.00 125.00
suction pressure psia 16.70 16.70 N/A
discharge pressure psia 131.70 131.70 N/A
flow GPM 225.00 225.00 1430.00
Total head ft 115.00 115.00 244.00
Electric motor power HP 70.00 70.00 122.00
Mechanical work HP 15.43 15.43 90.05
Efficiency % 22.04 22.04 73.81

The worst case was found at Amine booster pumps, the efficiency of P-101-A/B is only
22 %. The production process utilized two of the three pumps to support Lean amine
charge pumps. Each of these booster pumps pumping out fluid at 225 GPM.

The sum of fluid flow rate (450 GPM) is still far below the design flow rate for one
pump. Higher efficiency could be achieved should the fluid flowing is handled by one
pump only.

3.2.3 CONDENSATE STABILIZING SYSTEM

A. DESCRIPTION

Hydrocarbon liquid from inlet separator and LTS are sent to the stabilizer feed drum.
Gas from the feed drum is sent under back pressure control to the low pressure fuel
gas system.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 39 of 109

The hydrocarbon liquid from the feed drum is fed under level control to the top tray of
the condensate stabilizer. The stabiliser reboiler is a kettle type shell and tube
exchanger utilizing hot water from Medium Heater at operation.

The condensate product from the stabilizer is sent via the HC condensate cooler
bundle in the refrigerant condenser air cooled exchanger frame and a kettle type
hydrocarbon condenstae cooler by propane refrigerant, gas blanketed, condensate
storage tank.

B. PERFORMANCE

Main equipment of Condensate Stabilizing system are includes : Heat medium heater
257-H-101A/B, 257-H-201A/B; Stabilizer Re-boiler 235-E-101A/B, 235-E-201A/B;
Condensate Cooler 235-E-102, 235-E-102

Heat Medium Heater :

Table 3-14 : Performance of Heat Medium Heater

257-H-101A DESIGN
FUEL,
Flow, MMSCFD 0.12 0.10
FLUE GAS
T out, F 511.20 629.00
O2, % 13.90 3.00
Excess Air, % 179.07 15.27
HOT WATER
, lb/hr 106,647.53 110,000.00
T in, F 310.00 316.60
T out, F 350.00 360.00
P in, Psi N/A 200.00
P out, Psi N/A 200.00
PERFORMANCE
Heat absorption (LHV), MMBtu/hr 5.34 4.76
Heat absorption (HHV), 5.45 4.76
MMBtu/hr

Efficiency (LHV), % 73.57 83.00


Efficiency (HHV), % 67.94 75.49
CO2 EMISSION
CO2 Emission from fuel gas, lb/hr 1,122.86 937.53
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 40 of 109

Table 3-14 : Performance of Heat Medium Heater

257-H-201A 257-H-201B DESIGN

FUEL,
Flow, MMSCFD 0.15 0.14 0.17
FLUE GAS
T out, F 568.80 525.60 629.00
O2, % 8.50 10.20 3.00
Excess Air, % 62.20 86.38 15.27
HOT WATER
, lb/hr 228,820.95 180,110.31 164,900.00
T in, F 300.00 300.00 316.6
T out, F 330.00 330.00 360
P in, Psi N/A 225.00 227.5
P out, Psi N/A 210.00 200
PERFORMANCE
Heat absorption (LHV), MMBtu/hr 7.38 6.66 7.94
Heat absorption (HHV), MMBtu/hr 7.48 6.76 8.00

Efficiency (LHV), % 81.18 80.73 84.00


Efficiency (HHV), % 74.76 74.36 76.77
CO2 EMISSION
CO2 Emission from fuel gas, lb/hr 1,404.86 1,275.47 1,552.85

The above table shows that H-101 A, H-201 A and H-201-B are operated close to
design condition. The efficiency by using heat loss method are calculated based on
the fuel gas heating value, flue gas composition and temperature measurement by
using flue gas analyzer.

Flue gas temperature is lower than design condition but the excess air is very high.
Calculated Efficiency of 257-101-A is 73 % compare to design is 84 % and the
efficiency of 257-201-A/B is around 81 % compare to design is 84 %. The lower
efficiency is caused by higher excess air of the heater.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 41 of 109

Condensate Stabilizer Re boiler :

Table 3-15 : Performance Condensate Stabilizer Re-boiler

235-E-101 235-E-201 DESIGN


HEAT MEDIUM SIDE (SHELL)
Pressure, psig 180.00 200.00 200.00
Temp. inlet, F 350.00 335.00 350.00
Temp. outlet, F 295.00 300.00 310.00
Flowrate (Heat medium), Lb/hr 39,139.19 57,038.28 n/a
Hydrocarbon Side
Temp Condensate to reboiler, F 278.00 278.00 298.00

Delta T LMTD 34.78 32.93 45.36

HEAT DUTY, Btu/hr 2,214,754 2,053,347 3,000,000


HEAT TRANSFER RATE, (BTU/Hr.Ft2.F) 39.14 38.32 40.65

The above table shows that actual condition of heat duty of 235-E-201 and 235-E-101
is lower than design. The reboiler of 235-E-201 have capacity higher than 235-E-101
but the heat transfer rate are close to design.

Condensate Cooler :

Table 3-16 : Performance Condensate Cooler

235-E-102 235-E-202 DESIGN


CONDENSATE
Temp inlet, F 288.00 288 304.30
Temp outlet, F 106.60 106.5 120.00
Flowrate, GPM 101.89 193.4 287
AIR COOLANT:
Temp inlet, F 92.00 92 95.00
Temp outlet, F 136.00 136 139.90
Delta T LMTD 58.65 58.52 74.00

HEAT DUTY, Btu/hr 1,976,054 3,752,578 7,841,737


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 42 of 109

HEAT TRANSFER RATE, 1.11 2.12 2.36


BTU/HR.FT2.F
ELECTRIC CONSUMPTION **), 8.83 9.42 11.00
KW

The above table shows that the condensate cooler have heat duty only 25% for 235-
E-102 and 48% for 235-E-202 refer to the design value. This caused by the flow rate
of condensate, and LMTD.

The flow rate for 235-E-102 is 35% and 235-E-202 is only 67% refer to the design.
LMTD value for cooler 235-E-102 and 235-E-202 are 80% from LMTD design. This
affect the value of heat load (Q) of coolers, because the heat load is straight forward
with condensate flow rate and LMTD.

The overall heat transfer rate (U) at actual condition is 1.11 BTU/(Hr/Ft2.F) for 235-E-
102 and 2.12 BTU/(Hr/Ft2.F for 235-E-202 compare to the design is 2.36
2
BTU/(Hr/Ft .F).

3.2.4 DEW POINT CONTROL AND REFRIGERATION SYSTEM

A. DESCRIPTION

The propane refrigerant gas from gas chiller via suction scrubber enter the 1st stage
propane compressor. The propane refrigerant gas from the 1st compressor discharge
and from the economizer goes to the propane compressor 2nd stage than the
discharge of 2nd stage goes to the condenser cooler and enter to the accumulator.
Propane refrigerant from the accumulator goes to the economizer (flushing).

Propane gas from the economizer enter the suction of 2nd stage compressor and the
propane refrigerant enter the gas chiller via propane subcooler. The design flowrate
of the 1st stage propane compressor is 38,200 lbs/hr and the 2nd stage of propane
compressor is 52,800 lbs/hr.

There are 3 propane compressor driven by electric motor 1300 KW each and via
refrigerant header supply refrigerant for 4 gas chillers (1 gas chiller for 1 train). At the
actual condition only 2 compressor are in operation.

B. PERFORMANCE

Main equipment at Refrigeration system are includes propane condenser, propane


compressor and gas chiller.

Propane Condenser :

Table – 3.17 : Performance of Propane Condenser

230-E-104 DESIGN
PROPANE :
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 43 of 109

Pressure, psig 250 265


Temp inlet, F 140.00 180.00
Temp outlet, F 119.00 121.00
Flowrate, MMSCFD (gas) 30.00 32.90
AIR COOLANT:
Temp inlet, F 92.00 95.00
Temp outlet *), F 112.00 117.50
Delta T LMTD 27.50 26.30

HEAT DUTY, Btu/hr 19,151,470 25,387,806


ELECTRIC CONSUMPTION **), KW 17.67 22.00
HEAT TRANSFER RATE, BTU/HR.FT2.F 2.59 3.29

The above table shows that actual condition of heat duty of 230-E-104 is 75%
compare to design. The heat duty impact on the power required for fan driver which is
80% electric consumption respectively.
The U value (overall heat transfer rate) at actual condition is 2.59 BTU/(Hr/Ft2.F) and
3.29 BTU/(Hr/Ft2.F for the design value.
Entirely, the performance of propane condenser is operated at good condition.

Propane Compressor:

Table – 3.18 : Performance of Propane Compressor

UNITS DESIGN K 101 A K 101 C

PROPANE FLOW ST. 1 38,160.00 30,669.25 25,861.64


(calculated) (calculated)

PROPANE FLOW ST. 2 52,800.00 42,446.24 35,792.51


(calculated) (calculated)

ABSL SUCTION PRESSURE ST.1 24.50 24.00 24.00


ABL.DISCHARGE PRESS ST 1 101.00 100.00 100.00
ABSL DICHARGE PRESSURE ST. 2 265.00 260.00 260.00

TOTAL POWER REQUIRED 1,214.78 966.64 815.11


ACTUAL POWER 1,300.00 1,110.00 936.00
COP 1.89
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 44 of 109

The above table shows that the propane compressor operated at 70-80 % load. The
calculated propane flow of stage-1 K-101 A and K-101 C are 30,669 lb/hr and 25,861
lb/hr with the actual power are 1110 KW and 936 KW . The design propane flow of
stage-1 is 38,160 lb/hr with the power is 1,300 KW. It means that the propane
compressor is still operated at normal conditions.

The design COP of the propane compressor is 1.89. COP at actual condition can not
be calculated accurately because no meter for propane flow.

Gas Chiller:

Table – 3.19 : Performance of gas chiller

UNITS DESIGN GAS CHILLER


(230-E-
102/201/302/402)

GAS INTAKE TEMP.AT EVAP. DEG F 1.00 16.00


GAS OUTPUT TEMP.AT EVAP. DEG F (10.00) 5.00
SALES GAS FLOW MMCFD 300.00 533.00
CONDENSATE FLOW BBL/D 4,000.00 3,000.00

HEAT RELEASE MMBtu/hr 16.52 11.80


TOTAL POWER KW 2,600.00 1,930.00
C.O.P 1.86 1.79

The above table shows the cooling load of gas chiller is 71 % load and two of propane
compressor are operated to handle the refrigeration system.

Performance of each gas chiller can not be calculated, because two propane
compressors serve four gas chillers simultaneously. However total performance still
can be calculated.

The operating condition of four gas chiller almost similar (T gas inlet = 16 F , T out gas
= 5 F). Total COP of gas chiller is 1.79. It’s still close to design condition.

3.2.5 GAS COMPRESSION

A. DESCRIPTION

The pressure of treated gas after Amine System and Refrigeration System is
decrease lower than 1000 psig. To meet the pressure requirement of sales gas it
needs to compress sales gas by using Residual Gas Compressor. There are 4 gas
compressor 2 x 235 MMSCFD and 2 x 300 MMSCFD driven by gas turbine
generator. At the actual condition only 3 GTC in operation and 1 GTC standby
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 45 of 109

B. PERFORMANCE

Main equipment at Gas Compression System are 242-K-101, 242-K-102, 242-K-301


and 242-K-401,

Gas Compressor :

Table – 3.20 : Performance of Gas Compressor

UNITS DESIGN 242-K-301 242-K-401

SALES GAS FLOW ( Q ) MMSCFD 235.00 206.00 206.00


SUCTION PRESSURE PSIA 965.00 915.00 915.00
DISCHARGE PRESSURE PSIA 1,295.00 1,130.00 1,115.00
FUEL CONSUMPTION MMBtu 36.01 28.06 26.36

POWE REQUIRE HP 4,537.09 2,835.13 2,651.33


(POLYTROPIC)
ENERGY INTENSITY Btu/HP 7,936.81 9,896.28 9,940.95

DESIGN 242-K-101 242-K-201

SALES GAS FLOW ( Q ) MMSCFD 10,905.10 150.00 OFF


SUCTION PRESSURE PSIA 955.00 910.00
DISCHARGE PRESSURE PSIA 1,215.00 1,110.00
FUEL CONSUMPTION MMBtu 40.92 20.19

POWE REQUIRE (POLYTROPIC) HP 4,653.97 1,940.43


ENERGY INTENSITY Btu/HP 8,792.49 10,406.28

The above table shows that the compressor are operated at 80 % load compare to
design condition.

The Energy Intensity (Btu/HP) of 242-K-101, 242-K-301 and 242-K-401 are higher
compare to design value. This condition is caused by the lower operating load of
compressors. To know the performance of compressor, it should be compare with
design performance of gas turbine compressor (see table below).
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 46 of 109

Gas Turbine :

Table – 3.21 : Performance of Gas Turbine Compressor

29-Sep-07 DESIGN
242-KT-101 242-KT-201 242-KT-101 /201
A TURBINE
Fuel gas :
flow, MMSCFD 0.59 OFF 1.02
Flue gas :
Temperature, C 1,213 OFF 1,160
O2, % 14 OFF 14
Excess Air, % 191 OFF 185
Eff, % 19 OFF 25
Btu/HP 13,256 OFF 10,115
B COMPRESSOR
Power Required, KW 1,447 OFF 3,471
, HP 1,940 OFF 4,653

29-Sep-07 DESIGN
242-KT-301 242-KT-401 242-KT-301/ 401
A TURBINE
Fuel gas :
flow, MMSCFD 0.73 0.70 1.05
Flue gas :
Temperature, C 1,261 1,237 1,175
O2, % 14 14 14
Excess Air, % 168 174 174
Eff, % 23 23 27
Btu/HP 10,946 11,225 9,401
B COMPRESSOR
Power Required, KW 2,115 1,978 3,409
, HP 2,835 2,651 4,570
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 47 of 109

In the daily operation, the gas turbines efficiency is around 23 %, these efficiency is
less than the design condition (27%). Based on the design performance below, the
performance of gas turbine at low load are close to design figure.

DESIGN PERFORMANCE OF GTC K-301/401

POWER, HP
5,000.00 4,000.00 3,000.00 2,000.00 1,000.00

BTU/KWH
9,400.00 10,000.00 11,000.00 12,500.00 17,000.00

DESIGN PERFORMANCE OF GTC K-101/201

POWER, HP 5,000.00 4,000.00 3,000.00 2,000.00 1,000.00

BTU/KWH 10,100.00 10,700.00 11,600.00 13,200.0 17,000.00


0

3.2.6 GAS TURBINE GENERATOR

A. DESCRIPTION

Electrical power Generator driven by Gas turbine generator, with the gas supplied
from HP (high pressure) fuel gas system. There are 2 GTGs each 1173 KW from
Suban phase-1 and 3 GTGs each 5820 KW from Suban phase-2.

The Generator specification are 5820 KW of power, 6600 volt, freq 50 Hz, cos Q 0.85.
The large motors (lean amine charge pump, Amne reboiler HM Pump, propane
compressor) are supplied by 6600 volt and the other motors using 400 volts.

B. PERFORMANCE
The main equipment of gas turbine generator are 247-GTG-101A/B and 247-
GTG-201A/B/C

The performance of GTG are as follow :

Table – 3.22 : Performance of GTG

29-Sep-07 DESIGN
247-GT-201A 247-GT- 247-GT- 247-GT-201A
201B 201C
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 48 of 109

TURBINE
Fuel gas :
flow, MMSCFD 0.90 0.9 0.90 1.62
Flue gas :
Temperature, F 916 921 925 946
O2, % 16 16 16 15
Excess Air, % 312 309 308 243
Turbine Eff, % 18.04 18.04 18.01 30
Btu/kwh 16,925 16,926 16,950 11,336
CO2 emission :
Flow, lb/hr 5,611 5,611 5,611 4,446
GENERATOR
Power Output, KW 2,146 2,102 2,178 5,821
PF 0.83 0.83 0.83 0.84
Voltage, V 6,600 6,600 6,600 6,600
Frequency, Hz 50 50 50 50

GTGs are operated less than 40 % load each, total load is around 6,426 KW. This
load actually can be handle by two GTGs with 55 % load each. If any disturbance
occurs, the load shading system will shut off un-priority load, so system black out can
be avoided. The low load of GTG caused low efficiency of gas turbine.

The stack temperature of GTG are close to design condition but the calculated
efficiency is only 18 % compare to design which is 30 %. The decreasing efficiency is
caused by lower operating load which will increased radiation and convection loss.

Compare to the design performance of gas turbine generator (table below) , the
performance GTG at low load are still in good condition

Table – 3.23 : Design Performance of GTG

DESIGN PERFORMANCE OF GTG

POWER 5,800 5,000 4,000 3,000 2,000 1,000


BTU/KWH 11,340 11,800 12,600 14,300 17,200 25,000
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 49 of 109

3.2.7 AIR COMPRESSOR

A. DESCRIPTION

Instrument and utility air are supplied by the 1x340 scfm and 1x140 scfm screw type
compressor. The compressed air is filtered and then dried in heatless adsorption type
dries which are on automatic regeneration cycles. The instrument air compressor
packages are provided with local electronic control panels. The instrument air
receiver is normally operated between 110 and 120 psig.

B. PERFORMANCE

There are four compressors Atlas Copco GA 37 x 2 and GA 75 x 2 with design


capacity is 960 SCFM, the duty of each equipment are as follows,

The performance of air compressor are as follows :

Table 3-24 : Performance of Air Compressor

251-A-101A (ATLAS COPCO GA 75)

DESIGN ACTUAL

POWER 72.60 45.93


COMPRESS AIR FLOW 340.00 266.66
ACTUAL PERFORMANCE 0.20 0.20

251-A-101 B (ATLAS COPCO GA 37)

DESIGN ACTUAL

POWER 44.00 28.27


COMPRESS AIR FLOW 140.00 129.90
ACTUAL PERFORMANCE 0.33 0.25

The above table shows that the compressor is operated at low load. Actual power of
251-A-101 A is 45.93 KW compare to design 72.6 KW and 251-A-101 B is 28.27 KW
compare to design 44 KW.

Actual performance of air compressor calculated by :

(Actual power / Qs x ((Pd/Ps)^0.2857 – 1)) Note : Qs = air flow


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 50 of 109

3.2.8 ELECTRICAL MAP SUBAN GAS PLANT

Electrical map is derived from single line diagram, and intend to get a closer and clear
point of view to one that need brief description on power consumption at each
process. This map is made simple as possible so, it doesn't show how the electric
system is distributed. Emphasize is given to voltage, and power required for each
equipment. Note that the power mentioned below is the power in normal design
condition.

A. Inlet Gas System

400 V

215-EM-301/401/A/B 1-2
Inlet cooler fan
22 KW x8

B. Amine System

6.6 KV

225-P-102A/B/C 225-P-111A/B/C 225-P-211A/B/C


Lean Amine Charge pump A/B/C Amine reboiler H/M circ pump A/B/C Amine reboiler H/M circ pump A/B/C
1130 HP x3 185 HP x3 185 HP x3

400 V
225-P-102A/B/C 225-PM-103A/B 225-PM-203A/B
Lean Amine booster pump A/B/C Regenerator reflux pump A/B Regenerator reflux pump A/B
112 HP x3 3.73 HP x2 3.73 HP x2

225-EM-103A/B/C/D 225-EM-203A/B/C/D 225-EM-105/205/305/405 A 225-EM-105/205/305/405 B


Lean Amine cooler fan Lean Amine cooler fan Treated gas cooler fan Treated gas cooler fan
19 KW x4 19 KW x4 19 KW x4 19 KW x4

225-EM-101/201 A/B/C/D 225-PM-105 225-PM-104


Regenerator reflux condenser fan Amine transfer pump Amine sump pump

11 KW x8 14.7 HP 14.7 HP

C. Dehydration system

400 V
229-PM-302/402/A/B
Glycol Injection pump
26.8 HP
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 51 of 109

D. Propane Compressor System

6.6 KV

230-KM-101 A/B/C
Propane compressor A/B/C
1306 KW x3
400 V

230-EM-104 A/B/C/D 1-2 230-K-101-EM1-6 230-K-101-PM 1-3


Propane condenser fan A-D L.O. cooler fan propane compr. A/B/C L.O. pump for propane compr. A/B/C
22 KW x8 7.15 KW x6 6.7 HP x3

E. Depropanizer and Condensate Stabilization System

400 V

230-EM-107A/B 230-PM-102 230-PM-101


Depropaniser overhead condenser fan Depropaniser reflux pump Depropaniser overhead feed pump
7.5 KW x2 1.7 HP 7.1 HP

230-H-106 235-EM-202A/B 235-KM-201 235-PM-102D/E


Depropaniser reboiler heater Condensate cooler fan Vapoor recovery compr. Condensate shipping pump

106 HP 11 KW x2 29.5 HP 40 HP x2

F. Residue Gas Compressor System

400 V

242-EM-301/401 A-D
Residue gas compr. After cooler
15 KW x8

G. Air Compressor, and Utility

400 V

251-A-201 251-KM-201 A/B 252-PM-101 C-G 252-PM-104 A/B 252-PM-105 A/B


N2 generation Air compressor A/B Well water lift pump Portable water pump Amine makeup water pump A/B
30 KW 120 HP x2 5.36 HP x5 7.4 HP x2
15 HP x2
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 52 of 109

H. Flare, and Water handling

400 V

248-P-101/201 A/B 258-PM-202 A/B 257-PM-201 A/B/C


Flare KO drum A Produced water injection pump A/B Heat medium circ. pump A/B/C
3 HP x8 60 HP x2
49.5 HP x3

3.3 FINDINGS AND RECOMENDATION


1. Instrumentation and Metering

Based on the site survey founded that many metering and instrument are not work
properly. Findings and recommendations of metering and instrumentation at
Suban Gas Plant are as follows :

Equipments Findings Recommendations


1. Amine Reb H-  There are inaccurate  the oxygen analyzer
M Heater temperature indicator of should be repaired
circulation Hot Water
 Need to calibrate
 Combustion analyzer in meter of hot water
each HM Heater not temperature
work properly indicator

2 H-M Heater  No Oxygen analyzer  Need to install


oxygen analyzer in
 The calculated efficiency order to monitor the
of HM Heater from direct performance of this
method difference with equipment
heat loss method. This
discrepancy maybe  Need to calibrate
caused by lack of temperature
accuracy of Temperature indicator and hot
indicator and hot water water circulation flow
circulation flow meter. meter

3 Gas Turbine  There is no flow meter of  Need to install fuel


Generator fuel gas in each GTG. gas flow meter and
link to DCS
 Some indicator/sensor of
GTGs have no link to
DCS in CCR

4 Gas Turbine  lack of accuracy fuel  Need to calibrate


Compressor meter fuel flow meter and
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 53 of 109

link to DCS

5 Propane  No power record for  Need to implement


compressor propane compressor continues record for
propane compressor
to evaluate COP

6 Chiller  Temperature inlet and  need to install


outlet gas chiller are temperature
inaccurate indicator inlet and
outlet gas chiller for
performance
evaluation and link
to DCS

7 Air  No power meter for air  need to install meter


compressor compressor of air compressor for
performance
evaluation and link
to DCS

8 Pumps  No power meter for lean  need to install meter


amine booster pump of lean amine
booster pump for
performance
evaluation and link
to DCS

9 Heat  No temperature and  Need to install


Exchanger pressure indicator at temperature
gas-gas exchanger indicator at gas-gas
exchanger for
 Temperature indicator of performance
steam at amine Re-boiler monitoring
are not accurate
 Need to calibrate the
steam temperature
indicators at amine
re-boiler

10 Amine system  Temperature indicator  Recalibration of


between inlet and outlet temperature
are not accurate indicator

11 Electric  No continue recording for  Need to record


Distribution electrical distribution electrical distribution
(6000 V line) at daily
records
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 54 of 109

2. Heater

Based on the calculation bellows are the efficiency, heat absorb and CO2
emission of fired heater at Suban Gas Plant

EFFICIENCY HEAT DUTY CO2


EMISSION
% MMBtu/hr Lb/hr
AMINE REB H-M HEATER
DESIGN 89.11 57.98 10,609.42
225-H-111 85.80 31.81 5,730.36
225-H-211 84.87 28.70 5,203.54

HEAT MEDIUM HEATER


DESIGN 257 H-101A/B 84.00 4.37 712.53
257-H-101A 73.60 5.35 1,122.86
257-H-101B OFF OFF OFF
DESIGN 257 H-201A/B 84.00 7.94 1,552.85
257-H-201A 81.18 7.38 1,404.86
257-H-201B 80.73 6.66 1,275.47

Finding :

The above tables shows that :

 The heat duty of Amine H-M Heater is only 50 % and 44 % load compare to
design condition. The Gas Plant are operated at 517 MMSCFD of sales
gas or 74 % load compare to design condition. This condition means that
the design of fired heater is too large.

 Amine H-M Heater is operated at high excess air (44 % and 71 % )


compare to the design figure which is 15 % excess air. This excess air will
impact lower efficiency of H-M Heater

 HM Heater is operated at high excess air (62 %, 86 % and 179 % )


compare to the design figure which is 15 % excess air. This excess air will
impact lower efficiency of Heater (Calculated Efficiency from heat loss
method will be around 70 % compare to design is 84 %)

Recommendation :

 Design Amine H-M Heater is too large, so the heater can be handle for
revamping until 125 % Amine Capacity.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 55 of 109

 Amine H-M Heater is the main energy consuming equipment in the amine
system, so its performance should be monitored daily. Hence, it needs
temperature and O2 meters at flue gas line to support the monitoring
activity.

 Amine H-M Heater should be operated close to the design excess air (15%)
to achieve better efficiency,

 HM Heater should be operated close to the design excess air (15%) to


achieve better efficiency

5. Gas turbine generator

Based on the calculation, bellows are the efficiency, heat rate, BHP and CO2
emission of GTG at Suban Gas Plant:

GAS TURBINE GENERATOR EFFICIENCY HEAT RATE BHP CO2 EMISSION


% BTU/KWH KW Lb/hr

DESIGN 30.43 11,336.00 6,063.54 9,803.22


247-GT-201A 18.04 16,924.65 2,235.42 5,610.65
247-GT-201B 18.06 16,908.92 2,189.58 5,610.65
247-GT-201C 18.01 16,949.55 2,268.75 5,610.65

Finding :

 Three GTGs load are low in daily operation ( less then 40%),.the average
efficiency is around 18 % (design = 30 %)

 Heat rate of three GTGs are around 16.9 MBtu/KWH compare to design
11.3 MBtu/KWH

Recommendation :

 To achieve better efficiency, GTGs should be operated at more then 50 %


load (two GTGs in operation)

 Load shading should be operated properly to sustain two GTGs in


operation

6. Gas turbine Compressor

Power require and energy intensity of residue gas compressor are as follows :
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 56 of 109

COMPRESSOR SALES GAS POWE ENERGY


FLOW, REQUIRE, KW INTENSITY, KW
MMSCFD

DESIGN 242-K-301 235.00 4,537.09 7,936.81


242-K-301 206.00 2,835.13 9,896.28
242-K-401 206.00 2,651.33 9,940.95
DESIGN 242-K-101 300.00 4,653.97 8,792.49
242-K-101 150.00 1,940.43 10,406.28
242-K-102 OFF OFF OFF

Turbine efficiency, heat rate and CO2 emission are as follows :

TURBINE Turbine Eff, Heat Rate CO2 emission :


% Btu/BHP lb/hr

DESIGN 242-KT-301 29.13 7,878.86 5,341.69


242-KT-301 23.53 9,746.77 1,838.04
242-KT-401 23.35 9,942.20 1,753.20
DESIGN 242-KT-101 25.89 8,793.54 6,070.11
242-KT-101 21.78 10,737.29 1,385.60
242-KT-102 OFF OFF OFF

Finding :

 Max capacity of KT-401 and KT-301 are 235 MMSCFD each, with suction
press 950 psi and discharge 1280 psi

 Max capacity of KT-201 and KT-101 are 300 MMSCFD each, with suction
press 950 psi and discharge 1200 psi

 Actual turbine efficiency of KT-401 and KT-301 is around 23 % and KT-101


is 22 % compare to design efficiency of KT-401 and KT-301 are 29 % and
KT-101 is 26 %

 Based on the design flow rate, 3 GTCs can handle 770 MMSCF

7. Propane Compressor

Performance of propane compressor are as follows :


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 57 of 109

PROP COMPRESSOR POWER ACTUAL POWER, COP


REQUIRED, KW KW

DESIGN 1,214.78 1,300.00 1.89


230-K 101 A 966.64 1,110.00 1.78
230- K 101 C 815.11 936.00 1.78

Finding :

 Inlet flow of refrigerant vapor to propane compressors come from one


header, so difficult to evaluate COP each compressor.

 Design COP of propane compressor is 1.89, calculated COP at actual


condition (based on heat absorb) is around 1.78

8. Gas Chiller

Performance of gas chiller are asfollows :

GAS CHILLER UNITS DESIGN EVAPORATOR


(102,201,302,402)

GAS INTAKE TEMP.AT EVAP. DEG F 1.00 16.00


GAS OUTPUT TEMP.AT EVAP. DEG F (10.00) 5.00
SALES GAS FLOW MMCFD 300.00 533.00
CONDENSATE FLOW BBL/D 4,000.00 3,000.00

HEAT RELEASE MMBtu/hr 16.52 11.80


TOTAL POWER KW 2,600.00 1,930.00
C.O.P 1.86 1.79

Finding :

 Inlet flow of refrigerant to gas chiller come from one header, so difficult to
evaluate COP for each gas chiller

 Heat duty of four gas chiller is 11.8 MMBTU/hr compare to design is 16.52
MMBTU/hr. The motor power of propane compressor is 2046 kW

 Design COP of gas chiller is 1.86, calculated COP at actual condition


(based on heat release) is around 1.79
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 58 of 109

9. Pump

Finding :

Calculated efficiency of pumps are as follows;

PUMPS Flow, GPM Efficiency, %


Actual Design Actual Design

Amine Charge Pump


225-P-102A 265.00 1165.00 39.54 76.67
225-P-102B 265.00 39.54
Amine Booster Pump
225-P-101A 225.00 1430.00 22.04 73.81
225-P-101B 225.00 22.04
Amine Reboiler H/M Circulation Pump
225-P-111A 2211.00 3044.00 69.83 74.43
225-P-111B 2186.00 69.04
225-P-211A 1911.00 66.71
225-P-211B 1911.00 66.71

Amine charge pumps and Amine booster pumps were running in low efficiency. This
is due to very low of fluid rate they handled. Should two split of flow that flowing
through “Amine booster pumps is merged together to flow through one pump only(530
GPM), its total flow still far below the rate of design (1165 GPM).

The similar case was found at Amine booster pumps. Two pumps were running to
handle 225 GPM rate each.

Recommendation :

Higher efficiency could be achieved should the fluid flowing is handled by one pump
only (If total rate of flow not exceed flow rate at design).

10. Cooler

Findings :

Calculated of coolers are as below:

No COOLER HEAT DUTY HEAT TRANSFER ELECTRIC/


. RATE HEAT DUTY
(MMBTU/HR) (BTU/HR.FT2.oF) (%)
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 59 of 109

1. Inlet Gas Cooler


215-E-101 28.37 4.46 0.63%
215-E-201 28.37 4.46 0.63%
215-E-301 43.04 3.08 0.42%
215-E-401 43.04 3.08 0.42%
2. Treated Gas Cooler
225-E-105 4.62 3.91 4.19%
225-E-205 3.87 2.95 4.90%
225-E-305 5.35 1.89 3.77%
225-E-405 OFF OFF OFF
3. Regenerator Reflux
Condenser
225-E-101 9.26 1.94 0.65%
225-E-201 13.23 2.68 1.03%
4. Lean Amine Cooler
225-E-103 16.78 1.60 0.72%
225-E-203 16.25 1.53 0.74%
5. Condensate Cooler
235-E-102 1.98 1.11 1.53%
235-E-202 3.75 2.12 0.86%
6. Propane Cooler 230-E-104 19.15 2.59 0.31%

Power required to drive motors of fan coolers are below 1% due to their heat
duties. This condition indicate that the power consumption of these coolers are in
good condition except Treated gas cooler and Condensate cooler.

Recommendations :

Need to check again the performance of Treated gas cooler and Condensate
cooler, especially motor driver of fan coolers.

11. Heat Exchanger

Findings :

Calculated of Heat Exchangers are as listed below:


No. HEAT EXCHANGER HEAT DUTY HEAT TRANSFER DIRTY FACTOR
RATE
(MMBTU/HR) (BTU/HR.FT2.oF) ACTUAL DESIGN
1. Stabilizer Reboiler
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 60 of 109

235-E-101 2.21 39.14 0.0009 0.0010


235-E-201 3.02 48.13 0.0034 0.0010
2. De-C3 Reboiler 230-E- 0.18 N/A N/A N/A
106
3. Rich/Lean Amine Exch.
225-E-104A/B 16.40 N/A N/A N/A
225-E-204A/B 20.96 N/A N/A N/A
4. Gas-Gas Exch. 230-E- 14.00 157.31 0.0023 0.0020
307

The performance of heat exchangers still in good condition, except for Stabilizer
Reboiler 235-E-201, because the dirty factor more than design specification.

12. Energy Losses, Potential Saving and Emission Reduction Potential

Based on heat balance calculation, energy losses from high temperature flue gas at
Suban is coming from Stack of Thermal Oxidizer, GTG and GTC.

STACK LOSS, TEMP, Deg F


Btu/hr
Thermal Oxidizer

225-H-102 35,495,414 932


225-H-202 8,303,983 2,012
GTG
247-GT-201A 33,163,974 916
247-GT-201B 29,310,275 921
247-GT-201C 29,397,944 925
GTC
242-K-101 21,555,786 1,213
242-K-301 22,755,271 1,261
242-K-401 21,806,787 1,237
TOTAL 201,789,433 1,177

a. Energy Losses :

Total losses from flue gas is around 201 MMBtu/hr with average temperature 1,177
deg F. Actually, by utilizing economizer with stack temperature around 500 deg F, this
Flue gas losses can be used to generate saturated steam about 120,000 lb/hr.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 61 of 109

b. Potential Saving :

Based on the evaluation, shows that the potential saving are coming from :

 Optimize operation of GTG will increase efficiency from 18 % to 23 % that


will reduced HP Fuel consumption about 0.14 MMSCFD

 Optimize operation of all heater will increase efficiency around 5 %, that


will reduced LP fuel consumption about 0.1 MMSCFD

 Utilized flare gas that will reduced fuel consumption about 0.8 MMSCFD

Energy Conservation Opportunities :

 Optimize operation of GTGs can be implemented by load shading

 Optimize operation of Heater and utilized flare gas can be implemented by


installing booster compressor to compress gas up to 180 psig. This fuel
gas can be used for Gas turbine and in turn it will reduce HP Fuel
consumption. The simple calculation are as follows :

Fired Heater-saving, MMSCFD 0.10

, US $/Year 123,750.00

Flare Gas-saving, MMSCFD 0.80

, US $/Year 990,000.00

Total, MMSCFD 0.90

, US $/Year 1,113,750.00

*Cost to install the system for recovery gas which 2,400,000.00


includes : gas compressor, KO Drum,
Instrumentations , US $

Operation and Maintenance Cost , US $/year 120,000.00

Net income , US $/Year 993,750.00

Estimated payback period to install the system 2.42


, Years

* = refer to Beak Pacifik Report - Energy Audit at Cilacap Refinery Complex


(Beak Pacific Inc. , Vancouver, Canada)

c. Emission Reduction Potentials

CO2 emission at suban gas plant is 127,901 lb/hr. its come from combustion of
fuel gas at flare gas, heater, GTC and GTG.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 62 of 109

CO2 reduction, lb/hr

Optimized operation of GTG 642

Optimized operation of Heater 824

utilized flare gas 7,394

Total 8860

Optimised operation and utilized flare gas 7%


will reduce CO2 emission , %

13. Reporting system

Findings :

 Existing daily report just only for production activity, it does not cover the
data for plant performance evaluation purposes

 No data acquisition and evaluation based on daily log sheet .

 Important data for plant performance not covered in daily log sheet

Recommendation :

 Daily reporting must covers production activity and plant performance


indicator

 Regulars summary of log sheet regarding plant performance should be


evaluate.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 63 of 109

IV. ENERGY ASSESSMENT AT GRISSIK


CENTRAL GAS PLANT

4.1. GENERAL PLANT OPERATION AND PERFORMANCE

4.1.1. GENERAL PLANT OPERATION OF GRISSIK GAS PLANT

The Central Gas Processing – Grissik plant was designed firstly for processing gas
from four field in the Corridor Block, South Sumatra: Dayung/Sumpal and GLT
(Gelam/Letang/Tengah) field. The quality gas from Dayung field has high CO2
content (31 %) and the gas quality from GLT has high condensate content.
The source of inlet gas to be processed in CGP has changed after the Suban Gas
Plant was operated. Partly of Suban Gas sales line also was processed in CGP if the
specification of Suban Gas Sales was nearly out of specification, especially on the
CO2 content. So, the mixed gas from Suban plant and CGP plant will meet
specification at the gas sales pipeline.
The simple process flow of CGP-Grissik Plant is shown with block diagram in figure
1.1 below:

FlareGas
T
11 Permeate Gas Acid Gas

5 6 Suban Gas
Sales bypass

T 1 T 2A T 4 T 7 T 9

Gas/Liquid Gas Pretreatment Amine System GasDehydrationSystem GasSales to


Dayung Gas pipeline
Separation 2B
Gathering Station
T Propane
GelamGas Chiller
T T
8
Gelam Liquid
Suban Gas Sales
Gelam Gas/Liq
toprocessedin CGP
GatheringStation
3 T 10

Condensate Stabilization Condensateproduct


& C3 Recovery to Bentayan

Figure 4.1 Gas Processed Block Diagram of CGP plant

The flow diagram of CGP Grissik plant that obtained from basic design and field
survey can be described below:
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 64 of 109

Table 4.1. Flow Diagram (based on Design)


Stream
1 3 2A 2B 4 5 6 7 8 9 10 11
Unit
Dy&Sum GlmLiq. to Dy&Sum Dy&Sum Dy&Sum Dy&Sum Dyg/Sum Glm Dyg/Smp Codensat
GlmGas GlmGas GlmGas AcidGas GlmGas GlmGas FlareGas
Gas Stabilizer Gas Gas#1 Gas #2 Gas Gas Condensate Gas e prod.

Temp (deg F) 87 87 53 120 84 99 84 99 99 120 120 120 50 132 130 100 58


Pressure (psig) 1000 1000 176 1121 1133 1099 1133 1099 9 11 1093 1125 1094 1087 1119 575 75
Flow, Gas (MMSCFD) 310 129.46 0 302.2 129.46 114.02 129.46 114.02 70.22 46.5 197.56 114.38 0 197.06 114.1 0 0.16
Flow, Cond. (BBL/D) 0 0 520.2 0 0 0 0 0 0 0 0 0 777.83 0 0 1745 0
TOT_FLOW(MMSCFD)
ORBBL/D 439.46 520.2 302.2 129.46 357.5 70.22 46.5 311.94 777.83 311.16 1745 0.16

Table 4.2. Flow Diagram (Survey on Oct. 02, 2007)


Stream
Unit 1 3 2A 2B 4 5 6 7 8 9 10 11
Dy&Sum GlmLiq. to Dy&Sum Dy&Sum Dy&Sum DSS*) Glm Bypass
GlmGas Glm Gas Glm Gas Sub Gas AcidGas GlmGas DSSGas GlmGas Cod. prod. FlareGas
Gas Stablzr Gas Gas Gas Gas Cond. Sub
Temp (deg F) 87 87 84 138 84 123 84 87 109 143.15 120 120 37 94.5 93.1 90 80
Pressure (psig) 1105 1011 142 1001 1001 1023 1001 1000 23 12.1 993 1000 1000 998 993 203 205
Flow, Gas (MMSCFD) 53.2 47.1 0 53.2 47.1 46.7 47.1 101.6 2.57 20.6 132.85 41.95 0 434.68 146.46 39.39 0 5.75
Flow, Cond. (BBL/D) 0 0 866.77 0 0 0 0 0 0 0 0 0 829.95 0 0 0 1296 0
TOT_FLOW(MMSCFD)
OR BBL/Dfor Liquid 100.3035 866.77 100.3 47.1 195.4 2.57 20.6 174.8 829.95 620.53 1324 5.75
*) DSS : Dayung/Sumpal & Suban

Based on overall process, the processing load of CGP plant during field survey activity
is 54.6% of capacity design. This condition is caused by shut down condition for
repairing of the Amine Regenerator 25-C-202.

4.1.2. GENERAL PLANT PERFORMANCE OF GRISSIK CENTRAL GAS PLANT

The HP fuel gas supply for the plant is obtained from the Back-up sales gas line and
Suban taping gas line via the pressure control valve. Gas heated by steam, under
back pressure control, goes to the high pressure fuel gas scrubber which is operated
at about 260 psig. The high pressure fuel gas supplies fuel the gas turbine and partly
sent to Bentayan field.
The LP fuel gas from the stabilizer feed drum and stabilizer overhead is supplied for
TEG regeneration heater, gas pretreatment heater, fuel gas for WHB incenerator and
flare purge gas, flare stack pilot, tank blanket.
The HP fuel gas is supplied to GTG and to the LP fuel gas, when the LP gas demand
exceeds the available LP fuel gas supply.

CGP Grissik plant used three (3) type of energy for the process, utility and offsites
facilities. The types of energy that used are : LP Fuel gas, steam from WHB and
electricity from GTG.

Based on 2 October 2007, the amount of fuel gas coming from scrubber is 5.910
MMSCFD. The distribution of fuel gas as shown in table below;
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 65 of 109

Table 4.3 : Fuel gas distribution

1 Fuel Gas to Flare


C 1.460
2 Fuel Gas to WHB
46-B-101 D 1.550
46-B-201 D -
D 1.550
3 Fuel gas to Heater
41-H-101 C 0.023
41-H-201 C 0.023
41-H-301 C -
C 0.045
4 Fuel gas to Regen Heater
21-H-101 C 0.161
21-H-201 C -
0.161
5 Fuel gas to GTG
47-GTG-101A C 0.70
47-GTG-101B C 0.78
47-GTG-101C C -
D 1.48
6 Fuel gas to Bentayan
D 1.560

There are two type of fuel gas used, LP Fuel gas which is consumed by fired heater
and HP Fuel gas which is consumed by GTG. The heating value of LP Fuel gas is
around 1,060 Btu/SCF and HP Fuel is around 1,484 Btu/SCF

Based on heat balance calculation in WHB and GTG, the energy picture based on 2
October 2007 which includes total energy input/heat released, heat absorbed, heat
loss and CO2 emission as shown in table below,
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 66 of 109

Table 4-4 : The energy picture based on 2 October 2007

HEAT RELEASE, HEAT ABSORB, STACK LOSS, TEMP, CO2


Btu/hr Btu/hr Btu/hr Deg F Emission,
lb/hr

FLARE
90,840,020 0 84,736,763 1,562 12,421
HEATER
Regen Gas Heater
21-H-101 8,473,864 5,794,116 2,487,229 430 1,377
21-H-201 0 0 0 0 0
Glycol Heater
41-H-101 1,196,695 922,279 256,466 430 191
41-H-201 1,196,695 922,279 256,466 430 191
41-H-301 0 0 0 0 0
WHB
46-B-101 165,049,729 120,492,608 41,432,959 376 158,802
46-B-201 0 0 0 0 0
GTG
47-GTG-101A 37,103,706 7,084,939 19,478,242 949 4,569
47-GTG-101B 40,880,730 7,415,749 18,133,682 967 5,034
47-GTG-101C 0 0 0 0 0
TOTAL 344,741,441 142,631,970 166,781,807 468 182,585

Plant Performance :

The plant performance at 2 October 2007 are as follows :

Table 4-5 : Plant Performance of Grissik Central Gas Plant

PRODUCTION RATE
Sales Gas = 186.50 MMSCFD
= 31,083.33 BOE

Condensate = 1,234.00 BOE

Total Prod => 32,317.33 BOE

ENERGY CONSUME
Excluding Flare 256,621,725.71 Btu/hr
Including Flare 347,461,746.16 Btu/hr
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 67 of 109

ENERGY INTENSITY
Excluding Flare 7,940.68 Btu/BOE
Including Flare 10,751.56 Btu/BOE

Total heat input to WHB, GTG,Regeneration Gas Heater and Glycol Heater is
253,901,420 Btu/hr and total heat released including flare gas is 344,741,441 Btu/hr.
The production rate is 32,317.33 BOE which include 186.5 MMSCFD sales gas and
1,234 Barrel of condensate, means the energy consumed to produce one BOE
(energy intensity) is 7,940.68 BTU/BOE (Excluding flare) and 10,751.56 BTU/BOE
Including flare).

4.2. PERFORMANCE EVALUATION EACH SYSTEM

4.2.1. GAS PRETREATMENT & MEMBRANE SYSTEM

A. DESCRIPTION

The Gas Pre-Treatment Unit has been designed to operate at 2 x 50% each train with
a total gas throughput capacity of 230 MMSCFD and designed to remove heavy
hydrocarbons (C6+) from 380 ppm to 39 ppm.

The overall process works on the principles of Adsorption, Regeneration and, Cooling
and, is commonly referred to a Thermal Swing Adsorption (TSA) process. Each train
has 4 Adsorber Towers. Under normal operation each train has 2 Adsorber towers in
operation mode,one Adsorber Towers in Regeneration mode and one Adsorber
Towers in cooling mode.

The pretreatment consists of the following four steps process, i.e :


 Coalescing filter for the removal of aerosols and particulates;
 Heater to ensure the gas is above the dewpoint temperature;
 Guard bed for the removal of heavy hydrocarbons and glycol;
 Polishing filter

The Dayung gas from inlet separator is sent to the membrane unit to remove CO2,
lowering the CO2 content of the gas from about 30.5 mole% to less than 15.0%.

The Membrane CO2 separation unit was designed to process the Dayung gas to
reduce the CO2 content of the gas from 31% to 15%. The remainder of the CO2 in the
Dayung gas is then removed in the Amine-treating Unit, allowing the gas to meet the
sales gas pipeline specification for CO2, which has a minimum value of 5%. As the
Dayung gas flows through the semipermeable polimide membranes, approximately
63% of the CO2, 60% of the H2S, and 8% of the Methane is separated into the
permeate gas stream. The permeate Gas, consisting of about 80% CO2 and 20%
Methane, is sent to the Waste Heat Boilers as fuel gas.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 68 of 109

B. PERFORMANCE

The main equipment at Gas Pretreatment (TSA) system are Regenerator Gas Heater
and Regen Gas/Gas Exchanger

The performance of main equipment are as follows :

Table 4-6 : Performance of Performance of Regenerator Gas Heater :

2-Oct-07 DESIGN

21-H-101 21-H-201 21-H-101/201

1 FUEL,
Flow, MMSCFD 0.16 OFF 0.31
2 FLUE GAS
T out, F 430.00 OFF 430.40
(Estimated)
O2, % 14.00 OFF 14.00
(Estimated)
Excess Air, % 185.64 OFF 185.64
3 PERFORMANCE
Heat absorption (LHV), 5.75 OFF 11.06
MMBtu/hr
Heat absorption (HHV), 5.80 OFF 11.16
MMBtu/hr

Efficiency (LHV), % 74.65 OFF 74.62


Efficiency (HHV), % 68.40 OFF 68.38
4 CO2 EMISSION
CO2 Emission from fuel gas, 1,376.93 OFF 2,651.23
lb/hr

Regen gas heater is operated at 60% load compare to design condition and the fuel
consump is 0.16 MMSCFD

The stack temperature and oxygen content are estimated close to design condition
with the efficiency is 74.65 %
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 69 of 109

Table 4-7 : Performance of Regen Gas/Gas Exchanger (21-E-101/201)

21-E-101 21-E-201 DESIGN


Gas to Membrane (Shell side)
Pressure, psig 1097 OFF 1153
Temp inlet, F 85.00 OFF 85.78
Temp outlet, F 100.00 OFF 110.40
Flowrate of Gas, MMSCFD 26.00 OFF 215.07
Hot Gas (Regen Gas)
Temp inlet, F 230.00 OFF 309.90
Temp outlet, F 109.00 OFF 95.00

Delta T LMTD 62.74 OFF 61.89

HEAT DUTY, Btu/hr 475,664 OFF 7,497,708

HEAT TRANSFER RATE, BTU/(Hr/Ft2.F) 3.12 OFF 6.26

Table 4-8 : Performance of Cooler Gas/Gas Exchanger (21-E-102/202)

21-E-102 21-E-202 DESIGN


Regen Heater Gas/Hot Gas (Shell side)
Pressure, psig 1097 OFF 1155
Temp inlet, F 400.00 OFF 541.60
Temp outlet, F 230.00 OFF 309.90
Flowrate of Gas, MMSCFD 20.00 OFF 25.93
Cold Gas (Regen Gas)
Temp inlet, F 102.00 OFF 85.90
Temp outlet, F 120.00 OFF 335.60

Delta T, LMTD 194.18 OFF 212.40

HEAT DUTY, Btu/hr 4,674,675 OFF 8,267,466.11


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 70 of 109

HEAT TRANSFER RATE, BTU/(Hr/Ft2.F) 44.17 OFF 55.43

The above table shows that the heat duty operated only about 0.475 MMBTU/hr for E-
101 and 4.67 MMBTU/hr for E-102, although the design heat duty is 7.5 MMBTU/hr for
E-101 and 8.26 MMBTU/hr for E-102. This heat duty value produce capacity only
about 6.34 % for E-101 and 56.54 % for E-102 compare to design capacity.

This condition caused by the feed gas to TSA unit only 26 MMSCFD (110,283 lb/hr)
for adsorption and 20 MMCSFD (87,483 lb/hr) for cooling condition compare to the
design capacity for gas process adsorption is 115 MMSCFD (20% capacity).

The different between design and operation are the LMTD value. Actual LMTD is
62.74 oF for E-101 and 44.17 oF for E-102 compare to design is 61.9 F for E-101 and
55.43 oF for E-102.

The performance of heat exchanger can be evaluated from the value of overall heat
transfer rate (U). The U at operating condition give value about 3.12 BTU/(Hr/Ft2.F)
for 21-E-101 and 44.17 BTU/(Hr/Ft2.F for 21-E-102, while the design value is 6.26
BTU/(Hr/Ft2.F) for 21-E-101 and 55.43 BTU/(Hr/Ft2.F) for 21-E-102.

4.2.2. AMINE SYSTEM

A. DESCRIPTION

The gas treating process consists of three identical amine contactors, two normally
treating about 114 MMSCFD of Dayung gas each (referred design base) and the third
treating about 129 MMSCFD of Gelam, Letang, Tengah (GLT) gas. The amine units
are designed to produce treated gas containing less than 2% CO2 and 4 ppmV H2S
consequently the bypasses allow the sales gas still to meet its specification of 5%
CO2 and 8 ppmV of H2S.

Amine unit feed gas stream enters the bottom of an amine contactor where it is
counter-currently contacted with lean 50 wt% UCARSOL solution with main
composition is MDEA solution. CO2 and H2S are absorbed by the lean amine and the
treated gas exits the top of the tower. The amine contactor contains stainless steel
structured packing.

The design lean amine circulation rate to the Dayung gas contactors is about 1640 US
gpm and the design lean amine circulation rate to GLT gas is about 1621 USgpm
based on maximum allowable rich amine loading of 0.49 mole (CO2+H2S)/mole
UCARSOL (MDEA solution).

The rich amine from the contactors flows under level control to the rich amine flash
drums. Gas from the flash drums flows under back pressure control to the waste gas
incenerators. The rich amine flows under level/flow control through the lean/rich amine
exchangers where it is heated to about 206 oF by heat exchange with the hot lean
amine from the two regenerators.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 71 of 109

The rich amine feeds the regenerator above the stripping section which contains
stainless steel structured packing. CO2 and H2S are stripped from the rich solution by
steam produced in the regenerator reboilers which consist of 4 (four) kettle type shell
and tube heat exchanger for each regenerator.

B. PERFORMANCE

The main equipment of amine system are Regenerator Reflux Condenser 25-E-
101/202, Amine Reg. Reboiler 25-E-102A-D /202A-D , Lean amine cooler 25-E-
103/203, Rich / Lean Amine Exchanger 25-E-104A/B, 25-E-204A/B; Amine
Charge Pump 25-P-102A/B/C; Amine Booster Pump 25-P-101B/C

Table 4-9 : Performance of Amine Regenerator Re-boiler:

25-E-102A-D 25-E-202A-D DESIGN


STEAM SIDE (SHELL):
Pressure, psig 63.00 OFF 50.00
Temp sat'd steam, F 300.00 OFF 297.00
Flowrate Steam (25-FIC-121), Lb/hr 101,954.00 OFF 101,564.00
Flowrate Steam (25-FIC-122), Lb/hr 102,586.00 OFF 101,564.00
AMINE SIDE (TUBE):
Temp amine to Regenerator, F 259.50 OFF 261.00
Flow of Rich Amine to be regenerated, 1,309,729 OFF 1,299,665
Lb/hr
Delta T 44.25 OFF 39.25

HEAT DUTY, Btu/hr 184,589,323 OFF 194,088,804


HEAT TRANSFER RATE, 132 OFF 173
BTU/(HR.Ft2.degF)

The above table shows that the actual heat duty is closed to the design. The
difference between actual heat duty and design value only 5%, although the flow rate
regenerated rich amine higher than design, the temperature outlet of amine reboiler
less than design (actual is 249.5 deg F and design value is 262 deg F).

The overall heat transfer rate (U) at actual condition is 132 BTU/(Hr/Ft2.F) compare
the design is 173 BTU/(Hr/Ft2.F. This condition caused by the LMTD of actual is
higher than design value.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 72 of 109

Table 4-10 : Performance of Lean Amine Cooler :

25-E-103 25-E-203 DESIGN


LEAN AMINE side:
Pressure, psig 110.00 110.00 180.00
Temp inlet, F 190 190 224
Temp outlet, F 106 104 120
Flowrate of Lean Amine, Lb/hr 799,305 670,882 1,375,016

AIR COOLANT side:


Temp inlet, F 92 92 95
Temp outlet, F 129 129 141.3

Delta T LMTD 31.93 30.14 48.20

HEAT DUTY, Btu/hr 62,223,295 53,469,455 123,624,938


ELECTRIC CONSUMPTION, KW 336.84 367.46 447.60
ACTUAL FAN OPERATED 11 12 12
CALCULATE FAN OPERATED 6 5 12
HEAT TRANSFER RATE, 2 2 3
BTU/(HR.Ft2.degF)

The above table shows that the heat duty actual of 25-E-103 and 25-E-203 are
operated at 50% to the design. This caused by the flow rate of lean amine to be
cooled also only about 50% - 60% from design capacity.
The flow rate of lean amine does not affect to the power required of fan cooler driver,
so the power required to motors also higher than calculated value. At this case, the
actual fan be operated closed to design (11 fans for 25-E-103 and 12 fans running for
25-E-203). This condition related with performance of cooler, especially with heat
transfer rate. The U (overall heat transfer rate) at operating condition give value about
2 BTU/(Hr/Ft2.F) for operated and 3 BTU/(Hr/Ft2.F for the design value. This difference
indicated that the performance of cooler lower than the design performance.

Table 4-11 : Performance of Rich-Lean Amine Exchanger:

25-E-104A/B 25-E-204A/B DESIGN


RICH AMINE SIDE
Pressure, psig 108.00 OFF 95.00
Temp inlet, F 155.00 OFF 167.00
Temp outlet, F 203.00 OFF 206.00
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 73 of 109

Flowrate of Rich Amine, USGPM 2,572.00 OFF 2,496.80


LEAN AMINE SIDE
Temp inlet, F 250.00 OFF 261.00
Temp outlet, F 229.00 OFF 224.00
Delta T LMTD 59.48 OFF 55.99

HEAT DUTY, Btu/hr 53,656,356 OFF 42,413,111


HEAT TRANSFER RATE, BTU/(Hr/Ft2.F) N/A OFF N/A

The above table shows that the heat duty operated of exchanger 25-E-104A/B is
higher than design value. The difference is about 25% higher than design.

The different heat load should be caused by :


 Design amine is CR302, but the actual operation is AP-16668. The
difference of amine causes different specific heat.
 Flow rate of rich amine at operation is higher than the design value (3.5%
difference)
 The difference between operated LMTD and design is 6.5%.

Table 4-12 : Performance of Regenerator Reflux Condenser :

25-E-101 25-E-201 DESIGN

ACID GAS SIDE :


Temp inlet, F 218.47 OFF 217.00
Temp outlet, F 143.15 OFF 120.00
Flow of acid gas removed, MMSCFD 20.60 OFF 23.25
AIR COOLANT SIDE :
Temp inlet, F 92.00 OFF 95.00
Temp outlet, F 132.00 OFF 131.60
Delta T LMTD 67.27 OFF 57.60

HEAT DUTY, Btu/hr 55,701,905 OFF 61,714,112

ELECTRIC CONSUMPTION, KW 23.79 OFF 29.84


ACTUAL FAN OPERATED 11.00 OFF 12.00
CALCULATE FAN OPERATED 10.83 OFF 12.00
HEAT TRANSFER RATE, 3.57 OFF 4.19
BTU/(HR.Ft2.degF)

The above table shows that regen reflux condenser and amine regenerator re-boiler
are operated close to design condition. It has difference of heat duty about 11% than
the design value. This caused by the flow rate of acid gas to be removed also only
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 74 of 109

13% less than the design capacity (operated is 20.6 MMSCFD, and the design value
is 23.25 MMSCFD).

Power required of motor fan driver also proportional with the exchanger heat duty. At
this condition the actual operate 11 fans, and the calculated result is also same fans to
be operated.

Caused by the flow rate capacity of cooler load, the overall heat transfer also follow
with this condition. The U (overall heat transfer rate) at operating condition give value
about 3.57 BTU/(Hr/Ft2.F) and 4.19 BTU/(Hr/Ft2.F for the design value.

Table 4-13 : Performance of Amine Charge Pump

DESCRIPTION UNIT 25-P-102C Design


value value

specific gravity 1.03 1.00


Temperature F 245.00 70.00
suction pressure psia 98.00 25.00
discharge pressure psia 1210.00 1185.00
flow GPM 2862.00 2487.00
Total head ft 2,503.97 2679.60
Electric motor power HP 2240.00 2059.00
Mechanical work HP 1946.39 1719.89
Efficiency % 86.89 83.53

Only one Amine charge pump (Charge pump C) was running very close to design
condition. It’s efficiency reached 86.89% with flow rate of 2862 GPM, This pump is
designed to running with 83.53% efficiency at 2487 GPM flow rate. The pump was
running actually in even higher efficiency than the design condition. Attention should
be addressed to this situation since the pump draw consumed electric power of 2240
HP. It just below it's maximum power rating: 2250 HP.

Table 4-14 : Performance of Amine Booster Pump

DESCRIPTION UNIT 25-P-101B 25-P-101C Design


value value value
specific gravity 1.03 1.03 1.00
Temperature F 180.00 180.00 70.00
suction pressure psia 16.70 18.70 N/A
discharge pressure psia 119.70 129.70 N/A
flow GPM 1556.00 1306.00 2871.00
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 75 of 109

Total head ft 231.93 249.95 188.00


Electric motor power HP 142.00 136.00 170.00
Mechanical work HP 98.02 88.66 139.30
Efficiency % 69.03 65.19 81.94

Two of the Amine booster pumps were running. They were Amine Booster pump B
and C. Their efficiencies are 69.03% at 1556 GPM and 65.19% at 1306 GPM
respectively. At the other side, we have data from design condition when each pump
handles 2871 GPM. At this design condition, we got 81.94% efficiency. These two
pumps were running in good condition and within the range of operation.

4.2.3. REFRIGERATION SYSTEM

A. DESCRIPTION

Propane refrigerant gas from gas chiller at 75 psig, compress by propane compressor
(single stage screw compressor). The compressor discharge at about 252 psig goes
to the propane condenser where it is totally condensed at about 122 oF. The propane
condenser is an air cooled heat exchanger.

The condensed propane goes to the propane accumulator and then to the gas chiller
via the level control valve. The refrigerant chills the sales gas from 57 F to 45 F and
then goes to LTS to separate the gas from the condensate.

B. PERFORMANCE

The main equipment at Refrigeration System are Exchanger (Gas chiller 30-E-102),
Propane compressor 30-K-101A/B and Gas/Gas Exchanger.

Table 4-15 : Performance of Gas Chiller

UNITS DESIGN EVAPORATOR

TEMPERATURE GAS IN DEG.F 57.00 57.00


TEMPERATUR GAS OUT DEG.F 45.00 45.00
GAS FLOW MMCFD 100.00 39.00
CONDENSATE FLOW BCD 700.00 700.00

HEAT RELEASE BTU/H 2,477,633.80 841,348.85


ACTUAL POWER KW 260.00 110.00
C.O.P 2.79 2.24
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 76 of 109

The above table shows that the refrigeration system operated at low load and the
propane chiller are operated at 40 % load (39 MMSCFD ) at actual power 110 KW
compare to design condition. The COP at actual condition is 2.24 compare to design
value is 2.79

Table 4-16 : Performance of propane compressor

Only one compressor is operated to handle the refrigeration system. The operating
conditions are as follows;

UNITS DESIGN ACTUAL

o
SUCTION TEMPERATUR ( F) 35.00 30.00
o
CONDENSING TEMPERATUR ( F) 127.00 120.00
PROPANE FLOW LBS/H 14,000.00 7,191.72 (Calculated)

TOTAL POWER REQUIRED KW 242.17 101.64


ACTUAL POWER KW 260.00 110.00
COP 3.00 2.87

At the actual condition, the refrigerant flow is 7191 lb/hr at actual power 110 KW and
COP = 2.87. Compare to design condition, the refrigerant flow is 14,000 lb/hr at
power design 260 KW and COP = 3. It means that the performance of compressor is
still in good condition.

Table 4-17 : Performance of Gas/Gas Exchanger

30-E-101 DESIGN

HOT GAS (FR GELAM CONTACTOR):


Pressure, psig 1000 1120
Temp inlet, F 130.00 129.60
Temp outlet, F 60.00 64.40
Flow rate of Gas, MMSCFD 39.39 114.00

GELAM SALES GAS side:


Temp inlet, F 40.00 50.00
Temp outlet, F 120.00 117.00
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 77 of 109

Delta T LMTD 14.43 13.48

HEAT DUTY, Btu/hr 3,159,954 10,705,230.41


2
HEAT TRANSFER RATE, BTU/(Hr/Ft .F) 0.23 0.30

The above table shows that gas/gas exchanger at the dew point control system have
heat duty only 30% refer to the design value. This caused by the flow rate of gas also
only 35%. The temperature profile of gas also not have high different between
operated and design value.

Caused by the flow rate capacity of gas to the gas/gas exchanger, the overall heat
transfer also follow with this condition. The U (overall heat transfer rate) at operating
condition give value about 0.23 BTU/(Hr/Ft2.F) and 0.30 BTU/(Hr/Ft2.F for the design
value.

4.2.4. CONDENSATE STABILIZING SYSTEM

A. DESCRIPTION

The hydrocarbon liquid from the feed drum is fed under level control to the top tray of
the condensate stabilizer. The stabilizer is a 32 inch ID reboiled stripping column
containing 18 stainless steel valve trays.

The stabiliser reboiler is a kettle type shell and tube exchanger utilizing about 3404
lb/h of 140# steam at normal operation. During normal operation about 1738 bbl/day
of 10 psi RVP condensate are produced. The condensate product from the stabilizer
is sent via the HC condensate cooler bundle in the refrigerant condenser air cooled
exchanger frame.

B. PERFORMANCE

The main equipment at Condensate Stabilizing system are Stabilizer Re-boiler 35-E-
102, and Condensate cooler 35-E-101

Table 4-18 : Performance of Stabilizer Reboiler 35-E-102 :

35-E-102 DESIGN
STEAM SIDE (SHELL)
Pressure, psig 117.00 150.00
Temp sat'd steam, F 330.00 330.00
Flow rate (35-FIC-006), Lb/hr 803.00 3,751.35
CONDENSATE SIDE (TUBE)
Temp Condensate to re-boiler, F 278.00 261
Delta T 66.00 69.40
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 78 of 109

HEAT DUTY, Btu/hr 700,201 3,470,000


HEAT TRANSFER RATE, (BTU/Hr.Ft2.F) 6.52 30.73

The above table shows that actual heat duty of 35-E-102 is only 20 % compare to
design condition because the flow rate of feed liquid to the stabilizer is only 20 % - 25
% compare to design.

Due to the flow rate of stabilizer re-boiler is only 20% than the design, the U (overall
heat transfer rate) at operating condition give value about 6.52 BTU/(Hr/Ft2.F)
compare with the design value, 30.73 BTU/(Hr/Ft2.F

Table 4-19 : Performance of Propane Condenser and Condensate Cooler

30-E-105 DESIGN 35-E-101 DESIGN

FLUID SERVICES: PROPANE CONDENSATE


COONDENSOR
Pressure, psig 150 250
Temp inlet, F 140.00 158.00 316 316.00
Temp outlet, F 119.00 124.00 120 120.00
Flow rate, MMSCFD (gas) 4.50 5.13
Flow rate, BBL/day (liquid) 1324 2,174
AIR COOLANT SIDE :
Temp inlet, F 92.00 95.00 92 95.00
Temp outlet, F 105.00 109.90 105 109.90
Delta T LMTD 30.83 35.30 53.68 85.85

HEAT DUTY, Btu/hr 3,086,550 3,796,245 718,616 1,995,227

ELECTRIC CONSUMPTION, KW 14.72 22.38 14.72 22.38

The arrangement of cooler in this area is designed to serve three stream cooling fluid,
i.e : Propane condenser, Propane overhead condenser and condensate stabilizer.
Only one fans cooler installed to cool them. At the plant survey, the propane overhead
condenser was off.

Heat Load total at actual condition of two condenser (30-E-105 and 35-E-101) are 3.8
MMBTU/hr compare with the design value is 5.7 MMBTU/hr. This heat load gives
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 79 of 109

percentage about 65 % of heat load capacity similar with electrical consumption is 65


% too.

4.2.5. DEHYDRATION SYSTEM

A. DESCRIPTION

The water saturated gas from the three amine trains is dehydrated by contacting it
with lean triethylene glycol (TEG) in the three, identical glycol contactors. The design
water content of the dry gas is 10 lb H2O per MMSCFD. The dehydrated GLT gas is
recombined with the GLT amine unit bypass gas, sent through the dewpoint unit and
then to sales. The Dayung/Suban gases from two of the glycol contactors and the
Dayung/Suban amine unit bypass gas are sent directly to Sales.

Lean glycol is fed to the top of the glycol contactor at a rate of about 30-USgpm. A coil
is provided in the top of the tower to cool the glycol from about 210 oF to less than 150
oF by heat exchange with the dried gas leaving the contactor. The glycol flows
downwards through the structured packing in the column counter-currently contacting
and absorbing water from the gas flowing upwards through the packing.

The rich glycol accumulates on the chimney tray and is sent under level control to the
glycol regeneration skid. The dry gas exits the top of the contactor with the
Dayung/Suban gasses going to sales and the GLT gas going to the hydrocarbon dew-
point control unit.

The three glycol regeneration skids are identical. There are no connections between
the glycol regeneration skids or between the glycol lines in each train.

B. PERFORMANCE

Table 4-20 : Performance of Rich – Lean Glycol Exchanger

41-E-101 41-E-201 41-E-301 DESIGN

LEAN TEG SIDE


Pressure, psig 10.50 11.50 11.00 50.00
Temp inlet, F 380.00 370.00 360.00 360.00
Temp outlet, F 150.00 165.00 160.00 225.00
Flow rate of Lean TEG, USGPM 20.18 24.00 24.00 30.48
RICH TEG SIDE
Temp inlet, F 140.00 142.00 140.00 171.00
Temp outlet, F 200.00 200.00 196.00 306.20
Delta T LMTD 58.82 61.13 66.25 51.90

HEAT DUTY, Btu/hr 1,400,267 1,477,137 1,439,554 1,485,141


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 80 of 109

HEAT TRANSFER RATE, 104.88 88.55 92.66 128.20


BTU/(Hr/Ft2.F)

The above table shows that Rich/Lean Glycol Exchanger are operated close to design
condition. Its heat duty is only 5% differ than the design value, although the flow rate
of glycol at the operation only 70% - 80% than design capacity. This condition is
caused by the difference of LMTD between operated and design value. The operating
condition gives temperature outlet of Lean glycol lower than design value.

Due to the flow rate capacity of cooler load, the U (overall heat transfer rate) at
operating condition give value about 70%-80% than the design value.

Table 4-21 : Performance of Glycol Heater

2-Oct-07

41-H-101 41-H-201

1 FUEL,
Flow, MMSCFD 0.02 0.02
2 FLUE GAS
T out, F 430.00 430.00
O2, % 7.00 7.00
Excess Air, % 45.77 45.77
3 PERFORMANCE
Heat absorption (LHV), MMBtu/hr 0.91 0.91
Heat absorption (HHV), MMBtu/hr 0.92 0.92

Efficiency (LHV), % 84.91 84.91


Efficiency (HHV), % 77.08 77.08
4 CO2 EMISSION
CO2 Emission from fuel gas, lb/hr 191.42 191.42

The heat duty of Glycol heater is 0.91 mmbtu/hr (calculated from process site).
Assuming the oxygen content of flue gas is 7%, the calculated efficiency is 84.91%.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 81 of 109

4.2.6. WASTE HEAT BOILER

A. DESCRIPTION

Permeate gas from membranes, rich amine flash drum gas, and acid gas from the
amine reflux accumulators are combined and sent to the waste gas incenerator. In the
incenerator, the waste gas is incenerated by burning fuel gas at a sufficient high
temperature to ensure the complete destruction (oxidation) of the H2S and
hydrocarbons. The minimum exit gas temperature at the top of the stack is 450 oF to
ensure that the allowable ground level SO2 concentration is not exceeded.

150 psig saturated steam is produced by two heat recovey boilers with each capacity
of 230,000 lb/h. Normally, two boilers are operated to supply necessary steam for all
users in CGP.

B. PERFORMANCE

The main equipment of Waste Heat Boiler system are Waste Heat Boiler 46-B-
101/201, and BFW pump 46-P-102A/B/C.

Table 4-22 : Performance of Waste Heat Boiler

2-Oct-07 DESIGN

46-B-101 46-B-101/102

1 INLET GAS,
Fuel Gas Flow, MMSCFD 1.55 1.77
Acid Gas Flow, MMSCFD 20.23 48.11
Permeat Gas Flow, MMSCFD 8.35 68.39
2 FLUE GAS
T out, F 376.00 416.00
O2, % 7.00 2.62
Excess Air, % 45.77 13.17
3 BFW
lb/hr 200,392.00 245,000.00
T in Economizer, F 200.00 251.00
T out Evaporator, F 347.00 375.00

P in Economizer, Psi 132.40 175.70


P out Evaporator, Psi 123.00 170.00
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 82 of 109

4 PERFORMANCE
Heat Release (LHV), MMBtu/hr 149.52 822.94
Heat Release (HHV), MMBtu/hr 164.41

Heat Loss (LHV), MMBtu/hr 29.91 380.55


Heat Loss (HHV), MMBtu/hr 43.92

Heat absorption (LHV), MMBtu/hr 119.60 442.38


Heat absorption (HHV), MMBtu/hr 120.49

Efficiency (LHV), % 79.99 no Dsg Eff


Efficiency (HHV), % 73.29 no Dsg Eff
5 CO2 EMISSION
CO2 Emission from fuel gas, lb/hr 29,070.86 no Dsg CO2
CO2 Emission from Acid gas, lb/hr 103,029.15 no Dsg CO2
CO2 Emission from Permeat gas, lb/hr 42,586.20 no Dsg CO2
Total CO2 Emission, lb/hr 174,686.21 no Dsg CO2

The above table shows that the WHB are operated at only 50 % load compare to
design condition, and the calculated efficiency is 80%. The temperature in flue gas are
lower than design condition and the excess air is higher than design.

Table 4-23 : Performance of BFW Pump

DESCRIPTION UNIT 46-P-102A 46-P-102C Design


value value value
specific gravity 1.00 1.00 1.00
Temperature F 245.00 245.00 70.00
suction pressure psia 21.10 21.10 8.00
discharge pressure psia 274.70 274.70 230.00
flow GPM 380.00 380.00 528.00
Total head ft 585.82 585.82 512.82
Electric motor power HP 95.00 95.00 110.00
Mechanical work HP 57.45 57.45 69.88
Efficiency % 60.48 60.48 63.53
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 83 of 109

Like Amine booster Pumps, the two BFW pumps were running within the specification,
and the efficiency reached is accepted. This BFW pump is designed to run with
63.53% efficiency at 528 GPM flow rate. Actually, two pumps were running at same
rate of flow (380 GPM) with 60.48% efficiency.

4.2.7. GAS TURBINE GENERATOR

A. DESCRIPTION

Electrical power is generated and distributed to provide the prower requirements for
the gas plant and offsites. Electrical power Generator driven by Gas turbine generator,
which gas supplied from HP (high pressure) fuel gas system. Three gas turbine are
provided with two generator running and one on the standby mode. The design
capacity of generator is 4500 kW each unit. The actual capacity on the field survey
only about 2100 kW each turbine generator (45% of design capacity) and running two
of three generators.

Generator specification is power 4688, voltage 4160, freq 50 Hz, cos Q 0.85. The
large motor (lean amine charge pump, WHB Blower, propane compressor) supply by
6600 volt and the other motors using 400 volts.

B. PERFROMANCE

Gas turbine generators at Utility system are 47-GTG-101A/B/C

Table – 4.24 : performance of GTG

2-Oct-07 DESIGN
47-GT-101A 47-GT-101B 47-GT-101A/B/C
TURBINE
Fuel gas :
flow, MMSCFD 0.89 0.92 1.31
Flue gas :
Temperature, F 0 0 900
O2, % 16 16 16
Excess Air, % 296 281 267
Turbine Eff, % 21 21 30
Btu/kwh 16,571 16,077 11,559
CO2 Emission
lb/hr 4,870 5,034 7,914
GENERATOR
Power Output, KW 2,158 2,265 4,688
PF 0.81 0.83 0.84
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 84 of 109

V 4160 4160 4160


Frequency, Hz 50 50 50

The above table shows that GTG operated at 50 % load compare to design condition.

The calculated efficiency is only 21 % compare to design which is 30 %. The


decreasing of efficiency of GTG is caused by low load and will be impact the
increasing of the heat loss,

The heat rate of 47-GT-101A is 16,571 Btu/kwh, greather than design 16000 Btu/kwh
but 47-GT-101B 16,077 Btu/kwh close to design.

Table 4-25 : The design performance of GTG are as follows

POWER 4500 4000 3500 3000 2500 2000 1500 1000


BTU/KWH 11600 12000 12600 13000 14000 16000 18700 25000

4.2.8. AIR COMPRESSOR

A. OPERATION

Instrument and utility air are supplied by the two 340 scfm, screw type compressor
connectod in a lead-lag configuration. The compressed air is filtered and then dried in
heatless adsorption type dries which are on automatic regeneration cycles. The
instrument air compressor packages are provided with local electronic control panels.

The instrument air receiver is normally operated between 110 and 120 psig. The utility
air take-off is equipped with a shut off valves to prevent utility air usage from drawing
down the instrument air pressure.

B. PERFORMANCE

There are three compressors Atlas Copco GA 75 , 51-A-101A /B/C with design
capacity is 340 SCFM, the performance of each equipment are as follows,

Table 4-26 : Performance of air compressor :


UNITS DESIGN ACTUAL

SUCTION PRESS PSI 14.70 14.70


DISCHARD PRESS. PSI 182.00 132.30
COMPRESS AIR FLOW SCFM 340.00 257.45
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 85 of 109

POWER KW 72.60 44.17


ACTUAL PERFORMANCE 0.20 0.20

The above table shows that the compressor is operated at low load. The
performance can not be evaluate accurately because no flow meter of air

4.2.9. ELECTRICAL MAP CENTRAL GRISSIK GAS PLANT

Electric map for Central Grissik Plant is like the one for Suban Gas plant. It is derived
from single line diagram, and intend to get a closer and clear point of view to one that
need brief description on power consumption at each process. It Emphasize the
voltage, and power required for each equipment.

The power mentioned at each equipment is the power in normal design condition.

A. Amine System

4.16 KV
25-P-102 A/B/C
Amine Charge pump A/B/C
2250 HP x3

480 V

25-PM-101 A/B/C 25-EM-103 A-M 25-EM-203 A-M


Lean amine booster pump A/B/C Lean Amine cooler fan A-M Lean Amine cooler fan A-M
200 HP x3 37.3 KW x13 37.3 KW x13

25-EM-201 A-M 25-EM-101 A-M


Regenerator reflux condenser fan A-M Regenerator reflux condenser fan A-M

29.8 KW x13 29.8 KW x13

25-PM-105 25-PM-104 25-AM-101/102 25-PM-203A/B


Amine Transfer pump Amine Sump pump Anti foam injection pump Regenerator reflux pump A/B
9 HP 7.50 HP x2
15 HP 2 HP x2
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 86 of 109

B. Propane Chiller System

4.16 KV

30-K-101 A/B
Propane Compressor A/B
350 HP x2 480 V

30-K-101A/B-KM1 30-K-101A/B-PM1 30-PM-103


Propane Compr. A/B L.O. cooler fan Propane Compr. A L.O. pump motor Propane Transfer pump
5 HP x2 5 HP x2 3 HP

C. Depropanizer and Condensate Stabilization System

480 V

30-PM-102 30-PM-101 30-E-104 30-EM-105 A/B


Depropaniser reflux pump Depropaniser feed pump Depropaniser reboiler heater Propane condenser fan A/B
3.5 HP 5 HP 69 KW 22.3 KW x2

35-PM-102 A/B
Condensate shipping pump A/B
75 HP x2

D. Dehydration System

480 V

41-PM-101 41-PM-102/2020/302 A/B


Glycol transfer pump Glycol circulation pump
1.74 HP 25 HP x6

E. Incinerator/Heat recovery System

4.16 KV

46-K-101/201
Inc. Blower train A/B

400 HP
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 87 of 109

F. BFW steam and Condensate System

480 V

46-PM-102 A/B/C 46-EM-101 A/B 46-PM-103 A/B


BFW pump A/B/C Excess steam condenser fan A/B Condensate pump A/B
150 HP 22.3 HP x2 25 HP x2

G. Flare and Air compressor System

480 V

51-AM-101 A/B 48-PM-101 A/B 51-AM-101 A/B -2


Instr. Air compressor A/B Flare KO drum pump A/B Instr. Air compressor A/B cooler fan
125 HP x2 3 HP x2 4 HP x2

H. Utility System

480 V

55-PM-201 A/B 54-PM-201 A/B 53-PM-201 A/B


Utility water pump A/B Portable water pump A/B Softened water pump A/B
15 HP x2 7.5 HP x2 7.5 HP x2

4.3. FINDINGS AND RECOMMENDATION


1. Instrumentation and Metering

Based on the site survey founded that many metering and instrument are not work
properly. Findings and recommendations of metering and instrumentation at
Grissik Central Gas Plant are as follows :

Equipments Findings Recommendations


1. WHB  There are unbalance  Need to calibrate
between BFW flow and meter of steam and
steam flow that will BFW
impact the direct method
efficiency calculation is  Need to install
not accurate. sampling point to
measure Boiler
 Oxygen analyzer not water quality and
work properly ( direct control the blow
measurement = 7 % , on down
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 88 of 109

line analyzer = 14 %)

 No Sampling point for


water quality at steam
drum

2 Glycol &  No meter fuel gas at the  need to install fuel


Regen heater gas meter
Heater
 The position of flue gas  need to install
sampling point is far from sampling line of flue
platform gas close to the
platform

3 GTG  There are no flow meter  Need to install flow


of fuel gas in each GTG. meter of fuel gas

 Need to install
sampling line of flue
gas for each GTG

4 Propane  No continue record of  Need to records


Comp electric consumption for continously
motor compressor

5 Electric  No continue recorded for  Need to record


Distribution electric distribution electric distribution
(4160 line) at daily
records

2. Waste Heat Boiler

Calculation result of WHB :

EFFICIENCY HEAT CO2


ABSORB EMISSION
% MMBtu/hr Lb/hr
W H B - INCENERATOR 46-B-101
DESIGN N/A 442.38 N/A
46-B-101 79.99 119.60 174,686.21
46-B-102 OFF OFF OFF

Finding :

 WHB is operated at high excess air (77 %) compare to the design figure
which is 27 % excess air. The efficiency is 80 %
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 89 of 109

 WHB is operated at low load ( 50 % load)

Recommendation :

 WHB should be operated close to the design excess air

3. Heater

Calculation result of heater :

EFFICIENCY HEAT ABSORB CO2 EMISSION


% MMBtu/hr Lb/hr
GLYCOL HEATER : 41-H-101
DESIGN
41-H-101 84.91 0.91 191.42
41-H-201 84.91 0.91 191.42

REG GAS HEATER : 21-H-101/201


DESIGN 74.62 11.06 2,651.23
21-H-101 74.65 5.75 1,376.93
21-H-201 OFF OFF OFF

Finding :

The heater are operated at low load (50 % load)

4. GTG

Calculation result of GTG :

EFFICIENCY HEAT RATE BHP CO2 EMISSION


% BTU/KWH KW Lb/hr

GAS TURBINE GENERATOR


DESIGN 29.52 11,558.78 4,687.50 7,914.10
47-GT-101A 20.59 16,571.34 2,158.33 4,869.94
47-GT-101B 21.23 16,077.04 2,264.58 5,034.10
47-GT-101C OFF OFF OFF OFF

Findings :

GTG are operated at lower load is around 50 % compare to design, but the
performance ( heat rate ) are still close to design at low load
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 90 of 109

5. Propane Comp

Calculation result of Propane Compressor :

POWER ACTUAL PROPANE COP


REQUIRED, POWER, KW FLOW
KW

DESIGN 242.17 260.00 14,000.00 3.00


30-K-101A 101.64 110.00 7,191.72 2.87

Findings :

Based on the actual data, the refrigeration load is only 50 % compare to design
condition, but the COP is 2.87 compare to design COP is 3. It means that the
compressor is still in good condition

6. Gas Chiller

Calculation result of gas chiller :

UNITS DESIGN GAS CHILLER

GAS INTAKE TEMP.AT EVAP. DEG F 58.00 57.00


GAS OUTPUT TEMP.AT EVAP. DEG F 45.00 45.00
SALES GAS FLOW MMCFD 100.00 39.00
CONDENSATE FLOW BBL/D 700.00 700.00

HEAT RELEASE MMBtu/hr 2,645,934.62 841,348.85


TOTAL POWER KW 260.00 110.00
C.O.P 2.98 2.24
(Calculated)

Findings :

 the temperature indicator inlet and outlet are still in good conditions

 COP at gas chiller is 2.24 compare to design 2.98


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 91 of 109

7. Air cooler

Calculation result of coolers are as below:

No. COOLER HEAT DUTY HEAT TRANSFER ELECTRIC/HEAT DUTY


RATE
(MMBTU/HR) (BTU/HR.FT2.oF) (%)
1. Amine Regen Reflux Cooler
25-E-101 55.70 3.57 1.60%
25-E-201 OFF OFF OFF
2. Lean Amine Cooler
25-E-103 62.22 2.06 1.85%
25-E-203 53.47 1.88 2.34%
3. Stab. Condensate Cooler
35-E-101 0.72 5.03 8.85%
4. Propane Condenser Compressor Cooler
30-E-105 3.09 2.89 1.63%
5. Propane Ovhd Cooler
30-E-103 OFF OFF OFF

Findings :

 Power rated required for drive motors of fan coolers are below 1% - 2% due
to their heat duties, except for Lean Amine 25-E-203 and Condensate
cooler (25-E-101). This case indicate that power consumption of these
coolers more waste energy (less efficiency).

Recommendations :

 Need to check the cooler system of Lean amine cooler, because at the
plant survey, they have high power consumption although the capacity of
heat load only a half than design.

 Need to check again the properties of amine used in operation, because it


can effect the calculation performance of cooler and exchanger system in
amine system.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 92 of 109

8. Heat Exchanger

Calculation result of heat exchangers are as below:


No. HEAT EXCHANGER HEAT DUTY HEAT TRANSFER DIRTY FACTOR ELECTRIC/
RATE HEAT DUTY
(MMBTU/HR) (BTU/HR.FT2.oF) ACTUAL DESIGN (%)

1. Gas-Gas HE in TSA unit


Regen HE:
21-E-101 0.97 6.90 0.063 0.002 -
21-E-201 OFF OFF OFF OFF OFF
Cooler HE:
21-E-102 4.67 4.46 0.005 0.002 -
21-E-202 OFF OFF OFF OFF OFF
2. Rich/Lean Amine
Exchanger
25-E-104A/B 53.58 N/A N/A N/A -
25-E-204A/B OFF OFF OFF OFF OFF
3. Rich/Lean Glycol
Exchanger
41-E-101 1.40 104.88 0.002 0.001 -
41-E-201 1.73 117.99 0.001 0.001 -
41-E-301 1.67 111.25 0.001 0.001 -
4. Gas-Gas Dew Point
Control HE
30-E-101 3.16 0.29 0.09 0.10 -
5. Amine Regen Reboiler
25-E-102 A-D 184.59 132.16 0.002 0.001 -
25-E-202 A-D OFF OFF OFF OFF OFF
6. Stabilizer Reboiler 35-E- 0.70 6.52 0.001 0.001 -
102
7. Depropanizer Reboiler 30- 0.14 N/A N/A N/A 102.32%
E-105

Findings :

 Entirely, the performance of heat exchangers in Grissik plant still in good


condition, except for Gas/GAs Exchanger in TSA unit is needed to check
again for the fouling condition, because it’s dirty factor have higher than
their specification (design).
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 93 of 109

9. Gas Pretreatment & Membrane system

CALCULATION OF MEMBRANE SYSTEM

Membrane Separation Rate 0.321556 lbmole/ lbmole


Design Value of Membrane Separation 0.511022 lbmole/ lbmole

HYDROCARBON SLIP Rate 0.030709 lbmole/ lbmole


Design Value of Hydrocarbon Slip Rate 0.063241 lbmole/ lbmole

Findings :
 The Thermal swing adsorber (TSA) system running on good condition,
because the C6+ concentration at the feed gas to membrane is 29 ppm
compare to the design is 39 ppm.
 The membrane system separation only give separation rate is 32%
compare to the design 50% of CO2 feed, so the CO2 content in gas to
contactor still high than design value.
Recommendation :
 Need to check again the membrane module system to upgrade the
separation rate.

10. Amine System

Findings :

 The absortion rate capacity of amine contactor is only 38% refer to the
design capacity rate. This case caused by the flowrate of gas processing
capacity of lean amine only 40% than design.

Recommendation :

 Need to operate full gas processing capacity to increase absorption rate in


amine contactor due to reduce the energy consumption in amine system

11. Energy Conservation

a. Energy Losses :

Based on heat balance calculation, energy losses from high temperature flue gas
(more than500deg F) at Grissik is coming from Stack of GTG. Total losses is
57,821,543 Btu/hr.

STACK LOSS, TEMP, Deg


Btu/hr F
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 94 of 109

GTG
247-GT-201A 30,471,332 949
247-GT-201B 27,350,211 967
247-GT-201C 0 0
TOTAL 57,821,543 958

Actually, by utilizing economizer with stack temperature around 500 deg F, this
Fluegas losses can be used to generate saturated steam about 28,000 lb/hr.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 95 of 109

b. Potential Saving :

Based on the evaluation, shows that the potential saving are coming from :

 Optimize operation of WHB by reducing excess air (7 % O2 to 3% O2)


increase efficiency aroumd 4 %, that will reduced LP fuel consumption to
0.06 MMSCFD

 Utilized flare gas that will reduced fuel consumption to 1.0 MMSCFD

Energy Conservation Opportunities :

 Optimized operation of GTG can be implemented by load shading

 Optimized operation of Heater and utilized flare gas can be implemented by


installing booster compressor to compress gas up to 180 psig. This fuel
can be used for Gas turbine and in turn it will reduce HP Fuel consumption.
The simple calculation are as follows :

WHB-saving, MMSCFD 0.06


, US $/Year 76,725.00
Flare Gas-saving, MMSCFD 1.00
, US $/Year 1,237,500.00
Total, MMSCFD 1.06
, US $/Year 1,314,225.00
*Cost to install the system for recovery gas 3,000,000.00
which includes : gas compressor, KO Drum,
Instrumentations , US $

Operation and Maintenance Cost , US $/year 120,000.00


Net income , US $/Year 1,194,225.00

Estimated payback period to install the 2.51


system , Years

* = refer to Beak Pacifik Report - Energy Audit at Cilacap Refinery Complex


(Beak Pacific Inc. , Vancouver, Canada)

c. Emission Reduction Potentials

CO2 emission at suban gas plant is 182,886 lb/hr. its come from combustion of
fuel gas at flare gas, heater, WHB and GTG. Optimized operation and utilized
flare gas can reduce CO2 emission around 5 %
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 96 of 109

CO2 reduction,
lb/hr
utilized flare gas 8,507.79
Total 8,507.79

Utilized flare gas will reduce CO2 5%


emission , %

12. Reporting system

Findings :

 Existing daily report just for production activity it does not cover data for
plant performance evaluation purpose

 No data acquisition and evaluation based on daily log sheet .

 Important data for plant performance not cover in daily log sheet

Recommendation :

 Daily reporting must cover production activity and plant performance


indicator

 Regular summary of log sheet regarding plant performance should be


evaluate.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 97 of 109

V. ENERGY ASSESSMENT AT RAWA OIL


PLANT

5.1 GENERAL PLANT OPERATION AND PERFORMANCE

5.1.1. PLANT OPERATION

There are wells at ConocoPhillips South Sumatra area that contents oil in significant
amount and high gas concentration. Rawa plant is designed to process this oil, and re
inject the gases to the injection wells.

High-pressure oil & gas came firstly from wells entering the plant via manifold, before
entering the production processes. The first process is High-pressure separator (HP
separator). Oil, MP Gas and Water is separated in this process. MP gas (450 psig)
leave the top separator and water leave the bottom of the separator and then store it
in the production water tank before send to Central Ramba.

Oil & LP gas mixture goes to medium pressure (MP) separator. In MP Separator, Oil
& HP gas is separated. Oil is stored to the crude oil tank before ship to Plaju. LP Gas
(50 psig) compressed by LP Gas compressor (gas engine) to raise it the pressure until
450 psig.

MP gas from HP separator mix with MP Gas from LP Compressor and then the HP
Compressor driven by gas turbine to rise the pressure until 1200 psig. Water content
in HP Gas is reduced by glycol system before injected to the wells. The design of HP
Compressor is 45 MMSCFD and about 1 MMSCFD of process gas used for fuel.

The simplified process flow diagram of Rawa field is shown at diagram in figure 1.1

MP Gas 5

HP Compressor

Oil wells 2
1
Injection
To wells
HP Separator MP Separator Gas Scrubber
Glycol
System
3 4

Prod water To Ramba LP


tank Compressor
4
Oil
Send to Plaju and Bentayan

Figure 5.1. Rawa prod. Block diagram


(simplified)
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 98 of 109

Data from production records taken from 1-10 Aug 2007 at table 1 shows that oil
extracted from wells is about 300-320 barrels/day (0.001%) and water produced is
1500-1600 (0.003%). About 21 MMSCFD gas derived is re injected to injection wells
while the other product, i.e. fuel gas, is sent to Ramba station.

Table -5.1 : Oil Production Data

5.1.2. GENERAL PERFORMANCE EVALUATION

The Energy Source of Rawa oil Plant is LPgas used for gas turbine compressor (LP
and HP) and Glycol Regenerator which comes from LP Separator. LP Compressor
driven by gas engine to increase the LP Gas pressure from 60 psi to 450 psi and HP
Compressor driven by gas turbine to increase the MP gas from LP Compressor and
HP Separator to 1200 psi.

Fuel flow meter only for total consumption. There is no flow meter for each
consumers. The total consumption is 0.7 – 1.1 MMSCFD

Rawa oil processing plant doesn't have electric power generation systems inside the
plant itself. Electric power derived from Ramba power plant via medium voltage lines,
11KV, 3, 50 Hz. Incoming power line then is stepped down by a transformer to
380V/220V, 3, and in turn, this voltage system is applied to all the electrical
equipments and machines inside the plant. There is no KW Meter in main panel. The
estimate load is about 150 KW.

For emergency purposes, there is a diesel fueled electric generator (380V, 3, 50 Hz)
that has capacity of 505 KVA. This generator set needed extra maintenance due to
this machine is of the old type, and have been used over a long period of time.

5.2 PERFORMANCE EVALUATION OF MAIN EQUIPMENT


The main equipment at rawa oil plant are . HP Compressor 5000-PK-100 , LP
Compressor 5000-PK-101 and Glycol Reboiler 3600-HT-103

The performance of HP and LP Compressor are as follows :


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 99 of 109

HP Compressor 5000-PK-100

Table -5.2 : Performance of HP Compressor 5000-PK-100

UNITS ACTUAL DESIGN

INJECTION GAS MMCFD 39.20 45.00


ABSL.SUCTION PRESSURE (Ps) PSIA 455.00 515.00
ABSL. DISCHARED PRESSURE (Pd) PSIA 1,165.00 1,465.00

POWER REQUIRE HP 2,860 3,525

Injection gas flow at actual condition is 39.20 MMSCFD (87 % load) compare to
design (45 MMSCFD) and power require is 2860 HP compare to 3525 HP

Table -5.3 : Performance of turbine 5000-PK-100

21-Dec-07 DESIGN
HP Turbine 5000- HP turbine 5000-
PK-100 PK-100

A TURBINE
Fuel gas :
flow, MMSCFD 0.85 0.89
Flue gas :
Temperature, C 1,062 900
O2, % 15 16
Excess Air, % 234 279
Eff, % 22 27
Btu/BHP 11,460 9,392
CO2 emission :
Flow, lb/hr 2,217 2,450
B COMPRESSOR
Power Required, KW 2,134 2,630
, HP 2,860 3,525

Turbine is operated at 72 % load (2860 HP) compare to design (3525 HP) and heat
rate is 11.460 Btu/HP compare to the design heat rate is 10500 Btu/HP.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 100 of 109

Table -5.4 : Design performance of turbines

POWER,HP 4000 3500 3000 2500 2000 1500 1000

BTU/BHP 9500 9700 10500 11000 12000 12700 14000

LP Compressor 5000-PK-101

Table -5.5 : Performance LP Compressor 5000-PK-101 are as follows

UNITS ACTUAL DESIGN

INJECTION GAS MMCFD 6.00 15.00


ABSL.SUCTION PRESSURE (Ps) PSIA 75.00 75.00
ABSL. DISCHARED PRESSURE (Pd) PSIA 445.00 450.00
FUEL CONSUMPTION MCFD 250.00 400.00

POWER REQUIRE HP 533.05 1,439.09


ENERGY INTENSITY Btu/HP 19,541.46 11,581.36

LP compressor is operated at low load (less than 40 %) compare to design it will


impact the energy intensity very high (19,541 BTU/HP compare design value
11,581 BTU/HP)

5.3 FINDINGS AND RECOMMENDATION


Findings :

A. Instrumentation

 no flow gas meter for each gas consumer,

 no control monitoring system that can be used to monitor the operation of the
compressor from control room.

 No meter indicators for electric equipments.

B. Compressor

 Compressors is operated at low load for LP (less then 40%)


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 101 of 109

 HP compressor is operated 70% load compare to design, the heat rate is


higher then design heat rate at 70 % load.

 LP compressors shut down frequently and causing increase of flare gas from 1
MMSCFD to 4-9 MMSCFD.
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 102 of 109

VI. PERFORMANCE MONITORING INDICATOR


6.1. EQUIPMENTS
6.1.1. Fired Heater
Function : converting energy from fuel gas into thermal in order to increase the
temperature of process fluid
Key Performance Indicator :
Efficiency which is consist of combustion efficiency and heat transfer
efficiency
Variable should be Measured :
 % O2 in flue gas
 Stack Gas Temperature
 Ambient Temperature
 Fuel gas flow, composition
 Fuel gas heating value
Spread sheet :

See Appendix no.6.1

6.1.2. Waste Heat Boiler


Function : converting energy from fuel gas and permeat gas into thermal in order to
produce steam and oxidize H2S from acid gas
Key Performance Indicator :
Efficiency which consist of combustion efficiency and Heat transfer
efficiency
Variable should be Measured :
 % O2 in flue gas
 Stack Gas Temperature
 Ambient Temperature
 Flow and composition of fuel gas, permeat gas and acid gas
 Heating value of fuel gas, permeat gas and acid gas
Spread sheet :

See Appendix no.6.2


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 103 of 109

6.1.3. Gas Turbine Generator

Function : converting energy from fuel gas to mechanical energy to produce electricity
Key Performance Indicator :
Efficiency which is consist of gas turbine efficiency and generator
efficiency
Variable should be Measured :
 Fuel gas flow (input)
 Fuel gas heating value (LHV)
 Generator Output
 Oxygen content in flue gas
 Flue gas temperature
Spread sheet :

See Appendix no.6.3

6.1.4. Gas Turbine Compressor

Function : converting energy from fuel gas to mechanical energy to compress sales
gas
Key Performance Indicator :
 Efficiency which consist of gas turbine efficiency and compressor
efficiency
 Energy Intensity which is representing by fuel gas divided by
mechanical energy to compress sales gas
Variable should be Measured :
 Fuel gas flow (input)
 Fuel gas heating value (LHV)
 Oxygen content in flue gas
 Flue gas temperature
 Suction and discharge pressure of sales gas
 Flow of sales gas
Spread sheet :

See Appendix no.6.4


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 104 of 109

6.1.5. Air Compressor

Function : converting energy from electricity to compress air


Key Performance Indicator :

Actual power / Qs x ((Pd/Ps)^0.2857 – 1)

Note : Qs = air flow

Variable should be Measured :


 Electricity power (input)
 Pressure of compressed air
Spread sheet :

See Appendix no.6.5

6.1.6. Propane compressor

Functions : to evaporate refrigerant and to condense refrigerant vapor


Key Performance Indicator :
Coefficient of Performance (COP)
Variable should be Measured :
 Electricity power (input)
 Evaporation Temperature
 Condensing Temperature
Spread sheet :

See Appendix no.6.6

6.1.7. Pumps

Functions : to transfer or to lift up the liquid


Key Performance Indicator :
Efficiency which consist of pump efficiency
Variable should be Measured :
 Electricity power (input)
 Liquid flow
 Suction and discharge pressure
Spread sheet :
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 105 of 109

See Appendix no.6.7

6.1.8. Air Cooler

Functions : to cooling the fluid or to condense the vapor


Key Performance Indicator :
Overall heat transfer coefficient (U)
Variable should be Measured :
 Electricity power (input)
 Liquid flow
 Temperature and Pressure of fluid inlet and outlet
 Composition of fluid
Spread sheet :

See Appendix no.6.8

6.1.9. Heat Exchanger

Functions : to transfer heat from high temperature to low temperature of fluid


Key Performance Indicator :
Overall heat transfer coefficient (U)
Variable should be Measured :
 Fluid flow
 Temperature inlet and outlet of hot side and cold side
 Operating Pressure of hot side and cold side
 Composition of fluid
Spread sheet :

See Appendix no.6.9


Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 106 of 109

6.2. SYSTEM
6.2.1. TSA System

Functions : to reduce heavy hydrocarbon content of feed gas


Key Performance Indicator :
 Adsorption Rate
 TSA Regeneration Rate
Variable should be Measured :
 Feed gas flow
 Temperature of feed gas
 Pressure inlet and outlet gas
 Composition of feed gas and outlet gas

Spread sheet :

See Appendices no.6.10

6.2.2. Membrane System

Functions : to reduce CO2 content of feed gas


Key Performance Indicator :
 Membrane separation rate
 HC Slipped rate
Variable should be Measured :
 mole CO2 in Permeate Gas
 Mole CO2 in Feed Gas
 mole HC in Permeate Gas
 Mole HC in Feed Gas

Spread sheet :

See Appendices no.6.11

6.2.3. Amine System

Functions : to reduce acid gas (CO2 & H2S) content of treated gas
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 107 of 109

A. Amine Contactor

Functions : to absorb acid in treated gas by amine liquid


Key Performance Indicator:
 Absorbtion Rate
Variable should be measured:
 mole-CO2 absorbed
 Mole pure lean amine
Spread sheet :

See Appendix no.6.12

B. Amine Regenerator

Functions : to desorb/strip acid in rich amine by heating


Key Performance Indicator:
 Amine Regeneration Rate
Variable should be measured:
 CO2 content in lean amine and CO2 content in acid gas flow
 Quantity of steam or fuel gas consumption
 Operating temperature and pressure of regenerator
Spread sheet :

See Appendix no.6.13

6.2.4. Dehydration System

Functions : to remove moisture in treated gas by glycol


Key Performance Indicator:
 Absorbtion Rate
 Glycol Regeneration Rate
Variable should be measured:
 Flow of gas and glycol
 water content inlet and outlet of treated gas
 water content in lean glycol
 Operating temperature and pressure of contactor
Spread sheet :
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 108 of 109

See Appendix no.6.14

6.2.5. Dew Point Control System

A. Gas Chiller

Functions : chilling treated gas


Key Performance Indicator:
 COP (heat released by fluid divide by power of compressor unit)
Variable should be measured:
 Flow of sales gas and condensate
 Composition of sales gas and condensate
 Temperature inlet and outlet of chiller
Spread sheet :
See Appendices no.6.15

B. Low Temperature Separator

Functions : to separate of sales gas and condensate.


Key Performance Indicator:
Percentage of condensate content in sales gas compared to design value
Variable should be measured:
 Flow of sales gas and condensate
 Composition of sales gas and condensate
 Operating Temperature and Pressure of separator
Spread sheet :
See Appendices no.6.16

6.2.6. Condensate Stabilizer

Functions : to remove light hydrocarbon from condensate.


Key Performance Indicator:
 Yield of Stabilization
 Stabilizer Performance
Variable should be measured:
 Flow of raw condensate
 Flow of treated condensate
Final Report ID-N-GN-00000-00000-00068
Energy Management Audit / Assessment for PSC Corridor
ConocoPhillips Indonesia Page 109 of 109

 Composition of condensate
 Flow of steam
 Operating Temperature and Pressure of column
Spread sheet :
See Appendix no.6.17

6.2.7. Depropanizer

Functions : to produce propane.


Key Performance Indicator:
 Yield of Stabilization
 Depropanizer Performance
Variable should be measured:
 Flow of feed to column
 Flow of propane product
 Electric consumption
 Operating Temperature and Pressure of column
Spreadsheet:
See Appendix no.6.18

Potrebbero piacerti anche