Sei sulla pagina 1di 6

U.S.L S.S.L S.

L Others
1
Earth work from borrowpits for making embankments
or repair to embankments/excavating irrigation canal
or drainage channel /re-excavation or silt clearance in
irrigation canal or drainage channel/Earth work in
excavation for foundation trenches in various kinds of
soil as stated below,including removing & breaking
clods,stacking the spoils, levelling,rough dressing
whereever required.
P-1
b)Ordinary soil mixed with deposition of kankar,
ghooting , morrum etc to be excavated by spade.
I-1 Total volume of earth work ( 350 x 280 x ( 8 + 7 + 6 ) / 3 ) ft 686000 cft
i)Lead upto80'-160' &Lift 8'-11.5' of 25% of total volume 171500 cft 49 cft 3500
ii)Lead upto160'-240' &Lift 8'-11.5' of 25% of total volume 171500 cft 44 cft 3898
iii)Lead upto240'-320' &Lift 8'-11.5' of 25% of total volume 171500 cft 39 cft 4397
iv)Lead upto320'-400' &Lift 8'-11.5'of 25% of total volume 171500 cft 35 cft 4900
2 Water carrier & children creche work.@50 u s l=1 u s l 16695 u s l 334
3 Engagement of super viser(as a semi skilled labour) 16695 s s l 668
4 Work site facility
i)Display board (4'x5') 2
ii)Making & shifting of temporary shed 2
iii)Making Toilet block 2
iv)First Aid box 2
v)Provision of photography 50
17029 668
Detailed Estimate for the work: "Augmentation of reserver capacity by excavation of Golamara Dam in connection with Golamarajore Irrigation Scheme.
25 u s l=1
s s l
Wage Material
Sl no Description of Items Unit
MGN
REGS
Calculation Quantity
Out put
per
person
per day
50 u s l=1
u s l
1.942517
6.475058
Sl no Description of item unit Quantity Rate(Rs) Amount(Rs) Remarks
A a) Wage cost
1)Un-Skilled Labour Nos 17029 136.00 2315953.03
B b)Material cost
1.Semi Skilled Labour Nos 668 204.00 136232.53
2)Display board (4'x5') Nos 2 2000.00 4000.00
3)Making & shifting of temporary shed Nos 2 2000.00 4000.00
4)Making Toilet block Nos 2 1500.00 3000.00
5)First Aid box Nos 2 500.00 1000.00
6)Provision of photography Nos 50 50.00 2500.00
2466686
Abstract cost for the work: "Augmentation of reserver capacity by excavation of Golamara Dam in connection with Golamarajore Irrigation Scheme.
Total rupes
Rupes twenty four lacks sixty six thousand six hundred eighty six only
1
2 Name of the Scheme :
3 Name of G.P : Golamara Block : Purulia-II No Sansad No: Golamara-6
4 Location : Mouja- Golamara , J L No-226 , Plot No:1832,1821,1612
5 Serial no in annual action plan :
6 Sector : Irrigation
7 Schdule adopted : M G N R E G S-2012,P & RD DEPTT,Govt of W.B.
8 Completion of work : Two month (2)
9 Average engagement labour per day : 300 nos
10 Source of fund : M G N R E G S
11 estimated cost : wage cost-Rupes 2315953
150733
2466686
Ratio of labour component : Material component 94 : 6
Name of P I A : Manbazar irrigation Sub-Division/PID
"Augmentation of reserver capacity by excavation of Golamara Dam
in connection with Golamarajore Irrigation Scheme."
Material cost-Rupes
TECHINAL REPORT
Total costin Rupees
REPORT
The estimate amounting to Rs-2466686.00 has been framed to meet up the
probable cost of expendtiure for the work "Augmentation of reserver capacity
by excavation of Golamara Dam in connection Golamarajore Irrigation
This scheme envisages excavation of high lands with in the reserver area and
thereby augmenting the reserver capacity in addition to the designed reserver
capacity. With impleementaion of this scheme an additional storage capacity of
1.94 Ha-M would be created 6.47 Hectars area would get irrigation supply
during rabi season . this would provide oppartunity of further development of
aggriculture in the area and there by uplift the economic level of the people
being in proverty.
This is why this estimate has been framed and taken necessary items i.e earth
work etc.have been taken from current schdule of M G N R E G S -2012.
The cost of work is chargeble to the head of M G N R E G S.
GOVERNMENT OF WEST BENGAL
Augmentation of reserver capacity by excavation of
Golamara Dam in connection with Golamarajore
Irrigation Scheme at G.P-Golamara,P.S-Purulia-II
,Dist-Purulia.
Estimated Cost:Rs-2466686.00
PROPOSED UNDER M G N R E G S -2012.

Potrebbero piacerti anche