Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PREFACE
1.0
INTRODUCTION
2.0
OBJECTIVE 6
3.0
SIMPLIFIED THEORY
4.0
EQUIPMENTS
5.0
PROCEDURE OF WORK 16
6.0
ANALYSIS 24
7.0
CONCLUSION
9.0
REFERENCES
11
40
40
1.0
INTRODUCTION.
Road curve is a one from another survey work in engineering surveying. This work
includes levelling, traversing, long section, cross section and detailing. Two types of curve in
engineering survey namely horizontal curve and vertical curve.
Horizontal curve is to continue road with different direction. the purpose of horizontal
curve is to deflect a vehicle travelling along one of the straight safely and comfortably through
the angle to enable and to continue its journey along the other straight line. In horizontal curve
is known as deflection angle and its name horizontal curve because all measurement in their
design and construction is considered in the horizontal plane.
This practical works consist of 3 main surveys works. Traversing, levelling and
tacheometry. Each result has its tolerance to be acceptable and each works has its own way to
be carried out. All the works to investigate the road curve.
2.0
OBJECTIVE.
2.1 Levelling.
Establish a Temporary Bench Mark (TBM)
Learn how to book data and calculate it from the precise levelling
instrument
To know the procedures of precise levelling
To get close with precise level
Refresh back how to determine the reduce level of the TBM by
transferring the value from the Bench Mark (BM)
2.2 Traversing.
To apply concept whole to the part in this practical.
Propose for traversing survey is for surveying detail. A traverse network
of survey line and ground marks provides control points refer the lot which
can be accurately plotted in a plan. These details can be plotted as
reference to the plotted traverse lines and stations.
To learn about law to process traverse to find lot refer cadastral
surveying.
After we finish this practical with successfully we can learnt to process
traversing data and can plot the traverse.
2.3 Detailing
Determine the reduce level and location every details.
To get view about permanent details around the survey area such as
building, drain, tree and etc.
Departure
Linear misclose =
Latitudes misclose
Adjusted latitudes
Adjusted departures =
Final coordinate
= N/S/E/W + adjusted
3.2 Levelling
Levelling is the based on the horizontal line of the instrument (level) with the level
line of the point on the earth.
The difference between two points is the heights of the point itself.
The level is an optical instrument that provides a height reference. This reference
is a horizontal plane through the axis of the telescope; know as the Height of
Collimation. Once the height of collimation (or instrument height) has been
measured, the height of other station can be found by measuring from this plane
with a staff. The height of collimation is found by taking a back sight to a staff
place on a bench mark. The staff reading is added to the bench mark value to
obtain the height of collimation. Once the height of collimation has been found,
ground height at any spot below this plane can be found by observing the staff
and subtracting the staff reading from the height of collimation. The test that we
undertake in order to determine the amount of error and then eliminate it from our
measurement is known as the two peg test. If the level is in perfect adjustment
(Hb Ha) = (Hd Hc). However, it usual that there is a difference between the
true and appearance heights and since this has been measured over a distance
of L m the collimation error for the level is given by:-
If the collimation error is found to be less that about 0.001m, the level is
assumed to be in adjustment. If the collimation error is found to be greater than
about 0.001m, the level has to be adjusted
3.3 Tacheometry.
All total station will measure a slope distance, zenith angle recorded by the
theodolite along the line of sight to calculate the horizontal distance.
RLt = RLi + Hi + V T
V = L Sin
ii.
Accuracy of Tacheometry
The overall accuracy expected for distance measurement is 1 in 500.
The best possible accuracy is only 1 in 1000.
for long section the origin of the graph is at the left-hand side with levels
being plotted vertically and chainages horizontally
for cross section the point where the center line meet the cross section
is taken as the origin
distances from center line to points where the levels were taken are
plotted horizontally to the left and right of the origin with the levels being
plotted vertically
scales Hz=exaggerated
Vt= exaggerated
Transition curve is one type of the Horizontal curve that have varying
radius.
DIAGRAM 4.1
4.0 EQUIPMENTS.
1) Total station
Display data for tacheometric such as distance and bearing.
Picture:
2) Tripod.
Fix and make temporary adjustment for level instrument, total station and prism.
Picture:
3) Prism
Used for reflect the electromagnetic wave from EDM to get distance reading.
Picture:
4) Tape
Measured height instrument, height target and prism pole
Picture:
5) Mini prism
Reflecting the EDM waves to get a slope distance to details.
Picture:
6) Mini pole.
Fixed a mini prism and located to details, long section and cross section.
picture:
10
7) Level Instrument
Observe a staff reading along collimation line.
Picture :
8) Staff
Measured a height from ground level to coolimation line.
Picture :
11
9) Staff Bubble
Make sure the staff in upright condition while observation.
Picture :
12
Levelling
II.
Traverse
III.
Solar Observation
IV.
Tacheometry
I. Levelling.
1) Establish three points on the ground surface along the road curve.
2) Mark two points as point B and C and between the two points mark one point as
A. (DIAGRAM 5.2)
3) The distance from point A-B and point A-C is 50 meters and above. Make point A
as the Temporary Bench Mark (TBM) for the point B and C by Fly Levelling from
the bench mark to the point A.
4) The level instrument is set up, read the levelling staff at point A as a TBM which it
is the back sight and its reduce level is known.
5) Turn the level instrument to take front sight staff reading at point B (CP1).
6) Moved the instrument forward and make a temporary adjustment.
7) Take the reading from staff at point B as a back sight for new instrument position.
8) Take the staff reading point C as a front sight.
9) Transfer the instrument forward and take back sight and front sight reading until
close to another known reduce level point such as TBM, SBM or BM.
13
10) After finished finding the reduce level for the three points, all the traverse stations
or points must be measure to get the reduce level for each station, the method is
still the same.
DIAGRAM 5.1
C
> 50 m
B
> 50 m
Road Curve
14
DIAGRAM 5.2
II. Traversing.
1) First, set the instrument on station 1 and do the temporary adjustments.
2) A prism is placed into the tribrach and clamped in positions.
3) Using the certified plan the datum can be determined, it is shot from station 2 to 1
for the forward bearing and all the data that had been taken is in bearing.
4) After that, set up a total station and start work from station 2 to station 1 these
stations become as the back bearing. Station 2 to 3 became as forward bearing.
5) At the station 2 hold the value that get from the last observation, after that, release
hold and take a reading then write in a form both result, face left and face right.
6) This method continued the same for each station until the traverse close .
From the
total station is set
station
2
and
located the prism.
become as back
stations
2-3
bearing.
diagram 1.3, a
at the station 2 and
station
3
also
Stations
2-1
bearing
and
become as forward
15
DIAGRAM 5.3
16
SUN
THEODOLITE
TRIPOD
GROUND
DIAGRAM 5.4
17
DIAGRAM 5.5
DIAGRAM 5.6
IV. Tacheometry.
1) Produce the traverse at survey site and determine the coordinate of all traverse
stations.
18
2) Applied the reduce level (RL) at every traverse stations with fly levelling survey.
3) Make a temporary adjustment for total station at station 1 which the RL and
coordinate is known.
4) Measured the height of total station (hi) and mini prism pole (hp).
5) Set horizontal bearing to the RO station.
6) Located mini prism at details around the observed station.
7) Open the bearing to the mini prism.
8) Record the horizontal bearing, vertical angle, slope distance and the mini prism
height at every detail taken.
9) After all details was taken, transfer the total station to another station and
measured the instrument height.
10) Record all data for all details taken at every stations traverse until all details in
survey area are recorded.
11) Besides detailing, there are Cross Sections and Longitudinal Sections.
12) For the long sect. there are 5 chainages for each sides B-C and B-A.
13) The distances between the chainages at least 10 meters.
14) The chainages must be straight on the line between the 3 points.
15) And for the cross sect. each long sect. will have at least 5 chainages to the right
and to the left. The ten chainages on the straight line must be 90 degree from the
long. Sect.
16) Cross sect. crossing the long sect in the both side.
19
DIAGRAM 5.7
CH 01
CH 02
CH 03
CH 04
CH 05
DIAGRAM 5.8
2
20
DIAGRAM 5.9
Back
Sight
Intermediat
e sight
Fore
sight
Rise
Fall
1.781
Reduce
Level
15.811
Distance
Remarks
2.210
0.315
1.466
17.277
BM(15.81
1)
c.p
1.915
0.725
1.485
18.172
c.p
1.130
2.950
17.727
c.p
2.390
0.484
0.646
18.373
c.p
1.075
1.091
1.299
19.672
c.p
0.656
0.825
0.250
19.922
Stn 5
1.035
1.100
0.444
19.478
c.p
0.664
2.410
1.375
18.103
c.p
3.010
1.079
0.415
17.688
c.p
0.532
1.899
18.799
c.p
0.951
2.501
1.969
16.830
c.p
1.256
1.995
1.044
15.786
c.p
15.791
BM(15.81
1)
18.605
1.035
1.111
1.251
0.005
(18.625)
6.262
(6.282)
15.791
(18.625)
(6.282)
15.811
-0.02
-0.02
-0.02
BM
= 15.811
22
Observed value
= 15.791
Misclosure
= Observed value - BM
= 15.791 15.811
= -0.02m (20mm)
13
Allowable Misclosure, E
12mmn
1213
43.267mm (0.043267)
23
Back
Sight
Intermediat
e sight
Fore
sight
1.781
Reduce
Level
+/- e
(adj)
Adj
Reduced
level
15.811
Remarks
BM(15.811)
2.210
0.315
17.277
0.0015
17.279
c.p
1.915
0.725
18.172
0.003
18.175
c.p
1.130
2.950
17.727
0.005
17.732
c.p
2.390
0.484
18.373
0.006
18.379
c.p
1.075
1.091
19.672
0.008
19.680
c.p
0.656
0.825
19.922
0.009
19.931
Stn 5
1.035
1.100
19.478
0.011
19.489
c.p
0.664
2.410
18.103
0.012
18.115
c.p
3.010
1.079
17.688
0.014
17.702
c.p
0.532
1.899
18.799
0.015
18.814
c.p
0.951
2.501
16.830
0.017
16.847
c.p
1.256
1.995
15.786
0.018
15.804
c.p
1.251
15.791
0.02
15.811
BM(15.811)
Correction = misclose
N
= -0.02
13
= -0.0015
+ e (adj) when initial RL of the last reading < BM @ TBM value.
e (adj) when initial RL of the last reading > BM @ TBM value.
The adjustment of reduce level (RL) we can get when we () with the reduce level (RL).
24
6.1.2 RL Station 4.
Back
sight
Intermediate
Sight
Fore
Sight
Rise
Fall
2.088
0.610
0.593
2.698
(2.693)
(2.693)
1.495
21.426
Stn 4
1.490
19.936
Stn 5(19.931)
(1.490
)
19.936
19.931
0.005
= 19.931
Observed value
= 19.936
Misclosure
= Observed value - BM
= 19.936 19.931
= 0.005m (5mm)
remarks
Stn 5(19.931)
(1.490
)
0.005
0.005
distanc
e
19.931
1.495
2.100
Reduced
Level
Allowable Misclosure, E
12mmn
122
16mm (0.016m)
25
Back
sight
Intermediate
Sight
Fore
sight
2.088
Reduced
level
+/- e
(adj)
Adj
Reduce
d level
19.931
0.610
Correction = misclose
remarks
Stn 5(19.931)
0.593
21.426
-0.0025
21.424
Stn 4
2.100
19.936
-0.005
19.931
Stn 5(19.931)
N
= 0.005
2
= 0.0025
+ e (adj) when initial RL of the last reading < BM @ TBM value.
e (adj) when initial RL of the last reading > BM @ TBM value.
The adjustment of reduce level (RL) we can get when we () with the reduce level (RL).
26
6.1.3 RL Station 3.
Back
Sight
Intermediat
e sight
Fore
sight
Rise
Fall
Reduce
Level
2.109
Distanc
e
Remarks
21.424
Stn 4(21.424)
2.150
0.474
1.635
23.059
Cp
0.454
0.483
1.667
24.726
Stn 3
0.595
2.121
1.667
23.059
Cp
2.223
1.628
21.431
Stn 4(21.424)
(3.295)
21.431
5.308
(5.301)
3.302
(5.301)
(3.295)
(21.424)
0.007
0.007
0.007
Point 2/stn3
= 21.424
Observed value
= 21.431
Misclosure
= Observed value - BM
27
= 21.431 21.424
= 0.007m (7mm)
Based on number of instrument positions
No. of instrument position, n =
Allowable Misclosure, E
12mmn
124
24mm (0.024m)
Intermediat
e sight
Fore
sight
2.109
Reduce
Level
+/- e (adj)
Adj
reduced
level
21.424
Remarks
Stn 4(21.424)
2.150
0.474
23.059
-0.0018
23.057
Cp
0.454
0.483
24.726
-0.0036
24.722
Stn 3
0.595
2.121
23.059
-0.0054
23.054
Cp
2.223
21.431
-0.007
21.424
Stn 4(21.424)
Correction = misclose
N
= 0.007
4
= -0.0018
+ e (adj) when initial RL of the last reading < BM @ TBM value.
e (adj) when initial RL of the last reading > BM @ TBM value.
The adjustment of reduce level (RL) we can get when we () with the reduce level (RL).
28
Intermediat
e sight
Fore
sight
Rise
Fall
1.734
Reduce
Level
Distanc
e
Remarks
19.931
Stn 5(19.931)
2.091
1.420
0.314
20.245
Stn 6
1.970
1.135
0.956
21.201
Stn 7
1.775
0.141
1.829
23.030
Cp
2.048
0.933
0.842
23.872
Cp
0.862
0.308
1.740
25.612
Stn 8
0.285
1.755
0.893
24.719
Stn 3
1.614
1.315
1.030
23.689
Stn 2
0.339
0.505
24.798
Stn1
0.526
2.168
1.829
22.969
Cp
2.063
1.537
21.432
Stn 4(21.424)
5.289
21.423
13.244
11.743
1.109
6.790
(11.743)
(5.289)
(19.922)
1.501
1.501
1.501
29
Stn 4
= 21.417
Observed value
= 21.423
Misclosure
= Observed value - BM
= 21.423 21.417
= 0.006m (6mm)
10
Allowable Misclosure, E
12mmn
1210
37mm (0.037m)
30
Intermediat
e sight
Fore
sight
1.734
Reduce
Level
+/- e (adj)
Adj
reduced
level
19.922
Remarks
Stn 5(19.922)
2.091
1.420
20.236
-0.0006
20.235
Stn 6
1.970
1.135
21.192
-0.00067
21.091
Stn 7
1.775
0.141
23.021
-0.00075
23.020
Cp
2.048
0.933
23.863
-0.00085
23.862
Cp
0.862
0.308
25.603
-0.001
25.602
Stn 8
0.285
1.755
24.710
-0.0012
24.709
Stn 3
1.614
1.315
23.680
-0.0015
23.679
Stn 2
0.339
0.505
24.789
-0.002
24.787
Stn1
0.526
2.168
22.960
-0.003
22.957
Cp
2.063
21.423
-0.006
21.417
Stn 4(21.417)
Correction = misclose
N
= 0.006
10
31
= 0.0006m
+ e (adj) when initial RL of the last reading < BM @ TBM value.
e (adj) when initial RL of the last reading > BM @ TBM value.
The adjustment of reduce level (RL) we can get when we () with the reduce level (RL).
6.2 TRAVERSE
Bearing / Angle
Station
From
Line
To
Final Bearing
Station
Face Left
Face Right
Average
Station
Datum drpd
PA
160 04 15
Garisan
2-1
160 04 15
340 04 15
48 00 43
Finale
Distance
47 56 30
29.480
247 5 30
53.574
54.748
C - 1
2
3
48 00 40
228 00 45
M 45
228 00 45
48 00 45
247 9 43
C 2
3
4
279 09 40
67 09 45
M 45
67 09 45
247 09 45
195 40 43
195 36 20
C 3
Azimuth dgn
M 45
Matahari
4
5
195 40 40
15 40 45
32
15 40 45
195 40 45
341 27 10
341 12 46
34.130
C 4
5
6
341 27 10
161 27 10
M 45
Bearing / Angle
Station
5
Face Left
Face Right
Average
161 27 10
341 27 10
28 41 00
From
Station
Line
Final Bearing
To
Station
Final Distance
28 36 30
45.110
79 45 00
64.045
198 57 20
63.073
339 59 40
32.129
C 5
6
7
28 40 55
208 41 05
M 45
208 41 00
28 41 00
79 49 28
C 6
7
8
79 49 30
259 49 25
M 45
259 49 28
79 49 28
199 02 00
C 7
8
1
199 02 00
19 02 00
M 45
19 02 00
199 02 00
340 04 23
C 8
1
2
340 04 20
160 04 25
M 45
Garisan 1-2
dibaca
340 04 23
Sepatut
dibaca
340 04 15
33
Tikaian
Pembetula
n
-8
Dalam 8
Stesen melalui
-1 bagi
Setiap
stesen
stesen
1,2,3,4,5,6,7,8&1
Bearing
Distance
Latit
Depart
Adj.
Latit
Adj.
Depart
N/S
E/W
53483.726
-39939.592
47 56 40
29.480
19.747
21.889
19.748
21.886
53503.472
-39917.700
247 05 40
53.574
-20.852
-49.350
-20.850
-49.356
53482.618
-39967.044
195 36 40
54.748
-52.728
-14.733
-52.736
-14.739
53429.887
-39981.771
341 13 00
34.130
32.312
-10.990
32.313
-10.994
53462.198
-39992.757
28 36 50
45.110
39.601
21.603
39.603
21.598
53501.797
-39971.148
79 45 10
64.045
11.393
63.023
11.396
63.016
53513.188
-39908.118
198 57 50
63.073
-59.650
-20.497
-59.647
-20.504
53453.535
-39928.608
340 00 10
32.129
30.192
-10.987
30.193
-10.990
53483.726
-39939.592
Linear Misclose = 1 :
= 1 :
34
= 1 : 8437.312
The traverses linear Misclose is over the tolerance, 1:8000. So the traverse
is acceptable.
6.3 TACHEOMETRY.
7.3.1 Detailing, Cross Section & Longitudinal Section Result.
See in Appendix 2.
See in Appendix 2.
35
7. CONCLUSION.
All the data that had been received was processed to get the shape, the height
and the position of the curves on the plan. To get the best result, its mean to do well in
levelling, detailing, traversing, solar observation, longitudinal and cross sectioning. This practical
just like tacheometry, varieties elements are needed to build a plan of the road curvatures. The
plan is consists of every characteristics of the curves, the coordinates, and the reduce level. The
output of the project is like a certified plan, the plan that shows the roads curvature. All the data,
levelling and traversing is acceptable under and over the tolerances. A lot of things we had
learned in this practical form the beginning until the end.
36
9. REFERENCES.
37
APPENDIX A
DIARY OF WORK
38
Date
20th January 2009
(Tuesday)
Events
Remarks
In front UPELS &
T-junction to the
Sports Complex.
T-junction to the
Sports Complex.
T-junction to the
Sports Complex.
Padang Rani
T-junction to the
Sports Complex.
Padang Rani
T-junction to the
Sports Complex.
T-junction to the
Sports Complex.
Traversing
T-junction to the
Sports Complex.
Solar Observation
T-junction to the
Sports Complex.
2nd Traversing
T-junction to the
Sports Complex.
Solar Observation
For detailing and Cross Section and Longitudinal Section we did in the weekend.
39
40
APPENDIX B
COMP. SHEET
41