Contractor is responsible for Moderiate ensuring they have adequate resources available
Contractor
Low
Make sure Staff have adequate training and experience to work on the project
Contractor
Moderate
Ensure all approval and decision processes are worked out prior to project commencement
Contractor
Low
Ensure air pollution is kept to a minimal by insuring correct meters are installed
Contractor
Contamination of water
16
High
Contractor
Unidentified services
12
High
Contractor
12
High
Contractor
Low
Contractor
Moderate
Contractor
Moderate
Contractor
Moderate
Contractor
12
High
Supplier/ Contractor
Moderate
KMCF
Low
The consulting engineer is responsible for ensuring that an adequate design is completed
KMCF
Hydraulic features
16
High
KMCF
Moderate
KMCF
External Risks
Low
Roscommon Co Co
External Risks
15
High
Agree a necessary completion date for the project with Contractor Roscommon Co. Co. and schedule accordingly
External Risks
Moderate
Contractor
Public objections
External Risks
Moderate
Ensure all concerns are satisfied prior to submission for planning applications
Contractor
Permits delay
External Risks
15
High
Make sure all permits are in order before commencing the project
Contractor
Low
Contractor
Moderate
Make sure all relevant parties Contractor are on board before commencing of the project
Low
Contractor
Low
Contractor
Key Terms
Risk: The risk stated in a complete sentence which states the cause of the risk, the risk, and the effect that the risk causes to the project.
Risk Category: Categorization of risks by area of project affected, source of risk or other useful category. Probability: The likelihood that a risk or opportunity will occur (on a scale from 0 to 5 with 5 being the highest). Impact: The impact of the risk on the project if the risk occurs (scale from 0 to 5 with 5 being the highest). Risk Score: Determined by multiplying probability and impact (scale from 0 to 100). Risk Ranking: A priority list which is determined by the relative ranking of the risks (by their scores) within the project. Risk Response: The action which is to be taken if this risk occurs. Risk Owner: The person who the project manager assigns to watch for triggers, and manage the risk response if the risk occurs.