Sei sulla pagina 1di 29

All rights reserved.

Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

Rev. A

HR9002-001

HR9002-001

Energy System User Manual

48V/5.8kW/2.9kW Energy System

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

Contents
Chapter 1 Introduction 1.1 1.2 1.3 System Introduction System Key Features Main Applications 1-1 1-2 1-2

Chapter 2 Overview of the System 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 2.9 2.10 System Architecture Electrical Specification Environmental Specification Safety Specification Mechanical Specification System Internal Layout System Major Component List System Alarm System Protection Battery Management 2-1 2-2 2-3 2-3 2-3 2-4 2-5 2-5 2-6 2-6

Chapter 3 Installation 3.1 3.2 3.3 3.4 Transporting System Unpacking General Installation Guide Connection of Cables 3.4.1 Cable Entry Into System 3.4.2 Connection of AC Input and Ground Cables 3.4.3 Connection of Load Cables 3.4.4 Connection of Battery Cables 3.4.5 Connection of Signal Cables 3.4.6 Temperature Sensors Connection Local and remote control and monitoring 3.4.7 communication link Rectifier Installation Final Installation Check System Power Up Procedure 3-1 3-1 3-2 3-3 3-3 3-3 3-4 3-4 3-5 3-5 3-6 3-7 3-8 3-8

3.5 3.6 3.7

Chapter 4 Maintenance & Fault Tracing 4.1 4.2 4.3 4.4 Maintenance Recommended Spare Parts List Fault Tracing Replacing The Rectifier Procedure 4-1 4-1 4-1 4-3

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

Chapter 5 Important Notices 5.1 General Guidelines 5.1.1 Installation 5.1.2 System Operation 5.1.3 Environmental and Airflow Considerations 5.1.4 Maintenance and Repair Warranty Constraints 5-1 5-1 5-1 5-1 5-1 5-2

5.2 Appendix 1. 2.

Conductor Size Requirement for DC Applications Maintenance Record

A-1 A-2

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

1.
1.1

Introduction
System Introduction

The rectifier system is specially designed for the -48V telecommunication power applications. By incorporating state-of-the-art switched mode rectifier and advanced microprocessor technology, the system is able to perform efficient AC to DC power conversion and at the same time, carry out intelligent monitoring and control functions. The system can be divided into 4 major functional blocks. They are the 1. Control and Supervisory Module 6 (CSM6) (Refer to Fig. 1.1 for the CSM block diagram) 2. AC Power Distribution Unit (AC PDU), 3. Rectifier Modules 4. DC Power Distribution Unit (DC PDU).

Control & Supervisory Module (CSM 6)

AC Power

ACPDU

Rectifiers

DCPDU

Load

Power path Signal path

Battery

Fig. 1.1 CPS Block Diagram The Control and Supervisory Module 6 (CSM6) consists of the CSM6-1 and CSM6-2. The CSM6 is the central supervisory unit, which monitors and controls the operating parameters of the entire system. The CSM6-1 is equipped with LCD panel and soft keypads which serve as a user-friendly interface to monitor or program various system parameters and the CSM6-2 is the Data collector which collects and processes system data before passes to CSM6-1 for display. The CSM6 supports Local and Remote Monitoring & Control functions, for local monitoring & Control, the link between the system and the PC is made through the RS-232. However for the Remote Control and Monitoring, it can be achieved through Public Switch Telephone Network (PSTN) and Ethernet(TCP/IP). The CSM6 also has the battery management function which ensures proper charging of batteries so as to maximize energy storage and to prolong the life of batteries.

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

1-1

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

The AC PDU distributes AC power to the rectifiers and other portions of the system. A single pole MCB (Miniature Circuit Breaker) is available within the AC PDU to isolate the system from the mains. The AC PDU is also installed with an array of Surge Protection Device which protect the system against line surge. The rectifier modules carry out AC to DC power conversion in the system. Each rectifier is able to deliver a rated output power of 2900W at a nominal output voltage of -54V. Therefore, when the system is expanded to its fullest capacity of two rectifiers, it is capable of delivering a maximum power of 5800W to external loads and batteries. The rectifiers are modular in design, hot-swappable and exhibit excellent current share performance when operated in parallel configuration. The system is hence flexibly configurable to meet different power consumption requirements and to achieve N+1 redundancy. Control of rectifiers can be carried out in a centralized manner on the CSM6. In addition, the operating conditions of individual rectifier can also be easily monitored on the CSM6. The DC PDU distributes DC power from the rectifiers to external loads and batteries. Within the DC PDU, there are MCBs protected distribution ways to be connected to external loads. The DC PDU also incorporates two battery connections, which are equipped with two MCBs for protection purposes. The battery connections allow the system to have power backup capability in the event of an AC failure.

1.2

System Key Features


Wide input voltage range High power factor and efficiency Modular rectifier design with current share and hot-swappable capability Swift and convenient rectifier installation Microprocessor based intelligent monitoring and control Equipped with user friendly LCD and keypad interface Support remote monitoring and control Intelligent battery management system Comprehensive fault protection and detection schemes Low noise and electromagnetic interference level Efficient forced air cooling ensures low component thermal stress Front access air filter leading to easy maintenance

1.3

Main Applications
PBX, PABX station GSM station CDMA, TDMA, AMPS station Microwave communication station Railway switching control station Other -48V telecommunication systems

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

1-2

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

AC INPUT T.B.

DC(-) OUTPUT T.B.

B2-

B1-

L4-

L3-

L2-

L1-

AC INPUT DC(-) OUTPUT

AC Fail NO COM NC

Common Alarm NO COM NC NC

DC(+) OUTPUT B2+ B1+ L4+ L3+ L2+ L1+

NO COM

NC

NO COM

LV Alarm

LVDS Alarm

Alarm dry contact T.B.

DC(+) OUTPUT T.B.

BACK VIEW
441.0

3D VIEW (Without Top Cover)


100A LVDS 100A SHUNT

150.0

SIDE VIEW

16.0

400.0

TOP VIEW

TOP VIEW (Without Top Cover)

3D VIEW

AC MCB

SPD

DC MCB

Batt. MCB RJ45 Port

AC MCB

SPD L1

LOAD MCB L2 L3 L4

BATT. MCB B1 B2 TCP/IP

MBS

CSM Power

2900W SMR 2EA 465.0 482.6 CSM6

FRONT VIEW

Fig. 1.2 Power system outline

Rev. A

HR9002-001

132.6

57.2

48V/5.8kW/2.9kW Energy System

1-3

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

2.
2.1

Overview of the System


System Architecture

The ACPDU is fed by AC cables which are terminated at the AC input terminal block. Within the ACPDU, there is a single pole 40A MCB, which serve as the mains isolator, and a two pole 20KA Surge Protection Device (SPD) module, which provide protection against incoming line surge. The DC PDU distributes DC power from the rectifiers to external distributed loads and batteries. A positive and a negative busbar carries DC power from the rectifiers to the DC PDU. DC power is then distributed to the load MCBs. The MCB provides output overload protection and serves as a switch to isolate a load from the system when necessary. There are also two battery connections within the DC PDU which is equipped with two 50A MCBs and one 100A LVDS. The MCBs and LVDS provide protection against overload and over discharge of batteries. In the event of an AC failure, energy from the batteries will flow through the DC PDU to the external distributed loads. Hence, the loads will not experience power interruption. The energy system has two rectifier compartments. Rectifier installation is swift, straightforward and does not require further connection of cables. Since the LPR rectifier is modular and hot-swappable in design, different number of rectifiers can be installed onto the system to meet varying power consumption requirements. This allows incremental system expansion to be realized easily. Maintenance work can also conveniently carried out as any rectifier can be removed and replaced without interrupting system operation.

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

2-1

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

2.2

Electrical Specification

Table 2.1 Electrical Specification


System model Rectifier Model AC input Nominal voltage Operating voltage range (full output power) Operating voltage range (derated output power) Frequency Rated current (220Vac input; 54Vdc, 100% load) Maximum current (176Vac input; 54Vdc, 100% load) Efficiency (220Vac input; 54Vdc, 100% load) Power factor (220Vac input; 54Vdc, 100% load) DC output Nominal voltage Float voltage adjustable range Equalize voltage adjustable range Nominal Power (100% load) Soft start time Line regulation (176 ~ 286Vac input) Load regulation (0% ~ 100% load) Current share (50% ~ 100% load) Audible noise Psophometric noise Load MCB Battery MCB 54Vdc 40 ~ 60Vdc 40 ~ 60Vdc 5.8kW > 3s < 0.1% < 0.5% 3% deviation from mean current 55dBA (1 meter) < 2mV 20A x 2; 40A x 2 50A x 2 220Vac single phase 176Vac ~ 286Vac 90Vac ~ 176Vac; 286Vac ~ 300Vac 45 ~ 65Hz 29A 37A >91% >0.99 HR9002-001 OT7014

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

2-2

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

2.3

Environmental Specification
Operating temperature : -20C +70C (ideal operating temperature : 25C) Storage temperature : -40C +80C Relative humidity : 10%RH 90%RH (non-condensing) Altitude : < 3000 meter Illumination requirement : 750LX (even illumination)

Note : The operating environment must not contain corrosive and inflammable gas. Good ventilation and air-conditioning is highly recommended.

2.4 Safety Specification


Designed to meet UL1950, EN60950 requirements Hi-pot : Input to output 1500Vac, 50Hz for 1 minute Input to chassis (FG) 1500Vac, 50Hz for 1 minute Output to chassis (FG) 500Vac, 50Hz for 1 minute Earth continuity : Safety earth to chassis (FG) 25A for 1 minute (Earth resistance < 0.1)

2.5 Mechanical Specification


System dimensions (Shelf): 482.6mm x 441.0mm x 132.6mm (WxDxH) Weight : 11.2kg (excluding rectifiers and batteries) Each rectifier weights: 4.2kg

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

2-3

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

2.6

System Internal Layout


8

11

TOP VIEW (Without Top Cover)

3D VIEW

54
AC MCB SPD L1

6 7
LOAD MCB L2 L3 L4 BATT. MCB B1 B2 TCP/IP

10

B2-

B1-

L4-

L3-

L2-

L1-

AC INPUT DC(-) OUTPUT

AC Fail NO COM NC

Common Alarm NO COM NC NC

DC(+) OUTPUT B2+ B1+ L4+ L3+ L2+ L1+

NO COM

NC

NO COM

MBS

LV Alarm

LVDS Alarm

CSM Power

1
FRONT VIEW

9
BACK VIEW

Fig. 2.1 System Internal Layout

CSM6

Fig. 2.2 Outline Drawing of CSM6-1

CS M6

Fig. 2.3 Outline Drawing of CSM6-2

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

2-4

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

2.7

System Major Component List


Component Rectifier CSM6-1 CSM6-2 SPD AC MCB Specifications Rectifier 48V/2900W
CSM6-1 CARD DISPLAY UNIT FOR CSM6 CSM6-2 CARD CONTROL UNIT FOR CSM6

Item 1 2 3 4 5

Qty 2 1 1 1 1 2 2 2 1 1 1 2

SURGE ARRESTERS 275V 20KA 2P

AC Input MCB 40A/1P MCB 20A 1P

Load MCB MCB 40A 1P

7 8 9 10 11

Battery MCB LVDS Dry contact TB AC input terminal block Shunt

Battery MCB 50A/1P 100A LVDS Alarm Terminal Block/12P AC I/P TB 40A/1P Shunt 100A

2.8

System Alarm

The system is equipped with various fault detection schemes and alarms to keep users informed in the event of fault conditions. When a fault occurs, the buzzer will sound and the LCD panel on the CSM6 will clearly indicate the nature of the fault. Some main fault conditions which activate alarms include AC input or DC output abnormal, rectifier fail, system temperature high, MCB tripped etc. Display of fault messages on the LCD panel is explained in the CSM6 User Manual. The system is also equipped with four voltage free relay contacts (dry contacts) to keep remote users informed when a fault occurs. The relay contacts will respond to normal and fault conditions as indicated in the table below: Operating Conditions Normal condition Fault condition COM, NO contacts Opened Shorted COM, NC contacts Shorted Opened

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

2-5

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

2.9

System Protection

The system is equipped with various protection schemes to ensure no damage occurs in the event of abnormal conditions. Some of the main protection schemes are explained below : Overcurrent protection (OCP) : At the AC input, the system is protected against overcurrent by a MCB. The load MCBs at the DC PDU protect the system against overcurrent drawn by external distributed loads. The battery MCBs prevents overload of the battery bank. Overcurrent limit of rectifiers can be programmed in a centralized manner on the CSM6. Rectifier overload current will not exceed the preset limit. Overvoltage protection (OVP) : When the AC input exceeds 308Vac, the rectifiers will cease to operate to prevent component damage caused by overvoltage stress. The rectifiers will resume normal operation upon removal of abnormal condition. Output OVP will be activated when the system output voltage cannot be regulated and exceeds 60V 0.5V. Rectifiers at fault will be forced to shutdown. Manual reset is required to restart a rectifier which has been shutdown due to output OVP fault. Over temperature protection (OTP) : The system over temperature alarm will be activated when the ambient temperature in the system raises above a preset level. The default preset level is 40C. In addition, when the rectifier heatsink temperature raises above a default preset level of 90C, the rectifier fault alarm will be activated. If the heatsink temperature raises further and reaches 100C, the rectifier will be forced to shutdown. The rectifier will resume normal operation when the heatsink temperature reduces below 75C. Surge protection : At the AC input, the system is protected against line surge by an array of 20KA/275Vac SPD module.

2.10

Battery Management

The CSM6 carries out battery management functions according to the user preset parameter values. Details on the battery management parameters can be found in the CSM6 User Manual. In the event of an AC failure, the CSM6 will calculate the discharge Ampere-Hour (AH) of the batteries. When AC recovers, the batteries will be recharged automatically in equalize mode according to the preset charging coefficient (CC) or automatic charging time (ACT). One critical aspect of battery management is temperature compensation. The IC LM335 converts the battery temperature sensed into a current signal. The signal is then processed by the CSM6-2. Based on the temperature information obtained, the CSM6 will adjust the output voltage of the rectifiers accordingly. The desired temperature compensation characteristic can be obtained by changing the temperature reference point (TBP), temperature rise rate (TS) and voltage decrease rate (VS) settings. Low Voltage Disconnect (LVD) Protection : The Load LVDS is to disconnect load, The disconnect and reconnect voltages are preset at 43.0V and 50V respectively.

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

2-6

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

3.
3.1

Installation
Transporting

During shipment, the power shelves and rectifier modules are packed separate in cartons. Then, they are packed and shipped on separate pallets. The pallets are heavy and large in sizes. Hence, suitable transporting machines will be needed for transporting. Plan in advance on the transport route and the location to unpack and to assemble the system.

3.2
3.2.1

System Unpacking
Before dismantling the packing, inspect for damages, shape distortion or any trace of moisture on the package. Pictures should be taken and lodge a report immediately if any abnormal condition is observed. To unpack the system, please refer to Fig. 3.1. Step 1, 2 and 3. Upon completion on the unpack process, inspect the contents to ensure that no transit damage has occurred and check the completion of the contents

3.2.2 3.2.3

Step 1

Step 2

Step 3

Fig. 3.1 Unpacking

3.2.4

System Packing List Compare the contents in the crates with the attached packing list. Contact our sales representatives if there is any shortage or damaged item.
Package No. Part Description Power Shelve Qty (pcs) Crate Dimension (mm x mm x mm)
W545*H215*D510

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

3-1

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

3.3

General Installation Guide

3.3.1 Installation and Safety Guidelines System installation and wiring must only be carried out by qualified electrician. The floor loading capacity must be checked to ensure the floor can withstand the system weight (>20.0kg, including the rectifier modules). The floor must be flat so that the cabinets can be positioned firmly. AC mains must be switched off when connecting and examining system wiring. It must be ensured that there is no short circuit at the DC PDU, battery and distributed load terminals. During installation, check the polarity of batteries before connecting the battery cables. The batteries can be isolated from the system by switching off the battery breakers. 3.3.2 Foundation Bolt Positions of 19in open rack.

Unit : mm Fig. 3.2 Foundation Bolt Positions of 19in open rack

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

3-2

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

3.4

Connection of Cables

3.4.1 Cable Entry Into System Incoming AC cables, remote signal (dry contact) cables and outgoing DC cables are to be terminated at the terminal blocks. Please refer to the Fig.3.3 for the cable connections of the power shelve.

B2-

B1-

L4-

L3-

L2-

L1-

AC INPUT DC(-) OUTPUT DC(+) OUTPUT B2+ B1+ L4+ L3+ L2+ L1+

AC Fail NO COM NC

Common Alarm NO COM NC NO COM NC LVDS Alarm

NO COM NC LV Alarm

2
BACK VIEW
Fig. 3.3 Cables Connections

1 2 3 4

AC Input cables to the AC terminal block 40A/3P. Load(+) and battery(+) cables to the DC(+) output terminal block. Dry contact cables to the dry contact terminal block 10A/12P. Load(-) and battery(-) cables to the DC(-) output terminal block.

3.4.2 Connection of AC Input and Ground Cables For single phase input, incoming AC cables are to be terminated at the AC input terminal block., which is as shown in Fig. 3.5 below: -

B2-

B1-

L4-

L3-

L2-

L1-

AC INPUT DC(-) OUTPUT DC(+) OUTPUT B2+ B1+ L4+ L3+ L2+ L1+

AC Fail NO COM NC

Common Alarm NO COM NC NO COM NC LVDS Alarm

NO COM NC LV Alarm

L G N

Fig. 3.4 AC input terminal block connection for single phase system

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

3-3

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

3.4.3 Connection of Load Cables Incoming Load cables are to be connected to the DC output terminal block. Positive load cables are to be terminated at the common (+) and negative load cables are to be terminated at the load (-) DC output terminal blocks, The connection of Load cables as shown in Fig. 3.6 respectively below: -

L1L4- L3- L2-

B2-

B1-

L4-

L3-

L2-

L1-

AC INPUT DC(-) OUTPUT

AC Fail NO COM NC

Common Alarm NO COM NC NO COM NC LVDS Alarm

DC(+) OUTPUT B2+ B1+ L4+ L3+ L2+ L1+

NO COM NC LV Alarm

L1+ L4+ L3+ L2+

Fig. 3.6 Connection for load cables

3.4.4 Connection of Battery Cables Positive battery cables are to be connected to the battery (+) terminal block and negative battery cables are to be connected to the battery (-) terminal block. The connection of battery cables is as shown in Fig. 3.7 below: -

B2- B1-

B2-

B1-

L4-

L3-

L2-

L1-

AC INPUT DC(-) OUTPUT DC(+) OUTPUT B2+ B1+ L4+ L3+ L2+ L1+

AC Fail NO COM NC NO COM

Common Alarm NO COM NC NO COM NC LVDS Alarm

NC

LV Alarm

B2+ B1+

Fig. 3.7 Connection for battery cables

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

3-4

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

Caution:
Please switch off the battery MCBs before connecting the battery cable. Please confirm whether the polarity of incoming battery cables connected to the MCBs right or not before this system works.

3.4.5 Connection of Signal Cables Cables of warning signals are to be terminated at the upper terminals of the voltage free relay contact terminal block. There are three contact points for each signal namely the NO, COM and NC. The four dry contact warning signals are arranged in the order of Battery LV Alarm, Common Alarm, AC Fail Alarm and LVDS Alarm. Refer to Fig.3.8 below : -

B2-

B1-

L4-

L3-

L2-

L1-

AC INPUT DC(-) OUTPUT DC(+) OUTPUT B2+ B1+ L4+ L3+ L2+ L1+

AC Fail NO COM NC NO COM

Common Alarm NO COM NC NO COM NC LVDS Alarm

NC

LV Alarm

Fig. 3.8 Voltage free relay contact terminal block 3.4.6 Temperature Sensors Connection Attach the temperature sensor on one of the battery blocks. To ensure good contact, clean the surface of the battery before attaching the battery temperature sensor. Do not use the corrosive solvent during cleaning process. Adhesive strip

Fig. 3.9 Temperature sensor and cable connection

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

3-5

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

3.4.7 Local and Remote Control and Monitoring Communication Link CSM6 provides RS-232 and TCP/IP communication ports for the local and remote control and monitoring function. Local Control and Monitoring : connect a dedicated RS-232 cable to a local PC. Remote Control and Monitoring : (a) Dial-up by using Modem via PSTN (b) TCI/IP connection via Ethernet network Notes: TCP/IP address default setting: 192.168.128.244 TCP/IP port default setting: 4001

C 6 SM
CSM6-2 RS-232 Communication cable TCP/IP TCP/IP Port Communication cable Fig. 3.10 Local and Remote control and monitoring communication cable connection

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

3-6

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

3.5

Rectifier Installation
Unpack the rectifier. Insert the rectifier into the rectifier compartment in the power system.

Push Fig. 3.11 Insert rectifier into the rectifier compartment

Push the rectifier along the rail in the compartment. The rectifier must be pushed until the rear side of its front panel fully touches the cabinet. Secure the rectifier onto the power system with retaining screw provided.

Fig. 3.12 Tighten the rectifier with retaining screw

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

3-7

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

3.6

Final Installation Check

Use the checklist below to complete checks before progressing further. Ensure the system is positioned firmly Ensure all specified ground cables are connected and firmly tightened Ensure the ground resistance meets all specified requirements Ensure all AC and DC cable connections are correct and firmly tightened Ensure the battery polarities are correct at all connections Ensure all battery cable connections are firmly tightened Ensure all signal connections are correctly and firmly connected Ensure the correct cable size and number of cables are selected to carry the rated load correct and to ensure low voltage drop

3.7

System Power Up Procedure


Before turning on the AC mains, ensure the following breakers and switches are off : AC MCB at the AC PDU Load MCBs at the DC PDU Battery MCBs at the DC PDU Turn on the AC mains. Measure the AC input voltage at the AC terminal block. Turn on the AC MCB if the input voltage is normal. Set up the system according to the CSM User Manual. Check the system output voltage displayed on the LCD panel of the CSM. Turn on the battery MCB at the DC PDU if the system output voltage is normal. Turn on the load MCBs at the DC PDU. Check the LEDs status on the CSM and rectifiers. (1) No alarm (no red LED lighted) should occur. (2) Power normal (green LED lighted).

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

3-8

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

4.
4.1

Maintenance & Fault Tracing


Maintenance
Hazardous voltages exist within the system cabinet. Hence, test before touching any conducting part. Perform regular inspection on the system at time intervals recommended below : Check the environmental conditions (temperature, humidity level, air quality, ventilation etc.) every month. Wash the dust filter of the rectifier modules with clean water every month. Check the condition of the fans in the rectifier modules every half a year. Clean the surface of the cabinets once every year. An example of a maintenance record is given in Appendi 2 of this manual.

4.2
No. 1 2 3

Recommended Spare Parts List


Part Description Rectifier CSM6-1 CSM6-2 Quantity 1 pcs per 10 system 1 pcs per 20 system 1 pcs per 20 system

4.3

Fault Tracing

When a fault message is displayed on the LCD panel of the CSM6-1, the following guide can be used for fault tracing : -

Alarm
POWM ENVM LVA AU COMMXX SMR COMMXX MAJOR ALARM SMR ALARMXX AC FAIL 01

Description of Fault
RS-485 communication breakdown between CSM6-1, CSM6-2 or rectifiers. AC power failure or loss of phase

Check Items

AC FQ
DCV

1.

Check if any RS-485(USB line) connector is disconnected. Check if the AC MCCB/MCB is off. Check if AC power failure or loss of phase occurs. Check if AC power failure or loss of phase occurs. Check if any rectifier fails. Check if the AC INPUT switch of any rectifier is off or tripped. When the AC INPUT switch of a rectifier is off, its LCD will continue to display the output bus voltage. However, the green LED on the rectifier will be off and the red LED will be on.

1. 2. 1. 2. 3.

AC FQ

---

SMR ALARMXX

Rectifier fault or failure

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

4-1

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

4. 5. 6.

Check if the DC OUTPUT switch of any rectifier is off or tripped. Check if the address of any rectifier is incorrectly set. Check if any rectifier is in OCP, OTP, OVP or UVP mode by observing whether the red LED on any rectifier is on or any fault message is displayed on the LCD of any rectifier. Refer to the Rectifier User Manual for more details. Check if the DC output voltage is higher than the preset DCV alarm level in the CSM ALMS subscreen. Check if the DC output voltage is lower than the preset DCV alarm level in the CSM ALMS subscreen. Check if the battery is discharged to a voltage lower than the preset DCV alarm level in the CSM ALMS subscreen during an AC failure. Check if the DC output voltage is lower than the preset LVA alarm level in the CSM ALMS subscreen. Check if the battery is discharged to a voltage lower than the preset LVA alarm level in the CSM ALMS subscreen during an AC failure. Check if the internal ambient / battery temperature is higher than the preset TEMP alarm level in the CSM ALMS subscreen. Check if any load or battery MCB on the DCPDU is tripped or open. Check if the LVDS is off, tripped or fail.

1. DCV --DC output voltage high

1. MAJOR ALARM SMR ALARMXX

DCV

DC output voltage low, battery voltage low

2.

1. LVA DCV MAJOR ALARM SMR ALARMXX

DC output voltage low, battery voltage low.

2.

ETEMPxx BTEMPxx

---

Internal ambient / battery temperature high Load or battery MCBs tripped and opened LVDS tripped

1.

-----

LOAD MCBXX BATT MCBXX LVDSxx

1. 1.

Arresters damage checking procedure Whenever a lightning surge occurs and causes damage to the surge arrester at the site AC mains distribution board, check is to be conducted on the SPD on the rectifier system, if a SPD is fractured or shattered, replace it with a new one.

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

4-2

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

4.4

Replacing The Rectifier Procedure

4.4.1 Removing a rectifier . Loosen the rectifier retaining screw.

Fig. 4.1 Loosen the rectifier retaining screw

Pull out the rectifier.

Pull

Fig. 4.2 Pull out the rectifier

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

4-3

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

4.4.2 Inserting a rectifier Insert the new rectifier with the burst-out guides in the shelf.

Push

Fig. 4.3 Insert the new rectifier

Push the rectifier along the rail in the compartment. The rectifier must be pushed until the rear side of its front panel fully touches the cabinet. Secure the rectifier onto the power system with retaining screw on the front panel.

Fig. 4.4 Tighten the rectifier with retaining screw

Check the LEDs status on the CSM and rectifiers. (1) No alarm (no red LED lighted) should occur. (2) power normal (green LED lighted).

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

4-4

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

5. Important Notices
5.1 General Guidelines
The following guidelines must be observed during system installation, system operation or when maintenance work is carried out. 5.1.1 Installation System installation must only be carried out by qualified personnel. Ground resistance must meet local requirements. Any equipment connected to the system must be properly grounded. The conductors connecting external surge arresters must be as short as possible and the resistance must be less than 10. If metal tube is used to protect the conductors, both sides of the tube must be properly grounded. External surge arresters must be located far from inflammable materials. For safety reasons, surge arresters must be installed in protective case. The distance between any metallic part and exposed conductor must meet relevant safety clearance requirements. 5.1.2 System Operation Before operating the system, it must be ensured that the input voltage, input frequency and other operating conditions are within the specification. The rectifier module must only be operated with its pin housing mated with AMP 211149-1 housing. Refer to the rectifier user manual for more details. When using sealed lead acid batteries, attention must paid to the charge data and warning notices provided by the battery manufacturer. If any part of the system is damaged, it must undergo maintenance immediately. 5.1.3 Environmental and Airflow Considerations Operating the system in dusty environment may result in damage. Excessive dust settling inside the rectifier may result in poor heat dissipation and degradation of product performance. It is recommended to operate the system in air conditioned environment. The system must be operated in properly ventilated environment. Do not impede airflow through the system and rectifier modules by blocking or covering the ventilation holes on the front and back panel of the system. Do not operate the system in environment containing inflammable gas or material. Batteries produce combustible gas. Hence, the room must be properly ventilated. 5.1.4 Maintenance and Repair Maintenance work must only be carried out by qualified personnel. During maintenance or repair, do not touch any conducting part in the system while the system is in operation. Before carrying out repair work on the rectifiers, wait for at least 5 minutes after switching off the power to allow the internal capacitors to discharge.

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

5-1

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

5.2

Warranty Constraints

This equipment is guaranteed for one year. During the warranty period, the equipment is guaranteed against defective material and faulty manufacture. The equipment has been carefully inspected and undergone comprehensive test at the factory prior to delivery. If, within the warranty period, any material or workmanship related defect is discovered in the equipment, we undertake to make good the defect at our own expense subject to the standard conditions of sale. Our responsibility is in all cases limited to the cost of making good the defect in the equipment itself. The guarantee does not extend to third parties, nor does it apply to defects caused by improper installation, unauthorized alteration, abnormal working conditions, accident, natural disaster, misuse, or wear and tear.

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

5-2

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

1. 2.

Rev. A

Appendix :

Conductor Size Requirement for DC Applications Maintenance Record

HR9002-001

48V/5.8kW/2.9kW Energy System

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

1. Conductor Size Requirement for DC Applications


Current Rating (A) 20 30 40 50 60 70 75 90 100 125 150 175 200 225 250 275 300 350 400 500 600 700 800 1000 1250 1600 2000 2500 3000 4000 5000 Note : Follow local requirements if specified otherwise. Wire Size (mm x mm) 3.5 5.5 8 14 22 38 50 60 80 100 125 150 or 50 x 2 200 or 60 x 2 250 or 80 x 2 325 or 125 x 2 150 x 2 125 x 3 150 x 3 200 x 3 200 x 4 50 x 6t 50 x 10t 60 x 10t 80 x 10t 100 x 10t 2 x 80 x 10t 2 x 100 x 10t 2 x 120 x 10t 3 x 120 x 10t 3 x 150 x 10t Copper Busbar Size (mm x mm)

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

A-1

All rights reserved. Passing on and copying of this document, use and communication of its contents not permitted without written authorization from AcBel.

2. Maintenance Record
System Serial No. : System Alarm Date Check 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 Month : Environmental Condition Check Inspector : Dust Filter Cleaning Fan Rectifier Check Cabinet Cleaning

Rev. A

HR9002-001

48V/5.8kW/2.9kW Energy System

A-2

Potrebbero piacerti anche