Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
REDRH
MASTER MASON
CONTENT
? Introduction ? Aerial view of a room ? Site Selection ? Parts of the house ? Foundation ? Foundation footing (Chapri) ? Foundation pyramid ? Making rings ? Posts ? Plinth beam ? Roof beam ? Roof beam joint ? Making the slab
1 3 4 5 6 7 8 9 10 11 12 13 14
? Walls- brick laying ? Checking the quality of bricks ? Testing sand quality ? Curing of bricks and mortar ? Bricks laying ? Making the masala Mix ? Batching (Baan) ? Filling Concrete into Post ? Back Elevation ? Front Elevation ? Materals needed for one housel ? Stages progress
15 16 17 18 19 20 21 22 23 24 25 26
INTRODUCTION
The Reconstruction of Earthquake Damaged Rural Houses (REDRH) Project aims to reconstruct 7,972 rural houses fully or severely damaged during the 18th Sept, 2011 earthquake. Constructing these 7,972 houses which are scattered in the highest and steepest mountain terrain with existing manpower (who are already implementing ongoing programs) is a formidable task at hand. Also the unit cost of Rs 4.89 lakh per house is based on a standard unit cost. While construction is being undertaken in 2012-13, the estimate is based on SPWD SOR of 2006. While certain relaxations as a onetime dispensation are being explored, completing these houses without compromising on the design, construction quality, budgetary ceiling and time frame will need strong commitment, determination and team work. The capacity building of the masons constructing this house is critical, as the quality of the house will depend largely on their knowledge and expertise. Hence, in order to simplify the technical aspects of the house construction this illustrated Mason Training Booklet has been designed. It is hoped that the field engineers and masons will use this booklet as a ready reckoner for handy reference during house construction.
Namaste. My house got damaged during the 18th September, 2011 earthquake. But the government has helped me construct my new home along with 7972 others. Through this booklet, I will help you to construct this house in the correct manner step by step
MASTER MASON
This is what it looks like from the inside. It has two bedrooms, kitchen and Dining Room and a bathroom
R ED
RH
SITE SELECTION
Preferably away from Jhoras and stream Not attached to the slope, Min 3 ft distence
3 ft
MASTER MASON
Plinth Beam Plinth Beam The house is made of 9 posts, covering a total area of 605 sq. ft.
FOUNDATION
Next the foundation is the most important part of the house. You must dig minimum 6 ft height or more (till hard strata is reached) and 4ft x 4ft., depending on soil conditions.
RED RH
6 ft 4 ft
4 ft
Size of Footing 4 ft
L of post rod 2 ft
R EDRH
Post size 12 by 12
FOUNDATION PYRAMID
Ground Level
Cover 1.5"
This figure shows how the foundation should look like below the ground level.
RCC: 1:2:4
R ED
RH
MAKING RINGS
This is how rings are made. Bend them as shown in figure, bending ends to 135 degree.
This is very important during earthquakes as it does not come loose causing posts to collapse Here's a picture of what happens when these are not followed. Phot of Post Wall
8mm dia
9 3
135 Bend
42 "
8mm dia
POSTS
16 mm dia
The Post has 4 main rods of 16 mm dia. The post should be 12by 12 , so the rings should be 9 by 9 with 1.5 of concrete cover
Remember again!! Gap between rings near joints should be 3. This will again help give strength to the house during earthquakes.
Also place rings parallely (with no tilt) with their open ends at alternate positions as shown in figure
10
PLINTH BEAM
The Plinth Beam has 4 main rods of 12 mm dia. The beam should be 12by 12 , so the rings should be 9 by 9 with 1.5 of concrete cover
8mm dia
12 mm dia
VERY IMPORTANT! Gap between rings near joints should be 3. This will again help give strength to the house during earthquakes
MASTER MASON
Also place rings parallely (with no tilt) with their open ends at alternate positions as shown in figure
11
ROOF BEAM
8 mm dia 9" x13" 12 mm dia
12"
16"
16 mm dia
1.5" Alternate Bend The Roof beam has 2 rod of 12 mm dia on the top and 3 main rod of 16 mm dia at the bottom . Beam including the slab should be 12 by 16 , so the rings should be made of 9 by 13" size
12
MASTER MASON
Rotation
12"
12"
13
The slab should be of 4 width, and should have a cantilever of 4 all around.
The main bars are of 10 mm dia placed at 8 c/c bothways. Alternate bars should be cranked as shown in figure.
Short piece
10 mm dia
MASTER MASON
10 mm 6 ft long on all 14
8 ft (Height)
Sill = 6 x 5
Sill level= 3 ft
Plinth = 12 x 6"
MASTER MASON
Our house should also have a window sill band at a height of 3 ft from the plinth, as shown in yellow colour. This is important to tie the house together and make it stronger
15
REDRH
MASTER MASON
16
REDRH
Here is how we can check the quality of SAND. Pour sand in glass of water and let it settle. More mud means sand is not good quality.
MASTER MASON
17
DAY
28
DAYS
18
BRICKS LAYING
The laying of bricks should not exceed more than 3 ft height in a day
HRD E R
SAND CEMENT
MASTER MASON
SAND
SAND
SAND
3 ft.
19
1
SAND SAND
SAND
GITI GITI
GITI GITI
2
CEMENT
GITI GITI
GITI GITI
3
32 lit.
20
This figure shows the masala mix for posts and beams.
BATCHING (BAAN)
Always mix cement, sand and giti on a GCI sheet or concrete floor, avoid mixing the same on the ground as it will affect the quality of concrete mixture
21
R ED
RH
22
BACK ELEVATION
22'3" 3'
2'9"
R EDRH
2'11"
1'6"
23
FRONT ELEVATION
22'3" 3'
2'9"
2'9"
4'11"
1'6"
24
1025
kg
TMT Bars 10 mm
TMT Bars 16 mm
TMT Bars 12 mm
461
kg
TMT Bars 12 mm
300 Bags
CEMENT
SAND
STAGES OF PROGRESS
BDO
26
REDRH
C o n c e p t u a l i z e d b y R u r a l M a n a g e m e n t a n d D e v e l o p m e n t D e p a r t m e n t , G o v e r n m e n t o f S i k k i m S u p p o r t e d b y : W W F I n d i a , K h a n g c h e n d z o n g a L a n d s c a p e P r o g r a m m e I l l u s t r a t i o n , D e s i g n & P r i n t P e t e r L e p c h a A r t s & G r a p h i x , G t k . P h . 9 4 3 4 1 8 4 2 8 1