Sei sulla pagina 1di 9

HV

CERTIFICATION
OF HOUSE OF
FASHION
BUILDING,
COLOMBO
AMITHI POWER CONSULTANTS (PVT) LTD,
NO. 1080/9,
ATIGALA MAWATHA,
RAJAGIRIYA,
SRI LANKA

JUNE 2013

Report on HV Certification

House of Fashion Building

Contents
1

SCOPE OF TESTING .............................................................................................................................. 3

TESTING OF TRANSFORMER .............................................................................................................. 3

2.1

TRANSFORMER DETAILS ............................................................................................. 3

2.2

VISUAL INSPECTION ..................................................................................................... 4

2.3

INSULATION TEST ......................................................................................................... 4

TESTING OF HV CABLE......................................................................................................................... 4
3.1

VISUAL INSPECTION ..................................................................................................... 4

3.2

INSULATION TEST ......................................................................................................... 5

TESTING OF OVER CURRENT AND EARTH FAULT RELAY .............................................................. 6


4.1

REALAY DETAILS .......................................................................................................... 6

4.2

VISUAL INSPECTION ..................................................................................................... 6

4.3

SETTINGS OF THE RELAY ............................................................................................ 6

4.4

TEST RESULTS OF SECONDARY INJECTION TEST.................................................. 7

INSPECTION AND TEST ON EARTHING ELECTRODE ....................................................................... 9


5.1

VISUAL INSPECTION ..................................................................................................... 9

5.2

TEST ON EARTHING SYSTEM ...................................................................................... 9

COMMENTS AND RECOMENDATIONS ................................................................................................ 9

Report on HV Certification

House of Fashion Building

SCOPE OF TESTING

The scope of the testing was as follows;

Testing of the Transformer HV side

Visual inspection of transformers

Winding Insulation testing of transformer

Verification of transformer connection terminals

Earth electrode resistance testing

Verification of interlocks and safety

Insulation Testing of 11 kV Cables

Verification of cable connection terminals

Setting over current and Earth fault settings of the relay

Testing and verify the settings

Verification of connections of the Relay

TESTING OF TRANSFORMER

The system consists of a primary 2500kV, 11kV/400V 3 phase transformer feeding whole building
of House of Fashion.

2.1 TRANSFORMER DETAILS


Type

Cast Resin Transformer, Air Cooling, Indoor Type

Nominal Capacity

2500 kVA

High Voltage

11kV

Low Voltage

400V

HV side Current

131.22 A

LV side Current

3608.4 A

Vector Configuration

Dyn11

Insulation level

(12-28-76/ 1.1-3)

Impedance Voltage

6.6 %

2.5%

Report on HV Certification

House of Fashion Building

2.2 VISUAL INSPECTION


The following were noted during the visual inspection;
All terminal connection tightness has been inspected and the connections has been compared
with the drawings, as per the inspections installation is satisfactory.
Transformer neutral earthing is satisfactory.

2.3 INSULATION TEST


Transformer terminals were tested using insulation resistance tester. The following insulation
levels were measure for the transformer HV side.
Winding

Insulation Resistance

Test voltage

Between HV L1-Earth

> 200G

5kV

Between HV L2-Earth

> 200G

5kV

Between HV L3-Earth

> 200G

5kV

Between HV L1-L2

> 200G

5kV

Between HV L1-L3

> 200G

5kV

Between HV L3-L2

> 200G

5kV

Insulation resistance of winding is satisfactory as per the above observations

TESTING OF HV CABLE

3.1 VISUAL INSPECTION


The following were noted during the visual inspection;
All terminal connection tightness has been inspected and the connections has been compared
with the drawings, as per the inspections installation is satisfactory.

Report on HV Certification

House of Fashion Building

3.2 INSULATION TEST


HV cables were tested using insulation resistance tester. The following insulation levels were
measured for two no. of 3core x 150mm2 11kV power cables.
11kV cable from RMV panel to CEB panel
Cables

Insulation Resistance

Test voltage

Between L1-Earth

50 G

5kV

Between L2-Earth

50 G

5kV

Between L3-Earth

50 G

5kV

Between L1-L2

> 200G

5kV

Between L1-L3

> 200G

5kV

Between L3-L2

> 200G

5kV

11kV cable from RMV Panel to Transformer


Cables

Insulation Resistance

Test voltage

Between L1-Earth

> 200G

5kV

Between L2-Earth

> 200G

5kV

Between L3-Earth

> 200G

5kV

Between L1-L2

> 200G

5kV

Between L1-L3

> 200G

5kV

Between L3-L2

> 200G

5kV

Insulation resistance of cable is satisfactory as per the above observations

Report on HV Certification

House of Fashion Building

TESTING OF OVER CURRENT AND EARTH FAULT RELAY

4.1 REALAY DETAILS


RMU protection relay
CSD PR- V2 100
Over current and Earth Fault relay
Location: In the MV Panel Board
Make: C&S electronics

4.2 VISUAL INSPECTION


The following were noted during the visual inspection;
All terminal connection tightness has been inspected and the connections has been compared
with the drawings, as per the inspections installation is satisfactory.

4.3 SETTINGS OF THE RELAY


Relay Settings
Relay: CSDPR -V2-100
Make: C&S electronic
Location: Main Panel

Over Current Protection


In
Ip

=
=

1 A
0.70xIn

I>>>
TI>>>
I>>
TI>>
I>
TI >
T>
IEC Curve

=
=
=
=
=
=
=
:

(infinity)
0 s
3xIn
0.03 s
0.70xIn
0.5 s
(TMS)
0.030 s
Normal Inverse
6

Report on HV Certification

House of Fashion Building

Earth Over Current Protection


IE>>>
TIE>>>
IE>>
IE>
TI E>
IEp
T>
IEC Curve

=
=
=
=
=
=
=
:

(infinity)
0 s
0.5xIn
0.1
0.10
(TMS)
0.1xIn
(Min Available)
0.10 s
Normal Inverse

4.4 TEST RESULTS OF SECONDARY INJECTION TEST


IEC Equation for Normal inverse curve
Trip time characteristic acc. IEC
Acc.IEC 60255-3 and BS142 (Refer to figure3.1 and 3.2)
(

) (

)
( )

Report on HV Certification

House of Fashion Building

Test results for the over current testing


Relay: CSDPR -V2-100
Make: C&S electronic
Location: Main Panel
Current Setting: 0.7*In (Ip)
CT Ratio: 150/1
IEC Curve: Normal Inverse
TMS: 0.50 s

Injected Test Current( A)

Time taken to trip (ms) actual

Calculated time(ms)

value

0.80

10,000

26,180

0.85

7,610

17,991

0.90

5,926

13,891

0.95

4,953

11,426

1.00

4,175

9,777

3.10 (For I>>)

141.7

2,317

3.50 (For I>>)

84.5

2,139

4.00 (For I>>)

92.4

1,972

4.50 For I>>)

92.4

1,847

Injected Test Current (mA)

Time taken to trip (ms)

Calculated time(ms)

125

2,477

3,129

150

1,586

1,725

175

1,181

1,243

200

911

1,000

520

106

400

Test results for the Earth fault testing

Report on HV Certification

House of Fashion Building

INSPECTION AND TEST ON EARTH ELECTRODE

5.1 VISUAL INSPECTION


There were two main earthing systems, Electrical earthing and building structural earthing which
shall have bonded together in panel board. Transformer neutral earthing was connected to the
electrical earthing.

5.2 TEST ON EARTHING SYSTEM


Neutral earthing of the transformer was tested using Earth Megger tester. Resistance value of
electrical earthing system is 6.92 .

This resistances value of the earthing is satisfactory.

COMMENTS AND RECOMENDATIONS

As per the observations and tests all the HV side installations (As mentioned in the scope) are
satisfactory for energizing and continuous commercial operation.

Report Prepared and Certified by:

..
DG Rienzie Fernando
B.Sc. Eng, C.Eng, MIE (SL),
Managing Director,
Amithi Power Consultants (Pvt) Limited.