Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Case Study:
The Channel Tunnel Rail Link
The Channel Tunnel Rail Link (CTRL) will be Britain's first major new railway for over a century - a high-speed line running for 68 miles between St Pancras station in London and the Channel Tunnel.
Project background
Work on construction of the CTRL began in 1998. The total project is divided into 15 separate contracts. This case study deals with the use of sustainable aggregates in three of these contracts, C103, C310 and C440.
Economic
RSA had a lower cost than primary aggregates. Direct savings include:
initial cost of the recycled aggregate (free as they were all available
on site from construction and demolition of future/previous structures, or from nearby sites);
Environmental
Use of RSA reduced the demand for primary aggregates, and the re-use of materials created a reduction in the volumes of waste sent to landfill.
Photograph courtesy of CTRL
Performance
Testing of the RSA showed that for some of the uses, performance characteristics were superior to those of the primary aggregates which would have conventionally been used.
Project Specification
Name: Region: Type of project: Timescale: Client: Contractors: Engineers: Channel Tunnel Rail Link (CTRL) London Railway infrastructure 2001-2007 Union Railways North/Union Railways South C103 Kier Nuttall JV C310 Morgan Vinci C440 Balfour Beatty Major Projects Rail Link Engineering Project Manager
AggRegain
www.aggregain.org.uk
C310 C440
Lessons Learnt
Overall, the main lesson learnt from the use of RSA on the various CTRL contracts were that it was economical, sustainable and technically feasible. Close liaison and forward planning between the client and contractors was very important to the effective use of RSA.
Cost effectiveness
Use of recycled aggregate Aggregate cost: 0 Crushing and handling: 3 per tonne Total cost: 3 per tonne
Photograph courtesy of CTRL/Urban Exposure
Use of comparable primary aggregate Aggregate cost: 8 per tonne (including Aggregates Levy at 1.60 per tonne)
Total saving
Quantity used
Total saved
7 per tonne
130,000 tonnes
910,000
Contract 310: West Thames Ripple Lane to Thurrock Contract 440: Ashford to Cheriton
Over 30,000 tonnes of locally sourced spent foundry sand were used on this contract as fill around structures, providing an alternative to low-grade primary aggregate. The use of spent foundry sand was seen to have a number of performance advantages over primary aggregates as well as providing both economic and environmental benefits A total of 144,606 m3 of reject lightweight concrete blocks were used as a temporary and permanent engineering fill. The decision to use these materials was made because of their cost effectiveness and local availability. The blocks were also seen to have a number of distinct performance advantages when compared to the alternative low grade primary aggregates. The blocks allowed lighter structures to be built, had better weight resistance, reduced settlement and maintenance and excellent compressive strength and interlocking.
Cost effectiveness
Use of recycled aggregate Aggregate cost: 7.37 per m3 (including crushing, handling and transportation costs) Use of comparable primary aggregate Aggregate cost: 18.70 per m3 (including Aggregates Levy at 1.60 per tonne, and crushing,handling and transportation costs) Landfill tax: 2 per tonne 9.81 per m3 144,606 m3 1,417,904 Total saving Quantity used Total saved
Cost effectiveness
The use of spent foundry sand provided direct cost savings in terms of the reduced material costs. In addition, due to the availability of a local supply, transport costs were also significantly lower than for equivalent primary material.
Further information
WRAP. The Old Academy, 21 Horse Fair, Banbury OX16 0AH