Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
PRESENTATION COVERS
Location Overview Salient Features of The Tunnel Construction Approach Pre-construction Planning Usage Of NATM in T-80 Construction Activities Quality Assurance Environment Issues Social Impact
2
LOCATION OVERVIEW
BARAMULLA
SOPORE HAMRE PATTAN RAJWANSHE R BUDGA M SRINAGA R PAMPOR E KAKPORA AWANTIPORA PUNZGA BIJBEHARA M ANANTNAG SADUR A QAZIGUN D
ARPINCHALA BHATTA LOALE KOHLI SANGALDAN SURUKOT BARALA BASAND SALAL A--DHAR REASI
JAMM U
SOUTH PORTAL
4
Total length 11 Km Adit 774 m (58 m2 exc. Area) Shaft : 55 m depth , 12 m dia Maximum overburden - 1.10 Km Tunnelling method :NATM (New Austrian Tunneling Method) Completed Cost 1150 Crores Approx. 440 m below existing Jawahar Road Tunnel(2.75km) Underground excavation : 10 lac cubic meter Cross section Area : Excavation : 67 to 78 m2 , Finished Tunnel : 48 m2 Investigation Bore Holes depth upto 640 m 6
MANY FIRSTS
The Longest Transport Tunnel In The Country (11Km) Highest Over- burden of 1100M
for
Geotechnical
First Large Scale Use of New Austrian Tunneling Method (NATM) in India First Use of Road header for Tunnel Excavation in Railway Tunneling
8
CONSTRUCTION APPROACH
10
Adit 788 m
Cross Passage 55 m
11
STRUCTURAL GAUGE
12
13
PAY LINE 150 TH. FROM Min. EXCAVATION 25 mm 3 to 5m ROCK BOLTS AS PER SITE REQUIREMENT Min. EXCAVATION LINE 50mm TH. R.C.C. LAGGING ISHB 150 @ 500 C/C 300 TH. C.C. LINING FINISH LINE SHOTCRETE(25mm+WIRE MESH +50mm) OR 50mm SFRS
50 150
150
900
4370
1676
RAIL
50
675
150 100
1312
675
1 in 40
M20
75 50 150
65
150(max)
SEC. AT A-A
00
R2 6
R3 0
00
FINISH LINE
14
15
16
BENDING MOMENT DIAGRAM FOR ELLIPITCAL TUNNEL TOP PRESSURE 15000KG/M AND SIDE PRESSURE 5000KG/M
17
WITH TOP PRESSURE 15000 KG/M & SIDE PRESSURE 5000 KG/M D-SHAPED TUNNEL ELLIPTICAL TUNNEL 412.5KN 567 KN 137KN-M 35.80KN-M 15129 KG 9025 KG 0.083 M 0.024 M
WITH TOP PRESSURE 15000 KG/M D-SHAPED TUNNEL ELLIPTICAL TUNNEL 412.5KN 639 KN 48.10 KN-M 35.65 KN-M 8565 KG 9635 KG 0.03 M 0.028 M
19
20
ROAD HEADER
CONTINUOUS ADVANCELESS SURPRISES MORE CONTROLLED EXCAVATION- LESS OVERBREAK/CAVITY FORMATION SUITABLE FOR MEDIUM HARD ROCK CAN BE WITHDRAWN MID WAY TO GIVE WAY FOR OTHER METHODS
21
CONTINUOUS ADVANCE CIRCULAR SECTION NOT SUITABLE UNDER SQUEEZING CONDITIONS CANNOT BE WITHDRAWN MIDWAY TO GIVE WAY TO OTHER METHODS
22
WHY NO TBM
Likelihood of Mixed Geology Heavily Faulted Areas and/or Wide Fault Zones High Squeezing Anticipated in middle with High Overburden (1100 mts.) Heavy Water Flow in Lime Stone Zone with High overburden TBM may be Trapped by Ground Movement Behind the Face
23
PRE-CONSTRUCTION PLANNING
PRE-CONSTRUCTION PLANNING
Engagement of Consultant
QCB System Of tendering
Survey and Investigation Head start by Taking up ADIT and shaft works in advance Tender Planning
Key dates Multi Method Approach
Road Header/ D&B
25
Deformation Monitoring to assess the stress redistribution, and stabilization before final lining
27
INSTRUMENTATION
To provide early information about tunnel behaviour in order to optimize excavation & support activities during construction and to recognize the requisite remedial measures. Instrumentation data is basic input of the NATM, the observational approach.
Instrumentation in Pir Panjal Tunnel:
Optical 3 D monitoring:
Extensometers: Radial Pressure Cells: Shotcrete Strain meter: Piezometer:
28
CONSTRUCTION ACTIVITES
Open excavation & portal development Tunnel mining & primary lining Water-proof membrane installation + drainage system. Secondary lining. Ventilation, system and safety installations Track laying
29
QUALITY ASSURANCE
Laid down responsibilities, procedures and checklists for various activities through:
CPM, CQM, SH&EM PPM, PSM Organogram QAP ITP
30
31
32
ENVIRONMENT ISSUES
Identified Muck Dumping areas Recycling of Excavated Rocks
aggregate for concrete constn.
SOCIAL IMPACT
All weather link, Alternate to Jawahar Tunnel Even at Construction stage, given a boost to
local construction-industry Employment Transportation business
34
Time Line
35
2009
2010
2533
1739 Two Faces after Jan10
2011
2012
63
36
Miles to go
40
THANKS !
41
ENGAGEMENT OF CONSULTANT
Investigations for Tunneling Methodology Assessment Initial Design
Usage of NATM Usage of Water proof Membrane for Semi Dry Tunnel Development of 4-Arc Tunnel X-Section Additional Access through ADIT and Shaft Portal Location Review
2003-04 2004
2004 2004
Data input for Tendering and a Decision Support System for ADIT and Shaft decision Adit & Shaft Work Awarded in June 2004
2005
43
44
45
46
BASIC PRINCIPLES OF NATM Rock Mass is the major load bearing member Primary Support shall
maintain the integrity & strength of Rock Mass light, have good and area contact (shotcrete) strengthen Rock Mass (bolt, grouting) provide protection to workers (steel rib, mesh) installed quickly
Provide always an effective ring closure, if necessary by an invert if rock is not suitable
BASIC PRINCIPLES OF NATM (Contd.) Rounded shape of Cross-Section Continuous control of system behaviour by monitoring Inner lining shall be installed only after balance of stresses (zero deformation)
49
3D Monitoring Targets
50
51
52
EXTENSOMETER
53
FACE MAPPING
54
PROBING SHEET
55
56
57
58
59
60
61
Charging of Face
62
Ventilation Duct
63
Mucking
64
67
Rock Bolting
68
TUNNEL MINING
Activity
Drilling & Excavation
Charging , Blasting & Defuming Mucking Wire Mesh & Lattice Girder Shotcrete Rock Bolting Preparation of new face Cycle Time (hr.) 2 mt. RC IV Cycle time (hr.) 1.25 mt. RC V
1.7
2.7 1.1 2.4 0.9 1.8 0.3
0.9
1.5 0.8 2.3 0.8 1.0 0.3
Maintenance
Forepoling Total
1.6
1.6 14.1
1.1
1.7 10.4
69
70
Geotextile Fixing
72
73
Membrane Stitching
74
75
77
Core Cutting
80
81
Sedimentation Tank
82
83
84