MEP Upgradation Works - List of Activities for Shut Down planned on 15th & 16th Feb'14

SR. NO ACTIVITY AGENCY Start Time A Pre Shutdown Activities(offline Activities) Deliveries of 2x200KVA, 2 x 60KVA UPS, Isolation transformer,battery racks, base frames, batteries and accessories, Verification of all Material required for Installation activity Installation of Base frames & Positioning of UPS & ISO.TX. Pre-commisioning/inspection of UPS System & accessories Testing of New UPS(s) with temporary power supply Testing of 200kva UPS in C1 & C6 ( Supply required ) Testing of 60kva UPS in C1 &C6 (Supply required ) 5 DC Cable tray laying / installation from ups room to battery room. Laying of DC Cables and signal cables for optional monitoring & testing ( BMS /SNMP/External bypass) The above activities can be planned once the room is ready and all required temporary / permanent power is available for New UPS Room B Activities to be carried out during Shutdown Period (DISMENTALLING OF OLD UPS SYSTEM) 1 2 3 4 5 6 7 Shutdown of old UPS System, Power off all incomer and bypass/output breakers of exisiting panels. Removal of power cables from old UPS System/Iso.TX. Dismentalling of interlinks of old batteries and DC Cables Removal & shifting of old batteries from the battery racks. Removal of old battery racks Removal of Isolation transformer(old) Removal of Old UPS System RBS Operation/facility team/SEPL/Socomec Socomec Socomec Socomec Socomec Socomec Socomec 0:30:00 1:00:00 4:00:00 4:00:00 1:00:00 1:30:00 5:00:00 1 1 1 1 1 1 1 TIME DURATION End Time Total Duration in HRS Day

SOCOMEC

2 3 4

SOCOMEC SOCOMEC SOCOMEC SOCOMEC SOCOMEC SEPL SOCOMEC / SEPL

12:00:00 12:00:00 12:00:00 12:00:00

3 4 5 5 5 6

Removal of any other materials related to UPS System, like removal of Electrical cable, trays, HVAC Duct

other Vendors (HVAC/ELECTRICAL)

1:00:00

Handover of room to CIVIL/ELECTRICALS vendor for doing modification/renovation/paint finish if any Electrical Power point provision require for BMS Panel from UPS DB / Raw DB ( 5 nos.)

10

SEPL

The Old material will be directly loaded in the vehicle / Parking permission require near to the Exit door so that the activities can be completed in lesser time slot. If any permission require for taking the Material out need to be provided by Client / PMC. C Activities to be carried out during Shutdown Period (INSTALLATION OF NEW UPS SYSTEM 2 x 200KVA & 2X60KVA UPS, ISO.TX. and BATTERIES ) Once Battery room is completely ready positioning of base frames for new battery racks, new battery racks and BMS Panel positioning of new false flooring work in the battery room

18:00:00

1 2 3 4 5 6 7 8

Socomec FALSE FLOORING VENDOR

3:00:00

1 1

Interconnection of new batteries (150AH/164Nos & 75AH/88NOS) Socomec & BMS Signal cables installation lnstallation of DC Breakers & Laying of DC Cables from battery Socomec room to UPS Room Commisioning of UPS System with new battery and Battery Socomec monitoring system Functional test of UPS & charging of batteries Charging of New UPS Output Panels and integrated testing the panel with all simulation testing & Handing over of UPS System SEPL/PMC/Consultant/ to facility / operation team once confirmation from Socomec Consultant/PMC

12:00:00 2:00:00 8:00:00 5:00:00

2 2 2 2 2

30:00:00

Dependencies

floor shall be clear and false floor marking shall be comleted before positioning of baseframes

Power cabling shall be completed and supply is required from Panel for tesing of UPS ; Floor shall be clear and cut out from partition wall shall be provided cables for Monitoring shall be provided by BMS/IT Vendor.

APPROVAL FOR SHUTDOWN FROM RBS IT TEAM SHALL BE GIVEN

Old UPS & Battery removal activity will be done by Vendor of Socomec, necessary work permit shall be provided.

cable trays removal is not in our scope of work. Electrical vendor shall ensure all cable tray removed from floor and ceiling/walls to ensure new Battery rack positioning CIVIL Work inside the room shall be completed immediately so as to positioning new battery racks, Else Activity time may increase if the room is not handed over to us within time frame.

RBS/PMC SHALL ENSURE ANY PERSMISSION RELATED TO PREMISIES SECURITY SHALL BE PROVIDED TO ALLOW VEHICLE PARKING AND LABOUR MOVEMENT

False flooring marking shall be completed by respective vendor

HVAC Shall be working,