TRANSPORTATION PROJECT SCHEDULING WORKSHEET

PRODUCTION RATES - ENGLISH


PRODUCTION RATES ARE AVERAGE VALUES.
RATE MODIFICATIONS MAY BE NECESSARY TO MEET SPECIFIC PROJECT CONDITIONS.
USER ASSUMES ALL RESPOSIBILITY FROM USE AND/OR MODIFICATION OF THESE RATES.

Quantity Production Days


Work Item Unit
(User input) Rate (Calculated)

MOBILIZATION AND TRAFFIC CONTROL


Barrier, Temporary Lin. Ft. 3,001 -

ROADWORK
Removal, Concrete CY 20 -
Removal, Concrete Curb & Gutter Lin. Ft. 8 -
Pavement Removal SY 6,209 -
Pavement Cutting (AC) Lin. Ft. 2,001 -
Pavement Cutting (PCC) Lin. Ft. 754 -
Foundation Excavation CY 1,144 -
Excavation, Channel CY 650 -
Embankment CY 2,198 -
Excavation (Highway Trucks) CY 2,353 -
Excavation (Scrapers) CY 3,600 -
Excavation, Rock CY 99 -
Granular Embankment, Special CY 1,120 -
Stone Embankment CY 1,503 -
Subgrade Stabilization (1'-8" Average Depth) SF 8,070 -
Cement Treated Base (Max) CY 2,777 -
Cement Treated Base (Min) CY 1,667 -
Riprap CY 63 -
Riprap, Concrete SY 172 -
Pipe Removal Lin. Ft. 121 -
Category Total: -

DRAINAGE AND SEWERS


-Trench and Backfill CY 157 -
-Trench and Backfill - low production CY 21 -
-Storm Sewer (1' - 2' dia) Lin. Ft. 148 -
Pipe under pavement Lin. Ft. 148 -
-Storm Sewer (2' + dia) Lin. Ft. 98 -
-Storm Sewer in Rock (Max) Lin. Ft. 69 -
-Storm Sewer in Rock (Min) Lin. Ft. 49 -
-Storm Sewers Lin. Ft. 200 -
drywells, New Each 2 -
Inlets, New Each 2 -
Manholes, New Each 2 -
Inlets, Adjust Each 5 -
Category Total: -

1 of 8
TRANSPORTATION PROJECT SCHEDULING WORKSHEET

BRIDGES AND STRUCTURES


Holes Drilled, Concrete 4" dia Each 150 -
Piles, Driving Concrete Lin. Ft. 249 -
Piles, Driving Steel Lin. Ft. 351 -
Piles, Driving Timber Lin. Ft. 298 -
Reinforcement (Substructure) Lbs 2,500 -
Reinforcement (Superstructure) Lbs 5,001 -
Structural Concrete, Lightweight CY 10 -
Class 1 Deck Preparation SF 4,304 -
Structure Steel, Erecting Lbs 25,005 -
Handrail, Erecting Lin. Ft. 79 -
Handrail, Metal Lin. Ft. 79 -
Handrail, Aluminum Lin. Ft. 79 -
Rail, Type F - Pour Concrete Lin. Ft. 295 -
Membrane Waterproofing SF 495 -
Wall, MSE (Max) SF 1,076 -
Wall, MSE (Min) SF 215 -
Walls, Bin (Add 1/2 Day for Backfill) Lin. Ft. 26 -
Walls, Sound - Block Masonry SF 1,614 -
Walls, Sound - Block Masonry Footing(Exc.,Form, Pour) Lin. Ft. 492 -
Walls, Sound - Post & Panel (8' x 8' Max) Lin. Ft. 800 -
Walls, Sound - Post & Panel(8' x 8' Min) Lin. Ft. 492 -
Microsilica Overlay( 3" Deep) SF 6,994 -
Category Total: -

BASES
Cold Plane Pavement Removal (Max) SF 126,538 -
Cold Plane Pavement Removal (Min) SF 72,307 -
Aggregate Base CY 2,778 -
Aggregate Shoulder CY 2,778 -
Chip Seal (Add 1 Day to Broom) TONS 1,485 -
Rock Production (1/2"-3/8") CY 399 -
Rock Production (3/4"-0) CY 481 -
Rock Production (3/8"-#10) CY 399 -
Rock Production (Max) CY 3,472 -
Rock Production (Min) CY 2,083 -
Category Total: -

WEARING SURFACES
Recycling, Cold In Place SF 317,420 -
Recycling, Hot In Place SF 166,780 -
A.C. Paving (Max.) TONS 1,980 -
A.C. Paving (Min.) TONS 1,320 -
Mix Design (AC) Days 28 -
Paved Ditch Lin. Ft. 298 -
Concrete Pavement, Continuously Reinforced SF 2,195 -
PCC Reinf. Lin. Ft. 1,476 -
PCC Pavement, Unreinf. 6" (Max) SF 56,490 -
PCC Pavement, Unreinf. 6" MM (Min) SF 32,280 -

2 of 8
TRANSPORTATION PROJECT SCHEDULING WORKSHEET
Curb & Gutter, Concrete Lin. Ft. 298 -
Curb, Concrete (3 Day Minimum, Cure 1 Week) Lin. Ft. 1,000 -
Sidewalks, Concrete SF 1,076 -
Pavers, Unit (Max.) See Means Data SF 247 -
Category Total: -

PERMANENT TRAFFIC CONTROL AND GUIDANCE DEVICES


Guard Rail (3 Day Minimum) Lin. Ft. 1,000 -
Barrier, Permanent Lin. Ft. 1,000 -
Delineators Each 500 -
Pavement Marking Symbol, Thermoplastic SF 43 -
Pavement Marking, Thermoplastic Lin. Ft. 14,996 -
Pavement Marking, Permanent Painted Lin. Ft. 20,008 -
Category Total: -

PERMANENT TRAFFIC CONTROL AND ILLUMINTATION SYSTEMS


Signs SF 355 -
Illuminaire Poles (Manufacture & Test) Days 120 -
Signal Conduit, Laying Lin. Ft. 374 -
Signal Construction (1 Signal) Days 45 -
Signal Construction (2 Signals) Days 70 -
Signal Construction (3 Signals) Days 90 -
Signal Construction (4 Signals) Days 110 -
Signal Construction (5 Signals) Days 130 -
Signal Poles (Manufacture & Testing) Days 120 -
Traffic Signal Head Alterations Each 4 -
Traffic Signal Posts Each 4 -
Traffic Signal Posts, Relocate Existing Each 4 -
Category Total: -

RIGHT-OF-WAY DEVELOPMENT AND CONTROL


Top Soil CY 350 -
Sodding SF 904 -
Trees, Evergreens Each 22 -
Trees, Seedling Each 2,000 -
Trees, Shade Each 17 -
Shrubs Each 300 -
Fence, Chain Link Lin. Ft 200 -
Fence, Woven Wire Lin. Ft 492 -
Mail Boxes (3 Day Minimum) Each 10 -
Category Total: -

OTHER
Bituminous Base (Max) TONS 1,980 -
Bituminous Base (Min) TONS 792 -
Bituminous Concrete Base Course Widening 9" SF 1,098 -
Bituminous Concrete Binder & Surface Course, Sub 1-11 TONS 524 -
Bituminous Materials Pumped GAL 500 -
Cleaning and Painting Lbs 10,309 -

3 of 8
TRANSPORTATION PROJECT SCHEDULING WORKSHEET
Electric Cable Lin. Ft. 2,499 -
Excavation, Cofferdams CY 74 -
Grading (Broken) CY 601 -
Grading (Max) CY 1,961 -
Grading (Small) CY 784 -
Granular Backfill CY 299 -
Gravel or Crushed Stone Base Course CY 1,120 -
Gravel or Crushed Stone Shoulders CY 1,120 -
Gravel or Crushed Stone Surface Course CY 1,120 -
Gutter, Concrete Lin. Ft. 499 -
Median Surface (Concrete) SF 3,002 -
Mix Design (CTB) Days 21 -
Mix Design (PCC) Days 35 -
Patching, Cold 2" SF 3,002 -
Pavement Marking, Durastripe Non-Profile Inlaid Lin. Ft. 2,640 -
Pavement Marking, Durastripe Non-Profile Overlay Lin. Ft. 10,562 -
Pavement Removal and Replacement SF 75 -
PCC Base Course SF 2,195 -
PCC Base course Widening SF 1,194 -
PCC Driveway SF 97 -
PCC Stringline Lin. Ft. 8,178 -
Pipe Underdrains Lin. Ft. 499 -
Qualify Pit Days 25 -
Rail Demolition (Std. Dwg. BR280) Lin. Ft. 33 -
Rail Retrofit - Drill holes & place steel (Std. Dwg. BR280) Lin. Ft. 16 -
Rail, Type F, Tie Steel Cages (Std. Dwg. BR280) Lin. Ft. 98 -
Right of Way Markers, Erecting Each 30 -
Category Total: -

4 of 8
TRANSPORTATION PROJECT SCHEDULING WORKSHEET

PRODUCTION RATES - METRIC


PRODUCTION RATES ARE AVERAGE VALUES.
RATE MODIFICATIONS MAY BE NECESSARY TO MEET SPECIFIC PROJECT CONDITIONS.
USER ASSUMES ALL RESPOSIBILITY FROM USE AND/OR MODIFICATION OF THESE RATES.

Quantity Production Days


Work Item Unit
(User input) Rate (Calculated)

MOBILIZATION AND TRAFFIC CONTROL


Barrier, Temporary M 915 -

ROADWORK
Removal, Concrete M3 15 -
Removal, Concrete Curb & Gutter M 244 -
Pavement Removal M2 577 -
Pavement Cutting (AC) M 610 -
Pavement Cutting (PCC) M 230 -
Foundation Excavation M3 875 -
Excavation, Channel M3 497 -
Embankment M3 1,682 -
Excavation (Highway Trucks) M3 1,800 -
Excavation (Scrapers) M3 3,600 -
Excavation, Rock M3 76 -
Granular Embankment, Special MG 726 -
Stone Embankment M3 1,150 -
Subgrade Stabilization (500 MM Average Depth) M2 750 -
Cement Treated Base (Max) MG 1,800 -
Cement Treated Base (Min) MG 1,080 -
Riprap - 1.375 Mg/M3 M3 48 -
Riprap, Concrete M2 16 -
Pipe Removal M 37 -
Category Total: -

DRAINAGE AND SEWERS


-Trench and Backfill M3 120 -
-Trench and Backfill - low production M3 16 -
-Storm Sewer (300MM-600MM) M 45 -
Pipe under pavement M 45 -
-Storm Sewer (660MM +) M 30 -
-Storm Sewer in Rock (Max) M 21 -
-Storm Sewer in Rock (Min) M 15 -
-Storm Sewers M 61 -
drywells, New Each 2 -
Inlets, New Each 2 -
Manholes, New Each 2 -
Inlets, Adjust Each 5 -
Category Total: -

5 of 8
TRANSPORTATION PROJECT SCHEDULING WORKSHEET

BRIDGES AND STRUCTURES


Holes Drilled, Concrete 100 MM Each 150 -
Piles, Driving Concrete M 76 -
Piles, Driving Steel M 107 -
Piles, Driving Timber M 91 -
Reinforcement (Substructure) Kg 1,134 -
Reinforcement (Superstructure) Kg 2,268 -
Structural Concrete, Lightweight M3 8 -
Class 1 Deck Preparation M2 400 -
Structure Steel, Erecting Kg 11,340 -
Handrail, Erecting M 24 -
Handrail, Metal M 24 -
Handrail, Aluminum M 24 -
Rail, Type F - Pour Concrete M 90 -
Membrane Waterproofing M2 46 -
Wall, MSE (Max) M2 100 -
Wall, MSE (Min) M2 20 -
Walls, Bin (Add 1/2 Day for Backfill) M 8 -
Walls, Sound - Block Masonry (Quote from Art's Masonry) M2 150 -
Walls, Sound - Block Masonry Footing(Exc.,Form, Pour) M 150 -
Walls, Sound - Post & Panel (2.4M x 2.4M)(Max) M 244 -
Walls, Sound - Post & Panel(2.4M x 2.4M)(Min) M 150 -
Microsilica Overlay(75 MM Deep) M2 650 -
Category Total: -

BASES
Cold Plane Pavement Removal (Max) M2 11,760 -
Cold Plane Pavement Removal (Min) M2 6,720 -
Aggregate Base MG 1,800 -
Aggregate Shoulder MG 1,800 -
Chip Seal (Add 1 Day to Broom) MG 1,350 -
Rock Production (9mm - 12.5mm) M3 305 -
Rock Production (19mm-0) M3 368 -
Rock Production (9mm-#10) M3 305 -
Rock Production (Max) MG 2,250 -
Rock Production (Min) MG 1,350 -
Category Total: -

WEARING SURFACES
Recycling, Cold In Place M2 29,500 -
Recycling, Hot In Place M2 15,500 -
A.C. Paving (Max.) MG 1,800 -
A.C. Paving (Min.) MG 1,200 -
Mix Design (AC) Days 28 -
Paved Ditch M 91 -
Concrete Pavement, Continuously Reinforced M2 204 -
PCC Reinf. M 450 -
PCC Pavement, Unreinf. 150 MM (Max) M2 5,250 -
PCC Pavement, Unreinf. 150 MM (Min) M2 3,000 -

6 of 8
TRANSPORTATION PROJECT SCHEDULING WORKSHEET
Curb & Gutter, Concrete M 91 -
Curb, Concrete (3 Day Minimum, Cure 1 Week) M 305 -
Sidewalks, Concrete M2 100 -
Pavers, Unit (Max.) See Means Data M2 23 -
Category Total: -

PERMANENT TRAFFIC CONTROL AND GUIDANCE DEVICES


Guard Rail (3 Day Minimum) M 305 -
Barrier, Permanent M 305 -
Delineators Each 500 -
Pavement Marking Symbol, Thermoplastic M2 4 -
Pavement Marking, Thermoplastic M 4,572 -
Pavement Marking, Permanent Painted M 6,100 -
Category Total: -

PERMANENT TRAFFIC CONTROL AND ILLUMINTATION SYSTEMS


Signs M2 33 -
Illuminaire Poles (Manufacture & Test) Days 120 -
Signal Conduit, Laying M 114 -
Signal Construction (1 Signal) Days 45 -
Signal Construction (2 Signals) Days 70 -
Signal Construction (3 Signals) Days 90 -
Signal Construction (4 Signals) Days 110 -
Signal Construction (5 Signals) Days 130 -
Signal Poles (Manufacture & Testing) Days 120 -
Traffic Signal Head Alterations Each 4 -
Traffic Signal Posts Each 4 -
Traffic Signal Posts, Relocate Existing Each 4 -
Category Total: -

RIGHT-OF-WAY DEVELOPMENT AND CONTROL


Top Soil M3 268 -
Sodding M2 84 -
Trees, Evergreens Each 22 -
Trees, Seedling Each 2,000 -
Trees, Shade Each 17 -
Shrubs Each 300 -
Fence, Chain Link M 61 -
Fence, Woven Wire M 150 -
Mail Boxes (3 Day Minimum) Each 10 -
Category Total: -

OTHER
Bituminous Base (Max) MG 1,800 -
Bituminous Base (Min) MG 720 -
Bituminous Concrete Base Course Widening 225mm M2 102 -
Bituminous Concrete Binder & Surface Course, Sub 1-11 MG 476 -
Bituminous Materials Pumped L 1,893 -
Cleaning and Painting Kg 22,680 -

7 of 8
TRANSPORTATION PROJECT SCHEDULING WORKSHEET
Electric Cable M 762 -
Excavation, Cofferdams M3 57 -
Grading (Broken) M3 460 -
Grading (Max) M3 1,500 -
Grading (Small) M3 600 -
Granular Backfill M3 229 -
Gravel or Crushed Stone Base Course MG 726 -
Gravel or Crushed Stone Shoulders MG 726 -
Gravel or Crushed Stone Surface Course MG 726 -
Gutter, Concrete M 152 -
Median Surface (Concrete) M2 279 -
Mix Design (CTB) Days 21 -
Mix Design (PCC) Days 35 -
Patching, Cold 50 MM M2 279 -
Pavement Marking, Durastripe Non-Profile Inlaid M 805 -
Pavement Marking, Durastripe Non-Profile Overlay M 3,220 -
Pavement Removal and Replacement M2 7 -
PCC Base Course M2 204 -
PCC Base course Widening M2 111 -
PCC Driveway M2 9 -
PCC Stringline M 760 -
Pipe Underdrains M 152 -
Qualify Pit Days 25 -
Rail Demolition (Std. Dwg. BR280) M 10 -
Rail Retrofit - Drill holes & place steel (Std. Dwg. BR280) M 5 -
Rail, Type F, Tie Steel Cages (Std. Dwg. BR280) M 30 -
Right of Way Markers, Erecting Each 30 -
Category Total: -

8 of 8