Sei sulla pagina 1di 54

Risk management Value management and engineering Cost management

Managing the design development within the risk, quality and cost constraints

Construction Project Management

Risk Management

What is risk management Why is it essential When it should be conducted Who is accountable and who are the contributors

Construction Project Management

Risk Management role


More comprehensive identification of risks
Generation of coherent management strategies Formulation of realistic plans and programmes

Contingencies which reflect identified risks Faster response to risks when they occur
Provides an audit trail for decisions taken Greater team awareness of risk management Increased team understanding of the project Construction Project Management

Risk Management Overview


Life is uncertain
Many things go wrong

Take Control Identify


Assess Mitigate Risk management plan in order to control the risk:
Why the risk is significant

Control

What is to be done to reduce it


When the risk will have its impact upon the project

Risk Management Steps

Who is responsible for resolving the risk How the reduction will be achieved

Construction Project Management

Risk identification information sources


Prompt List Table
Provides adequate scope Starting point of identifiable types of risk

Product description
The performance requirements of the building
Less detailed at the early stages of the project, more detailed as the design develops The drivers for the project (client needs and requirements)

Other PM outputs
Cost estimates, programme constraints, resource constraints, planning constraints, procurement options, etc.

Historical information
Lesson learnt from previous projects

Construction Project Management

Risk sources
Sources of Risk Client, gov, agencies Funding Definition of project Project organisation Design Local conditions Permanent plant supply Construction contractors Construction materials Construction labour Construction plant Logistics Estimating data Inflation Exchange Rates Force majeure Examples Bureaucratic delays, changes in local regulations Changes in Government funding policy, liaison between several funders Change in project scope Authority of project manager, involvement of outside bodies Adequacy to meet need, realism of design programme Local customs, weather windows Degree of novelty, damage or loss during transportation Experience, financial stability Excessive wastage, quality, delivery Industrial relations, multi-racial labour force Resale value, spares availability Remoteness, access to site Relevancy to specific project, availability Change in rate impact on loans, prices, wages Change in rate impact on prices Change of government, natural disaster

Construction Project Management

Prompt List Contents


Project definition
Concept and Design

Plans Financing arrangements


Project organisation Procurement contracts

Execution
Construction Client risks Construction Project Management

Risk identification tools


Checklists
Lists prepared from past experience showing potential risks (Prompt List)
Organised by source of risk such as internal sources, project context and other process outputs

Flowcharting
Such as Ishikawa diagram (Fishbone diagram) to show the cause and possible consequences.

Interviewing
Risk-oriented interviews with various stakeholders

Brainstorming
To fill in any gaps Distinguish a number of risk drivers in a particularly complex aspect of a project.

Construction Project Management

Identified risks information


Sources of risk
e.g. stakeholder actions, unreliable estimates etc. that may affect the project for better or worse.

Potential risk events


Discrete occurrences such as natural disasters.

Risk symptoms
e.g. poor morale may be an early warning signal of an impending schedule delay or cost overruns on early activities may be indicative of poor estimating.

Inputs to other processes


The risk identification process may indicate the need for further work in other processes in the project

Construction Project Management

Risk assessment tools


Risk Register Typical Headings:
Risk code (1) Summar y of risk (2) Timing Outline managem ent plan (4) Responsib le person (5) Probability of occurrence (6) Averag e impact (7) Minimu m impact (8) Most likely impact (9) Maximu m impact (10)

(3)

HML matrix:
L Impact H M L

Likelihood M

Construction Project Management

Risk Register Example


Risk Register Title of Risk Dependancie s (Ref to) Effect Time,Cost T,C T,C T,C T,C T,C T,C T,C T,C Allowance Average Development of Authority Requirements 1. D / Option Study proposals Change in scope of Works ( extension 2. CI etc) - Pre & Post Tender 3. 4. 5. S S T Asbestos removal Structural Upgrade/Repairs of existing buildings Amendments required to obtain planning approvals Delays in obtaining internal (MoD/DEO etc) approvals Upgrade existing drainage/services 107,000 71,100 18,000 90,000 500 30,400 3,600 45,600 Maximum 426,000 355,300 180,000 450,000 5,000 121,500 36,000 121,500 Allowance for PM team to develop detailed design solution for factors which only become apparent from detailed design development. Allowance fro the Authority to modify requirements within general scope of works identified in Project Brief, but beyond Option Study allowances. Minimal cost allowance as a result of the Authority identifying minimal asbestos content in existing buildings and only partial removal may be anticipated. Asbestos Minimal cost allowance made as the structure is believed to be well maintained and sound, but investigations may reveal additional requirements Authority considers planning to be minor issue therefore cost allowance low. Discussion with Planners will identify areas of concern. Delay in appointment of consultants and contractor may impact on costs. Should delay occur after appointment costs increase significantly. Ensure approvals available prior to award. Existing drainage should be adequate as it already caters for similar levels of use/numbers of occupants. Minor alterations only anticipated. Relocation of current occupants may be delayed due to many factors including lack of alternative accommodation. Any such delay will result in delay to the project, with resultant additional costs. Prompt relocation will minimise delays. Possibility that outside agents, ie stats and planners may cause delay to the project during some stage, which may impact on contractor's preliminary costs. Security alerts and prevention of activities to reduce disturbance of remaining and adjacent occupiers is likely to result in disruption to contractor's working practices. Wherever possible restrictions to be identified prior to entering into contract. "Act's of God" and the like unforseen activities which would incur additional cost for the Authority. Increase Costs = Increase from current costs to projection of Base Estimate plus other Risk Allowances x start TPI / Base TPI + half increase in TPI between start of construction and programmed completion, ie projection to mid point of contract Additional cost to the Authority to procure an alternative contractor to complete the works following receivership of the main contractor appointed under the contract. Tender lists to be drawn up taking into account financial status of Contractors. 11-Nov-11 Comments

6. CI 7. S

8. CI Delay in relocating existing facilities Delay to progress through agents outwith the contract (Statutory Authorities etc) Restrictions imposed on Contractors general working practice (e.g. Hours of 10. CI work / means of access / security alerts etc.) 9. T 11. CI Force Majeure Increase in RICS BCIS TPI for Current Quarter

T,C

30,400

121,500

T,C

12,200

121,500

T,C

2,000

100,000

12.

1,311,100

1,482,100

13. CO Receivership of Contractor

T,C

7,100

71,100

Construction Project Management

Risk Matrix Start


10 21, 35, 53, 65, 69, 75, 82, 73 11, 12, 13, 14, 16, 25, 29, 42, 45, 46, 48, 55, 59, 67 8, 28, 36 9, 10, 15, 2, 52, 78 47, 58, 68, 76, 77 39, 61 72

Impact

8 7 66

94

80

24 30

6 5
4 3 2 33, 41, 54, 63 18, 26, 38, 43, 50, 56 22, 23, 40, 44

5, 6 20 74
7, 70, 85

31

60

81

19, 32, 51, 62, 71, 82b, 83 1

27, 34, 57, 64

17, 49, 84

79

Likelihood
2 3 4 5 6 7 8 9 10

Construction Project Management

Response & Mitigation


Avoid
Where risks have serious consequence: eliminate, withdraw from or not become involved

Reduce
Reduce to acceptable level: e.g. redesign, more details (site investigations), different materials or methods.

Transfer
When accepting wouldnt give best value for money: sharing, outsource or insure

Accept
Retain and budget (contingency)

Construction Project Management

Risk Matrix Finish


10 69, 75, 14, 25, 82a 46, 55 9

8 7

42

80

Impact

6
5 4 3 2 20 74 85 9, 16b, 41, 48b 18, 26, 81 43, 50, 56 1 16a, 22, 27, 57 23, 44, 48a 2 3

84

79

10

Likelihood

Construction Project Management

Planning risk control


Risk Management Plan
The procedure to be used to manage risk throughout the project.
Identifying the result of the risk identification and risk quantification processes Actions: who covers what risk, how to maintain outputs, how to implement contingency plans, how reserves will be allocated.

Actual risk events


The project management team must recognise that they have occurred and implement the required response.

Additional risk identification:


As project develops, potential risk events not previously identified may surface.

Construction Project Management

Risk Management Plan e.g.


Risk Area Impacted PRM(P) Source Identified Risk Mitigation Strategy / Particular Issues Actions Response/Progress Action Owner Status, Target Date 1.2 Ongoing, Monthly. Consultants Integration of 1.2 Production of ITT the integrated activity Construction programmes. Programme with the BTS IT migration Programmes/ strategy. 1.2 Contact BTS IT 1.2 Initial meeting with Barclays BTS, Radbroke Hall. Migration staff Barclays update layout plan of equipment in Gloucester Computer Centre every week this will be copied to Capita. A communication link with the staff on the BTS Migration project has been established. More information is required e.g. streaming of IT kit and position of PDUs. This information is required before the appointment of the Principal Contractor (target date of 24 Jan 00 for appointment of PC) Target Date for Appointment of Principal Contractor now revised to 28 Jan 00. A meeting has been organised with BTS for 1 Mar 00 to resolve the streaming issue. The meeting on 1 Mar 00 defined an approach to streaming. The proposed sequence of works defined by Capita is based on assumptions derived from the agreed approach to streaming. Changes may impact the project programme. A monthly forum will continue. A meeting, planned for 27 Apr 00, will bring together GPS, How ES and BTS. Hows detailed construction programme will be presented to BTS and over-layed on their programmes to determine if any of the tasks clash with planned BTS operations. IT IS EXPECTED THAT CLASHES WILL BE INEVITABLE THESE WILL HAVE TO BE CAREFULLY MANAGED! How ES Draft contract programme issued 5 May 00 How ES Final contract programme issued 26 May 00 further copies awaited for distribution Paul Craven (BTS) has issued definitive information defining the computer hall layout and power arrangements. This information has been distributed to the project in letter from Intec dated 25 May 00. 1.2 BuroFour Barclays GPS (Action transferred 8 Dec 99)

Construction Project Management

Risk control process


Take corrective action of identified risks as planned
Workaround unplanned risk events and take corrective actions

Develop response to additional risks:


If the risk event was not anticipated, or the effect is greater than anticipated, the planned response may be inadequate. In these circumstances, it will be necessary to repeat the risk response process or even the risk identification process.

Updates risk management plan


Risk events occur or fail to occur
Actual risk event effects are evaluated, estimates of probabilities and value Other aspects of the risk management plan should be updated.

Construction Project Management

Input

Process

Output

Client Input

Brainstorm Hazards

Risk Management Process Cycles: The first cycle is at the project initiation and concept design stage.

Risk Identification Project Team Input Risk Assessment Quantify Rank HML matrix Risk Register & Plan Risk Register

Ongoing maintenance up to feasibility stage. During feasibility stage, ongoing development during initial stages of scheme design. Ongoing Risk Management activities during detailed design stages.

Control Measures Identification

Risk Mitigation

Remove Transfer Reduce Accept

Review Mitigation

Is Risk acceptable No

Yes

Risk Register & Plan

Control Measures Implementation

Review Options

Monitor

Construction Project Management

Update Risk Register

Risk Register & Plan

Qualitative/Quantitative Analysis
Risk Analysis can be split into 2 separate phases:
Qualitative Identification Initial Risk Assessment Quantitative Estimates of uncertainty for cost & time Probabilistic combination

Qualitative risk analysis tools e.g.


Checklists Questionnaires Brainstorming

Quantitative risk analysis tools e.g.


Probabilistic Monte Carlo Sensitivity analysis Decision Trees

Qualitative risk analysis is sufficient for most projects

Construction Project Management

Risk management strategies


STRATEGY
Modify objectives Avoid Prevent Mitigate

METHOD OF HANDLING UNCERTAINTY


Reduce or raise performance targets, change trade-offs between multiple objectives Plan to avoid specified sources of uncertainty Change the probability of occurrence Modify the impact of a source of uncertainty

Develop Contingency Set aside resources to provide a reactive ability to cope with plans events Keep options open Delay choices and commitment, choose versatile options Monitor Accept Collect and update data about probabilities of occurrence, anticipated impacts, and additional risks Accept risk exposure, but do nothing about it

Remain unaware

Ignore the possibility of risk exposure, take no action to identify or manage risk

Construction Project Management

Risk management strategies for the control of time


Pre-engineer the project
work out sequences, methods and timing agree with the designer the most effective methods and details innovate to gain an improved product or process decide work packages and design the interface boundaries

develop the logistics plan

Involve the trade contractors early Fast build not Fast Track

Interface management
Set realistic, understandable and achievable dates Construction Project Management

Good practice
Get the constructor involved as early as possible
designers and constructors use their complimentary skills to provide solutions that can be built efficiently and economically.

Chose the procurement route carefully


Risk versus flexibility.

Build an effective team


Common understanding of the objectives to achieve the goals even though there may be unexpected events.

Undertake risk analysis


Identify the risks that would delay the project.

Rate the likelihood of each occurring & rank their importance.


Proactively manage the most important risks & update each month.

Construction Project Management

Summary
Risk Management Process to enable the analysis and response to risks associated with a project Why is it used Identification Assessment Mitigation Response/Management

Increased understanding of project and risk to increase probability of achieving time, cost, performance objectives Throughout project cycle Qualitative Analysis Quantitative Analysis

When is it carried out How is it done

Construction Project Management

Value Management
Value planning
Value engineering Value reviewing

Construction Project Management

Value Management

Value management is defined as: a structured approach to defining what value means to a client in meeting a perceived need by establishing a clear consensus about the project objectives and how they can be achieved Connaughton and Green, 1996

Construction Project Management

Value Management aims


To help the Client to revalidate what they want
Look for flexibility / headroom for future expansion

Team building and understand each stakeholders major issues


To enable the voice of the client to carry through the project

Construction Project Management

Value issues
Definition
value (judgement of worth; hence positive and negative)

values (criteria for judging value, subjective)

Determine:
key functional requirements

Identifying:
alternative solutions (speculation)

Examine for each alternative:


Cost Value

Enable best value selection

Construction Project Management

Value Management stages


addresses the value process during
concept

definition
implementation operation

enhances project value throughout life of facility embraces the whole value process including
value planning value engineering value reviewing

Construction Project Management

Value Management stages


Feedback
Value Planning VP (VM1 & VM2) Confirmation of clients objectives

Feedback
Value Engineering VE (VE1 & VE2)

Feedback
Value Reviewing VR
Monitoring the value process Correction of defects Feedback into subsequent areas of work

Detailed functional analysis Confirmation of functional requirements


Ranking and prioritizing Preferred systems

Review of every system solution Preferred elements Buildability issues VE proposal & final report Implementation & follow up

Construction Project Management

Value Planning VM1 (Concept)


Input
Clients objectives

Approach
VM1 Workshop

Output
Framework for debate

Analysed objectives

Calculation

Information needs

Functional requirement

Construction Project Management

Value Planning VM2 (Scheme)


Input
Functional requirements

Approach
VM2 Workshop

Output
Framework for debate

Analysed requirements

Calculation

Information needs

Preferred Systems

Construction Project Management

Value Engineering VE1 (Detailed design)


Input
Preferred systems

Approach
VE1 Workshop

Output
Framework for debate

Analysed Systems

Calculation

Information needs

Preferred Elements

Construction Project Management

Value Engineering VE2 (Construction)


Input
Preferred elements

Approach
VE2 Workshop

Output
Framework for debate

Analysed elements

Calculation

Information needs

Buildability
requirements

Construction Project Management

VM workshop goals
Identify and prioritise project needs and objectives
Establish and evaluate alternatives

Optimise programme Search for unnecessary cost in implementation phase Search for unnecessary cost to business in operation phase
Restate the business risks to the client, the operation risks and the project risks.

Construction Project Management

VM workshop benefits
With VM
Without VM

More efficient design development


Reduction in costs Reduction in development time Increase in productivity

Decisions

Improved product quality and reliability


Concept Definition Implementation Operation

Greater client satisfaction

Time

Construction Project Management

Notes for VM workshop


Everybody should contribute
Off the wall discussions

The focus by end of workshop will probably be on the 10 most important issues in terms of value for money

Construction Project Management

Cost Management
Early Cost Advice / Preliminary Estimate
Cost planning / Cost control Change management and control

Construction Project Management

Cost management objectives


Achieving value for money
Sensible distribution of cost

Keeping expenditure within budget Checking costs as design develops


Managing design risks and contingencies Presenting costs in a logical and orderly way to the client as the design develops Audit trail of decision making process

Construction Project Management

Advantages & Disadvantages


Advantages:
Tender sum equates estimate

No abortive redesign at the tender stage


Balanced design leads to cost effectiveness

Cost considerations are integral part of the process


A smoother running of the project

Benchmarking

Disadvantages:
Restricts designers thought development process Time consuming Additional fees

Construction Project Management

Cost Management process in relation to project stages


Inception Early cost advice Feasibility Studies Preliminary estimate

Concept Design

Preliminary cost plan

Cost planning

Outline Design

The cost plan

Project Stages

Scheme Design Cost control of alternative design solutions Detailed Design

Cost Management Process


Cost control

Procurement (Bills of Quantities) STCs Detailed Design (Production information)

Tender reconciliation

Post-contract cost control Construction

Construction Project Management

Early cost advice


Value Management

Design risks identification

POTENTIAL VARIATIONS

COST FORECAST

Why early cost advice?


buildings cost a lot of MONEY
building client must know his likely financial commitment before extensive design work is undertaken.

QS gives advice on the probable cost of the project Construction Project Management

Cost estimate
Based on:
Site preliminary investigations

Important design decisions such as height and shape


Alternatives considered

Outline proposals

Determine the cost targets for different building main systems

Approved cost target


Cost target can be also:
Fixed restricted design solutions Based on similar projects update considering inflation, regional costs of labour materials etc.

Construction Project Management

Estimating techniques
The choice of method depends on the availability of:

Information
Time

Unit method Floor area method


Storey enclosure method Elemental cost (designing to cost)

Comparative cost (costing a design)

Construction Project Management

The Cost Plan


Towards the end of the outline design stage or early scheme design stage Develops as the design develops The individual elements targets = Total target cost

Or range of probable elements targets = average agreed total cost


Required information:
Drawings
Specifications Contractual arrangement Cost analysis from other projects

Construction Project Management

Cost plan considerations


Pricing conditions
Inflation

Changes in market conditions

Quantity considerations
Approximate quantities

Proportion
Inspection

Quality considerations
For particular important elements of the project

Construction Project Management

Design risks management (level of customization)


Cost planning
Concept Design Estimate

Contingency

Scheme Design

Cost control
Estimate
Contingency

Detailed Design

Estimate

Contingency

Construction Project Management

Cost control and design development


Design proposal

Agreed cost plan

Change proposal

+/Variations Change Order

Revised design

Revised cost plan

Construction Project Management

Response to design change


Redesign the element
Approve change and amend cost plan

Approve change and reduce other elements costs


Never assume that you might get an element of design cheaper than what is expected

Construction Project Management

Tender reconciliation

Target cost of tender

+/=
Final cost of tender

Tender

Construction Project Management

Design Change initiation


Change can be initiated by: client, designers, contractors:
Request for Instructions/Information (RFI)

Request for Change (RFC) Non Conformance Report (NCR) fix by contractor
Concessions approval by client Variations

Modifications
Extras

Construction Project Management

Change Management
CHANGE REQUEST

REVIEW IMPACT OF CHANGE DESIGN Yes


Approval
RAISE CHANGE ORDER

CONSTRUCTION

No

REJECTE CHANGE

Construction Project Management

Cost of change

Cost reduction potential Owner

Cost to change

Designers Constructors Users


Concept

Time

Definition

Implementation

Operation

Construction Project Management

Financial assurance requirements


The client is well funded and the project is properly funded All STCs are well founded and financially stable The STCs only submit well documented claims for payment Valuations include the full amount of the work done Variations are valued in full and are included in the valuations Payments are made in accordance with the contract terms

Construction Project Management

Final accounts
Financial control process is kept up to date
All variations agreed before implementation

Final payment claim from STCs is received on time Final account and payment is made immediately
No need for STCs to cover the outstanding income by borrowing A one month target from end of the work to payment of the final account should be the norm

Construction Project Management

Potrebbero piacerti anche