Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Managing the design development within the risk, quality and cost constraints
Risk Management
What is risk management Why is it essential When it should be conducted Who is accountable and who are the contributors
Contingencies which reflect identified risks Faster response to risks when they occur
Provides an audit trail for decisions taken Greater team awareness of risk management Increased team understanding of the project Construction Project Management
Control
Who is responsible for resolving the risk How the reduction will be achieved
Product description
The performance requirements of the building
Less detailed at the early stages of the project, more detailed as the design develops The drivers for the project (client needs and requirements)
Other PM outputs
Cost estimates, programme constraints, resource constraints, planning constraints, procurement options, etc.
Historical information
Lesson learnt from previous projects
Risk sources
Sources of Risk Client, gov, agencies Funding Definition of project Project organisation Design Local conditions Permanent plant supply Construction contractors Construction materials Construction labour Construction plant Logistics Estimating data Inflation Exchange Rates Force majeure Examples Bureaucratic delays, changes in local regulations Changes in Government funding policy, liaison between several funders Change in project scope Authority of project manager, involvement of outside bodies Adequacy to meet need, realism of design programme Local customs, weather windows Degree of novelty, damage or loss during transportation Experience, financial stability Excessive wastage, quality, delivery Industrial relations, multi-racial labour force Resale value, spares availability Remoteness, access to site Relevancy to specific project, availability Change in rate impact on loans, prices, wages Change in rate impact on prices Change of government, natural disaster
Execution
Construction Client risks Construction Project Management
Flowcharting
Such as Ishikawa diagram (Fishbone diagram) to show the cause and possible consequences.
Interviewing
Risk-oriented interviews with various stakeholders
Brainstorming
To fill in any gaps Distinguish a number of risk drivers in a particularly complex aspect of a project.
Risk symptoms
e.g. poor morale may be an early warning signal of an impending schedule delay or cost overruns on early activities may be indicative of poor estimating.
(3)
HML matrix:
L Impact H M L
Likelihood M
6. CI 7. S
8. CI Delay in relocating existing facilities Delay to progress through agents outwith the contract (Statutory Authorities etc) Restrictions imposed on Contractors general working practice (e.g. Hours of 10. CI work / means of access / security alerts etc.) 9. T 11. CI Force Majeure Increase in RICS BCIS TPI for Current Quarter
T,C
30,400
121,500
T,C
12,200
121,500
T,C
2,000
100,000
12.
1,311,100
1,482,100
T,C
7,100
71,100
Impact
8 7 66
94
80
24 30
6 5
4 3 2 33, 41, 54, 63 18, 26, 38, 43, 50, 56 22, 23, 40, 44
5, 6 20 74
7, 70, 85
31
60
81
17, 49, 84
79
Likelihood
2 3 4 5 6 7 8 9 10
Reduce
Reduce to acceptable level: e.g. redesign, more details (site investigations), different materials or methods.
Transfer
When accepting wouldnt give best value for money: sharing, outsource or insure
Accept
Retain and budget (contingency)
8 7
42
80
Impact
6
5 4 3 2 20 74 85 9, 16b, 41, 48b 18, 26, 81 43, 50, 56 1 16a, 22, 27, 57 23, 44, 48a 2 3
84
79
10
Likelihood
Input
Process
Output
Client Input
Brainstorm Hazards
Risk Management Process Cycles: The first cycle is at the project initiation and concept design stage.
Risk Identification Project Team Input Risk Assessment Quantify Rank HML matrix Risk Register & Plan Risk Register
Ongoing maintenance up to feasibility stage. During feasibility stage, ongoing development during initial stages of scheme design. Ongoing Risk Management activities during detailed design stages.
Risk Mitigation
Review Mitigation
Is Risk acceptable No
Yes
Review Options
Monitor
Qualitative/Quantitative Analysis
Risk Analysis can be split into 2 separate phases:
Qualitative Identification Initial Risk Assessment Quantitative Estimates of uncertainty for cost & time Probabilistic combination
Develop Contingency Set aside resources to provide a reactive ability to cope with plans events Keep options open Delay choices and commitment, choose versatile options Monitor Accept Collect and update data about probabilities of occurrence, anticipated impacts, and additional risks Accept risk exposure, but do nothing about it
Remain unaware
Ignore the possibility of risk exposure, take no action to identify or manage risk
Involve the trade contractors early Fast build not Fast Track
Interface management
Set realistic, understandable and achievable dates Construction Project Management
Good practice
Get the constructor involved as early as possible
designers and constructors use their complimentary skills to provide solutions that can be built efficiently and economically.
Summary
Risk Management Process to enable the analysis and response to risks associated with a project Why is it used Identification Assessment Mitigation Response/Management
Increased understanding of project and risk to increase probability of achieving time, cost, performance objectives Throughout project cycle Qualitative Analysis Quantitative Analysis
Value Management
Value planning
Value engineering Value reviewing
Value Management
Value management is defined as: a structured approach to defining what value means to a client in meeting a perceived need by establishing a clear consensus about the project objectives and how they can be achieved Connaughton and Green, 1996
Value issues
Definition
value (judgement of worth; hence positive and negative)
Determine:
key functional requirements
Identifying:
alternative solutions (speculation)
definition
implementation operation
enhances project value throughout life of facility embraces the whole value process including
value planning value engineering value reviewing
Feedback
Value Engineering VE (VE1 & VE2)
Feedback
Value Reviewing VR
Monitoring the value process Correction of defects Feedback into subsequent areas of work
Review of every system solution Preferred elements Buildability issues VE proposal & final report Implementation & follow up
Approach
VM1 Workshop
Output
Framework for debate
Analysed objectives
Calculation
Information needs
Functional requirement
Approach
VM2 Workshop
Output
Framework for debate
Analysed requirements
Calculation
Information needs
Preferred Systems
Approach
VE1 Workshop
Output
Framework for debate
Analysed Systems
Calculation
Information needs
Preferred Elements
Approach
VE2 Workshop
Output
Framework for debate
Analysed elements
Calculation
Information needs
Buildability
requirements
VM workshop goals
Identify and prioritise project needs and objectives
Establish and evaluate alternatives
Optimise programme Search for unnecessary cost in implementation phase Search for unnecessary cost to business in operation phase
Restate the business risks to the client, the operation risks and the project risks.
VM workshop benefits
With VM
Without VM
Decisions
Time
The focus by end of workshop will probably be on the 10 most important issues in terms of value for money
Cost Management
Early Cost Advice / Preliminary Estimate
Cost planning / Cost control Change management and control
Benchmarking
Disadvantages:
Restricts designers thought development process Time consuming Additional fees
Concept Design
Cost planning
Outline Design
Project Stages
Tender reconciliation
POTENTIAL VARIATIONS
COST FORECAST
QS gives advice on the probable cost of the project Construction Project Management
Cost estimate
Based on:
Site preliminary investigations
Outline proposals
Estimating techniques
The choice of method depends on the availability of:
Information
Time
Quantity considerations
Approximate quantities
Proportion
Inspection
Quality considerations
For particular important elements of the project
Contingency
Scheme Design
Cost control
Estimate
Contingency
Detailed Design
Estimate
Contingency
Change proposal
Revised design
Tender reconciliation
+/=
Final cost of tender
Tender
Request for Change (RFC) Non Conformance Report (NCR) fix by contractor
Concessions approval by client Variations
Modifications
Extras
Change Management
CHANGE REQUEST
CONSTRUCTION
No
REJECTE CHANGE
Cost of change
Cost to change
Time
Definition
Implementation
Operation
Final accounts
Financial control process is kept up to date
All variations agreed before implementation
Final payment claim from STCs is received on time Final account and payment is made immediately
No need for STCs to cover the outstanding income by borrowing A one month target from end of the work to payment of the final account should be the norm