Sei sulla pagina 1di 2

GE Global Research JFWTC, Bangalore

Mobile Crane Hoist Operations - Lift Plan


Date: 27/0108/2014 Prepared By: Ratheesh Competent Supervisor/Manager Approval:Sandeep GEGR Site Safety Engineer Approval:Kevin

EMERGENCY PHONE #GEGR Site Phone 72222 / 75555


Contact Number 9886061541 Contact Number 9741111387 Contact Number 9740192112 Cell Phone 9845382222 / 9980875555 GEGR Site Radio BASE Crane type& Location : Pick and Carry / XX T

Project Work Area Evaluation


Yes No N/A

Task/Job Evaluation
Yes No N/A

Does the crane have sufficient SWL capacity and travel capabilities for the intended lift? Have you walked the project work area? Have Evacuation Routes and emergencyresponse equipment been identified? Emergency Shut off switch Fire Extinguisher&Call Point Nearest Phone First Aid Box Is the work location in a high traffic or common area? If yes, delineate your work area with Danger or caution rope, signs, cones or boundary tape. Have employees of the area been notified of the lifting operation? Has an adequate laydown/staging area been identified/designated?

Has three part communication been established? Has the Lifting team been identified? Are the rigging equipment in acceptable condition? all rigging equipment have proper ID marks all riggingequipment have known WLL/SWL all rigging equipment been inspected Are the rigging equipment being used as per design/manufacturer specs?

Has the item to be lifted been evaluated for sharp edges or other circumstances that may cause rigging equipment to be damaged or slip? Are the attachment points on the object to be lifted designed for lifting? Will there be any side or angular loading?

Mandatory Personal Protective Equipment


Safety Helmet /Hard HatSafety Glasses w/Side Shields Safety Shoes Long Pants

Additional PPE based on Task (check all that apply)


Hearing Protection Dust Mask Tyvek Coveralls Hi-Visibility VestWork GlovesPersonal Fall Arrest System (PFAS) Other __None________________________________

General Rigging and Lifting Reminders


Once rigging equipment has been installed, lift object slowly to ensure level lift, adjust as needed Use tag lines and keep a 45 SAFETY ZONE under the suspended load. (Safety Zone = Height of the bottom of load off ground) Avoid using hands to maneuver load until load is in final placement position. Hands and Feet shall NEVER pass below suspended load If using more than two slings, determine required capacity by assuming only two slings are handling the load and the additional slings are providing stability

Potential Hazard Checklist


Yes No Yes No Yes No Yes No Yes No

Pinch Points High Noise

Falling Objects Defective Tools

Slips and Trips Bump Hazards

Cold Stress Heat Stress

Manual Lifting

Estimated Rated Capacity based on Single-Leg Hitch for Wire Rope and Synthetic Web Slings Vertical Choker (120) 90 Vertical Basket

Estimated Rated Capacity based on Two-Leg or Single Basket Hitch for Wire Rope and Synthetic Web Slings
Vertical (90) 100% each leg, or 200% for basket 60 45 30 Endless Loop

100%

80%

200%

85%

70%

50%

100%

Rigging Best Practices

Rigging Sketch

Reeving through connections to load increases load on connection fittings by 2x DO NOT REEVE

Pick & Carry Crane /Mobile


SWL -2 TON at 67

Width-1800 DO NOT SIDE, BACK, OR TIP LOAD HOOKS Loads shall be applied in the plane of the eye Shouldered lift eyes are preferred Consult manufacturer for angular capacity reductions Shackle pins should fit freely without bindig Avoid side loading Do not bunch slings

40

67
Self Weight0. 8TON Height- 2000

Crane ID & Capacity Weight of Object/Load # of Shackles & WLL # of Slings & WLL # of Eyebolts/Swivel-Eyes & WLL Estimated loop angle Boom angle

Hydra crane 10 T@75 0.8T 2T 2 nos. & 6 T Nil 40 (Included) 67

Sling Tension

Pre-Lift Acknowledgement
Lift Operator/Lift team Member Lift Operator/Lift team Member Lift Operator/Lift team Member Lift Operator/Lift team Member

GE internal for internal distribution only

Potrebbero piacerti anche