Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
Required fields are: a) Resource estimation chart b) Scheduling through schedule network diagram c) Work Break down structure (Using major deliverables) (5 Marks) (5 Marks) (5 Marks)
ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66
WBS
Task Name 1 Contracts 1.1 1.2 1.3 2.1 2.2 2.3 2.4 2.5 2.6 2.7 3.1 3.2 3.3 3.4 3.5 Supply Construction Agreement Supply Contract Plans Supply Contract Site Plan Review & Finalize Plans Review & Finalize Specifications Review & Finalize Site Plan Print Construction Drawings Approve Revised Plans Approve Revised Specifications Approve Revised Site Plan Make Copies of Plans Make Copies of Specifications Distribute Plans & Specifications Receive Bids Review Bids Sales Construction Execute Subcontractor Agreements File Grading Permit Application File Building Permit Application Post Lot Identification Meet Sediment Control Inspector Walk Lot w/ Owner Install Construction Entrance Install Sediment Controls Sediment Control Insp. Grading Permit Issued Area Permit Process Building Permit Approved Pay Permit Fees and Excise Taxes Building Permit Issued Clear Lot Strip Topsoil & Stockpile Stake Lot for Excavation Rough grade lot Excavate for foundation Layout footings Dig Footings & Install Reinforcing Footing Inspection Pour footings Pin Footings Stock Block, Mortar, Sand Build Block Foundation Fill Block Cores w/ Concrete Construction of Boudary wall Constrcution of Bedroom 1 Constrcution of Bathroom 1 Constrcution of Bedroom 2 Constrcution of Bathroom 2 Constrcution of Lounge Constrcution of Dinning Room Constrcution of Bathroom 3 Constrcution of Guest room Constrcution of Bathroom 4 Constrcution of Kitchen Selection of paints Paint Steel Delivery Roof structure construction Waterproofing and Drain Tile
Duration
Start
Finish
Predecessors
Resource Names
No De De De De De Jan Jan Jan Jan Feb Feb Feb Feb Mar Mar Mar Mar Mar Apr Apr Apr Apr Ma Ma Ma Ma Jun Jun Jun Jun Jun Jul Jul Jul Jul Au Au Au Au Se Se Se Se Se Oct Oct Oct Oct No No No No De De De De De Jan J
3 days Mon 11/25/13 Wed 11/27/13 1 day 1 day 32 days 20 days 5 days 2 days 2 days 2 days 34 days 3 days 2 days 1 day 20 days 5 days 5 days 5 days 5 days 22 days 1 day 3 days 1 day 1 day 1 day 1 day 2 days 1 day 1 day 10 days 1 day 3 days 3 days 20 days 3 days 5 days 7 days 5 days 5 days 200.13 days 3 days 5 days 1 day 1 day 1 day 1 day 20 days 7 days 7 days 10 days 5 days 10 days 5 days 10 days 10 days 5 days 10 days 5 days 10 days 3 days 20 days 3 days 30 days Mon 11/25/13 Tue 11/26/13 Mon 11/25/13 Mon 11/25/13 Mon 12/30/13 Mon 1/6/14 Mon 1/6/14 Mon 1/6/14 Wed 1/8/14 Wed 1/8/14 Wed 1/8/14 Mon 1/13/14 Tue 1/14/14 Tue 2/11/14 Tue 2/11/14 Tue 2/11/14 Tue 2/18/14 Wed 1/8/14 Wed 1/8/14 Wed 1/8/14 Mon 1/13/14 Tue 1/14/14 Wed 1/15/14 Thu 1/16/14 Thu 1/16/14 Mon 1/20/14 Tue 1/21/14 Mon 1/13/14 Mon 1/27/14 Thu 1/30/14 Tue 2/4/14 Wed 1/22/14 Wed 1/22/14 Mon 1/27/14 Mon 1/27/14 Wed 2/5/14 Wed 2/12/14 Wed 2/19/14 Wed 2/19/14 Mon 2/24/14 Mon 3/3/14 Tue 3/4/14 Wed 3/5/14 Thu 3/6/14 Fri 3/7/14 Fri 4/4/14 Fri 4/25/14 Tue 5/6/14 Tue 5/20/14 Tue 5/27/14 Tue 6/10/14 Tue 6/17/14 Tue 7/1/14 Tue 7/15/14 Tue 7/22/14 Tue 8/5/14 Tue 8/12/14 Tue 8/26/14 Fri 8/29/14 Fri 9/26/14 Wed 10/1/14 Mon 11/25/13 Tue 11/26/13 2 Wed 11/27/13 2 Tue 1/7/14 Tue 12/24/13 3 Fri 12/20/13 Fri 12/27/13 4,6 Fri 1/3/14 6,7,8 Tue 1/7/14 9 Tue 1/7/14 9 Tue 1/7/14 9 Mon 2/24/14 Fri 1/10/14 10 Thu 1/9/14 11 Mon 1/13/14 14,15 Mon 2/10/14 16 Mon 2/17/14 Mon 2/17/14 17 Mon 2/17/14 17 Mon 2/24/14 19 Thu 2/6/14 Wed 1/8/14 12 Fri 1/10/14 10,11,12 Mon 1/13/14 23,24 Tue 1/14/14 23FS+2 days,25 Wed 1/15/14 26 Thu 1/16/14 26,27 Fri 1/17/14 26,27 Mon 1/20/14 28,29 Tue 1/21/14 30 Fri 1/24/14 24 Mon 1/27/14 32,31 Mon 2/3/14 33FS+2 days Thu 2/6/14 34 Tue 2/18/14 Fri 1/24/14 31 Fri 1/31/14 37 Tue 2/4/14 37 Tue 2/11/14 37,39 Tue 2/18/14 33,39,37,40 Tue 11/25/14 Fri 2/21/14 41 Fri 2/28/14 43 Mon 3/3/14 44 Tue 3/4/14 45 Wed 3/5/14 46 Thu 3/6/14 47 Thu 4/3/14 47,48 Mon 4/14/14 49 Tue 5/6/14 50 Tue 5/20/14 51 Tue 5/27/14 52 Tue 6/10/14 53 Tue 6/17/14 54 Tue 7/1/14 55 Tue 7/15/14 56 Tue 7/22/14 57 Tue 8/5/14 58 Tue 8/12/14 59 Tue 8/26/14 60 Fri 8/29/14 61 Fri 9/26/14 62 Wed 10/1/14 63 Wed 11/12/14 64 Tue 11/25/14 65 Concrete Subcontracto Concrete Subcontracto Building Inspector Concrete Subcontracto Civil Engineer Block Masonry Subcon Block Masonry Subcon Block Masonry Subcon Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Home Decorator Home Decorator Steel Supplier Builder Waterproofing Subcon Concrete Subcontractor Concrete Subcontractor Building Inspector Concrete Subcontractor Civil Engineer Block Masonry Subcontractor Block Masonry Subcontractor Block Masonry Subcontractor Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Home Decorator Home Decorator Steel Supplier Builder Waterproofing Subcontractor Excavation Subcontrac Excavation Subcontrac Civil Engineer Excavation Subcontrac Excavation Subcontrac Excavation Subcontractor Excavation Subcontractor Civil Engineer Excavation Subcontractor Excavation Subcontractor Builder Builder Builder Builder Builder Excavation Subcontrac Excavation Subcontrac Sediment Control Inspe Sediment Control Inspe Department of Permits Department of Permits Builder Department of Permits Builder Builder Builder Builder Builder Excavation Subcontractor Excavation Subcontractor Sediment Control Inspector Sediment Control Inspector Department of Permits & Licenses Department of Permits & Licenses Builder Department of Permits & Licenses Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Client Client Client Builder Builder Builder Builder Client Client Client Builder Builder Builder Builder Builder Builder
3.5.1 3.5.2 3.6 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 4.12 4.13 5.1 5.2 5.3 5.4 5.5 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 6.21 6.22 6.23 6.24
5 Site Work
6 Foundation
Task
Split
Progress
Milestone
Summary Page 1
Project Summary
External Tasks
External Milestone
Deadline
Contracts
Site Work
Foundation
Clear Lot
Layout footings
Receive Bids
Review Bids
Sales Construction
Constrcution Rooms
Paints
Contracts
Start: 11/25/13 Finish: 11/27/13 Comp: 0% ID: 1 Dur: 3 days
Network Diagram
Print Construction Drawings
Start: 12/30/13 Finish: 1/3/14 Res: Builder ID: 9 Dur: 5 days
Receive Bids
Start: 1/14/14 Finish: 2/10/14 Res: Builder ID: 17 Dur: 20 days
Review Bids
Start: 2/11/14 Finish: 2/17/14 Comp: 0% ID: 18 Dur: 5 days
Sales
Start: 2/11/14 Finish: 2/17/14 Res: Builder ID: 19 Dur: 5 days
Construction
Start: 2/11/14 Finish: 2/17/14 Res: Builder ID: 20 Dur: 5 days
Excavation Subcontractor
Excavation Subcontractor
Site Work
Start: 1/22/14 Finish: 2/18/14 Comp: 0% ID: 36 Dur: 20 days
Clear Lot
Start: 1/22/14 Finish: 1/24/14 Res: ID: 37 Dur: 3 days
Excavation Subcontractor
Excavation Subcontractor
Civil Engineer
Excavation Subcontractor
Excavation Subcontractor
Foundation
Start: 2/19/14 Finish: 11/25/14 Comp: 0% ID: 42 Dur: 200.13 days
Layout footings
Start: 2/19/14 Finish: 2/21/14 Res: ID: 43 Dur: 3 days
Footing Inspection
Start: 3/3/14 Finish: 3/3/14 Res: ID: 45 Dur: 1 day
Pour footings
Start: 3/4/14 Finish: 3/4/14 Res: ID: 46 Dur: 1 day
Pin Footings
Start: 3/5/14 Finish: 3/5/14 Res: ID: 47 Dur: 1 day
Concrete Subcontractor
Concrete Subcontractor
Building Inspector
Concrete Subcontractor
Civil Engineer
Constrcution of Bedroom 1
Start: 5/6/14 Finish: 5/20/14 Res: Builder ID: 52 Dur: 10 days
Constrcution of Bathroom 1
Start: 5/20/14 Finish: 5/27/14 Res: Builder ID: 53 Dur: 5 days
Constrcution of Bedroom 2
Start: 5/27/14 Finish: 6/10/14 Res: Builder ID: 54 Dur: 10 days
Constrcution of Bathroom 2
Start: 6/10/14 Finish: 6/17/14 Res: Builder ID: 55 Dur: 5 days
Constrcution of Lounge
Start: 6/17/14 Finish: 7/1/14 Res: Builder ID: 56 Dur: 10 days
Constrcution of Bathroom 3
Start: 7/15/14 Finish: 7/22/14 Res: Builder ID: 58 Dur: 5 days
Constrcution of Bathroom 4
Start: 8/5/14 Finish: 8/12/14 Res: Builder ID: 60 Dur: 5 days
Constrcution of Kitchen
Start: 8/12/14 Finish: 8/26/14 Res: Builder ID: 61 Dur: 10 days
Selection of paints
Start: 8/26/14 Finish: 8/29/14 Res: ID: 62 Dur: 3 days
Paint
Start: 8/29/14 Finish: 9/26/14 Res: ID: 63 Dur: 20 days
Steel Delivery
Start: 9/26/14 Finish: 10/1/14 Res: ID: 64 Dur: 3 days
Home Decorator
Home Decorator
Steel Supplier
Waterproofing Subcontractor