Project Monitoring and Control PRM704 Assignment No.

1 Submitted by: Mudasar Shehzad Enrolment Number: Sp13rpm229


Consider the construction of the Home project using any of the following software I. II. MS Project (Preferably) MS Excel

Required fields are: a) Resource estimation chart b) Scheduling through schedule network diagram c) Work Break down structure (Using major deliverables) (5 Marks) (5 Marks) (5 Marks)

Project constraints are:


1. Scope: Single storey, 2 bedrooms, 1 lounge, 1 guest room, 1 dining 2. Cost: 20 Million Rupees 3. Schedule: 1 year

ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66

WBS

Task Name 1 Contracts 1.1 1.2 1.3 2.1 2.2 2.3 2.4 2.5 2.6 2.7 3.1 3.2 3.3 3.4 3.5 Supply Construction Agreement Supply Contract Plans Supply Contract Site Plan Review & Finalize Plans Review & Finalize Specifications Review & Finalize Site Plan Print Construction Drawings Approve Revised Plans Approve Revised Specifications Approve Revised Site Plan Make Copies of Plans Make Copies of Specifications Distribute Plans & Specifications Receive Bids Review Bids Sales Construction Execute Subcontractor Agreements File Grading Permit Application File Building Permit Application Post Lot Identification Meet Sediment Control Inspector Walk Lot w/ Owner Install Construction Entrance Install Sediment Controls Sediment Control Insp. Grading Permit Issued Area Permit Process Building Permit Approved Pay Permit Fees and Excise Taxes Building Permit Issued Clear Lot Strip Topsoil & Stockpile Stake Lot for Excavation Rough grade lot Excavate for foundation Layout footings Dig Footings & Install Reinforcing Footing Inspection Pour footings Pin Footings Stock Block, Mortar, Sand Build Block Foundation Fill Block Cores w/ Concrete Construction of Boudary wall Constrcution of Bedroom 1 Constrcution of Bathroom 1 Constrcution of Bedroom 2 Constrcution of Bathroom 2 Constrcution of Lounge Constrcution of Dinning Room Constrcution of Bathroom 3 Constrcution of Guest room Constrcution of Bathroom 4 Constrcution of Kitchen Selection of paints Paint Steel Delivery Roof structure construction Waterproofing and Drain Tile

Duration

Start

Finish

Predecessors

Resource Names

No De De De De De Jan Jan Jan Jan Feb Feb Feb Feb Mar Mar Mar Mar Mar Apr Apr Apr Apr Ma Ma Ma Ma Jun Jun Jun Jun Jun Jul Jul Jul Jul Au Au Au Au Se Se Se Se Se Oct Oct Oct Oct No No No No De De De De De Jan J

3 days Mon 11/25/13 Wed 11/27/13 1 day 1 day 32 days 20 days 5 days 2 days 2 days 2 days 34 days 3 days 2 days 1 day 20 days 5 days 5 days 5 days 5 days 22 days 1 day 3 days 1 day 1 day 1 day 1 day 2 days 1 day 1 day 10 days 1 day 3 days 3 days 20 days 3 days 5 days 7 days 5 days 5 days 200.13 days 3 days 5 days 1 day 1 day 1 day 1 day 20 days 7 days 7 days 10 days 5 days 10 days 5 days 10 days 10 days 5 days 10 days 5 days 10 days 3 days 20 days 3 days 30 days Mon 11/25/13 Tue 11/26/13 Mon 11/25/13 Mon 11/25/13 Mon 12/30/13 Mon 1/6/14 Mon 1/6/14 Mon 1/6/14 Wed 1/8/14 Wed 1/8/14 Wed 1/8/14 Mon 1/13/14 Tue 1/14/14 Tue 2/11/14 Tue 2/11/14 Tue 2/11/14 Tue 2/18/14 Wed 1/8/14 Wed 1/8/14 Wed 1/8/14 Mon 1/13/14 Tue 1/14/14 Wed 1/15/14 Thu 1/16/14 Thu 1/16/14 Mon 1/20/14 Tue 1/21/14 Mon 1/13/14 Mon 1/27/14 Thu 1/30/14 Tue 2/4/14 Wed 1/22/14 Wed 1/22/14 Mon 1/27/14 Mon 1/27/14 Wed 2/5/14 Wed 2/12/14 Wed 2/19/14 Wed 2/19/14 Mon 2/24/14 Mon 3/3/14 Tue 3/4/14 Wed 3/5/14 Thu 3/6/14 Fri 3/7/14 Fri 4/4/14 Fri 4/25/14 Tue 5/6/14 Tue 5/20/14 Tue 5/27/14 Tue 6/10/14 Tue 6/17/14 Tue 7/1/14 Tue 7/15/14 Tue 7/22/14 Tue 8/5/14 Tue 8/12/14 Tue 8/26/14 Fri 8/29/14 Fri 9/26/14 Wed 10/1/14 Mon 11/25/13 Tue 11/26/13 2 Wed 11/27/13 2 Tue 1/7/14 Tue 12/24/13 3 Fri 12/20/13 Fri 12/27/13 4,6 Fri 1/3/14 6,7,8 Tue 1/7/14 9 Tue 1/7/14 9 Tue 1/7/14 9 Mon 2/24/14 Fri 1/10/14 10 Thu 1/9/14 11 Mon 1/13/14 14,15 Mon 2/10/14 16 Mon 2/17/14 Mon 2/17/14 17 Mon 2/17/14 17 Mon 2/24/14 19 Thu 2/6/14 Wed 1/8/14 12 Fri 1/10/14 10,11,12 Mon 1/13/14 23,24 Tue 1/14/14 23FS+2 days,25 Wed 1/15/14 26 Thu 1/16/14 26,27 Fri 1/17/14 26,27 Mon 1/20/14 28,29 Tue 1/21/14 30 Fri 1/24/14 24 Mon 1/27/14 32,31 Mon 2/3/14 33FS+2 days Thu 2/6/14 34 Tue 2/18/14 Fri 1/24/14 31 Fri 1/31/14 37 Tue 2/4/14 37 Tue 2/11/14 37,39 Tue 2/18/14 33,39,37,40 Tue 11/25/14 Fri 2/21/14 41 Fri 2/28/14 43 Mon 3/3/14 44 Tue 3/4/14 45 Wed 3/5/14 46 Thu 3/6/14 47 Thu 4/3/14 47,48 Mon 4/14/14 49 Tue 5/6/14 50 Tue 5/20/14 51 Tue 5/27/14 52 Tue 6/10/14 53 Tue 6/17/14 54 Tue 7/1/14 55 Tue 7/15/14 56 Tue 7/22/14 57 Tue 8/5/14 58 Tue 8/12/14 59 Tue 8/26/14 60 Fri 8/29/14 61 Fri 9/26/14 62 Wed 10/1/14 63 Wed 11/12/14 64 Tue 11/25/14 65 Concrete Subcontracto Concrete Subcontracto Building Inspector Concrete Subcontracto Civil Engineer Block Masonry Subcon Block Masonry Subcon Block Masonry Subcon Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Home Decorator Home Decorator Steel Supplier Builder Waterproofing Subcon Concrete Subcontractor Concrete Subcontractor Building Inspector Concrete Subcontractor Civil Engineer Block Masonry Subcontractor Block Masonry Subcontractor Block Masonry Subcontractor Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Home Decorator Home Decorator Steel Supplier Builder Waterproofing Subcontractor Excavation Subcontrac Excavation Subcontrac Civil Engineer Excavation Subcontrac Excavation Subcontrac Excavation Subcontractor Excavation Subcontractor Civil Engineer Excavation Subcontractor Excavation Subcontractor Builder Builder Builder Builder Builder Excavation Subcontrac Excavation Subcontrac Sediment Control Inspe Sediment Control Inspe Department of Permits Department of Permits Builder Department of Permits Builder Builder Builder Builder Builder Excavation Subcontractor Excavation Subcontractor Sediment Control Inspector Sediment Control Inspector Department of Permits & Licenses Department of Permits & Licenses Builder Department of Permits & Licenses Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Builder Client Client Client Builder Builder Builder Builder Client Client Client Builder Builder Builder Builder Builder Builder

1 day Wed 11/27/13 20 days Wed 11/27/13 3 days Wed 12/25/13

2 Document Review & Revision

3 Bids & Contracts

3.5.1 3.5.2 3.6 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 4.12 4.13 5.1 5.2 5.3 5.4 5.5 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 6.21 6.22 6.23 6.24

4 Grading & Building Permits

5 Site Work

6 Foundation

10 days Wed 11/12/14

Project: b4ubuild_sample_07a Date: Mon 11/25/13

Task

Split

Progress

Milestone

Summary Page 1

Project Summary

External Tasks

External Milestone

Deadline

WBS Construction of the Home Project

Contracts

Document Review & Revision


Review & Finalize Plans

Bids & Contracts

Grading & Building Permits


File Grading/Building Permit Application Install Construction Entrance

Site Work

Foundation

Supply Construction Agreement

Make Copies of Plans

Clear Lot

Layout footings

Supply Contract Plans

Review & Finalize Specifications

Make Copies of Specifications

Strip Topsoil & Stockpile

Dig Footings & Install Reinforcing

Supply Contract Site Plan

Review & Finalize Site Plan

Distribute Plans & Specifications

Install Sediment Controls

Stake Lot for Excavation

Build Block Foundation

Print Construction Drawings

Receive Bids

Sediment Control Insp.

Rough grade lot

Construction of Boudary wall

Approve Revised Plans

Review Bids
Sales Construction

Area Permit Process

Excavate for foundation

Constrcution Rooms

Approve Revised Specifications

Execute Subcontractor Agreements

Building Permit Approved

Paints

Approve Revised Site Plan

Pay Permit Fees and Excise Taxes

Roof structure construction

Building Permit Issued

Waterproofing and Drain Tile

Contracts
Start: 11/25/13 Finish: 11/27/13 Comp: 0% ID: 1 Dur: 3 days

Supply Construction Agreeme


Start: 11/25/13 Finish: 11/25/13 Res: Builder ID: 2 Dur: 1 day

Supply Contract Plans


Start: 11/26/13 Finish: 11/26/13 Res: Builder ID: 3 Dur: 1 day

Supply Contract Site Plan


Start: 11/27/13 Finish: 11/27/13 Res: Builder ID: 4 Dur: 1 day

Document Review & Revision


Start: 11/25/13 Finish: 1/7/14 Comp: 0% ID: 5 Dur: 32 days

Review & Finalize Plans


Start: 11/27/13 Finish: 12/24/13 Res: Builder ID: 6 Dur: 20 days

Review & Finalize Site Plan


Start: 12/25/13 Finish: 12/27/13 Res: Builder ID: 8 Dur: 3 days

Network Diagram
Print Construction Drawings
Start: 12/30/13 Finish: 1/3/14 Res: Builder ID: 9 Dur: 5 days

Approve Revised Plans


Start: 1/6/14 Finish: 1/7/14 Res: ID: 10 Dur: 2 days

Approve Revised Specificatio


Start: 1/6/14 Finish: 1/7/14 Res: ID: 11 Dur: 2 days

Approve Revised Site Plan


Start: 1/6/14 Finish: 1/7/14 Res: ID: 12 Dur: 2 days

Review & Finalize Specificatio


Start: 11/25/13 Finish: 12/20/13 Res: Builder ID: 7 Dur: 20 days

Bids & Contracts


Start: 1/8/14 Finish: 2/24/14 Comp: 0% ID: 13 Dur: 34 days

Make Copies of Plans


Start: 1/8/14 Finish: 1/10/14 Res: Builder ID: 14 Dur: 3 days

Distribute Plans & Specificatio


Start: 1/13/14 Finish: 1/13/14 Res: Builder ID: 16 Dur: 1 day

Receive Bids
Start: 1/14/14 Finish: 2/10/14 Res: Builder ID: 17 Dur: 20 days

Make Copies of Specifications


Start: 1/8/14 Finish: 1/9/14 Res: Builder ID: 15 Dur: 2 days

Review Bids
Start: 2/11/14 Finish: 2/17/14 Comp: 0% ID: 18 Dur: 5 days

Sales
Start: 2/11/14 Finish: 2/17/14 Res: Builder ID: 19 Dur: 5 days

Construction
Start: 2/11/14 Finish: 2/17/14 Res: Builder ID: 20 Dur: 5 days

Execute Subcontractor Agreem


Start: 2/18/14 Finish: 2/24/14 Res: Builder ID: 21 Dur: 5 days

Grading & Building Permits


Start: 1/8/14 Finish: 2/6/14 Comp: 0% ID: 22 Dur: 22 days

File Grading Permit Applicatio


Start: 1/8/14 Finish: 1/8/14 Res: Builder ID: 23 Dur: 1 day

Post Lot Identification


Start: 1/13/14 Finish: 1/13/14 Res: Builder ID: 25 Dur: 1 day

Meet Sediment Control Inspec


Start: 1/14/14 Finish: 1/14/14 Res: Builder ID: 26 Dur: 1 day

Walk Lot w/ Owner


Start: 1/15/14 Finish: 1/15/14 Res: Builder ID: 27 Dur: 1 day

Install Construction Entrance


Start: 1/16/14 Finish: 1/16/14 Res: ID: 28 Dur: 1 day

Sediment Control Insp.


Start: 1/20/14 Finish: 1/20/14 Res: ID: 30 Dur: 1 day

Grading Permit Issued


Start: 1/21/14 Finish: 1/21/14 Res: ID: 31 Dur: 1 day

Excavation Subcontractor

Sediment Control Inspector

Sediment Control Inspector

Install Sediment Controls


Start: 1/16/14 Finish: 1/17/14 Res: ID: 29 Dur: 2 days

Excavation Subcontractor

File Building Permit Applicatio


Start: 1/8/14 Finish: 1/10/14 Res: Builder ID: 24 Dur: 3 days

Area Permit Process


Start: 1/13/14 Finish: 1/24/14 Res: ID: 32 Dur: 10 days

Building Permit Approved


Start: 1/27/14 Finish: 1/27/14 Res: ID: 33 Dur: 1 day

Pay Permit Fees and Excise T


Start: 1/30/14 Finish: 2/3/14 Res: Builder ID: 34 Dur: 3 days

Building Permit Issued


Start: 2/4/14 Finish: 2/6/14 Res: ID: 35 Dur: 3 days

Department of Permits & License

Department of Permits & License

Department of Permits & License

Site Work
Start: 1/22/14 Finish: 2/18/14 Comp: 0% ID: 36 Dur: 20 days

Clear Lot
Start: 1/22/14 Finish: 1/24/14 Res: ID: 37 Dur: 3 days

Strip Topsoil & Stockpile


Start: 1/27/14 Finish: 1/31/14 Res: ID: 38 Dur: 5 days

Excavation Subcontractor

Excavation Subcontractor

Stake Lot for Excavation


Start: 1/27/14 Finish: 2/4/14 Res: ID: 39 Dur: 7 days

Civil Engineer

Rough grade lot


Start: 2/5/14 Finish: 2/11/14 Res: ID: 40 Dur: 5 days

Excavation Subcontractor

Excavate for foundation


Start: 2/12/14 Finish: 2/18/14 Res: ID: 41 Dur: 5 days

Excavation Subcontractor

Foundation
Start: 2/19/14 Finish: 11/25/14 Comp: 0% ID: 42 Dur: 200.13 days

Layout footings
Start: 2/19/14 Finish: 2/21/14 Res: ID: 43 Dur: 3 days

Dig Footings & Install Reinforc


Start: 2/24/14 Finish: 2/28/14 Res: ID: 44 Dur: 5 days

Footing Inspection
Start: 3/3/14 Finish: 3/3/14 Res: ID: 45 Dur: 1 day

Pour footings
Start: 3/4/14 Finish: 3/4/14 Res: ID: 46 Dur: 1 day

Pin Footings
Start: 3/5/14 Finish: 3/5/14 Res: ID: 47 Dur: 1 day

Stock Block, Mortar, Sand


Start: 3/6/14 Finish: 3/6/14 Res: ID: 48 Dur: 1 day

Concrete Subcontractor

Concrete Subcontractor

Building Inspector

Concrete Subcontractor

Civil Engineer

Block Masonry Subcontractor

Build Block Foundation


Start: 3/7/14 Finish: 4/3/14 Res: ID: 49 Dur: 20 days

Fill Block Cores w/ Concrete


Start: 4/4/14 Finish: 4/14/14 Res: ID: 50 Dur: 7 days

Construction of Boudary wall


Start: 4/25/14 Finish: 5/6/14 Res: Builder ID: 51 Dur: 7 days

Constrcution of Bedroom 1
Start: 5/6/14 Finish: 5/20/14 Res: Builder ID: 52 Dur: 10 days

Constrcution of Bathroom 1
Start: 5/20/14 Finish: 5/27/14 Res: Builder ID: 53 Dur: 5 days

Constrcution of Bedroom 2
Start: 5/27/14 Finish: 6/10/14 Res: Builder ID: 54 Dur: 10 days

Block Masonry Subcontractor

Block Masonry Subcontractor

Constrcution of Bathroom 2
Start: 6/10/14 Finish: 6/17/14 Res: Builder ID: 55 Dur: 5 days

Constrcution of Lounge
Start: 6/17/14 Finish: 7/1/14 Res: Builder ID: 56 Dur: 10 days

Constrcution of Dinning Room


Start: 7/1/14 Finish: 7/15/14 Res: Builder ID: 57 Dur: 10 days

Constrcution of Bathroom 3
Start: 7/15/14 Finish: 7/22/14 Res: Builder ID: 58 Dur: 5 days

Constrcution of Guest room


Start: 7/22/14 Finish: 8/5/14 Res: Builder ID: 59 Dur: 10 days

Constrcution of Bathroom 4
Start: 8/5/14 Finish: 8/12/14 Res: Builder ID: 60 Dur: 5 days

Constrcution of Kitchen
Start: 8/12/14 Finish: 8/26/14 Res: Builder ID: 61 Dur: 10 days

Selection of paints
Start: 8/26/14 Finish: 8/29/14 Res: ID: 62 Dur: 3 days

Paint
Start: 8/29/14 Finish: 9/26/14 Res: ID: 63 Dur: 20 days

Steel Delivery
Start: 9/26/14 Finish: 10/1/14 Res: ID: 64 Dur: 3 days

Roof structure construction


Start: 10/1/14 Finish: 11/12/14 Res: Builder ID: 65 Dur: 30 days

Waterproofing and Drain Tile


Start: 11/12/14 Finish: 11/25/14 Res: ID: 66 Dur: 10 days

Home Decorator

Home Decorator

Steel Supplier

Waterproofing Subcontractor