Sei sulla pagina 1di 44

TP48200B-N18C1 V300R001

Quick Installation Guide

Issue Date

02 2013-05-14

HUAWEI TECHNOLOGIES CO., LTD.

Copyright Huawei Technologies Co., Ltd. 2013. All rights reserved.


No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd.

Trademarks and Permissions


and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders.

Notice
The purchased products, services and features are stipulated by the contract made between Huawei and the customer. All or part of the products, services and features described in this document may not be within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements, information, and recommendations in this document are provided "AS IS" without warranties, guarantees or representations of any kind, either express or implied. The information in this document is subject to change without notice. Every effort has been made in the preparation of this document to ensure accuracy of the contents, but all statements, information, and recommendations in this document do not constitute a warranty of any kind, express or implied.

Huawei Technologies Co., Ltd.


Address: Huawei Industrial Base Bantian, Longgang Shenzhen 518129 People's Republic of China Website: Email: http://www.huawei.com support@huawei.com

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide

About This Document

About This Document


Purpose
This document describes how to install and commission the power system. The figures of this document are for reference only.

Intended Audience
This document is intended for:

Installation and commissioning engineers Technical support engineers

Symbol Conventions
The symbols that may be found in this document are defined as follows: Symbol Description Alerts you to a high risk hazard that could, if not avoided, result in serious injury or death.

Alerts you to a medium or low risk hazard that could, if not avoided, result in moderate or minor injury.

Alerts you to a potentially hazardous situation that could, if not avoided, result in equipment damage, data loss, performance deterioration, or unanticipated results. Provides a tip that may help you solve a problem or save time. Provides additional information to emphasize or supplement important points in the main text.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

ii

TP48200B-N18C1 Quick Installation Guide

About This Document

Change History
Changes between document issues are cumulative. The latest document issue contains all the changes made in earlier issues.

Issue 02 (2013-05-14)
This issue is the second official release, which incorporates the following changes: Figure 3-1, Figure 5-2, Figure 7-1, Table 7-1, Figure 8-5 Figure 8-8 and Figure 9-2 are modified because the cabinet structure is changed.

Issue 01 (2012-11-30)
This issue is the first official release.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

iii

TP48200B-N18C1 Quick Installation Guide

Contents

Contents
1 Safety Precautions ......................................................................................................................... 1
1.1 Health and Safety ............................................................................................................................................. 1 1.1.1 Overview ................................................................................................................................................. 1 1.1.2 Electrical Safety ...................................................................................................................................... 3 1.1.3 Inflammable Environment ...................................................................................................................... 4 1.1.4 Battery ..................................................................................................................................................... 4 1.1.5 Working at Heights ................................................................................................................................. 6 1.1.6 Mechanical Safety ................................................................................................................................... 7 1.1.7 Bundling Signal Cables ........................................................................................................................... 8 1.2 Equipment Safety ............................................................................................................................................. 9 1.2.1 Electricity Safety ..................................................................................................................................... 9 1.2.2 Electrostatic Discharge............................................................................................................................ 9 1.2.3 Laying Cables ....................................................................................................................................... 10

2 Installation Preparations ........................................................................................................... 11


2.1 Tools ............................................................................................................................................................... 11 2.2 Unpacking and Check .................................................................................................................................... 12 2.3 Precautions ..................................................................................................................................................... 12 2.4 Installation Space Requirements .................................................................................................................... 12

3 Configuration............................................................................................................................... 13 4 Installing the Cabinet ................................................................................................................. 15


4.1.1 Marking the Installation Holes of Cabinet ............................................................................................ 15 4.1.2 Drilling Holes and Installing Expansion Sleeves .................................................................................. 15 4.1.3 Securing the Cabinet ............................................................................................................................. 16

5 Installing a PGND Cable ........................................................................................................... 17 6 Installing Components............................................................................................................... 19


6.1 Installing Rectifiers ........................................................................................................................................ 19

7 (Optional) Installing User Equipment .................................................................................... 20 8 Installing Cables ......................................................................................................................... 23


8.1 Installing Signal Cables and Communication Cables ..................................................................................... 23 8.1.1 UIM02C ................................................................................................................................................ 23

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

iv

TP48200B-N18C1 Quick Installation Guide

Contents

8.1.2 Installing Dry Contacts Signal Cables .................................................................................................. 23 8.1.3 Installing Boolean Value Signal Cables ................................................................................................ 24 8.1.4 Installing Communications Cables ....................................................................................................... 24 8.2 Installing Power Cables .................................................................................................................................. 24 8.2.1 Installing DC Output Power Cables ...................................................................................................... 25 8.2.2 (Optional) Installing Batteries ............................................................................................................... 25 8.2.3 Installing AC Input Power Cables ......................................................................................................... 29

9 Commissioning............................................................................................................................ 30
9.1 Installation Verification .................................................................................................................................. 30 9.2 Powering On and Commissioning .................................................................................................................. 30 9.2.1 Setting Parameters ................................................................................................................................ 30 9.3 Powering On................................................................................................................................................... 33

A Prepare Terminal........................................................................................................................ 35 B UIM02C Pin Definition ............................................................................................................. 36

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide

1 Safety Precautions

1
1.1 Health and Safety
1.1.1 Overview
Introduction

Safety Precautions

This section describes the safety precautions you must take before installing or maintaining Huawei equipment. To ensure safety of humans and the equipment, pay attention to the safety symbols on the equipment and all the safety instructions in this document. The "NOTE", "CAUTION", and "WARNING" marks in other documents do not represent all the safety instructions. They are only supplements to the safety instructions. Installation and maintenance personnel must understand basic safety precautions to avoid hazards. When operating Huawei equipment, in addition to following the general precautions in this document, follow the specific safety instructions given by Huawei. Only trained and qualified personnel are allowed to install, operate, and maintain Huawei equipment.

Local Safety Regulations


When operating Huawei equipment, you must follow the local laws and regulations. The safety instructions in this document are only supplements to the local laws and regulations.

General Requirements
To minimize risk of personal injury and damage to equipment, read and follow all the precautions in this document before performing any installation or maintenance. Ensure that the instructions provided in this document are followed completely. This section also provides guidelines for selecting the measuring and testing devices.

Installation

The device (or system) must be installed in an access-controlled location. The device can be mounted only on concrete or non-combustible surfaces.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide


1 Safety Precautions

The device must be fixed securely on the floor or to other immovable objects such as walls and mounting racks before operation. When installing the unit, always make the ground connection first and disconnect it at the end. Do not block the ventilation while the device is operating. Keep a minimum distance of 5 cm between the device and the wall or other objects that may block the ventilation. Tighten the thumbscrews by using a tool after initial installation and subsequent access to the panel.

Ground

Do not damage the ground conductor or operate the device in the absence of a properly installed ground conductor. Conduct the electrical inspection carefully. The device (or system) must be connected permanently to the protection ground before an operation. The cross-sectional area of the protective ground conductor must be at least 10 mm2.

Power Supply

For AC-supplied models: The device applies to TN, TT power system. For DC-supplied models: Reinforced insulation or double insulation must be provided to isolate the DC source from the AC mains supply. For DC-supplied models The device applies to DC power source that complies with the Safety Extra-Low Voltage (SELV) requirements in IEC 60950-1 based safety standards. Prepared conductors are connected to the terminal block, and only the appropriate AWG/Type of wire is secured with the lug terminals. The plug-socket combination must be accessible at all times because it serves as a main disconnect device.

Human Safety

Do not operate the device or cables during lightning strikes. Do not use fixed terminals or touch terminals or antenna connectors when there is lightning. To avoid electric shock, do not connect safety extra-low voltage (SELV) circuits to telecommunication network voltage (TNV) circuits. Move or lift the chassis by holding its lower edge. Do not hold the handles on certain modules such as power supply, fans, and boards because they cannot support the weight of the device. At least two persons are required to lift the chassis. When lifting it, keep your back straight and move stably. Do not wear jewelry or watches when you operate the device.

Operator

Only qualified professional personnel are allowed to install, configure, operate, and disassemble the device. Only the personnel authenticated or authorized by Huawei are allowed to replace or change the device of the parts of the device (including the software). Any fault or error that might cause safety problems must be reported immediately to a supervisor.
Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd. 2

Issue 02 (2013-05-14)

TP48200B-N18C1 Quick Installation Guide

1 Safety Precautions

Only qualified personnel are allowed to remove or disable the safety facilities and to troubleshoot and maintain the device.

1.1.2 Electrical Safety


High Voltage

The high voltage power supply provides power for the device operation. Direct or indirect contact (through damp objects) with high voltage and AC mains supply may result in fatal danger.

During the installation of the AC power supply facility, follow the local safety regulations. The personnel who install the AC facility must be qualified to perform high voltage and AC operations. Do not wear conductive articles, such as watches, hand chains, bracelets, and rings during the operation. When water is found in the rack or the rack is damp, switch off the power supply immediately. When the operation is performed in a damp environment, make sure that the device is dry.

Non-standard and improper high voltage operations may result in fire and electric shock. Therefore, you must abide by the local rules and regulations when bridging and wiring AC cables. Only qualified personnel are allowed to perform high voltage and AC operations.

Before powering on a device, ground the device. Otherwise, personal injury or device damage may be caused by high leakage current.

Tools

Dedicated tools must be used during high voltage and AC operations. Avoid using ordinary tools.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide

1 Safety Precautions

High Electrical Leakage

Ground the device before powering it on. Otherwise, personal injury or device damage may be caused by high leakage current. If a "high electrical leakage" tag is present on the power terminal of the device, you must ground the device before powering it on.

Power Cable

Do not install or remove power cables when the device is on. Transient contact between the core of the power cable and the conductor may generate electric arcs or sparks, which may cause fire or hurt human eyes.

Before installing or removing the power cable, turn off the power switch. Before connecting a power cable, check that the label on the power cable is correct.

1.1.3 Inflammable Environment


Operating the electrical device in an inflammable environment can be fatal.

Do not place the device in an environment that has inflammable and explosive air or gas. Do not perform any operation in this environment.

1.1.4 Battery

Before operating storage batteries, carefully read the safety precautions for battery handling and connection.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide

1 Safety Precautions

Improper handling of storage batteries causes hazards. When operating storage batteries, avoid short circuit and overflow or leakage of the electrolyte. Electrolyte overflow may damage the device. It will corrode metal parts and circuit boards, and ultimately damage the device and cause short circuit of circuit boards.

Basic Precautions
Before installing and maintaining the battery, note the following:

Do not wear metal articles such as wristwatch, hand chain, bracelet, and ring. Use special insulation tools. Take care to protect your eyes when operating the device. Wear rubber gloves and a protective coat in case of electrolyte overflow. When handling a storage battery, ensure that its electrodes are upward. Leaning or reversing the storage battery is prohibited.

Short Circuit

Battery short circuit may cause human injuries. Although the voltage of ordinary batteries is low, the instantaneous high current caused by the short circuit releases a great deal of energy. There is danger of explosion if the battery is incorrectly replaced. Therefore, replace the battery only with the same or equivalent type recommended by the manufacturer.

Keep away metal objects, which may cause battery short circuit, from batteries. If metal objects must be used, first disconnect the batteries in use before performing any other operations.

Hazardous Gas

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide

1 Safety Precautions

Do not use unsealed lead acid storage batteries. Lead acid storage batteries must be placed horizontally and stably to prevent the batteries from releasing flammable gas, which may cause fire or erode the device. Lead acid storage batteries in use emit flammable gas. Therefore, ventilation and fireproofing measures must be taken at the sites where lead acid storage batteries are used.

Battery Temperature

If a battery overheats, the battery may be deformed or damaged, and the electrolyte may overflow. When the temperature of the battery is higher than 60, check the battery for electrolyte overflow. If the electrolyte overflows, absorb and counteract the electrolyte immediately.

Battery Leakage

When the electrolyte overflows, absorb and counteract the electrolyte immediately. When moving or handling a battery whose electrolyte leaks, note that the leaking electrolyte may hurt human bodies. When you find the electrolyte leaks, use the following substances to counteract and absorb the leaking electrolyte:

Sodium bicarbonate (baking soda): NaHCO3 Sodium carbonate (soda): Na2CO3

Select a substance to counteract and absorb the leaking electrolyte according to the instructions of the battery manufacturer.

1.1.5 Working at Heights

Avoid object falling when you work at heights. When working at heights, fulfill the following requirements:

Only trained personnel can work at heights.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide


1 Safety Precautions

Prevent the devices and tools that you carry from falling down. Take safety and protection measures, for example, wear a helm and safety belt. Wear warm clothes when working at heights in a cold region. Before working at heights, check that all the lifting facilities are in good condition.

Using Ladders Checking a Ladder


Before using a ladder, check whether the ladder is damaged. Only the ladder in good condition can be used. Before using a ladder, you should know the maximum weight capacity of the ladder. Avoid overweighing the ladder.

Placing a Ladder
The recommended gradient of ladders is 75 degrees. You can measure the gradient of the ladder with an angle square or your arms. When using a ladder, ensure that the wider feet of the ladder are downward, or take protection measures for the ladder feet to prevent the ladder from sliding. Ensure that the ladder is placed securely.

Climbing Up a Ladder
When climbing up a ladder, note the following:

Ensure that the center of gravity of your body does not deviate from the edges of the two long sides. To minimize the risk of falling, hold your balance on the ladder before any operation. Do not climb higher than the fourth rung of the ladder (counted from up to down). If you want to climb up a roof, ensure that the ladder top is at least one meter higher than the roof.

1.1.6 Mechanical Safety


Drilling Holes

Do not drill the cabinet at will. Drilling holes without complying with the requirements affects the electromagnetic shielding performance of the cabinet and damages the cables inside the cabinet. In addition, if the scraps caused by drilling enter the cabinet, the printed circuit boards (PCBs) may be short circuited.

Before you drill a hole in the cabinet, remove the internal cables from the cabinet. Wear an eye protector when drilling holes. This is to prevent your eyes from being injured by the splashing scraps. Wear insulated gloves when drilling holes. Ensure that the scraps caused by drilling do not enter the cabinet.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide


1 Safety Precautions

Drilling holes without complying with the requirements affects the electromagnetic shielding performance of the cabinet. After drilling, clean the metal scraps immediately.

Sharp Objects

Before you hold or carry a device, wear protective gloves to avoid getting injured by sharp edges of the device.

Handling Fans
When handling fans, note the following:

When replacing a component, place the component, screws, and tools in a safe place. Otherwise, if any of them fall into the operating fans, the fans may be damaged. When replacing a component near fans, do not insert your fingers or boards into the operating fans until the fans are switched off and stops running.

Lifting Heavy Objects

When heavy objects are being lifted, do not stand or walk under the cantilever or the lifted object.

1.1.7 Bundling Signal Cables

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide

1 Safety Precautions

Do not bundle signal cables with high current cables or high voltage cables. Maintain a minimum space of 150 mm between adjacent ties.

1.2 Equipment Safety


1.2.1 Electricity Safety
High Electrical Leakage

If the "high electrical leakage" tag is present on the power terminal of the device, you must ground the device before powering it on.

Fuse

If a fuse is to be replaced, the new fuse must be of the same type and specifications.

1.2.2 Electrostatic Discharge

The static electricity generated by human bodies may damage the electrostatic-sensitive components on boards, for example, the large-scale integrated (LSI) circuits. Human body movement, friction between human bodies and clothes, friction between shoes and floors, or handling of plastic articles causes static electromagnetic fields on human bodies. These static electromagnetic fields cannot be eliminated until the static is discharged. To prevent electrostatic-sensitive components from being damaged by the static on human bodies, you must wear a well-grounded ESD wrist strap when touching the device or handling boards or application-specific integrated circuits (ASICs). Figure 1-1 shows how to wear an ESD wrist strap.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

TP48200B-N18C1 Quick Installation Guide

1 Safety Precautions

Figure 1-1 Wearing an ESD wrist strap

1.2.3 Laying Cables


When the temperature is very low, violent strike or vibration may damage the cable sheathing. To ensure safety, comply with the following requirements:

Cables can be laid or installed only when the temperature is higher than 0. Before laying cables which have been stored in a temperature lower than 0, move the cables to an environment of the ambient temperature and store them at the ambient temperature for at least 24 hours. Handle cables with caution, especially at a low temperature. Do not drop the cables directly from the vehicle.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

10

TP48200B-N18C1 Quick Installation Guide

2 Installation Preparations

2
2.1 Tools
Figure 2-1 Tools

Installation Preparations

Figure 2-1 shows the tools that must be obtained before installation.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

11

TP48200B-N18C1 Quick Installation Guide

2 Installation Preparations

2.2 Unpacking and Check


Step 1 Unpack the carton. Step 2 Check whether the cabinet is intact. If not, contact the local office. Step 3 Check whether the fittings are complete. The fittings include a marking-off template, and a material package.
NOTE

Rectifiers and batteries are delivered separately.

----End

2.3 Precautions

Do not bind PGND cables together with signal cables. Leave certain distance between them to reduce the interruption.Bind AC power cables, DC power cables, signal cables, and communications cables separately. In this manual, the equipment interior is for reference only. The cable colors in the manual are for reference only. The colors vary depending on the countries and regions.

2.4 Installation Space Requirements


Figure 2-2 shows the installation space requirements. Figure 2-2 Installation space requirements

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

12

TP48200B-N18C1 Quick Installation Guide

3 Configuration

3
Specifications
Table 3-1 Specifications Category Dimensions (H x W x D) Specifications Weight

Configuration

1800 mm x 600 mm x 600 mm (70.87 in. x 23.62 in. x 23.62 in.) < 100 kg (without rectifiers or batteries)

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

13

TP48200B-N18C1 Quick Installation Guide

3 Configuration

Interior of the Cabinet


Figure 3-1 Interior of the TP48200B-N18C1

(1) RTN+ busbar

(2) Battery circuit breaker

(4) Site monitoring module (SMU) (7) Space for installing batteries (10) User interface module (UIM)

(5) Battery switch (8) Load low voltage disconnection (LLVD) circuit breaker (11) Battery rack

(3) Battery low voltage disconnection (BLVD) circuit breaker (6) Space for installing rectifiers (9) Ground bar for cabinet

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

14

TP48200B-N18C1 Quick Installation Guide

4 Installing the Cabinet

4
Figure 4-1 Marking the installation holes

Installing the Cabinet

4.1.1 Marking the Installation Holes of Cabinet


Mark the position of the cabinet based on the delivered marking-off plate to confirm the positions of the expansion bolts (A hole), as shown in Figure 4-1.

(1) Marking-off plate

(2) Concrete pad

(3) Installation hole

4.1.2 Drilling Holes and Installing Expansion Sleeves


Drill holes and install expansion sleeves as shown in Figure 4-2. Step 1 Use a hammer drill bit to drill holes with a depth ranging from 52 mm (2.05 in.) to 60 mm (2.36 in.). Step 2 Tighten the expansion bolts slightly and place one vertically into each hole. Pound the expansion bolt with a rubber mallet until it goes all the way into the hole. Step 3 Fasten the expansion bolt clockwise until the nut is firmly inserted into the expansion tube.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

15

TP48200B-N18C1 Quick Installation Guide

4 Installing the Cabinet

Step 4 Turn the expansion bolt counterclockwise and remove the expansion bolt, spring washer and flat washer in turn. Figure 4-2 Drilling holes and installing expansion sleeves

(1) Expansion bolt(M12) (4) Expansion sleeve

(2) Spring washer (5) Concrete pad

(3) Flat washer

----End

4.1.3 Securing the Cabinet


Step 1 Move the cabinet onto the concrete pad and align the installation hole in the base with the expansion bolt hole. Step 2 Tighten the expansion bolt, as shown in Figure 4-3. Figure 4-3 Tightening the expansion bolt

----End

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

16

TP48200B-N18C1 Quick Installation Guide

5 Installing a PGND Cable

5
NOTE

Installing a PGND Cable

The PGND cable is used to connect PGND screws on the cabinet and the ground busbar outside the cabinet to ensure proper grounding of the cabinet.

Select any of the following ways to route cables based on the cable bundle cross-sectional area: If the total cross-sectional area of a cable bundle is less than the area of a rodent-proof mesh, cut a hole in the mesh or reduce the mesh size for cable routing. If the total cross-sectional area of all bundles of cables is greater than or equal to the area of a rodent-proof mesh, remove the mesh for cable routing. If the total cross-sectional area of all bundles of cables is greater than the total area of all rodent-proof meshes, remove the top cover for cable routing.

Figure 5-1 The position of the rodent-proof mesh

(1) Rodent-proof mesh

Install the PGND cable of the TP48200B-N18C1, as shown in Figure 5-2.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

17

TP48200B-N18C1 Quick Installation Guide

5 Installing a PGND Cable

Figure 5-2 Installing the PGND cable of the TP48200B-N18C1

(1) Ground bar of the cabinet

(2) Ground bar of the site

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

18

TP48200B-N18C1 Quick Installation Guide

6 Installing Components

6
6.1 Installing Rectifiers
Step 2 Pull handle out.

Installing Components

The rated output current of each rectifier is 50 A. The number of rectifiers depends on actual capacity requirements, as shown in Figure 6-1. Step 1 Remove the bolts from the handle. Ensure that the module handle is open.

Step 3 Gently push the rectifier into the related slot along the guide rail. Step 4 Push the handle upwards, lock the handle. Step 5 Tighten the bolts in the handle and secure the handle. Figure 6-1 Installing a rectifier

----End

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

19

TP48200B-N18C1 Quick Installation Guide

7 (Optional) Installing User Equipment

(Optional) Installing User Equipment

System Configuration
Figure 7-1 shows the two scenarios of the TP48200B-N18C1. Figure 7-1 Scenarios

Table 7-1 Configuration Scenarios Scenarios 1 Scenarios 2 Space for batteries 2 x 330 mm 3 x 310 mm Space for customer 445 mm (19-inch rack) 178 mm (19-inch rack)

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

20

TP48200B-N18C1 Quick Installation Guide

7 (Optional) Installing User Equipment

Removing the Battery Rack

CAUTION
Three layers of racks are available for installing batteries by default. If space for installing customer equipment needs to be expanded, remove the battery racks from top to bottom

Remove one layer battery rack, as shown in Figure 7-2. Figure 7-2 Removing one layer battery rack

Installing the User Equipment


Step 1 Install the mounting bar, as shown in Figure 7-3. Figure 7-3 Installing the mounting bar

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

21

TP48200B-N18C1 Quick Installation Guide

7 (Optional) Installing User Equipment

Step 2 Install the guide rail, as shown in Figure 7-4. Figure 7-4 Installing the guide rail

Install the user equipment according to actual conditions. Figure 7-5 shows how cables for user equipment are routed.

CAUTION
Route power cables and signal cables separately. Figure 7-5 Cables routing of the user equipment

(1) Cable-through hole of the user equipment

----End

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

22

TP48200B-N18C1 Quick Installation Guide

8 Installing Cables

8
8.1.1 UIM02C
Appearance
Figure 8-1 UIM02C panel

Installing Cables

8.1 Installing Signal Cables and Communication Cables


The UIM02C provides eight dry contact outputs, six Boolean value inputs, and seven sensor ports.

8.1.2 Installing Dry Contacts Signal Cables


Install dry contacts signal cables, as shown in Figure 8-2. Figure 8-2 Installing dry contacts signal cables

(1) White Contact plate

(2) Dry contact

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

23

TP48200B-N18C1 Quick Installation Guide

8 Installing Cables

8.1.3 Installing Boolean Value Signal Cables


Connect Boolean value signal cables to the UIM02C ports as required. For the UIM02C port description, see Table B-1 in Appendix B.

8.1.4 Installing Communications Cables


If the power system connects to BBU, connect the communications cables to the RS485/RS232 port on the SMU, as shown in Figure 8-3. Figure 8-3 Installing communications cable

(1) RS485/RS232 port

(2) BBU

If the power system connects to the WebUI, NetEco, or an SNMP-compliant element management system (EMS) for remote management, connect the communications cables to the FE port on the SMU, as shown in Figure 8-4. Figure 8-4 Installing communications cable

(1) FE port

(2) WebUI, NetEco, or EMS

8.2 Installing Power Cables

CAUTION
Switch all circuit breakers to OFF before installing power cables.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

24

TP48200B-N18C1 Quick Installation Guide

8 Installing Cables

8.2.1 Installing DC Output Power Cables


Install DC output power cables for the TP48200B-N18C1. Connect the load cable to the corresponding circuit breaker based on the load capacity, as shown in Figure 8-5. Figure 8-5 Installing DC output power cables for the TP48200B-N18C1

(1) Primary load

(2) Secondary load

8.2.2 (Optional) Installing Batteries

All the tools used, such as a screwdriver, must be insulated to prevent the batteries from being burned and to ensure personal safety. Before installing batteries, ensure that the circuit breakers of the batteries to the OFF position. During the installation, avoid short circuits or reverse connections between the positive and negative poles of the batteries.

Step 1 Install each battery in order, as shown in Figure 8-6.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

25

TP48200B-N18C1 Quick Installation Guide

8 Installing Cables

Figure 8-6 Installing each battery in order

Step 2 Install the copper bars, the signal cables for monitoring the middle point voltage of the battery string, as shown in Figure 8-7. Figure 8-7 Installing the copper bars between the batteries, the signal cables for monitoring the middle point voltage of the battery string

Step 3 Install battery cables.

CAUTION
When installing the battery cables, install the negative cable before the positive cable.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

26

TP48200B-N18C1 Quick Installation Guide

8 Installing Cables

If two layers of batteries are installed, install the short-circuit copper bar first, and then battery cables, as shown in Figure 8-8 and Figure 8-9.

Figure 8-8 Installing the short-circuit copper bar

Figure 8-9 Installing battery cables

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

27

TP48200B-N18C1 Quick Installation Guide

8 Installing Cables

If three layers of batteries are installed, you need only to connect battery cables, as shown in Figure 8-10.

Figure 8-10 Installing battery cables

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

28

TP48200B-N18C1 Quick Installation Guide

8 Installing Cables

8.2.3 Installing AC Input Power Cables


Step 1 Prepare a socket with a switch, set the switch to OFF. Step 2 Pull the industrial plug out, and then insert the plug into the socket, as shown in Figure 8-11. Figure 8-11 Installing AC input power cables

(1) Industrial plug

----End

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

29

TP48200B-N18C1 Quick Installation Guide

9 Commissioning

9
9.1 Installation Verification
After installation, verify that:

Commissioning

The cabinet is installed properly and the cables are connected properly. (Cables fastened by screws are not easily removable.) Cables are arranged neatly and bound properly by using cable ties. The battery is connected properly and battery terminals cannot be connected reversely. Check for short circuits between the live wires, between the live wire and the ground cable, between the live wire and the neutral wire, between the RTN+ and the 48 V busbar. Rectify short circuits before powering on the power system.

9.2 Powering On and Commissioning


9.2.1 Setting Parameters
Figure 9-1 SMU02B panel

(1) Running status indicator (4) Liquid crystal display (LCD)

(2) Minor alarm indicator (5) FE

(3)Major alarm indicator (6) Locking latch

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

30

TP48200B-N18C1 Quick Installation Guide


(7) Four buttons (10) Hold hands
NOTE

9 Commissioning
(8) USB (Reserved) (9) RS485/RS232

If the Run indicator (green) on the SMU02B panel is blinking and the LCD is on, the SMU02B is powered on successfully.

Button Description
Button description of SMU panel as shown in Table 9-1 Table 9-1 Button description of SMU panel Button Name Up Down Back Confirm Description Turns to the previous menu or sets parameter values. Turns to the next menu or sets parameter values. Returns to the previous menu without saving the settings.

Enters the main menu from the standby screen. Enters a submenu from the main menu. Saves the menu settings.

Note:

After a menu is displayed, the standby screen is displayed and the LCD screen becomes dark if you do not press any button within 5 minutes. You need to log in again if you do not press any button for 8 minutes. The preset user name is admin and preset password is 000001.

Setting Parameters
Step 1 Measure the voltage across the input ports of AC input circuit breakers. The voltage must range from 200 V to 240 V. The rated voltage is 220 V. If not, ask professionals to rectify the fault. Step 2 Ensure that the industrial plug is inserted into the appropriate socket. If the socket has a switch, set the switch to ON. Step 3 Measure the voltage between L wiring and N wiring terminal. The voltage must range from 200 V to 240 V. The rated voltage is 220 V. Step 4 Set the Qty of Battery, Rated Capacity, Set Date and Set Time according to actual conditions. (Always set Qty of Battery to 1 and set Rated Capacity to the total capacity of all battery strings.) Step 5 Set the IP Address, Subnet Mask and Default Gateway according to actual conditions.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

31

TP48200B-N18C1 Quick Installation Guide

9 Commissioning

Step 6 Set the NetEco Main IP, NetEco Bak IP, NetEco Port, LUI Language and Set Time Zone according to actual conditions. Table 9-2 Parameter settings Main Menu Settings Second-Leve l Menu Comm Para Third-level Menu NetEco Main IP NetEco Bak IP NetEco Port Host Comm Addr Comm Baudrate System Para LUI Language Set Time Zone Quick Settings Qty of Battery Rated Capacity Set Date Set Time IP Address Subnet Mask Default Gateway Forth-Level Menu Default Value 31220 0 9600 ENGLISH GMT +08:00 1 150Ah 192.168.0.10 255.255.255.0 192.168.0.1

You can set parameters to modify the alarm mode of the Boolean value input ports and the dry contact output ports, as shown in Table 9-3. Table 9-3 Modifying the alarm mode of the Boolean value input ports and the dry contact output ports Main Menu Settings Second-Level Menu Site Summary Third-Level Menu DIN1 Alarm DIN2 Alarm DIN3 Alarm DIN4 Alarm DIN5 Alarm DIN6 Alarm ALM1 Alarm Act Default Value Close Close Close Close Close Close Close

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

32

TP48200B-N18C1 Quick Installation Guide

9 Commissioning

Main Menu

Second-Level Menu

Third-Level Menu ALM2 Alarm Act ALM3 Alarm Act ALM4 Alarm Act ALM5 Alarm Act ALM6 Alarm Act ALM7 Alarm Act ALM8 Alarm Act

Default Value Close Close Close Close Close Close Close

You can set parameters to modify the related relay of the alarm. For example, set Battery1 Lost to ALM8, as shown in Table 9-4. Table 9-4 Setting Battery1 Lost to ALM 8 Main Menu Settings Second-Level Menu Alarm Setting Third-Level Menu Batt Summ Forth-Level Menu Battery1 Lost Default Value None Set Value ALM8

----End

9.3 Powering On
CAUTION
Before switching the battery circuit breaker to ON, correectly set battery parameters on the SMU to avoid damaging batteries. Step 1 Switch the battery circuit breakers in the PDU to the ON positions. Step 2 Check whether the voltage between the RTN+ busbar and DC output terminal are the same as the battery voltage and the voltage displayed on the monitoring unit. If not, ask professionals to rectify the fault. Step 3 Check whether the run indicator of rectifiers is normal. If not, ask local professionals. Step 4 Switch the LLVD and BLVD branches to the ON positions. Step 5 Measure whether the voltage between RTN+ and the DC output terminal. The voltage must range from 42 V to 58 V. The rated voltage is 53.5 V. Check whether the loads work normally. If the loads work abnormally, rectify the fault according to the relevant user guides. Step 6 Switch all circuit breakers as required.

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

33

TP48200B-N18C1 Quick Installation Guide

9 Commissioning

Step 7 Check whether the element management system (EMS) can receive the information from the power system. If not, check whether the IP address is set correctly.

CAUTION

The battery switch is in the AUTO position by default before delivery and the system is under automatic control. Open the panel and flip the battery switch to MANUAL only when you need to power on the battery forcibly. Remember to flip the battery back to AUTO after the commissioning.

Figure 9-2 The position of battery switch

(1) Battery switch

Step 8 Observe the operation of the power system for 15 minutes. If no alarms are generated, and current/voltage parameters of the battery and loads are set properly, then lock the door to the cabinet, give the key of the cabinet door to the customer, and clean the site before leaving. ----End

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

34

TP48200B-N18C1 Quick Installation Guide

A Prepare Terminal

A
Figure A-1 Prepare OT terminals

Prepare Terminal

Cut cables to a length suitable for the actual cable route, and then add OT terminals or cord end terminals to each end of the cables, as shown in Figure A-1 and Figure A-2.

Figure A-2 Prepare cord end terminals

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

35

TP48200B-N18C1 Quick Installation Guide

B UIM02C Pin Definition

B
B.1 Appearance
Figure B-1 UIM02C panel

UIM02C Pin Definition

B.2 Port Description


Table B-1 UIM02C port description Port Type Sensor ports Silkscreen TEM_HUM WATER TEMP1 TEMP2 GATE SMOKE BTEMP Boolean value input ports DIN1 DIN2 DIN3 Description Temperature and humidity sensor Water sensor Reserved Reserved Door status sensor Smoke sensor Battery temperature sensor Boolean value input 1 Boolean value input 2 Boolean value input 3

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

36

TP48200B-N18C1 Quick Installation Guide

B UIM02C Pin Definition

Port Type

Silkscreen DIN4 DIN5 DIN6

Description Boolean value input 4 Boolean value input 5 Boolean value input 6 AC power failure alarm Default mode (Close: alarm; Open: normal) can be modified as required.

Dry contact output ports

ALM1

ALM2

DC undervoltage alarm or DC overvoltage alarm Default mode (Close: alarm; Open: normal) can be modified as required.

ALM3

Rectifier faults alarm, rectifier protect alarm, or communication faults alarm Default mode (Close: alarm; Open: normal) can be modified as required.

ALM4

SPD failure alarm Default mode (Close: alarm; Open: normal) can be modified as required.

ALM5

Fuse burn-out alarm Default mode (Close: alarm; Open: normal) can be modified as required.

ALM6

Battery temperature alarms Default mode (Close: alarm; Open: normal) can be modified as required.

ALM7

Water Detector Alarm Default mode (Close: alarm; Open: normal) can be modified as required. Smoke Detector Alarm Default mode (Close: alarm; Open: normal) can be modified as required. RS485

ALM8

Communication Port

COM

B.3 Pin Definition


Table B-2 UIM02C pin definitions Silkscreen TEM-HUM No. 1 Pin Definitions 12 V

Issue 02 (2013-05-14)

Huawei Proprietary and Confidential Copyright Huawei Technologies Co., Ltd.

37

TP48200B-N18C1 Quick Installation Guide

B UIM02C Pin Definition

Silkscreen

No. 2 3 4

Pin Definitions ENV_TEMP 12 V ENV_HUM 12 V WATER GND TEMP1 GND TEMP2 GND DIN7+ JTD7 12 V SMOKE BTEM1 GND

WATER

1 2 3 4

TEMP1

1 2

TEMP2

1 2

GATE

1 2

SMOKE

1 2

BTEMP

1 2

Issue 02 (2013-05-14)