ID 0 1 2 3 4 5 6 7 8 9 10 11

Task Name

Duration

Start

Finish

Jan 12, '14 Jan 19, '14 W F S T T

Jan 26, '14 Feb 2, '14 M W F S T T

Feb 9, '14 M W

Feb 16, '14 S T T

Feb 23, '14 Mar 2, '14 M W F S T T

Mar 9, '14 M W

Tender Design process by Tariq


Mobilization Site Survey Existing available services Demolition Dwgs if required Preliminary Dwgs Approved Project information index filled Project information approved Tender Stage Architecture Xref Baseplan File Naming system, directory Structure, Acess rights, Auto Backup system BasePlan ready for other Discipline

44 days
6 days 4 days 1 day 2 days 1 day 1 day 2 days 43 days 14 days 2 days 1 day

Mon 1/20/14
Mon 1/20/14 Mon 1/20/14 Thu 1/23/14 Fri 1/24/14 Mon 1/20/14 Tue 1/21/14 Wed 1/22/14 Tue 1/21/14 Fri 1/24/14 Fri 1/24/14 Fri 1/24/14

Tue 3/11/14
Sat 1/25/14 Thu 1/23/14 Thu 1/23/14 Sat 1/25/14 Mon 1/20/14 Tue 1/21/14 Thu 1/23/14 Tue 3/11/14 Sat 2/8/14 Sat 1/25/14 Fri 1/24/14

12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71

1 day

Mon 1/27/14 Mon 1/27/14 Mon 1/27/14 Tue 1/28/14 Thu 1/30/14 Sat 2/1/14 Thu 1/30/14 Sat 2/1/14 Tue 2/4/14 Tue 2/4/14 Wed 2/5/14 Fri 2/7/14 Sat 2/8/14 Tue 1/21/14 Tue 1/21/14 Wed 1/22/14 Thu 1/23/14 Sat 1/25/14 Mon 1/27/14 Wed 1/29/14 Wed 1/29/14 Fri 1/31/14 Mon 2/3/14 Fri 1/31/14 Mon 2/3/14 Wed 2/5/14 Wed 2/5/14 Fri 2/7/14 Wed 1/22/14 Thu 1/23/14 Thu 1/30/14 Sat 2/1/14 Wed 2/5/14 Thu 2/13/14 Fri 2/14/14 Mon 2/17/14 Sat 2/22/14 Mon 3/3/14 Mon 2/17/14 Thu 3/6/14 Fri 1/24/14 Mon 1/27/14 Thu 1/30/14 Mon 2/3/14 Tue 1/28/14 Tue 2/4/14 Wed 2/5/14 Mon 2/10/14 Mon 2/17/14 Mon 2/24/14 Tue 2/25/14 Tue 1/21/14 Tue 1/21/14 Wed 1/29/14 Wed 1/29/14 Fri 1/31/14 Mon 2/3/14 Fri 1/31/14 Mon 2/3/14 Tue 2/4/14 Wed 2/5/14 Thu 2/6/14 Fri 2/7/14 Sat 2/8/14 Sat 2/8/14 Wed 1/22/14 Wed 1/22/14 Fri 1/24/14 Sat 1/25/14 Tue 1/28/14 Thu 1/30/14 Thu 1/30/14 Sat 2/1/14 Tue 2/4/14 Sat 2/1/14 Tue 2/4/14 Thu 2/6/14 Thu 2/6/14 Sat 2/8/14 Mon 3/3/14 Thu 1/23/14 Sat 2/1/14 Tue 2/4/14 Fri 2/7/14 Fri 2/14/14 Sat 2/15/14 Mon 2/17/14 Mon 2/24/14 Mon 3/3/14 Mon 2/17/14 Fri 3/7/14 Tue 2/25/14 Mon 1/27/14 Thu 1/30/14 Tue 2/4/14 Tue 1/28/14 Wed 2/5/14 Wed 2/5/14 Tue 2/11/14 Tue 2/18/14 Tue 2/25/14 Wed 2/26/14 Sat 2/15/14 Tue 1/21/14

Master Plan 3 days Floor Plans 2 days Elevations 2 days Sections 2 days Opening details 2 days Schedule of finish 2 days Manufacturer List 1 day Blown up Details 2 days Standard Details 2 days General Notes, List of Dwgs, Face 1 day sheet Formatting Printing Archiving 1 day Structure 17 days Soil Report 2 days Zoning of Seismic/wind Data 1 day Analysis of Str on Pre Arch+dynamic 2 days Load+Special Load Confirmation pf sizes with 1 day Arch/coordination Design of Superstructure 2 days Design of SubStructure 14 hrs Column Layout Details/Elevations 2 days Footing, UG Tank, Lift layout, & details 2 days Plinth Beam & Details 2 days Slab framing & Details 2 days OH tank/Stair tower 2 days Miscellaneous Details 2 days General Notes, List of Dwgs 2 days Formatting Printing Archiving 2 days Electrical 35 days Location of Meter/Db's-Arch 1 day Lux Calculation/ Nos Lights 2 days Internal layouts Lights 2 days Internal layouts Power 2 days Load Calculation & Schematic Diagram 2 days Detailing 2 days Schedule of fixture / Equipments 1 day Manufacture list 1 day General Notes, List of Dwgs 1 day Formatting Printing Archiving 1 day Boq Elec 1 day Telephone 28 days Location of Db 1 day Telephone layouts 1 day Data cable layouts 1 day Calculation & Schematic Diagram 1 day Load to electrical 1 day Detailing 1 day Schedule of fixture / Equipments 1 day Manufacture list 1 day General Notes, List of Dwgs 1 day Formatting Printing Archiving 1 day Plumbing 23 days Location of UG & OH Tank, Water 1 day Heater Int Layouts of Plumb Fixture-From 1 day Arch Calculations 1 day External layout and Rain Water Calculations Sizes of UG & OH Tank, Pumps Schematic Diagram Detailing Schedule of fixtures
Task Split

Tue 1/28/14 Tue 1/28/14 Wed 1/22/14 Wed 1/22/14 Thu 1/30/14 Thu 1/30/14 Thu 1/23/14 Thu 1/23/14 Sat 1/25/14 Mon 1/27/14

1 day 1 day 1 day 1 day 1 day 2 days

Wed 1/29/14 Thu 1/30/14 Mon 2/3/14 Tue 2/4/14 Tue 2/4/14 Thu 2/6/14
External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Page 1 Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress

Project: Tender Design process by Date: Mon 1/20/14

Milestone Summary Project Summary

ID 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131

Task Name

Duration

Start

Finish

Jan 12, '14 Jan 19, '14 W F S T T

Jan 26, '14 Feb 2, '14 M W F S T T

Feb 9, '14 M W

Feb 16, '14 S T T

Feb 23, '14 Mar 2, '14 M W F S T T

Mar 9, '14 M W

Manufacturer List General Notes, List of Dwgs Formatting Printing Archiving Fire Alarm Control Panel location-Arch Calculations Fire Detection system Layout / Zoning Schematic Diagram Load to electrical Detailing Schedule of Equipments Manufacturer List General Notes, List of Dwgs Formatting Printing Archiving Fire Fighting UG Tank / Pump Room Location-Arch

1 day 1 day 1 day 23 days 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 20 days 1 day

Mon 2/10/14 Mon 2/10/14 Fri 2/14/14 Sat 2/15/14 Mon 1/27/14 Mon 2/3/14 Sat 2/8/14 Fri 2/14/14 Thu 2/13/14 Fri 2/14/14 Sat 2/15/14 Wed 2/19/14 Thu 2/20/14 Thu 2/27/14 Fri 2/28/14 Mon 1/27/14 Mon 2/3/14 Fri 1/31/14 Fri 2/14/14 Sat 2/15/14 Sat 2/22/14 Tue 2/4/14 Mon 2/10/14 Fri 2/14/14 Thu 2/13/14 Fri 2/14/14 Sat 2/15/14 Thu 2/20/14 Fri 2/21/14 Fri 2/28/14 Sat 3/1/14 Wed 2/19/14 Mon 2/3/14 Fri 1/31/14

Hose Reel, Hydrant Layouts, 1 day Calculations Confirmation of Size/ Capacity of UG 1 day Tank & Pump Size Schematic Diagram 1 day Detailing Schedule of Equipments Manufacturer List General Notes, List of Dwgs Formatting Printing Archiving HVAC Plant Room (Incase chiller)-Arch CFM & BTU Tonnage Calculation Conformation of Plant Room Size Out Door-Indoor Units Location-Arch Electrical Load- to elec dwgs Ducting Layout / Piping Layout incase of chiller Thermostat Diagram Schematic Diagram Detailing Schedule of Equipments Manufacturer List General Notes, List of Dwgs Formatting Printing Archiving Gas Room Heater,Gas heater Locations -Arch Calculation Piping Layout Schematic Diagram Detailing Schedule of Equipments Manufacturer List General Notes, List of Dwgs Formatting Printing Archiving Tender Document Boq Str Boq Arch Boq Telephone Boq Plumb Boq FA Boq FF Boq HVAC BOQ Gas 1 day 1 day 1 day 1 day 1 day 32 days 1 day 7 hrs 1 day 1 day 1 day 2 days 1 day 1 day 2 days 1 day 1 day 1 day 1 day 18 days 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 26 days 1 day 2 days 1 day 2 days 1 day 1 day 1 day 1 day

Wed 2/19/14 Wed 2/19/14 Thu 2/6/14 Thu 2/6/14

Thu 2/20/14 Thu 2/20/14 Sat 2/8/14 Mon 2/10/14 Thu 2/13/14 Fri 2/14/14 Tue 2/18/14 Tue 2/18/14 Mon 2/24/14 Tue 1/21/14 Tue 1/21/14 Thu 1/23/14 Sat 1/25/14 Fri 1/31/14 Mon 2/3/14 Tue 1/28/14 Fri 1/31/14 Sat 2/8/14 Tue 2/11/14 Thu 2/13/14 Tue 2/18/14 Tue 2/25/14 Wed 2/26/14 Fri 1/24/14 Mon 1/27/14 Fri 1/31/14 Tue 2/25/14 Wed 2/26/14 Tue 1/21/14 Thu 1/23/14 Mon 1/27/14 Sat 2/1/14 Tue 2/4/14 Wed 1/29/14 Thu 2/6/14 Sat 2/8/14 Wed 2/12/14 Thu 2/13/14 Wed 2/19/14 Tue 2/25/14 Wed 2/26/14 Thu 2/13/14 Mon 1/27/14 Sat 2/1/14

Wed 1/29/14 Wed 1/29/14 Mon 2/3/14 Tue 2/4/14 Sat 2/1/14 Thu 2/6/14 Mon 2/3/14 Fri 2/7/14

Mon 2/10/14 Tue 2/11/14 Fri 2/14/14 Sat 2/15/14

Sat 2/15/14 Mon 2/17/14 Mon 2/10/14 Tue 3/11/14 Mon 2/10/14 Mon 2/10/14 Mon 2/10/14 Tue 2/11/14 Thu 2/27/14 Fri 2/28/14 Mon 2/17/14 Tue 2/18/14 Mon 3/10/14 Tue 3/11/14 Sat 3/1/14 Mon 3/3/14 Fri 2/28/14 Fri 2/28/14 Mon 2/17/14 Tue 2/18/14 Tue 3/4/14 Tue 3/4/14 Wed 3/5/14 Wed 3/5/14 Fri 3/7/14 Sat 3/8/14

Specifications 1 day Tender Conditions 1 day Formatting Printing Archiving Bindings 1 day

Task Split Project: Tender Design process by Date: Mon 1/20/14 Milestone Summary Project Summary

External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Page 2

Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only

Finish-only Deadline Progress