FORMWORK CARRIAGE
for bridge edge beams and accessories
BRIDGE CONSTRUCTION
ROBUSTA-GAUKEL
GMBH &CO.KG
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR BRIDGE EDGE BEAMS
BRCKENBAU
FORMWORK CARRIAGE FOR BRIDGE EDGE BEAMS
General information:
safe and quick working when casing and concreting bridge egde beams modular system built of carriage units L = 5.26 m connected carriages movable as one unit quick adjusting of the formwork molding construction with spindles and free wheeling wrench. All horizontal and vertical directions of adjustment are possible independant from each other and without mutual action effective protection against falling of small parts because of continuous plancking of the working platform made of riffle sheet with lateral edge setting working platform width 2.40 m, if needed turnable at 180, in case the platform may not reach underneath the cantilever all parts for the continuous side protection including all connection parts are delivered to the site, no improvisation with wooden boards provided on the side of the builder necessary wheels 300 mm made of solid steel, adm. load 20 to./wheel, with chocks to secure the carriage against rolling
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR EXTERNAL BRIDGE EDGE BEAMS
2. cantilever girders with diagonal bracing and sliding undercarriage to suspend the working platform W = 3950 kg
3. working platform complete with formwork walings and side protection frames W = 2300 kg
BRCKENBAU
FORMWORK CARRIAGE FOR EXTERNAL BRIDGE EDGE BEAMS
The basic units with a length of 5.26 m can be connected with cross connection elements to individual lengths of the carriage also as polygon.
900
1500 2400
1500 2400
900
The universal construction allows an arrangement of the working platform turned by 180 at narrow space.
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR EXTERNAL BRIDGE EDGE BEAMS
3. step: onnecting of 2 cantilever beams to 1 element with 3 cross struts and 2 diagonal bracings
4. step: placing onto the carriage and installation of the rear anchoring
5. step: mounting of the vertical beams with steel walings to the platform
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR EXTERNAL BRIDGE EDGE BEAMS
7. step: inserting the bolt, fixing the vertical beam to the sliding undercarriage without any risk, workman standing in safe position behind the edge protection.
8. step: the working platform is closed allaround and can be walked on at once without danger.
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR EXTERNAL BRIDGE EDGE BEAMS
Universal and quick possibilities of adjustment: All spindles to adjust the formwork walings can be reached easily from one side, standing on the platform. The adjustment at all spindles can be done quickly with the help of the delivered free wheeling wrench SW 46. During construction we took careof the fact that all horizontal and vertical directions of the steel walings can be adjusted separatly and independent from each other. The steel walings for the side formwork can be inclined with 2 adjustment spindles independent to the vertical beam of the platform, without adjusting the whole platform. The special effect: The steel waling adjusted to a special angle can be adjusted subsequently in height without changing the angle. The result is a enormous quick adjusting and time saving. Additionally an adjustable brace is fixed at the lower side of the girder to adjust the complete suspended construction in horizontal direction. With the help of the inclinded brace the vertical girder will be placed into the vertical position with the formwork construction. After that the fine adjustment of the formwork as decribed above can be done.
BRCKENBAU
FORMWORK CARRIAGE FOR INTERNAL BRIDGE EDGE BEAMS
Solutions for the encasing of internal bridge edge beams:
When producing internal edge beams several types of methods have to be concerned. We are offering a perfect solution for each method. A: Both bridge superstructures have been completed in carcase works. The carriage can be placed on both bridges. Production of the bridge edges either one sided or both parallel B: The first bridge superstructure is finished and already under traffic. Therefore the carriage can be placed only on the second bridge superstructure in carcase works. Production of the edges beams only possible one sided. The same configuration occurs also at renovations of bridges. In this case it is very important that there is no contact to the other bridge under traffic with vibrations or shocks. For both demands ROBUSTA-GAUKEL offers optimized solutions of formwork, which will replace solutions on site and shuttering works with lots of time effort. Optimized solutions of shuttering for economical work: 1) Both edge beams will be concreted at the same time. 2) One edge beam will be concreted without contact to the other already finished beam. Maximum safety: In both cases the working platforms and the formwork are suspended with different tie rods. Thus an unintentional loosening and the violent downfall of the platform is reliably prevented.
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR INTERNAL BRIDGE EDGE BEAMS
10
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR INTERNAL BRIDGE EDGE BEAMS
Formwork solution: both bridge edge beams simultaneously
counter nut and counter plate to fix the wedge layers against pivoting when concreting and vibrating.
adjusting nut and counter plate to adjust the height of the wedgeformed metal sheet layer.
For the casing and striking of the internal edge beams we provide a mechanism using steel wedge insertions. The side formwork made of wood must have according inclined wooden layers on the back side. To adjust the correct lateral distance for the gaps between the edge beams the wedges at the spindles can be lifted or lowered exactly in height. For striking the wedge layers will be lifted, the side formwork will come free and can be removed upwards.
11
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR INTERNAL BRIDGE EDGE BEAMS
The basic racks with cantilever girders and ballast placed on one superstructure are identical with the construction for the external edge beams. A main girder willl be placed exactly over the gap between the bridge onto the cantilever beams . The suspension of the working platform is done with an according number of tie rods, the same way as with the carriage at both sides of the bridge (see drawing page 10).
12
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR INTERNAL BRIDGE EDGE BEAMS
Formwork solution: one bridge edge beam, one sided
For the lateral fixing and holding of a one sided formwork with bottom a clamping rail will be clamped with anchors to the lower side of the bridge. Because of the continuous longitudinal gap of the clamping rail it can be fixed independent to the distances of the concreted anchors. This clamping rail is used as an abutment to take up the pressure of concrete with the help of a swingable anchor tie rod and as a supporting console to clamp the formwork close to the lower side of the bridge.
100
2400
wooden wedge layer, on the part of the builder nut with swivelling plate pressing spindle clamping rail
Encased for concreting: Clamping rail clamped, thus the formwork will be thightened. If needed the formwork can be pressed against the lower side of the bridge with the help of the pressing spindle.
Striked for moving: Clamping rail will be turned down, no removing of loose parts
13
BRIDGE CONSTRUCTION
FORMWORK CARRIAGE FOR BRIDGE EDGE BEAMS
TECHNICAL DATA:
4070
0 75 0 00 /9 0
5260
0 24
Fromwork carriage
basic unit accessories for individual planning on request!
Weight [kg/unit]
8700
Item No.
810000
14
BRIDGE CONSTRUCTION
REWORKING CARRIAGE
General information:
Easy to set up from a few pre-assembled units. Wrap-around side protection including all connection materials included with delivery. No emergency solutions of wood are required! Safe and fast work for renovation, forming and concrete works on bridge molding formwork. Modular set-up system adjusts to different bridge shapes. Effective protection against small parts falling off due to closed floor covering of the work platform made of corrugated sheet metal. The sides are also raised all around.
Because of its compact design and dimensions, the ROBUSTA reworking carriage is fast and uncomplicated to set up, move and change over. It also offers all the safety advantages of a large forming carriage. It can be easily and economically adapted to your own specific usage conditions. The reworking carriage consists of a sturdy, base frame made of steel. It is movable with 4 wheels and very resistant to bending. The boom girders with attached work platform and side protection are mainly made of light-weight aluminium sections. When working on bridges at great heights, safety is the top priority. Because of this, we consistently avoid the use of wood in construction parts intended to provide side protection. The closed base covering made of corrugated sheet metal with a raised side piece guarantees reliable protection against small pieces rolling off and falling down. This is especially important for bridges over travelled traffic routes. The side protection on all four sides is formed from plug-in aluminium frames that are so sturdy that they can be used as a ladder for climbing up and down.
3950
Revisionswagen,
Item No.
820000
15
Berlin office: