Documenti di Didattica
Documenti di Professioni
Documenti di Cultura
February 1994
This document has been prepared under the direction
of the WSA/FWR sponsored Sewerage Working Group
of the Engineering and Operations Committee. WRc
gratefully acknowledges the funding provided by
the Foundation for Water Research in the revision
of this document.
Technical Inquiries
Technical inquiries relating to this document should
be addressed to:
Further copies
Further copies of this document are available from:
The work on updating the document has been carried out by WRc
in close co-operation with the Engineering and Operations
Committee's Sewerage Working Group under the Chairmanship of
Mr W G Sheldon of North West Water. I acknowledge the input of
the Working Group in the work and I expect that this will
ensure that the document continues to be a success in the
future.
BILL FRASER
Chairman
PAGE
ACKNOWLEDGEMENTS 93
(i)
(ii)
SECTION 1 - INSTRUCTIONS TO TENDERERS
GENERAL
1.12 Sub-contractor(s) 5
GENERAL
2. Form of Tender.
3.
Other Requirements as listed in Clause
6.20.
1.3Tender return
2
[It is the retained by the Tenderer.
Engineer's
responsibility to
complete the
Information and
Instruction
Schedule (Section 1.4Interpretation and qualified tenders
6). It is assumed
that where a The Tenderer shall make no alteration to
section of the the documents. Qualifications in the
Schedule is left nature of statements, or interpretation
blank the Engineer of Contract Documents should, if
has elected not to possible, be avoided by referring
use that them to the Engineer during the tender
particular period (Clause 6.1). A qualified tender
clause.] will not be admitted.
1.5Addenda
[This approach to
the return of the Should any additions or changes to the
Tender may not be documents be necessary prior to the date
appropriate. The for submission these will be issued by
Engineer should the Engineer to all Tenderers in the form
check the of written instructions which will form
Employer's part of the documents.
procedures for
letting Tenderers will be required to acknowledge
contracts.] receipt of such instructions in writing.
[The period to be
allowed for the 1.6Late tenders
Tenderer to
prepare his tender Any tender received after the due date
should normally be and time will be rejected by the
4 weeks. This Employer.
period may be
altered if the
Engineer so 1.7Period for acceptance
decides.]
Every tender shall be open to acceptance
by the Employer for the period stated in
Clause 6.4 of the Information and
Instruction Schedule following the date
stated in Clause 6.3 of the Schedule.
1.8Fixed price
1.9Pre-tender inspection
3
[It is preferable being in, on or under private land or
that the Engineer premises, Tenderers wishing to inspect
makes available the site, shall make their own
adequate plans at arrangements with the owner(s) or
the tendering occupier(s) of such land or premises and
stage so that the obtain any necessary permission to enter
Tenderer can thereon. Tenderers will make such entry
ascertain the at their own risk and be responsible for
nature of the any injury or damage whatsoever caused by
Works and what them in the course of entering or leaving
element of the the land or premises or whilst they are
Works is "off the on the land or within the premises. If
highway". If work entry is refused the matter should be
needs to be referred to the person named in Clause
undertaken "off 6.1 who will use his best efforts to
the highway" the arrange matters.
Engineer should
indicate this in If this requires lifting manhole covers
the Information the Tenderer shall only do so with the
and Instruction express permission of the person named in
Schedule and may Clause 6.1. Where in exceptional
provide an circumstances entry into the sewer is
additional Bill required, permission must be obtained in
item. If plans are writing from the person named in Clause
not available the 6.1.
Engineer should
provide as much
detail as possible
in the Information
and Instruction
Schedule. This
clause may be 1.10Acceptance of tenders
deleted for Term
Contracts.] The Employer does not bind himself to
accept the lowest or any tender, nor will
the Employer be responsible for or pay
for any expenses or losses incurred by
the Tenderer in the preparation of his
tender. Where appropriate the Employer
reserves the right to accept the Tender
as a whole or any part or parts thereof
(unless the Tenderer stipulates otherwise
at the time of tendering, in which case
such stipulation must be without
prejudice to the Employer's right to
delete any provisional items or to
amend, vary or modify any works as
provided for under the Contract).
1.11Arithmetical errors
4
[Clause 1.13 to rates will be deemed to stand and the
Clause 1.15 apply extension will be corrected. Where an
to CCTV surveys arithmetical error is found in the make
only.] up of the final sum, the Tenderer will be
informed of the error in writing and
given the choice between withdrawing the
tender or correcting the error.
[See Clause 3.24,
and Clause 2.6.7.]
1.12Sub-contractor(s)
1.13Calibration chart
5
[In Scotland this executed CCTV sewer survey work. This tape
document may need shall be used by the Engineer as one of the
modification(s) to controls against which the performance of the
bring it into line Contractor shall be measured.
with the Law of
Contract under
Scottish Law.]
CLAUSE TITLE
2.1 Definitions
6
2.6 Acceptance, commencement, programme and
contract period 12
2.13 Accident 14
2.14 Insurance 15
2.15 Liquidated damages 16
2.19 Forfeiture 18
8
[Plans will be showing the location of and/or extent of
supplied or made the Survey.
available prior to
tender as listed 2.1.10 Survey means the work referred to in
in Clause 6.12.] the Contract which is intended to be
executed and performed by the Contractor
on under in or through the site.
2.2Engineer's Representative
9
allow the Engineer Conditions of Contract, and any act of
to liaise with the any such person within the scope of his
Highway authority shall, for the purposes of the
Authority.] Contract, constitute an act of the
Engineer. Prior notice in writing of any
such authorisation shall be given by the
Engineer to the Contractor. Such
authorisation shall not be given in
[The Engineer respect of any decision to be taken or
shall delete certificate to be issued under Clauses
either clause 2.6, 2.17.3, 2.18.3 or 2.21.1.
2.6.2 and/or 2.6.3
whichever shall
not be applicable 2.3Assignment and sub-letting
see Clause 6.6.]
2.3.1 The Contractor shall not assign
the Contract or any part thereof or any
benefit or interest therein or thereunder
without the written consent of the
Employer.
2.3.2 The Contractor shall not sub-let
the whole of the Works. Except where
otherwise provided by the Contract the
Contractor shall not sub-let any part of
the Works without the written consent of
the Engineer and such consent if given
shall not relieve the Contractor from any
liability or obligation under the
Contract and he shall be responsible for
the acts, defaults and neglects of any
Sub-contractor, his agents, servants or
workpeople as fully as if they were the
acts defaults or neglects of the
Contractor, his agents, servants or
workpeople.
2.4Contract documents
10
Engineer may wish for providing:
to make it the
Contractor's (a)plans necessary for the
responsibility for location of sewers and access points
locating the except where the Contractor is
manhole covers. If specifically required to locate the
so this should be sewers and access points by some other
stated in Clause provision of this document.
6.20.]
(b)two full copies of the
contract documents.
2.4.3 The Contractor shall give
adequate notice in writing to the
Engineer of any further information or
instruction that the Contractor may
require for the execution of the Survey
or otherwise under the Contract.
2.5General obligations
11
[Clarification by water and sewerage
shall be given by
the Engineer on undertakers on land, approved by the
the nature of Secretary of State under Section 182 of
accidents to be the Water Industry Act 1991.
notified.]
2.6Acceptance, commencement, programme and
contract period
12
[This clause may the Engineer of the reasons for his
be deleted by the departure and the proposed date and time
Employer if he for his return.
considers the use
of liquidated 2.6.6 If for any reason (which does not
damages in- entitle the Contractor to an extension of
appropriate.] time) the rate of progress of the Survey
is at any time in the opinion of the
Engineer too slow, the Engineer shall so
notify the Contractor in writing and the
Contractor shall thereupon take such
actions as are necessary as the Engineer
may approve to expedite progress so as to
complete the Survey by the prescribed or
extended time. The Contractor shall not
be entitled to any additional payment for
taking such actions. If as a result of
any notice given by the Engineer under
this clause the Contractor shall seek the
Engineer's permission to do any work at
night or at weekends, such permission
shall not be unreasonably refused.
2.8Employer's responsibilities
13
[The Engineer (e)providing clear, readable
shall make copies of plans showing the sewers to
allowances for any be surveyed.
additional works
by extending the (f) arranging any road
Contract period if closures necessary for the Works.
appropriate.]
(g)Traffic matters related to
traffic-sensitive areas in the context
of the New Roads and Street Works Act
1991.
2.9Public relations
14
[It may be 2.10Contractor's responsibility: health and
necessary to hire safety
stand-pipes and to
enter into an 2.10.1 The Contractor shall take full
agreement with the responsibility for the adequacy of site
water undertaker. operations and methods of carrying out
If a supply from the Survey and compliance in all respects
the water with the requirements of applicable EC
undertaker is directives, general or local acts of
unavailable, or Parliament, regulations and by-laws of
for reasons of any local or statutory authority. The
economy, the Contractor shall be responsible for the
Engineer may allow safety of all site operatives and
the use of sewage operations.
effluent or a
surface water
supply.] 2.11Skilled operators and supervision
15
[The issue of any or of any other person and the Contractor
Statutory Notice shall save harmless and indemnify the
shall be the Employer in respect of all claims,
responsi- bility demands, proceedings, damages, costs,
of the Employer. charges and expenses whatsoever arising
The Engineer's out of or in relation to any such
attention is drawn matters.
to the
requirements of
the New Roads and 2.13Accident
Street Works Act
1991, The Code of 2.13.1 Should any accident occur on or
Practice for the in the vicinity of the site, the matter
Co-ordination of shall be reported immediately to the
Street Works and Engineer.
Works for Road
Purposes and
Related Matters,
November 1992, and 2.14Insurance
The Street Works
(Registers, 2.14.1 The Contractor shall indemnify
Notice, Direc- the Employer against all losses and
tions and claims for injury or damage to any person
Designations) or property whatsoever which may arise
Regulations, out of or in consequence of the carrying
Statutory out of this Contract and against all
Instrument No. claims, demands, proceedings, damages,
2985 1992, all costs, charges and expenses whatsoever
published by HMSO. provided that the Contractor shall not be
Provision is made required to indemnify the Employer
in Clause 6.18 for against:
the Engineer to (a)any action by the Employer,
indicate known his agents and servants.
traffic sensitive
areas.] (b)any compensation or damages
for or with respect to crops being on
[Where considered the site (except where possession has
necess- ary by the not been given to the Contractor) or
Engineer, the with respect to the use or occupation
Employer may need of the land which has been provided by
to supply signs to the Employer.
the Contractor.]
(c)damage which is the
unavoidable result of the execution of
the Survey in accordance with the
Contract.
[A Bill item is 2.14.2 The Employer shall not be liable
provided for the for or in respect of any damages or
provision of compensation payable at law in respect or
traffic lights, in consequence of any accident or injury
etc, see Clause to any workpeople or other person in the
4.8.5.] employment of the Contractor or any
Sub-contractor save and except to the
extent that such accident or injury
results from or is contributed to by any
act or default of the Employer, his
16
[This may entail agents or servants, and the Contractor
the use of a shall indemnify and keep indemnified the
permit to enter Employer against all such damages and
the sewer before compensation (save and except as
commencing any aforesaid) and against all claims,
part of the Works. demands, proceedings, costs, charges and
The Engineer is expenses whatsoever in respect thereof or
advised to consult in relation thereto.
the Employer's
policy/procedures.] 2.14.3 The Contractor shall secure the
indemnities above by entering into such
insurance or otherwise as the Employer
shall approve, which shall include
Employer's Liability and Public Liability
insurance. The policies and premium
receipts shall be produced upon the
request of the Employer. Such policies
and receipts to be supplied to the
Employer within 28 days of the acceptance
of Tender and at other times as requested
by the Engineer. The insurances shall be
for at least the amount stated in Clause
6.16 of the Information and Instruction
Schedule in respect of any one claim or
series of claims arising out of any one
event and unlimited in any one year of
insurance.
17
[Clause 3.15.3 to Survey Report within the prescribed time,
Clause 3.15.7 or any extension thereof granted under
apply to CCTV Clause 2.6.4, the Contractor shall pay to
sewer surveys the Employer for such default the sum
only.] stated in Clause 6.15 for every week or
part week which shall elapse between the
date on which the prescribed time or any
extension thereof expired and the date of
completion of the Survey or the Survey
Report. All sums payable by the
Contractor to the Employer pursuant to
this clause shall be paid as liquidated
damages for delay and not as a penalty.
18
[Clause 3.19.1 and not later than 28 days after the
applies to sewers event and shall make contemporary records
up to 2000 mm to support his claim which shall be
diameter. Over produced to the Engineer upon request.
this size a The Engineer shall certify for payment
separate such sums to which in his opinion the
specification will Contractor is entitled.
be required.]
19
[The Engineer in accordance with the Bill of
should note that Quantities. The Contractor shall submit
if photographs are such records to the Engineer's
specified in Representative at intervals not exceeding
Clause 6.32 then seven days (see Clause 6.20 of the
the camera will Information and Instruction Schedule).
have to be stopped
when these are The Engineer's Representative shall
being taken.] certify such records for record purposes
only and the Engineer shall have sole
power to authorise payment if payment is
due. A copy of each record shall be
supplied to the Engineer's
Representative.
20
in writing and the items affected. The Contractor shall
then submit an interim claim for the items not in dispute
(see Clause 2.18.2) together with a revised statement of
final account.
2.19Forfeiture
21
then the Employer may after giving 7 days' notice in
writing to the Contractor enter upon the site of the
Survey and expel the Contractor therefrom without thereby
avoiding the Contract or releasing the Contractor from any
of his obligations or liabilities under the Contract or
affecting the rights and powers conferred on the Employer
or the Engineer by the Contract and may himself complete
the Survey or may employ any other Contractor to complete
the Survey and the Employer or such other Contractor may
use for such completion so much of the Survey materials
and data which have been deemed to become the property of
the Employer. By the said notice or by further notice in
writing within 14 days of the date thereof the Engineer
may require the Contractor to assign to the Employer and
if so required the Contractor shall forthwith assign to
the Employer the benefit of any agreement for the supply
of any survey materials and data and/or for the execution
of any work for the purpose of this Contract which the
Contractor may have entered into.
2.22Tax matters
22
[The Engineer directly in respect of the Survey) shall
should specify be added to or deducted from payments
whether pipe otherwise due to the Contractor under the
length references Contract.
or manhole
references are to
be used.] 2.23Value Added Tax
2.24Copyright
23
[Surveys are SECTION 3 - SPECIFICATION
undertaken for
different types of
work and varying CLAUSE TITLE
methods are
adopted by
different GENERAL
Employers for 3.1 Extent of survey
organising and
supervising the 3.2 Location
work and for
storing the 3.3 Survey units
information. This 3.4 Survey vehicle
results in the
need for different 3.5 Supply of water
types of Survey
Report. The Survey 3.6 Parked vehicles
Report 3.7 Traffic
requirements are
indicated in 3.8 Police notification
Clause 6.31 and
shall include Site 3.9 Manholes
Coding Sheets, 3.10 Dealing with flow and blockages
i.e. the Coding
Sheets completed 3.11 Advance notice
in accordance with
Clauses 3.27 and 3.12 Health and safety
2.11.1, and visual 3.13 Noise
data i.e. the
video cassette 3.14 Metric measurements
tapes and
photographs SEWER CONDITION INSPECTION
covering the 3.15 Survey and operational equipment
Survey. In
addition, some or 3.16 Abandonment of Survey
all of the
following items 3.17 Equipment Recovery
may be included: 3.18 Forced Ventilation
24
only). Manually 3.27 Site coding sheets
checked Coding
Sheets: i.e. 3.28 Drawings
typed Coding
Sheets produced 3.29 CCTV Photographs (off screen
in the office colour) 35
after manually 3.30 Control sample photographs and/or
checking the video tapes
Site Coding
Sheets filled 3.31 Type and extent of survey
in as
instructed. 3.32 Monochrome CCTV
3.33 Colour CCTV
(c) Magnetic
tape, etc.: 3.34 Focus/iris/illumination
i.e. the supply
of the survey 3.35 Video playback
data in 3.36 Contractor's quality control
computerised procedure 40
form using
diskette or 3.37 Random selection
magnetic tape
or in the 3.38 Survey extraction
computer format 3.39 Checking
requested by
the Sewerage 3.40 Examples of quality control
Undertaker or
the Local Diagram 1 Definition of manhole length
Authority. Diagram 2 Definition of camera cable
calibration
(d) Longhand
Format Report:
i.e. a machine
printed report
produced by the
Contractor from
validated
computer data
summarising the
findings of the
Survey and
giving complete
defect
descriptions
rather than
defect codes.
(e)
Annotated
Drawings: i.e.
the drawings
issued to the
Contractor
annotated by
the Contractor
to record
significant
25
errors and 3. SPECIFICATION
variations
found during
the Survey.] GENERAL
3.1Extent of survey
3.6Parked vehicles
26
[This document 3.6.1 The Contractor shall inform the
excludes In Sewer Engineer where parked vehicles are found
Photography (ISP) to impede the progress of the Survey and
which is no longer shall continue with the next available
used due to the length to be surveyed. The Engineer shall
improvement in then give instructions as to what action
colour CCTV. If is to be taken.
ISP is required,
reference should
be made to the
second edition of
the model contract
document for non 3.7Traffic
man entry sewer
inspection 3.7.1 The Contractor shall comply with
published in the requirements of the New Roads and
1986.] Street Works Act 1991 together with any
Regulations enacted thereunder and Codes
of Practice relating thereto.
3.7.2 The Contractor shall comply with
the relevant provisions of the Traffic
Safety Measures for Road Works as
contained in Chapter 8 of the Traffic
Signs Manual and the booklet Safety at
Street Works and Road Works published by
Her Majesty's Stationery Office.
3.8Police notification
3.9Manholes
28
[The Engineer may 3.10.1 Pre-cleaning of sewers is covered
need to seek in Clause 6.17 but does not form part of
advice on the this Contract.
acceptability of
any alternative 3.10.2 The Contractor shall be
test device responsible for dealing with flow as far
proposed. as is reasonably possible by temporary
stoppering for limited periods without
affecting the general effectiveness of
the sewer. Such arrangements shall be
subject to the Engineer's approval.
3.11Advance notice
29
normally preferred (issued from time to time) and in
with maximum particular Guideline No. 2 "Safe Working
illumination to in Sewers and at Sewage Works". In
achieve maximum addition to the National Guidance
depth field.] Publications the Contractor shall
recognise all local health and safety
requirements as may be listed in Clauses
6.18 and 6.19.
3.14Metric measurements
30
[Other methods may clearance of all equipment, etc. from the
be approved by the site on completion of the Survey. The
Engineer.] Contractor shall make all reasonable
efforts to gain access into the manhole
for a period of 15 minutes. If failure
results he shall proceed to the next
manhole but shall report the difficulty
to the Engineer who shall make
arrangements for the seized manhole cover
to be freed.
31
[See Appendix B non-elastic material to ensure the smooth
for example.] and steady progress of the CCTV camera.
All winches shall be inherently stable
under loaded conditions.
[See Appendix B
for example.]
32
[The Contractor's arrangements laid down in Clause 6.13),
attention is also of his inability to maintain picture
brought to quality and shall then continue with the
provisions set out Survey pending a decision by the Engineer
in Clause 6.18.] on the merits of continuing.
33
[This clause is possible or proceed to the next length of
provided for sewer to be surveyed or proceed as
guidance only and directed by the Engineer.
the Engineer may
wish to omit or
add to as 3.17Equipment recovery
necessary
dependent on the 3.17.1 The Contractor shall be
Employer's policy responsible for all his costs relating to
and procedure.] the recovery of or damage to his camera
system and any other equipment in any
sewer forming part of the Survey and the
Contractor shall be liable for all costs
and damages incurred by the Employer in
the recovery of such equipment UNLESS the
Contractor has demonstrated to the
satisfaction of the Engineer that the
loss of such equipment was for reasons
beyond the Contractor's control.
3.17.2 If excavation is necessary this
shall be carried out only after the issue
of a written instruction from the
Engineer.
3.18Forced Ventilation
34
3.20Photographic camera position - Man entry
surveys
35
3.21.2 The camera shall be "stopped"
whenever defects are being noted on the
coding sheet.
3.22Linear measurement
36
3.23.1 At the start of each sewer length
being surveyed, the length of sewer from
zero chainage up to the cable calibration
point shall be recorded and reported in
order to obtain a full record of the
sewer length (see diagram No.2).
� Date of survey.
� Road name/location.
� Direction of Survey.
37
� Automatic update of the camera's
metreage position in the sewer line
from adjusted zero (see Clause
3.23.1).
� Sewer dimension.
38
3.25.3 The illumination described in
Clause 3.25.1 shall be capable of
allowing the camera to operate in all
sewers at an iris setting providing an
adequate depth of field for the size of
sewer being surveyed.
3.26Survey reporting
39
3.27.2 Each sewer length shall be
recorded in the format laid down in the
WAA/WRc "Manual of Sewer Condition
Classification" Third Edition published
1993. Any changes shall be noted in
Clause 6.31. Where a length of sewer
between consecutive manholes is surveyed
from each end (due to an obstruction) two
coding sheets should be used.
40
qualification for sewer survey and fault
classification as issued by Water
Training or other equivalent body for the
type(s) of sewer being inspected. Copies
of these certificates shall be deposited
with the Engineer before commencement of
the Survey.
3.28Drawings
41
photograph in brick sewers.
42
the Contractor to provide a sample of the photographs
and/or CCTV tapes taken during the contract period. The
Contractor shall provide the information within 5 working
days of receiving the written instruction.
3.32Monochrome CCTV
43
Resolution
3.33Colour CCTV
� White
� Yellow
� Cyan
� Green
� Magenta
� Red
� Blue
� Black.
44
monitor shall be of such quality as to enable the
following to be achieved:
Shades of grey
Linearity
The background grid shall show squares of equal size,
without convergence/divergence over the whole of the
picture. The centre circle shall appear round and have the
correct height/width relationship (+5%).
Resolution
3.34Focus/iris/illumination
45
3.35Video playback
46
carried out by one surveyor over a
period of time (normally 1 year).
3.38Survey extraction
3.39Checking
47
checking each error/omission should be
highlighted on the report from which the
following totals are calculated for each
survey report:
48
Water Training (or equivalent body) Post
Course Test for Pipe and Brick Sewer
Condition Classification (see Clause
2.11.1).
Code Code
FH FH
Measured le
for CCTV su
and for pay
FH
Uncharted
Measured length manhole
for CCTV survey (whether
and for payment buried
or not) 0.00 chainage
ST
Measured le
for CCTV su
and for pay
FH FH
Measurement Measurement
covered in covered in
manhole survey manhole survey
50
(a) For circular or regular shaped sewers (plan view)
Diameter
of sewer
Cable calibration
H/3
H
2H/
Camera cable
calibration length
Diagram 2 - Definition of camera
cable calibration (Clause 3.23.1)
51
SECTION 4 - PREAMBLE TO THE BILL OF QUANTITIES
GENERAL
53
Drawings and the Information and Instruction Schedule
shall be read in conjunction with the Bill of Quantities.
The work or materials covered by items in the Bill of
Quantities are as detailed in the Specification.
4.2Stated quantities
4.4Rates to include
4.5Unpriced items
54
4.5.1 Any items left unpriced should have the word
"Inc." inserted in the Tender, but in any event unpriced
items will be held to have had their costs included in the
prices for other items of work. Items shall not be
bracketed together.
4.6Preliminary item
4.8Method of measurement
55
outside the Contract period, it shall be on a dayworks
basis.
4.9Working hours
4.10Dayworks rates
4.10.1 Work ordered by the Engineer to be carried out on
a dayworks basis will be valued at the appropriate
Contract Rates for Dayworks in the Bill of Quantities,
which shall be inclusive of all the Contractor's costs,
including supervision, all overheads and profit.
56
4.10.2 The rates for dayworks shall include for all items
covered by the Bill rates.
4.11Dayworks quantities
4.14Engineer's instructions
4.15Provisional items
4.16Fixed price
4.16.1 The Contractor shall include in his rates entered
in the Bill of Quantities for any variation in the price
of materials, labour rates and any other costs whatsoever
except labour tax matters described in Clause 2.22 and
Value Added Tax described in Clause 2.23 which he
anticipates might take place during the term of the
57
Contract and it must be clearly understood that no
additional payment will be allowed in respect of any
increase in such prices, rates or other costs.
4.17Term contracts
4.18Equipment set up
5.1.5Manhole up to 3m deep. No
61
5.1 cont.
62
5.1 cont.
64
Provision of survey team(s) and mobile vehicle with
specified equipment.
5.4 - SUMMARY
Amount
� p
65
Page 55 Measured Work
Page 56 Measured Work
Page 57 Measured Work
Page 58 Dayworks CCTV surveys
Page 59 Dayworks Man Entry surveys
TOTAL ------------
�
------------
66
SECTION 6 - INFORMATION AND INSTRUCTION SCHEDULE
ADDRESSES
CALENDAR OF EVENTS
6.5 Programme 63
CONTRACT INFORMATION
6.10 Employer 64
6.11 Engineer 65
FINANCIAL INFORMATION
6.14 Interim payments 66
OPERATIONS INFORMATION
67
6.17 Pre-cleaning of sewers 67
GENERAL
REPORT
6.33 Negatives 74
STATEMENT
6.34 Engineer's statement of modifications to standard
document 75
ADDRESSES
68
6.1 Enquiries about the
tender documents
shall be addressed to:
.......................................................................
.......................................................................
Tel No.:
.......................................................................
.......................................................................
.......................................................................
CALENDAR OF EVENTS
.......................................................................
.......................................................................
69
6.6 The Contractor will be required to commence the Survey
within:
........................................(Tick as appropriate).
NOTE:
CONTRACT INFORMATION
.......................................................................
70
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
71
6.13 Liaison arrangements. (This item may be left blank at the
time of Tender but must be completed on the award of the
Contract):
..............................................................
..............................................................
Tel:
..............................................................
(b) The Engineer's Representative,
..............................................................
may be contacted during office hours at:
..............................................................
..............................................................
Tel:
..............................................................
..............................................................
..............................................................
..............................................................
..............................................................
FINANCIAL INFORMATION:
72
amount less than �..................
(Tick as appropr�2,000,000
OPERATIONS INFORMATION
..................................................................
.......................................................................
.......................................................................
.......................................................................
73
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
GENERAL
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
74
6.21 Additional quality control procedures:
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
.......................................................................
MONOCHROME COLOUR
Foul
Surface
Combined
75
.......................................................................
.......................................................................
.......................................................................
* delete as necessary
Recommended Standard
.......................................................................
.......................................................................
.......................................................................
.......................................................................
76
6.27 Provisions for site coding and qualifications of
operatives:
.................................................................
.................................................................
.................................................................
.................................................................
.....................................................................
.....................................................................
.....................................................................
.....................................................................
79
6.32Photographs
............................
Crack
Fractures
Deformation
Collapse
Dropped invert
Mortar loss
80
(iii)Pipe sewers
Crack
Fractures
Broken pipes
Deformation
Collapse
..............................................................
..............................................................
..............................................................
6.33Negatives
Clause No.
Change Made
Signed:
Designation:
Date
82
SECTION 7 - FORM OF TENDER
CONTRACT: .........................
SURVEY WORKS
To: ..........................................................
................................................................
................................................................
................................................................
Gentlemen,
We are, Gentlemen,
Yours faithfully
................................................ Signature
Duly Authorised Signatory
...................................................... Status
........................................................ Date
Name of Firm:
...............................................................
Registered address:
................................................................
................................................................
.
................................................................
Address for
correspondence:
................................................................
83
(if different
from above)
................................................................
................................................................
................................................................
Telephone No.
................................................................
84
SECTION 8 - NON-COLLUSIVE TENDERING CERTIFICATE
(to be completed by Tenderers)
.......................................................................
Signature
Duly Authorised Signatory
.......................................................................
Status
.......................................................................
Date
Name of Firm:
................................................
Registered Address:
................................................
................................................
85
................................................
Telephone No.:
................................................
86
87
APPENDICES
Contract:
.......................................................................
I/We acknowledge receipt of the following Tender Documents
relating to the above.
1. Instructions to Tenderers.
2.
Conditions of Contract.
3. Specification.
5. Bill of Quantities.
7. Form of Tender.
8.
Non-Collusive Tendering Certificate.
9. Appendices.
Date......................... Signed:
..................................................
Director/Partner/Secretary
Tenderer's Name:
....................................................
....................................................
....................................................
....................................................
.................Post Code...................
Telephone No:
....................................................
90
91
APPENDIX B - QUALITY CONTROL
93
RIG MANAGER:___________________________________
Actual
Errors
Actual
Errors
Actual
Errors
Actual
Errors
Actual
Errors
Actual
Errors
Actual
Errors
Actual
Errors
Actual
Errors
SURVEY DETAIL RATING
CONTROL UNIT -
Q.C. SUM X
ACTUAL �
ERRORS 5
RESULTS
CONTROL UNIT -
Q.C. SUM X
ACTUAL �
ERRORS 5
RESULTS
CONTROL UNIT -
Q.C. SUM X
ACTUAL �
5
ERRORS
RESULTS
CONTROL UNIT -
Q.C. SUM X
ACTUAL �
ERRORS 5
RESULTS
CONTROL UNIT -
Q.C. SUM X
ACTUAL �
ERRORS 5
RESULTS
100
90 X
X
X
80 X
X
70
60
50
Rig Manager: T Smith Surveyor Accuracy Graph
LINEAR MEASUREMENT AUDIT FORM
Date of
1 Marker
Marker0
Marker1
Marker2
Marker3
Marker4
Marker5
Metres
Diff(�) 0.2 0.2 0.2 0.2 0.2 0.2 0.2
20 0.3 0.3 0.3 0.3 0.3 0.3 0.3
30 0.4 0.4 0.4 0.4 0.4 0.4 0.4
40 0.5 0.5 0.5 0.5 0.5 0.5 0.5
Engineer's Observations:
signature
PICTURE QUALITY AUDIT FORM
Week:Date of
Test Standard
Focus Far to
IlluminaMinimum/
ApertureOpen
Central Less
ContrastMin 5
FocusingCrisp
Monitor No of
Video No of
Video No.
Tape Digits
EngineerObservations: P-Pass Tot
Signature: Action-YN
Adjust-YN Per
Replace-YN
APPENDIX C - SOURCES OF INFORMATION
3.
NATIONAL JOINT HEALTH AND SAFETY COMMITTEE FOR THE WATER SERVICE H
Guideline No. 2 - Safe Working in Sewers and at Sewage Works and G
Respiratory Protective Equipment.
9.
WATER SERVICES ASSOCIATION. Civil Engineering Specification for th
Edition 1993.
The group gratefully acknowledges the large number of people who offer
the drafting stages of this document and the following members of the
The Sewerage Working Group welcomes any comments which should be addre
Nick Orman
Technical Secretary
WSA/FWR Sewerage Working Group
WRc Swindon
Frankland Road
Blagrove
Swindon
SN5 8YF
MODEL CONTRACT DOCUMENT FOR SEWER CONDITION INSPECTION
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
##################################################################################
#########################################