SECTION 07110 SHEET MEMBRANE WATERPROOFING
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

ENGG

CERT

PMT

SUBSECTION INDEX Part 1 - General

DESCRIPTION

1.01 1.02 1.03 1.04 1.05

Description Applicable Codes and Standards Quality Control Submittals Product Handling

Part 2 - Products
DATE JOB/EWO

2.01 2.02

General Materials

REV. NO.

Part 3 - Execution 3.01 3.02 3.03 Installation Protection Inspection

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

PART 1 - GENERAL 1.01 Description A. General: All underground reinforced concrete structures when located within the water table and the capillary fringe and as shown on the Drawings shall be totally enveloped (tanked) with waterproofing membrane. This section does not cover reinforced concrete structures above the water table and out of capillary fringe. B. Work Included: This section covers the furnishing and installation of membrane waterproofing materials as required on concrete structures. Contractor shall furnish all labor, materials, tools and equipment required to complete the Work. Related Work Specified Elsewhere: 1. 2. Section 01005 - Miscellaneous Requirements. Section 01400 - Quality Control.
DWG. TYPE PLANT NO. INDEX DRAWING NO.

CERTIFIED _ __________
DATE: ________

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

Date:

C.

SECTION 07110
SHT. NO. REV. NO.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

1 OF 6

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

ENGG

CERT

3.

Section 02210 - Excavation, Trenching, Back-filling and Compacting. Section 03300 - Cast-in-Place Concrete.

4. 1.02

Applicable Codes and Standards A. The following codes and standards are intended to provide an acceptable level of quality for materials and products. The requirements of latest editions of these codes and standards shall apply. In case of conflict between these standards and text of this Specification, the Specification text shall govern: 1. ASTM - American Society for Testing and Materials: a. ASTM D 41 - Specification for Asphalt Primer Used in Roofing, Damproofing and Waterproofing. ASTM D1751 - Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Non-extruding and Resilient Bituminous Types). ASTM D4586 - Specification for Asphalt Roof Cement, Asbestos-Free. ASTM E96 - Test Methods for Water Vapor Transmission of Materials

DATE JOB/EWO

DESCRIPTION

b.

REV. NO.

DISCIPLINE ENGINEER

c.

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

d.

CERTIFIED _ __________
DATE: ________

1.03

Quality Control A. Contractor shall be responsible for the quality of all work and materials to be used in the Work and shall propose quality control program for review. The program shall cover shop inspection, field supervision and the installation procedures in compliance with Section 01400 - Quality Control.

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

1.04

Submittals Contractor shall submit the following information, data and drawings, to the Saudi Aramco Representative: A. Before Commencing Work: 1. Manufacturer's recommended specification and instructions for transporting, handling and storage of materials. Certificate of compliance stating that the materials used and the installation procedures conform to all requirements of this Specification.
DWG. TYPE PLANT NO. INDEX DRAWING NO.

Date:

2.

SECTION 07110
SHT. NO. REV. NO.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

2 OF 6

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

CERT

3. 4.

Qualifications of the waterproofing membrane installers. Contractor's proposed installation procedures based instructions and recommendations by the manufacturer. on

ENGG

5.
DESCRIPTION

Manufacturer's Quality Control and Quality Assurance Program related to the production, testing and handling. Catalog data sheets related to proposed materials and 3 sets of samples for all proposed materials.

6.

B.

At Completion of Work: As-built drawings prepared in accordance with Section 01000, General Specifications.

1.05
DATE JOB/EWO

Product Handling A. All materials shall be delivered to site in manufacturer's original containers and pallets. Each container and pallet shall include a packing list in a waterproof envelop. The materials shall be checked against packing lists on delivery to the work site and shall be inspected for damage. Damaged materials shall be removed from the site. Each container and individual roll of membrane sheet shall be labeled to show brand name, type of material, lot and shelf life, date of manufacture, batch number and instructions for storage and handling, if any. All materials shall be adequately protected during shipment, loading and unloading, storage and installation against incidental damage, sunlight and UV radiation, rain, and high temperatures. The materials shall be stored in dry, shaded and covered areas. In open areas the material shall be covered with a heavy duty black PVC sheet. The rolls of membrane shall be stored vertically on a smooth hard surface. All necessary precautions shall be taken to prevent fire hazards in the storage area and during installations.

REV. NO.

B.

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

C.

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

D.

CONSTRUCTION AGENCY
________________ DATE:

E.

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

F.

Date:

SECTION 07110

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

3 OF 6

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

PART 2 - PRODUCT 2.01 General A. All materials and products covered by these Specifications shall be procured from an in-Kingdom manufacturer. Procurement of materials and products from an out-of-Kingdom manufacturer/supplier must be approved by the Saudi Aramco Representative.

DESCRIPTION

ENGG

CERT

2.02

Materials A. Membrane: Shall be preformed, cold applied, self-adhering, laminated sheet membrane. The laminate shall consist of glass fiber core coated on both side with a polymer modified rubber bitumen compound. The membrane shall have a polypropylene film bonded on one side and a siliconized release paper backing on the adhesive side. The nominal thickness off the laminate shall be 1.5 mm. Moisture vapor transmission rate shall not exceed 0.2 gm/m2/24 hours measured according to ASTM E96. The glass fiber core shall be nonwoven mat with minimum mass of 50 gms/m2. B. Solar Reflective Membrane: Shall have similar construction as the membrane above but the exposed face shall have solar reflective properties. Primer: Shall be solvent based bituminous primer conforming to ASTM D41. The primer shall be compatible with the membrane and shall ensure proper adhesion. Flashing Compound: Shall be trowel grade, cold applied rubberized bitumen cement, conforming to ASTM D4586. Fillets: Shall be extruded PVC triangular shaped 40 x 40 mm Sections coated with self-adhesive compound. Protection Board: Shall be either of the following: 1. 6 mm thick sandwich board. The core shall consist of fine aggregate bounded in modified bitumen covered with 2 layers of tough asphalt paper. 12 mm thick sandwich board. The core shall consist of granulated cork bound in modified bitumen and encased in 2 layers of tough asphalt paper conforming to ASTM D1751. 3 mm thick tempered masonite boards incorporating resin and I mpregnating with hot drying oils.
DWG. TYPE PLANT NO. INDEX DRAWING NO.

REV. NO.

DATE JOB/EWO

DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

C.

CERTIFIED _ __________
DATE: ________

D.

CONSTRUCTION AGENCY
________________ DATE:

E.

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

F.

Date:

2.

3.

SECTION 07110
SHT. NO. REV. NO.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

4 OF 6

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

PMT

CERT

PART 3 - EXECUTION 3.01 Installation A. Typical installation details shall be in accordance with the Drawings, and Details for Membrane Waterproofing of Concrete Structure. 1. The concrete surfaces shall be dry and free of all dust and debris. All sharp protrusions shall be ground smooth and all hollows and honeycomb voids, and similar surface defects shall be filled with approved concrete fillers in accordance with Section 03300, Castin-Place Concrete. The concrete surfaces shall be painted with one coat of bitumen primer and allowed to dry until touch dry. The adhesive side of membrane sheets shall be unrolled onto prepared surfaces after progressively peeling back the protective release paper. The sheets shall be rolled to ensure exclusion of air under the membrane. A minimum lap of 75 mm shall be provided at the edges and 150 mm at the ends between the adjacent sheets. Edge and end laps shall be rolled with pressure to ensure complete adhesion. Unless otherwise indicated in the drawings. 5. One layer of membrane shall be laid directly over the horizontal surface of blinding under the footings and a layer of sand/cement screed 25 mm thick shall be cast over it before erecting forms for footings. All angles and corners, external or internal, shall be reinforced with an extra strip of 300 wide membrane sheet. The external and internal corners shall have cut and cloaked membrane pieces. External corners shall have a minimum 25 mm chamfer and internal angles between slab and walls shall be provided with a 40 x 40 mm preformed fillet. In no case the membrane shall be stretched at the angles or corners. The membrane shall be dressed and eased around corners and angles. At the location of pipes through the walls and floor slabs, reinforcing strips and collars shall be used.
SECTION 07110

DESCRIPTION

ENGG

2.
DATE JOB/EWO

3.

REV. NO.

4.
DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

CERTIFIED _ __________
DATE: ________

CONSTRUCTION AGENCY
________________ DATE:

6.

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

7.

8.
Date:

9.

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

5 OF 6

00

Saudi Aramco 2616-ENG (3/99)


OPERNS.


SAUDI ARAMCO OIL COMPANY
10. For structures projecting above ground, the membrane shall be extended at least 150 mm above grade and terminated and finished in a 20 x 20 mm chase in the concrete. The chase shall be pointed immediately with bitumen flashing compound prior to backfilling. Portions of membrane exposed to sunlight and UV radiation shall be of solar reflective construction and shall have an end lap of 200 mm.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.

ENGG

CERT

PMT

11.
DESCRIPTION

3.02

Protection A. All below ground membrane surfaces shall be protected with protection boards before the backfilling operations can begin. On horizontal surfaces with membrane, where reinforcing steel is to be placed, 25 mm thick layer of sand/cement screed shall be cast. Placing of formwork, reinforcement and concrete shall only begin after the screed has sufficiently hardened. Other membrane protection materials in lieu of screed may be used provide approval is obtained from the Saudi Aramco Representative. Areas with membrane shall be protected either with screed or protection board at the end of a working day. No storage of materials or traffic shall be allowed on the unprotected membraned areas. Care shall be exercised during the backfilling operations so as not to dislocate the protection boards and damage the membrane.

B.
DATE JOB/EWO REV. NO.

C.
DISCIPLINE ENGINEER

__ ________ _ DATE: ________

PROJECT ENGINEER
____________ DATE

D.

CERTIFIED _ __________
DATE: ________

3.03

Inspection A. Before covering the installed membrane, a careful inspection shall be made of all areas where membrane work has been completed. Any damaged to the membrane shall be repaired by patching.

CONSTRUCTION AGENCY
________________ DATE:

OPERATIONS
______________ DATE:_________ REVISION CERTIFICATION EDSD VERIFICATION THIS INDICATES THAT REV. NO.________ OF THIS DRAWING IS COVERED, FOR ALL APPROVAL/CERTIFICATION REQUIREMENTS,, CONTROL NUMBER BY DRAWING COMPLETION CERTIFICATE (DCC) NO.: __________________________ By:

- END OF SECTION -

Date:

SECTION 07110

CONSTRUCTION SPECIFICATIONS
KAUST TOWN CENTER RESIDENTIAL & COMMUNITY SUPPORT BUILDINGS

DWG. TYPE PLANT NO. INDEX

DRAWING NO.

SHT. NO. REV. NO.

DOC

K55 SAUDI ARABIA

VE-417361 BI-25-00002

RABIGH

14-Sep-07

JOB/EWO#

6 OF 6

00

Potrebbero piacerti anche