Sei sulla pagina 1di 5

Construction management or construction project management (CPM) is the overall planning, coordination, and control of a project from inception

to completion aimed at meeting a clients requirements in order to produce a functionally and financially viable project. CPM is project management that applies to the construction sector Construction Manager fall into the following 7 categories: Project Management Planning, Cost Management, Time Management, Quality Management, Contract Administration, Safety Management, and CM Professional Practice which includes specific activities like defining the responsibilities and management structure of the project management team, organizing and leading by implementing project controls, defining roles and responsibilities and developing communication protocols, and identifying elements of project design and construction likely to give rise to disputes and claims. The functions of construction project management typically include the following[1] : Specifying project objectives and plans including delineation of scope, budgeting, scheduling, setting performance requirements, and selecting project participants. Maximizing resource efficiency through procurement of labor, materials and equipment. Implementing various operations through proper coordination and control of planning, design, estimating, contracting and construction in the entire process. Developing effective communications and mechanisms for resolving conflicts Typically the construction industry includes three parties: an owner, a designer (architect or engineer), the builder (usually called the general contractor). Traditionally, there are two contracts between these parties as they work together to plan, design, and construct the project. [6] The first contract is the ownerdesigner contract, which involves planning, design, and construction administration. The second contract is the owner-contractor contract, which involves construction. An indirect, third-party relationship exist between the designer and the contractor due to these two contracts. An alternate contract or business model replaces the two traditional contracts with three contracts: owner-designer, owner-construction project manager, and owner-builder. The construction project management company becomes an additional party engaged in the project to act as an adviser to the owner, to which they are contractually tied. The construction manager's role is to provide construction advice to the designer, on the owner's behalf, design advice to the constructor, again on the owner's behalf, and other advice as necessary. ArchitectureEngineer Work inspection Change orders Review payments Materials and samples Shop drawings 3d image Planning and scheduling Project management methodology: Work breakdown structure Project network of activities Critical path method (CPM) Resource management Resource leveling Construction managers coordinate and schedule design and construction processes in the building of office complexes, residential homes, and industrial structures. They may be involved in the construction of highways, bridges, schools and hospitals. A construction manager approves and hires specialty contractors for operations such as plumbing, electrical wiring and framing. Construction managers

usually work on a project from conception to completion. On large projects, they may be responsible for only one segment of the operation. Architects design buildings and structures that not only look good but are safe, energy efficient and functional. An architect works with a client to set the parameters of the construction, such as construction objectives, budget and requirements of the structure. Architects often do pre-construction assessments to determine the feasibility of the project and any environmental impact the structure might have. When pre-construction assessment is complete, an architect will then develop the final construction plan, including construction details and building appearance. General Risks to Consider There are several areas of liability to watch for when providing construction management services. The degree to which you assume any of these risks depends on your role as a CM and your responsibilities as stated in your contract and demonstrated by your actions. Consider the following: Design. When CMs conduct design and constructability reviews, they may, along with the architect or engineer of record, be subject to claims involving design errors and omissions. Selection of materials. CMs may have exposure arising from the selection and timely delivery of construction materials and subsystems. Cost estimates. Project owners typically have high expectations that a CMs construction cost estimates are accurate. If costs exceed a CMs estimate, there is substantial risk of a claim Jobsite safety. CMs may assume responsibility for construction means and methods, as well as the contractors jobsite safety program and safety plans. OSHA rulings have generally concluded that a CMConstructors responsibilities for jobsite safety are akin to those of a general contractor. Scheduling and coordination. Work not performed on schedule or not well coordinated can lead to claims for project delays, increased overhead expenses and added overtime costs. Hazardous site conditions. If not careful, the CMConstructor can assume liability for existing hazardous site conditions. In addition, if toxic materials on the site must be disposed of or transported, the CM can be deemed an operator of the site or an arranger of the disposal and thus subject to severe (and sometimes criminal) sanctions in the event of an illegal dumping or accident The following provisions should be adhered to wherever practicable:(i) Vehicles and mechanical plant used for the purpose of the works shall be fitted with effective exhaust silencers, maintained in good and efficient working order and operated in such a manner as to minimise noise emissions. The contractor shall ensure that all plant complies with the relevant statutory requirements. (ii) Machines in intermittent use should be shut down or throttled down to a minimum when not in use. (iii) Compressors should be fitted with properly lined and sealed acoustic covers which should be kept closed whenever in use. Pneumatic percussive tools should be fitted with mufflers or silencers of the type recommended by the

manufacturers. (iv) Equipment which breaks concrete, brickwork or masonry by bending or bursting or nibbling shall be used in preference to percussive tools where practicable. Avoid the use of impact tools where the site is close to occupied premises. (v) Where practicable, rotary drills and bursters activated by hydraulic, chemical or electrical power shall be used for excavating hard or extrusive material. (vi) Where practicable, equipment powered by mains electricity shall be used in preference to equipment powered by internal combustion engine or locally generated electricity. (vii) Neither any part of the works nor any maintenance of plant shall be carried out in such a manner as to cause unnecessary noise or vibration except in the case of an emergency when the work is absolutely necessary for the saving of life or property or the safety of the works. (viii) Plant shall be maintained in good working order so that extraneous noise from mechanical vibration, creaking and squeaking is kept to a minimum. (ix) Noise emitting machinery which is required to run continuously shall be housed in a suitable acoustic lined enclosure wherever practicable.

Any plant used for the crushing of materials should be issued with a Permit by a Local Authority under the Pollution Prevention and Control Regulations 2000. All work should be carried out in accordance with the conditions of the Permit. Where plant is used to recycle materials, the appropriate licence from the Environment Agency shall be obtained. The process operator should notify the local authority in whose area the process is proposed prior to operation.
To ensure that our construction works do not affect residents and businesses, noise levels are continuously monitored and kept within the National Environment Agency (NEA) permissible levels.

Contractors must comply with the following noise pollution control requirements: Prior to the commencement of works, contractors are required to carry out a baseline noise survey for one week, on a 24-hour basis, to establish the background noise levels. A Noise Management Plan must be submitted before any construction work is started. The plans must include the baseline noise record, indicate the Noise Sensitive Receivers (NSRs) and proposed mitigation measures and public relation strategies to handle noise matters. Throughout the construction duration, contractors must implement all practicable measures while continuously monitoring the noise levels closely. For effective noise control, the main focus should be on control at source supplemented with control at pathway. Examples of practicable control measures to mitigate the noise impact are as follows: Use of noise reduced plants and machineries
Enclose noisy plant in an acoustic shed. Barricade noisy activities with portable noise barriers/panels. Erect noise barriers before commencement of works. 5. Establish good rapport with the community.
a) improve the planning and management of projects from the very start; (b) identify hazards early on, so they can be eliminated or reduced at the design or planning stage and the remaining risks can be properly managed; (c) target effort where it can do the most good in terms of health and safety; and (d) discourage unnecessary bureaucracy.

Clients must appoint dutyholders who are competent and adequately resourced. Clients must provide those who need it (eg, designers, contractors, CDM Co-ordinators) with preconstruction information that can reasonably be obtained. A range of surveys and reports will be needed

- for example, to check for presence of asbestos; structural stability of site and nearby structures; the location of above and below ground live services in the work area; etc. These should be done before work begins and not be left for the principal contractor to organise once the demolition work has started. CDM Co-ordinators plan effective site management that keeps people (site workers and the public) as far as possible from the risks. They should give principal contractors as much information as possible. Principal contractors co-ordinate and manage health and safety issues during the demolition project. Site managers supervise workers and ensure they are following safe working practice. Sub-contractors and site workers must understand and follow the precautions and ensure that their colleagues do too. Back to top Falls from height During demolition and dismantling, workers can be injured falling from edges, through openings, fragile surfaces and partially demolished floors. Dutyholders have a responsibility to assess, eliminate and control the risks of falls from height. Find out more about falls from height. Back to top Injury from falling materials Workers and passers-by can be injured by the premature and uncontrolled collapse of structures, and by flying debris. A safe system of work is one that keeps people as far as possible from the risks. This may include: establishing exclusion zones and hard-hat areas, clearly marked and with barriers or hoardings if necessary covered walkways using high-reach machines reinforcing machine cabs so that drivers are not injured training and supervising site workers Back to top Uncontrolled collapse The structural survey should consider: the age of the structure its previous use the type of construction nearby buildings or structures the weight of removed material or machinery on floors above ground level The method statement for the demolition should identify the sequence required to prevent accidental collapse of the structure. Back to top Risks from connected services Gas, electricity, water and telecommunications services need to be isolated or disconnected before demolition work begins. If this is not possible, pipes and cables must be labelled clearly, to make sure they are not disturbed. Back to top Traffic management Effective traffic management systems are essential on site, to avoid putting workers at risk of being hit by vehicles turning, slewing, or reversing. Where possible, vision aids and zero tail swing machines should be used. Find out more about traffic management Back to top

Hazardous materials Hazardous materials that need to be considered include dust, asbestos and respirable crystalline silica (RCS).There may also be material or contamination on site that has not been cleared, for example: acids from industrial processes paints flammable liquids unidentified drums microbiological hazards (especially in old hospital buildings). Find out more about the control of substances hazardous to health (COSHH) Back to top Noise and vibration Frequent exposure to loud noise can permanently damage a persons hearing. Noise can also create a safety risk if it makes it difficult for workers to communicate effectively or stops them hearing warning signals. More information on noise at work Vibrating hand tools used in demolition can cause hand-arm vibration syndrome (HAVS).Workers exposure to vibration needs to be managed and reduced as far as possible. Find out more about managing the risks caused by use of vibrating tools Back to top Fire Fire is a risk where hot work (using any tools that generate spark, flame or heat) is being done. During structural alteration, the fire plan must be kept up to date as the escape routes and fire points may alter. There must be an effective way to raise the alarm.

Potrebbero piacerti anche