Sei sulla pagina 1di 55

TRUBINE AND DRIVE SYSTEM

Krishna B. Nakarmi

21st April 2010

Krishna B. Nakarmi /UTSS

Development steps on the

Turbine Manufacturing of Micro

Hydro Plants of NEPAL .

21st April 2010

Krishna B. Nakarmi /UTSS

Krishna Bahadur Nakarmi


Micro Hydro Consultant

IOE, CES
Project Coordinator

Technical Associates
Addresses Tel: Email : Residence : Post Box No.:
21st April 2010

00 977 1 4244313 kbnakarmi @ ntc.net.np 00 977 1 4276686, 10996


Krishna B. Nakarmi /UTSS 3

Professional Experience
30 Years of experience in the Mechanical Field as a Technical In-charge of Engineering Department at Balaju Yantra Shala (P) Ltd.

Hydropower Technology Feasibility Study Designing of MHP equipment Supervision on production in the work shop Installation and Commissioning of equipment at site. Machine constructions, R & D of Mech. Devices, Repair and Maintenance, Any kinds of general services
Krishna B. Nakarmi /UTSS 4

21st April 2010

General Layout of MHP

21st April 2010

Krishna B. Nakarmi /UTSS

Traditional Ghatta (Nepalise Indegenous Technology)

21st April 2010

Krishna B. Nakarmi /UTSS

Water Mill (Ghatta)

21st April 2010

Krishna B. Nakarmi /UTSS

Improved Water Mill

21st April 2010

Krishna B. Nakarmi /UTSS

Water mill with flour fortification device

21st April 2010

Krishna B. Nakarmi /UTSS

T1- CF Turbine

This model is a hand regulated straight forward design to mechanically drive a flat belt transmission for the operation of agro-processing machineries such as flour-mill, rice huskers and oil expellers etc.

21st April 2010

Krishna B. Nakarmi /UTSS

10

21st April 2010

Krishna B. Nakarmi /UTSS

11

T1- turbine design

21st April 2010

Krishna B. Nakarmi /UTSS

12

T2- Turbine

This model is an attempt to come up with a low cost design. The expensive turbine housing is omitted to a large extent. It result in having water splashing all round the equipment, increasing the humidity in the mill house and spoiling the flour. This design is obsolete.
Krishna B. Nakarmi /UTSS 13

21st April 2010

T3 - Turbine

This model is a compact design, and the first machine with butterfly valve for flow regulation. The bearing concept is under design and not suitable for outputs higher than 20kW. This design is modified to avoid the bearing problem that rotor can be removed from the side flange.
Krishna B. Nakarmi /UTSS 14

21st April 2010

T3-turbine design

21st April 2010

Krishna B. Nakarmi /UTSS

15

Split flow Turbine

This turbine is designed for high head low flow site and expecting it will have high efficiency. But result show opposite way. So, stop production and obsolete.

21st April 2010

Krishna B. Nakarmi /UTSS

16

21st April 2010

Krishna B. Nakarmi /UTSS

17

Split flow turbine design

21st April 2010

Krishna B. Nakarmi /UTSS

18

T4 - Turbine

T4 model has a circular wing foe flow regulation. It was the first turbine with automatic governor control used in village electrification projects.

21st April 2010

Krishna B. Nakarmi /UTSS

19

T5 - Turbine

T5 model is basically the concept of an enlarged T3 model. However the machine size was not adequate for the production facility in Nepal. This design was phased out.

21st April 2010

Krishna B. Nakarmi /UTSS

20

T6- Turbine

T6 model suitable for governor control, having a butterfly valve as the flow regulating device. This machine is much stiffer than previous design, therefore has low vibration and noise level during operations. It is a good design for high specific discharge.
Krishna B. Nakarmi /UTSS 21

21st April 2010

T6-turbine design

21st April 2010

Krishna B. Nakarmi /UTSS

22

T7- Turbine

T7 is first model with fully machine turbine blades in order to increase its efficiency. This advanced technology led to a runner failure due to fatigue stress problem, so blade design was changed and used for agro processing only. This model also recommended for 20 kW plant only.
Krishna B. Nakarmi /UTSS 23

21st April 2010

T7- turbine design

21st April 2010

Krishna B. Nakarmi /UTSS

24

T8- Turbine

T8 model is the replacement of T7 turbine in case of electrification projects. It is fully tested machine with known characteristics. This allowed to define the application ranges and to standardize the design.

21st April 2010

Krishna B. Nakarmi /UTSS

25

T8- turbine design

21st April 2010

Krishna B. Nakarmi /UTSS

26

T9 T11 Turbine

T9 T11 models are test model for the following T12 Models. All performance tests were conducted at the University of Hong Kong. The efficiency hill diagram is the result of these tests. The design adheres to the concept of the T8 series with the modified hydraulic profile and secured quality Control to guarantee the exchangeability of the spare parts.
Krishna B. Nakarmi /UTSS 27

21st April 2010

T12- Turbine

T12 model is the collection of past experiences, emphasizing longevity, rugged design etc. It used a new concept to ventilate the jet (Free jet approach) and is specially suited for jet flow control. The main advantage of this machine is good part load efficiency as in full load.
Krishna B. Nakarmi /UTSS 28

21st April 2010

T12-turbine design

21st April 2010

Krishna B. Nakarmi /UTSS

29

T13- Turbine

T13 is the test model turbine. It is made for testing purpose with few modifications on some parts. The performance result shows that the efficiency is increased by some percent.

21st April 2010

Krishna B. Nakarmi /UTSS

30

T14- Turbine

T14 model is made with specific design for particular site as a working model with reference to the T13 model hydraulic profile. It replaced the old model turbine, and thus produces more power than previous ones and runs very smoothly.
Krishna B. Nakarmi /UTSS 31

21st April 2010

T14- turbine design

21st April 2010

Krishna B. Nakarmi /UTSS

32

T15- Turbine

T15 model is the advance model turbine with T 12 turbine characteristic and efficiency wise T14 turbine. It is now being familiar through GTZ as T15 turbine in Nepal.

21st April 2010

Krishna B. Nakarmi /UTSS

33

T16- Turbine

T16 model is developed with new concept. It is basically upgraded version model or combination of T7 and T12 Turbine and few design parameters changed. This is not tested at any laboratory. But it is installed at existing plant where only turbine has to be replaced.
Krishna B. Nakarmi /UTSS 34

21st April 2010

T16

The client informed that they found the electric power output is increased significantly. It means the turbine efficiency is increased. So the turbine efficiency can be guessed that it reached up to 78% to 80%

21st April 2010

Krishna B. Nakarmi /UTSS

35

T16

On the basis of this experience if the turbine components are made precisely the turbine efficiency can be considered as 80%

21st April 2010

Krishna B. Nakarmi /UTSS

36

A Typical Cross Flow Turbine Design


Design by: Model:
21st April 2010

Krishna B. Nakarmi UTSS-08KBN/CF-03


Krishna B. Nakarmi /UTSS 37

A typical Pelton Turbine Design


Design by: Model:
21st April 2010

Krishna B. Nakarmi UTSS-08KBN/PT-03


Krishna B. Nakarmi /UTSS 38

Uses of turbine
1.

Micro Hydro Electricity Generating Saw Milling Heat Generating Agro-Processing Stone Crushing

21st April 2010

Krishna B. Nakarmi /UTSS

39

1.

Selection of turbine

Plant Size Locally / Imported Skill Man power for O & M Efficiency of Turbine Cost of Equipment

21st April 2010

Krishna B. Nakarmi /UTSS

40

Working principle of different turbines

21st April 2010

Krishna B. Nakarmi /UTSS

41

EXAMPLE (IMAGINARY SITE)

SITE DATA Gross Head Discharge

Hg Ql/s

36 600

m l/s (AT Rriver)

Designed net head Hn = 32.4 m (Gross Head minus Pipe Lie Losses = 5 to 10 % Hg) Designed discharge Q Available flow at river * 0.8 = 480 l/s (80% of flow of the river)

21st April 2010

Krishna B. Nakarmi /UTSS

42

Turbine speed
Desired turbine speed is 1500 rpm. (Because normal gen. operating speed is 1500rpm) Turbine speed depends upon the working pressure and selected turbine rotor diameter.

21st April 2010

Krishna B. Nakarmi /UTSS

43

Desired speed of the turbine nturb is 1500 rpm.


( because operating speed of the commercial standard alternator is 1500 rpm)

Turbine Speed to be calculated


But the speed of turbine varies according to the available net head and selected turbine rotor diameter

21st April 2010

Krishna B. Nakarmi /UTSS

44

Turbine Specification(T12 / T15 CF Turbine)


Unit speed Unit discharge Efficiency of turbine Turbine Rotor Diameter Rotor shaft Diameter n11 Q11 D d 40 80 0.75 0.3 80 m mm normally

21st April 2010

Krishna B. Nakarmi /UTSS

45

(H m)

0.5

nturb =

40*

---------Dm
0.5

(32.4 m)

nturb =

40*

------------(0.3)

nturb =

758.9 rpm

21st April 2010

Krishna B. Nakarmi /UTSS

46

Specific speed
(Q m3/s.)^0.5

ns = 3.65 * nturb rpm *

---------------(Hm)^0.75

(0.480)^ 0.5

ns = 3.65 * 758.9 *

------------------(32.4 0)^.75

141.3

CAN

(REFERING THIS ns CROSSFLOW OR FRANCIS TURBINE BE SELLECTED)

21st April 2010

Krishna B. Nakarmi /UTSS

47

Hydraulic Power
Hnet * Q l/s

Phy

-------------- (kW) 102 32.4 m * 480 l/s

Phy Phy

-----------------(kW) 102 152.4 kW (available power at the site)


Krishna B. Nakarmi /UTSS 48

21st April 2010

Plant efficiency ( plant )


is determined as follows: Electrical Power Output

Pel = Phy * turb*trans*gen

21st April 2010

Krishna B. Nakarmi /UTSS

49

Turbine Efficiency
0.70 to 0.80 in case of Cross Flow 0.75 to 0.90 in case of Pelton/ Francis

21st April 2010

Krishna B. Nakarmi /UTSS

50

Efficiency of transmission system (belt , coupling system) =


0.9 to 0.95 to 0.98 to 0.99 in case of normal belts in case of Habasit flat belt in case of Flexible Coupling

= 0.95 = 0.98

21st April 2010

Krishna B. Nakarmi /UTSS

51

Efficiency of generator = 0.76


to 0.92 in case of Synchronous Generator ( gen = 0.85 can be confirmed )

21st April 2010

Krishna B. Nakarmi /UTSS

52

Electrical power output


Pturb = = = Phy * turb*Trans*gen 152.4 * 0.75*0.95*0.85 92.3 kWel

So, plant equipment efficiency can be determined to be 0.6.

21st April 2010

Krishna B. Nakarmi /UTSS

53

21st April 2010

Krishna B. Nakarmi /UTSS

54

Thank You
21st April 2010 Krishna B. Nakarmi /UTSS 55

Potrebbero piacerti anche